GES-Port Charlotte (Details) (USD $)
12 Months Ended 1 Months Ended 3 Months Ended 12 Months Ended
Dec. 31, 2012
Dec. 31, 2011
LEAD
Oct. 31, 2011
LEAD
MW
Dec. 31, 2012
LEAD
GES-Port Charlotte
Dec. 31, 2010
LEAD
GES-Port Charlotte
Oct. 31, 2010
LEAD
GES-Port Charlotte
GES-Port Charlotte            
Amount paid to acquire           $ 2,650,000
Term of the power purchase agreement         20 years  
Landfill-gas to electricity facility the construction of which is completed (in megawatts)     2.8      
Cost to construct the facility   4,700,000        
U.S. Treasury Grant received for the project   1,800,000        
Amount of term loan used for financing portion of construction costs 3,600,000          
Impairment charge $ 3,547,000     $ 3,500,000