Expropriation of Brisas Project by Venezuela and Related Arbitration:
12 Months Ended
Dec. 31, 2011
Expropriation of Brisas Project by Venezuela and Related Arbitration:

Note 3.        Expropriation of Brisas Project by Venezuela and Related Arbitration:

From 1992 to 2008 the Company focused substantially all of its management and financial resources on the development of the Brisas gold and copper project located in the Kilometer 88 mining district of the State of Bolivar in south-eastern Venezuela. After approval of the Brisas operating plan by the Ministry of Mines and the Environmental and Social Impact Study by the Ministry of Environment in 2003 and early 2007, respectively, the Ministry of Environment issued in March 2007, the Authorization for the Affectation of Natural Resources for the Construction of Infrastructure and Services Phase of the Brisas Project (the “Authorization to Affect”) which authorized the commencement of construction activities on the Brisas Project.  In April 2008, the Ministry of Environment revoked, without notice, the Authorization to Affect.

In October 2009 we filed a Request for Arbitration under the Additional Facility Rules of the International Centre for Settlement of Investment Disputes (“ICSID”), against the Bolivarian Republic of Venezuela (“Respondent”) seeking compensation in the arbitration for all of the loss and damage resulting from Venezuela’s wrongful conduct. Gold Reserve alleges violations of three provisions of the Canada-Venezuela BIT culminating in the effective expropriation of Gold Reserve’s sizable investments in the world-class Brisas gold/copper project and the promising Choco 5 property. In November 2009 our Request for Arbitration was registered by ICSID (Gold Reserve Inc. v. Bolivarian Republic of Venezuela (ICSID Case No. ARB(AF)/09/1)). Our claim includes the full market value of the legal rights to develop the Brisas Project at the date of the Tribunal’s decision, the value of the Choco 5 Property and interest on the claim calculated since the loss. Our claim as last updated in our July 2011 Reply totals approximately $2.1 billion which includes interest from April 14, 2008 (the date of the loss) to July 29, 2011 (the date of our last filing) of approximately $400 million. See “Part I- Item 3. Legal Proceedings– Arbitration.” 

The full market value of the legal rights to develop the Brisas Project was measured by an independent expert pursuant to a fair market value standard utilizing three standard valuation approaches: (1) the Discounted Cash Flow (“DCF”) Approach, (2) the Comparable Publicly Traded Company (“CPTC”) Approach, and (3) the Comparable Transaction (“CT”) Approach. These three valuations converged in a reasonably consistent range of values, which were combined to arrive at a weighted average valuation based upon the independent expert’s qualitative assessment of the robustness of the data available to implement each valuation methodology.

Venezuela has numerous pending arbitration actions being pursued against it at this time before ICSID (See ICSID website-http://icsid.worldbank.org/ICSID/) and has reportedly settled and/or made full or partial payment for damages to a limited number of claimants in past months, although management has no specific information regarding the actual amounts paid or what percentage such payments represented of the original claim against Venezuela. Based on the uncertain nature of arbitration under investment treaties, the timing and the amount of an award or settlement, if any, the likelihood of its collection and the timing thereof cannot be determined at this time.

In compliance with the schedule originally set by the Tribunal which has been amended by the Tribunal from time-to-time, we filed our initial written submission, referred to as the Memorial, in September 2010. Thereafter in April 2011, the Respondent submitted its response to the Company’s Memorial, referred to as the Counter-Memorial. Subsequent to that, the Company submitted its Reply to the Respondent’s Counter Memorial in July 2011 and finally Respondent filed its Rejoinder in December 2011. The Rejoinder was the last filing to be made prior to the oral hearing which was held February 13 to February 17, 2012.

 The oral hearing was the culmination of an extensive undertaking by the Company’s counsel, technical, legal and financial experts, as well as its employees which focused on the evidentiary record in the case and allowed counsel for both the Company and Venezuela to address the issues of jurisdiction, liability and damages.  The oral hearing also allowed the Tribunal to hear testimony from certain fact and expert witnesses, as well as to address questions to each of the parties.

The Tribunal granted both parties the opportunity to submit a post-hearing brief, to be filed simultaneously, in order to comment in conclusion on the full evidentiary record, as is typically permitted in such arbitrations.  Those briefs are due to be filed by March 16, 2012.  The Tribunal may request additional information from the parties and in any event may issue its decision thereafter.  It is typical for tribunals in this type of arbitration to require six to eighteen months (the historical average is approximately 1.2 years) to finalize and issue its decision.