XML 35 R19.htm IDEA: XBRL DOCUMENT  v2.3.0.11
Contingent Liabilities
6 Months Ended
Jun. 30, 2011
Contingent Liabilities [Abstract]  
Contingent Liabilities
Note 12. Contingent Liabilities
Issues Resulting from California Energy Crisis
     Our former power business was engaged in power marketing in various geographic areas, including California. Prices charged for power by us and other traders and generators in California and other western states in 2000 and 2001 were challenged in various proceedings, including those before the Federal Energy Regulatory Commission (FERC). We have entered into settlements with the State of California (State Settlement), major California utilities (Utilities Settlement), and others that substantially resolved each of these issues with these parties.
     Although the State Settlement and Utilities Settlement resolved a significant portion of the refund issues among the settling parties, we continue to have potential refund exposure to nonsettling parties, including various California end users that did not participate in the Utilities Settlement. We are currently in settlement negotiations with certain California utilities aimed at eliminating or substantially reducing this exposure. If successful, and subject to a final “true-up” mechanism, the settlement agreement would also resolve our collection of accrued interest from counterparties as well as our payment of accrued interest on refund amounts. Thus, as currently contemplated by the parties, the settlement agreement would resolve most, if not all, of our legal issues arising from the 2000-2001 California Energy Crisis. With respect to these matters, amounts accrued are not material to our financial position.
     Certain other issues also remain open at the FERC and for other nonsettling parties.
Reporting of Natural Gas-Related Information to Trade Publications
     Civil suits based on allegations of manipulating published gas price indices have been brought against us and others, in each case seeking an unspecified amount of damages. We are currently a defendant in class action litigation and other litigation originally filed in state court in Colorado, Kansas, Missouri and Wisconsin brought on behalf of direct and indirect purchasers of natural gas in those states. These cases were transferred to the federal court in Nevada. In 2008, the court granted summary judgment in the Colorado case in favor of us and most of the other defendants based on plaintiffs’ lack of standing. In 2009, the court denied the plaintiffs’ request for reconsideration of the Colorado dismissal and entered judgment in our favor. The court’s order became final on July 18, 2011, and we expect that the Colorado plaintiffs will appeal.
     In the other cases, on July 18, 2011, the Nevada district court granted our joint motions for summary judgment to preclude the plaintiffs’ state law claims because the federal Natural Gas Act gives the FERC exclusive jurisdiction to resolve those issues. The court also denied the plaintiffs’ class certification motion as moot. On July 22, 2011, the plaintiffs’ filed their notice of appeal with the Nevada district court. Because of the uncertainty around these current pending unresolved issues, including an insufficient description of the purported classes and other related matters, we cannot reasonably estimate a range of potential exposures at this time. However, it is reasonably possible that the ultimate resolution of these items could result in future charges that may be material to our results of operations.
Environmental Matters
  Continuing operations
     Our interstate gas pipelines are involved in remediation activities related to certain facilities and locations for polychlorinated biphenyl, mercury contamination, and other hazardous substances. These activities have involved the U.S. Environmental Protection Agency (EPA), various state environmental authorities and identification as a potentially responsible party at various Superfund waste disposal sites. At June 30, 2011, we have accrued liabilities of $11 million for these costs. We expect that these costs will be recoverable through rates.
     We also accrue environmental remediation costs for natural gas underground storage facilities, primarily related to soil and groundwater contamination. At June 30, 2011, we have accrued liabilities totaling $8 million for these costs.
     In March 2008, the EPA proposed a penalty of $370,000 for alleged violations relating to leak detection and repair program delays at our Ignacio gas plant in Colorado and for alleged permit violations at a compressor station. Tentative settlement was reached in first-quarter 2011.
     In September 2007, the EPA requested, and our Transco subsidiary later provided, information regarding natural gas compressor stations in the states of Mississippi and Alabama as part of the EPA’s investigation of our compliance with the Clean Air Act. On March 28, 2008, the EPA issued notices of violation alleging violations of Clean Air Act requirements at these compressor stations. Transco met with the EPA in May 2008 and submitted our response denying the allegations in June 2008. In May 2011, we provided additional information to the EPA pertaining to these compressor stations in response to a request they had made in February 2011. In August 2010, the EPA requested, and our Transco subsidiary provided, similar information for a compressor station in Maryland.
  Former operations, including operations classified as discontinued
     We have potential obligations in connection with assets and businesses we no longer operate. These potential obligations include the indemnification of the purchasers of certain of these assets and businesses for environmental and other liabilities existing at the time the sale was consummated. Our responsibilities relate to the operations of the assets and businesses described below.
    Former agricultural fertilizer and chemical operations and former retail petroleum and refining operations;
 
    Former petroleum products and natural gas pipelines;
 
    Discontinued petroleum refining facilities;
 
    Former exploration and production and mining operations.
     At June 30, 2011, we have accrued environmental liabilities of $30 million related to these matters.
     Actual costs for these matters could be substantially greater than amounts accrued depending on the actual number of contaminated sites identified, the actual amount and extent of contamination discovered, the final cleanup standards mandated by the EPA and other governmental authorities. Any incremental amount cannot be reasonably estimated at this time.
     Certain of our subsidiaries have been identified as potentially responsible parties at various Superfund and state waste disposal sites. In addition, these subsidiaries have incurred, or are alleged to have incurred, various other hazardous materials removal or remediation obligations under environmental laws.
  Environmental matters — general
     The EPA and various state regulatory agencies routinely promulgate and propose new rules, and issue updated guidance to existing rules. These new rules and rulemakings include, but are not limited to, rules for reciprocating internal combustion engine maximum achievable control technology, new air quality standards for ground level ozone, and one hour nitrogen dioxide emission limits. We are unable to estimate the costs of asset additions or modifications necessary to comply with these new regulations due to uncertainty created by the various legal challenges to these regulations and the need for further specific regulatory guidance.
Other Legal Matters
  Gulf Liquids litigation
     Gulf Liquids contracted with Gulsby Engineering Inc. (Gulsby) and Gulsby-Bay (a joint venture between Gulsby and Bay Ltd.) for the construction of certain gas processing plants in Louisiana. National American Insurance Company (NAICO) and American Home Assurance Company provided payment and performance bonds for the projects. In 2001, the contractors and sureties filed multiple cases in Louisiana and Texas against Gulf Liquids and us.
     In 2006, at the conclusion of the consolidated trial of the asserted contract and tort claims, the jury returned its actual and punitive damages verdict against us and Gulf Liquids. Based on our interpretation of the jury verdicts, we recorded a charge based on our estimated exposure for actual damages of approximately $68 million plus potential interest of approximately $20 million. In addition, we concluded that it was reasonably possible that any ultimate judgment might have included additional amounts of approximately $199 million in excess of our accrual, which primarily represented our estimate of potential punitive damage exposure under Texas law.
     From May through October 2007, the court entered seven post-trial orders in the case (interlocutory orders) which, among other things, overruled the verdict award of tort and punitive damages as well as any damages against us. The court also denied the plaintiffs’ claims for attorneys’ fees. On January 28, 2008, the court issued its judgment awarding damages against Gulf Liquids of approximately $11 million in favor of Gulsby and approximately $4 million in favor of Gulsby-Bay. Gulf Liquids, Gulsby, Gulsby-Bay, Bay Ltd., and NAICO appealed the judgment. In February 2009, we settled with certain of these parties and reduced our liability as of December 31, 2008, by $43 million, including $11 million of interest. On February 17, 2011, the Texas Court of Appeals upheld the dismissals of the tort and punitive damages claims and reversed and remanded the contract claim and attorney fee claims for further proceedings. The appellate court ruling is subject to a potential appeal to the Texas Supreme Court. If the appellate court judgment is upheld, our remaining liability could be less than the amount of our accrual for these matters.
  Royalty litigation
     In September 2006, royalty interest owners in Garfield County, Colorado, filed a class action suit in District Court, Garfield County Colorado, alleging we improperly calculated oil and gas royalty payments, failed to account for the proceeds that we received from the sale of natural gas and extracted products, improperly charged certain expenses, and failed to refund amounts withheld in excess of ad valorem tax obligations. Plaintiffs sought to certify as a class of royalty interest owners, recover underpayment of royalties and obtain corrected payments resulting from calculation errors. We entered into a final partial settlement agreement. The partial settlement agreement defined the class members for class certification, reserved two claims for court resolution, resolved all other class claims relating to past calculation of royalty and overriding royalty payments, and established certain rules to govern future royalty and overriding royalty payments. This settlement resolved all claims relating to past withholding for ad valorem tax payments and established a procedure for refunds of any such excess withholding in the future. The first reserved claim is whether we are entitled to deduct in our calculation of royalty payments a portion of the costs we incur beyond the tailgates of the treating or processing plants for mainline pipeline transportation. We received a favorable ruling on our motion for summary judgment on the first reserved claim. Plaintiffs appealed that ruling and the Colorado Court of Appeals found in our favor in April 2011. In June 2011, Plaintiffs filed a Petition for Certiorari with the Colorado Supreme Court. We anticipate that court will issue a decision on whether to grant further review later in 2011 or early in 2012. The second reserved claim relates to whether we are required to have proportionately increased the value of natural gas by transporting that gas on mainline transmission lines and, if required, whether we did so and are thus entitled to deduct a proportionate share of transportation costs in calculating royalty payments. We anticipate trial on the second reserved claim following resolution of the first reserved claim. We believe our royalty calculations have been properly determined in accordance with the appropriate contractual arrangements and Colorado law. At this time, the plaintiffs have not provided us a sufficient framework to calculate an estimated range of exposure related to their claims. However, it is reasonably possible that the ultimate resolution of this item could result in a future charge that may be material to our results of operations.
     Other producers have been in litigation or discussions with a federal regulatory agency and a state agency in New Mexico regarding certain deductions, comprised primarily of processing, treating and transportation costs, used in the calculation of royalties. Although we are not a party to these matters, we have monitored them to evaluate whether their resolution might have the potential for an unfavorable impact on our results of operations. One of these matters involving federal litigation was decided on October 5, 2009. The resolution of this specific matter is not material to us. However, other related issues in these matters that could be material to us remain outstanding. We received notice from the U.S. Department of Interior Office of Natural Resources Revenue (ONRR) in the fourth quarter of 2010, intending to clarify the guidelines for calculating federal royalties on conventional gas production applicable to our federal leases in New Mexico. The ONRR’s guidance provides its view as to how much of a producer’s bundled fees for transportation and processing can be deducted from the royalty payment. We believe using these guidelines would not result in a material difference in determining our historical federal royalty payments for our leases in New Mexico. No similar specific guidance has been issued by ONRR for leases in other states, but such guidelines are expected in the future. However, the timing of receipt of the necessary guidelines is uncertain. In addition, these interpretive guidelines on the applicability of certain deductions in the calculation of federal royalties are extremely complex and will vary based upon the ONRR’s assessment of the configuration of processing, treating and transportation operations supporting each federal lease. From January 2004 through December 2010, our deductions used in the calculation of the royalty payments in states other than New Mexico associated with conventional gas production total approximately $55 million. Correspondence in 2009 with the ONRR’s predecessor did not take issue with our calculation regarding the Piceance Basin assumptions which we believe have been consistent with the requirements. The issuance of similar guidelines in Colorado and other states could affect our previous royalty payments and the effect could be material to our results of operations.
  Other
     In 2003, we entered into an agreement to sublease certain underground storage facilities to Liberty Gas Storage (Liberty). We have asserted claims against Liberty for prematurely terminating the sublease and for damage caused to the facilities. In February 2011, Liberty asserted a counterclaim for costs in excess of $200 million associated with its use of the facilities. Due to the lack of information currently available, we are unable to evaluate the merits of the counterclaim and determine the amount of any possible liability.
Other Divestiture Indemnifications
     Pursuant to various purchase and sale agreements relating to divested businesses and assets, we have indemnified certain purchasers against liabilities that they may incur with respect to the businesses and assets acquired from us. The indemnities provided to the purchasers are customary in sale transactions and are contingent upon the purchasers incurring liabilities that are not otherwise recoverable from third parties. The indemnities generally relate to breach of warranties, tax, historic litigation, personal injury, property damage, environmental matters, right of way and other representations that we have provided.
     At June 30, 2011, we do not expect any of the indemnities provided pursuant to the sales agreements to have a material impact on our future financial position. However, if a claim for indemnity is brought against us in the future, it may have a material adverse effect on our results of operations in the period in which the claim is made.
     In addition to the foregoing, various other proceedings are pending against us which are incidental to our operations.
Summary
     Litigation, arbitration, regulatory matters, and environmental matters are subject to inherent uncertainties. Were an unfavorable ruling to occur, there exists the possibility of a material adverse impact on the results of operations in the period in which the ruling occurs. Management, including internal counsel, currently believes that the ultimate resolution of the foregoing matters, taken as a whole and after consideration of amounts accrued, insurance coverage, recovery from customers or other indemnification arrangements, will not have a material adverse effect upon our future liquidity or financial position.