EX-10.2 4 exhibit_10-50x20211231.htm EX-10.2 Document
image_6a.jpgNAME OF OFFEROR OR CONTRACTOR
American Centrifuge Operating, LLC
11.THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
image_0a.jpg    The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers    is extended,     is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing Items 8 and 15, and returning     ___________    copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
image_1.jpg
12.ACCOUNTING AND APPROPRIATION DATA (If required)    Net Increase:    $3,491,000.00
See Schedule
image_1.jpg
13.THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
52.243-2 Changes
X
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
image_3a.jpgis required to sign this document and return __________________ copies to the issuing office.
14.DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT1. CONTRACT ID CODE
PAGE OF PAGES
1
11
2. AMENDMENT/MODIFICATION NO.
P00014
3. EFFECTIVE DATE
See Block 16C
4. REQUISITION/PURCHASE REQ. NO.
22NE000035
5. PROJECT NO. (If applicable)
6. ISSUED BY    CODE
EM-Oak Ridge
EMCBC
U.S. Department of Energy 200 Administration Road
Oak Ridge TN 37831
893035
7. ADMINISTERED BY (If other than Item 6)    CODE
OREM
U.S. Department of Energy Oak Ridge
Office of Environmental Management
P.O. Box 2001 Oak Ridge TN 37831
03011
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
American Centrifuge Operating, LLC
Attn: Charles Kerner
6901 Rockledge Dr, Suite 800
Bethesda MD 20817
(x)
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
x
10A. MODIFICATION OF CONTRACT/ORDER NO.
89303519CNE000005
10B. DATED (SEE ITEM 13)
05/31/2019
CODE 079679750
FACILITY CODE


image_6a.jpgNAME OF OFFEROR OR CONTRACTOR
American Centrifuge Operating, LLC
DUNS Number: 079679750
See Page 6
Period of Performance: 05/31/2019 to 06/01/2022
Change Item 00001 to read as follows(amount shown is the total amount):
00001 Demonstrate the capability to produce HALEU with 121,409,607.00 existing US origin enrichment technology, and provide DOE with HALEU for near term use in its Continued ...
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Karen S. Shears
15B. CONTRACTOR/OFFEROR
image_5.jpg
(Signature of person authorized to sign)
15C. DATE SIGNED
16B. UNITED STATES OF AMERICA
image_5.jpg
(Signature of Contracting Officer)
16C. DATE SIGNED
12/06/2021
Previous edition unusable    STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243

ITEM NO.
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(A)
(B)
(C)(D)
(E)
(F)
    NSN 7540-01-152-8067    OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110

image_6a.jpgNAME OF OFFEROR OR CONTRACTOR
American Centrifuge Operating, LLC
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
 research and development for the advancement of civilian nuclear energy and security, and other programmatic missions. Line item value is: $121,409,607.00
 Incrementally Funded Amount: $121,409,607.00
 Accounting Info:
 89-0319 Fund: 05350 Appr Year: 2013 Allottee: 30
 Report Entity: 471999 Object Class: 25233
 Program: 2721004 Project: 0000000 WFO: 0000000
 Local Use: 0000000
 Funded: $0.00 Accounting Info:
 Fund: 05350 Appr Year: 2010 Allottee: 30 Report Entity: 471999 Object Class: 25233 Program:
 2721004 Project: 0000000 WFO: 0000000 Local Use:
 0000000
 Funded: $0.00 Accounting Info:
 Fund: 05350 Appr Year: 2014 Allottee: 30 Report Entity: 471999 Object Class: 25233 Program:
 2721004 Project: 0000000 WFO: 0000000 Local Use:
 0000000
 Funded: $0.00 Accounting Info:
 Fund: 05350 Appr Year: 2015 Allottee: 30 Report Entity: 471999 Object Class: 25233 Program:
 2721004 Project: 0000000 WFO: 0000000 Local Use:
 0000000
 Funded: $0.00 Accounting Info:
 Fund: 05350 Appr Year: 2016 Allottee: 30 Report Entity: 471999 Object Class: 25233 Program:
 2721004 Project: 0000000 WFO: 0000000 Local Use:
 0000000
 Funded: $0.00 Accounting Info:
 Fund: 05350 Appr Year: 2017 Allottee: 30 Report Entity: 471999 Object Class: 25233 Program:
 2721004 Project: 0000000 WFO: 0000000 Local Use:
 0000000
 Funded: $0.00 Accounting Info:
 89-0319 Fund: 05350 Appr Year: 2019 Allottee: 30
 Report Entity: 471999 Object Class: 25233
 Program: 2721004 Project: 0000000 WFO: 0000000
 Local Use: 0000000
 Funded: $0.00 Accounting Info:
 89-0319 Fund: 05350 Appr Year: 2019 Allottee: 30 Continued ...
    NSN 7540-01-152-8067    OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110

image_6a.jpgNAME OF OFFEROR OR CONTRACTOR
American Centrifuge Operating, LLC

ITEM NO.
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(A)
(B)
(C)(D)
(E)
(F)
    NSN 7540-01-152-8067    OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110

image_6a.jpgNAME OF OFFEROR OR CONTRACTOR
American Centrifuge Operating, LLC
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
 Report Entity: 471999 Object Class: 25233
 Program: 2721004 Project: 0000000 WFO: 0000000
 Local Use: 0000000
 Funded: $0.00 Accounting Info:
 89-0319 Fund: 05350 Appr Year: 2020 Allottee: 30
 Report Entity: 471999 Object Class: 25233
 Program: 2721019 Project: 0000000 WFO: 0000000
 Local Use: 0000000
 Funded: $0.00 Accounting Info:
 89-0319 Fund: 05350 Appr Year: 2020 Allottee: 30
 Report Entity: 471999 Object Class: 25233
 Program: 2721019 Project: 0000000 WFO: 0000000
 Local Use: 0000000
 Funded: $0.00 Accounting Info:
 89-0319 Fund: 05350 Appr Year: 2020 Allottee: 30
 Report Entity: 471999 Object Class: 25233
 Program: 2721019 Project: 0000000 WFO: 0000000
 Local Use: 0000000
 Funded: $0.00 Accounting Info:
 89-0319 Fund: 05350 Appr Year: 2020 Allottee: 30
 Report Entity: 471999 Object Class: 25233
 Program: 2721019 Project: 0000000 WFO: 0000000
 Local Use: 0000000
 Funded: $0.00 Accounting Info:
 89-0319 Fund: 05350 Appr Year: 2020 Allottee: 30
 Report Entity: 471999 Object Class: 25233
 Program: 2721019 Project: 0000000 WFO: 0000000
 Local Use: 0000000
 Funded: $0.00 Accounting Info:
 Fund: 05350 Appr Year: 2021 Allottee: 60 Report Entity: 302218 Object Class: 25233 Program:
 2721019 Project: 0000000 WFO: 0000000 Local Use:
 0000000
 Funded: $0.00 Accounting Info:
 Fund: 05350 Appr Year: 2021 Allottee: 60 Report Entity: 302218 Object Class: 25233 Program:
 2721019 Project: 0000000 WFO: 0000000 Local Use:
 0000000
 Funded: $0.00 Accounting Info:
 Fund: 05350 Appr Year: 2021 Allottee: 60 Report Entity: 302218 Object Class: 25233 Program:
 2721019 Project: 0000000 WFO: 0000000 Local Use:
 Continued ...
    NSN 7540-01-152-8067    OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110

image_6a.jpgNAME OF OFFEROR OR CONTRACTOR
American Centrifuge Operating, LLC

ITEM NO.
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(A)
(B)
(C)(D)
(E)
(F)
    NSN 7540-01-152-8067    OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110

image_6a.jpgNAME OF OFFEROR OR CONTRACTOR
American Centrifuge Operating, LLC
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
 0000000
 Funded: $0.00 Accounting Info:
 Fund: 05350 Appr Year: 2021 Allottee: 60 Report Entity: 302218 Object Class: 25233 Program:
 2721019 Project: 0000000 WFO: 0000000 Local Use:
 0000000
 Funded: $0.00 Accounting Info:
 Fund: 05350 Appr Year: 2021 Allottee: 60 Report Entity: 302218 Object Class: 25233 Program:
 2721019 Project: 0000000 WFO: 0000000 Local Use:
 0000000
 Funded: $0.00 Accounting Info:
 05350-2022-60-302218-25233-2721019-0000000-0000000
 -0000000 Fund: 05350 Appr Year: 2022 Allottee: 60
 Report Entity: 302218 Object Class: 25233
 Program: 2721019 Project: 0000000 WFO: 0000000
 Local Use: 0000000
 Funded: $0.00 Accounting Info:
 05350-2022-60-302218-25233-2721019-0000000-0000000
 -0000000 Fund: 05350 Appr Year: 2022 Allottee: 60
 Report Entity: 302218 Object Class: 25233
 Program: 2721019 Project: 0000000 WFO: 0000000
 Local Use: 0000000
 Funded: $0.00 Accounting Info:
 05350-2022-60-302218-25233-2721019-0000000-0000000
 -0000000 Fund: 05350 Appr Year: 2022 Allottee: 60
 Report Entity: 302218 Object Class: 25233
 Program: 2721019 Project: 0000000 WFO: 0000000
 Local Use: 0000000
 Funded: $3,491,000.00 Payment: VIPERS
      https://vipers.doe.gov Any questions, please contact by call/email 855-384-7377 or VipersSupport@hq.doe.gov Payment: VIPERS
      https://vipers.doe.gov Any questions, please contact by call/email 855-384-7377 or VipersSupport@hq.doe.gov Continued ...
    NSN 7540-01-152-8067    OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110

image_6a.jpgNAME OF OFFEROR OR CONTRACTOR
American Centrifuge Operating, LLC

ITEM NO.
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
(A)
(B)
(C)(D)
(E)
(F)
    NSN 7540-01-152-8067    OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110

image_6a.jpgNAME OF OFFEROR OR CONTRACTOR
American Centrifuge Operating, LLC
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
 Payment: VIPERS
      https://vipers.doe.gov Any questions, please contact by call/email 855-384-7377 or VipersSupport@hq.doe.gov Payment: VIPERS
      https://vipers.doe.gov Any questions, please contact by call/email 855-384-7377 or VipersSupport@hq.doe.gov Payment: VIPERS
      https://vipers.doe.gov Any questions, please contact by call/email 855-384-7377 or VipersSupport@hq.doe.gov Payment:
      Oak Ridge
      U.S. Department of Energy
      P.O. Box 2001 Oak Ridge TN 37831 Payment:
      Oak Ridge
      U.S. Department of Energy
      P.O. Box 2001 Oak Ridge TN 37831 Payment:
      Oak Ridge
      U.S. Department of Energy
      P.O. Box 2001 Oak Ridge TN 37831
    NSN 7540-01-152-8067    OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110

Contract No: 89303519CNE000005
Modification P00014
Page 10 of #NUM_PAGES#
The purpose of this Change Order is to revise the description and date of Milestones 9 and 10 and delete Milestones 11-14, and define activities. A not-to-exceed amount of $3,491,000 is authorized to implement these changes and is obligated with this modification. Changes are denoted in underlining and strikethrough.
A. Section C, Project Objectives, is deleted in its entirety and changed to the following:
Project Objectives
The objective of the HALEU Demonstration Program is to demonstrate the capability to produce HALEU with existing US origin enrichment technology and provide DOE with HALEU for near term use in its research and development for the advancement of civilian nuclear energy and security, and other programmatic missions. While DOE will retain title to the HALEU produced, DOE is amenable to make it available to the Contractor for DOE R&D purposes. Title to UF6 by-product (tails) from the HALEU enrichment process will be retained by DOE. This demonstration consists of the deployment of a 16 machine AC100M HALEU Cascade to be located at DOE’s site in Piketon, Ohio, producing a 19.75% U235 enriched product by April 1, 2022. In order to fulfill these objectives, the Project will accomplish 14 defined Milestones. The Milestones to be completed by the Contractor are:
MILESTONE 1 - Rescind the License Amendment Request (License Number SNM-7003) to the Nuclear Regulatory Commission (NRC) for removal of enrichment as an authorized activity and for downgrade of licensed activities for the Lead Cascade by July 1, 2019. This activity is considered complete when the Contractor’s letter is submitted to the NRC. (Complete June 1, 2019)
MILESTONE 2 - Re-establish required site services under the Memorandum of Agreement for the Supply of
Services (Article 6, Section 6.1 of the GCEP Lease) by January 1, 2020. (Complete June 1, 2019)
MILESTONE 3 – Award Purchase Order for machine casings by October 31, 2019. (Completed October 22, 2019)
MILESTONE 4 - Re-establish vendor supply chain(s) of materials and equipment necessary for deployment and production of unobligated HALEU by June 1, 2020. (Completed June 1, 2020)
MILESTONE 5- Re-constitute the security program to support possession of C-24 technology and assembly/installation/operation of the HALEU Cascade at the DOE leased facilities located in Piketon, Ohio by November 1, 2020.
a)Obtain Security Plan approval from NRC.
b)Modify and implement Security Plan procedures.
c)Request security clearances for new personnel.
d)“Stand up” Piketon facilities for possession of C-24 technology and assembly/installation/operation of the HALEU Cascade.
MILESTONE 6 - Deliver sub-assemblies for 16 AC100M machines (Drawing no. 1007800 Rev. 3) to the DOE leased facilities located in Piketon, Ohio:
a)Transfer title of Contractor-owned machine components to DOE by December 1, 2019 or as mutually agreed by the parties.


Contract No: 89303519CNE000005
Modification P00014
Page 11 of #NUM_PAGES#
b)Initiate delivery of sub-assemblies for 16 AC100M machines to DOE leased facilities in Piketon, Ohio by December 31, 2020.
MILESTONE 7 - Complete reconstitution of HALEU Balance of Plant (BOP) and cascade infrastructure (e.g., utilities, controls, service module) by November 1, 2021.
MILESTONE 8 – Assemble and dry 16 AC100M machines for the HALEU cascade by November
1, 2021.
MILESTONE 9 - Install 16 AC100M machines for the HALEU cascade All systems except Mass Spectrometer, Distributed Control System and Fissile Material Storage Area ready for operations by December 1, 2021 March 31, 2022.
MILESTONE 10 - Complete operational readiness for operation of the HALEU Cascade on UF6 gas by March 1, 2022. Staff qualified for operations by April 30, 2022.
MILESTONE 11 - Obtain an NRC license revision for the Combined License (COL) to support production of 19.75% U235 by March 1, 2022.
MILESTONE 12 - Initiate operation of the HALEU 16 AC100M machine cascade by March 1, 2022.
MILESTONE 13 Operate the HALEU Cascade on UF6 and produce a nominal 19.75% ± 0.24% U235 Pinch Tube or P-10 sample(s) by March 15, 2022.
MILESTONE 14 –Operate the HALEU Cascade to produce a minimum of 200 Kg UF6 HALEU and up to 600 Kg UF6 of HALEU by June 1, 2022.”
B. Section C, Program Scope, is deleted in its entirety and replaced with the following:
Program Scope
The Program will support the following major areas of activity and any other necessary activities to complete the Objectives and Milestones described in Section C.1.1:
Engineering/Procurement/Construction (EPC) of the HALEU Cascade
Manufacturing of the AC100M Components and Subassemblies
Plant Support and Cascade Startup/Operations
Regulatory Support
HALEU Program Management
Nuclear Safety Support
Each major activity area is described separately as follows:


Contract No: 89303519CNE000005
Modification P00014
Page 12 of #NUM_PAGES#
C.1 Engineering/Procurement/Construction (EPC) of the HALEU Cascade
EPC activities will include all the engineering, procurement and construction associated with reconstituting the Balance of Plant (BOP) and cascade components and systems to support the HALEU Cascade at Piketon, Ohio, including the vacuum, air, chilled water, and electrical systems and associated instrumentation and controls; the emergency power system; the distributed control system; the feed and withdrawal modules; the mass spectrometer, and the service module. Included also, are CTTF refurbishment; vent monitoring and centrifuge conditioning systems; and physical security modifications. Construction commissioning and Integrated System Test support is included. Also included is Program management of the EPC activities. Additional activities to be performed include:
Complete punch list items found during integrated systems testing
Complete the demobilization of work crews associated with HALEU systems construction/installation
Complete modification process to the point of systems turnover to operations IAW ACD2-EG-
003, Nuclear & Commercial Modification Controls
C.2 Manufacturing (AC100M Components and Subassemblies)
Manufacturing activities will include all associated procurement and manufacturing of machine parts, components and subassemblies of the AC100M machines for the HALEU cascade, including the machine controls, upper and lower suspension, column, casing, and rotors (including balancing). Transportation of the manufactured items to Piketon, Ohio is included as well as program management of the Manufacturing activities.
C.3 Plant Support and Cascade Startup/Operations
Plant Support activities include all preparation of the facility for installation of the HALEU 16machine cascade, assembly and drying of the AC100M centrifuges, and installation and tie-ins of the machines to complete the HALEU cascade configuration. Cascade Startup/Operation activities include the Internal Readiness Review, and the Operational Readiness Review. cascade startup and operation (including maintenance), and production of the nominal 19.75% U235 sample, a minimum of 200 Kg UF6 HALEU and up to 600 Kg UF6 HALEU. Maintain and operate Balance of Plant (BOP) facilities. Also included is program management of the activities. Additional activities include: •      Assist engineering with integrated systems testing and final modification items for turnover
Modify procedures for operation of the cascade
Develop/modify training and qualification materials for the qualification of minimum staffing for cascade operations
Implement maintenance program for upkeep of turned over systems and begin maintenance schedule in accordance with recommended maintenance intervals determined by engineering
Implement surveillance program for upkeep of IROFS and begin surveillance schedule in accordance with periodicity intervals determined by engineering.
Centrifuges will remain in the drying station for the remainder of the Contract.


Contract No: 89303519CNE000005
Modification P00014
Page 13 of #NUM_PAGES#
C.4 Regulatory Support
Regulatory Support activities include NRC licensing, safeguards and security, and permitting. Also included is program management of the activities. Activities to be continued include:
Complete licensing actions to support systems Ready for Operations (except Mass Spectrometer, Distributed Control System and FMSA).
Perform necessary licensing work to upkeep both the Lead Cascade License and Commercial Plant License and all license driven programs, procedures, and processes.
C.5 HALEU Program Management
Program Management will provide overall project direction of all activities and participants and management of the project including establishing a project Work Breakdown Structure (WBS) and baseline against which, performance will be measured using an earned value management system. The Contractor shall develop and provide a WBS that aligns with Contractor activities sequencing and execution of the HALEU Demonstration Program. Also, the Contractor shall develop and provide an integrated logic driven critical path schedule reflecting the WBS and which identifies contract milestones and deliverables. Formal status reports and meetings will be provided and held monthly with DOE to report and discuss schedule progress, milestone performance, cost performance, any variances, any concerns, and to identify action items. The Contractor will develop an agenda for these meetings and submit it to DOE at least seven (7) calendar days prior to the meeting. The formal status report is to be submitted at least three (3) business days prior to the meeting. The meeting date and the location will be mutually agreed upon between the Contractor and DOE. In addition, reports will be prepared and submitted to DOE to provide evidence of completion of project milestones. In addition, a weekly highlights report shall be provided electronically. Ad hoc meetings or conversations with DOE outside any formal meetings are to be utilized in a timely manner to identify and address any potential problems and concerns. Program Management will conduct activities that reduce overall risk to the program and assure a robust quality assurance program is implemented across the program.
C.6 Nuclear Safety Support
The Nuclear Safety Support involves the work related to the restoration of Piketon nuclear safety/nuclear criticality safety programs and processes. This includes the revision of parts of the Integrated Safety Analysis Summary (ISA) and Addendum 1, ISA supporting documentation, and nuclear criticality safety analysis and associated documentation. Also included is program management of the activities. Additional activities include:
Complete Implementation of Nuclear Safety IROFS associated with ISAS and NCSEs to support systems Ready for Operations (except Mass Spectrometer, Distributed Control System and FMSA) and Staff Qualified for Operations.
Complete documentation closeout activities associated with passive, active, and administrative
IROFS flowdown
Perform license driven NCS and ISA functions


Contract No: 89303519CNE000005
Modification P00014
Page 14 of #NUM_PAGES#
American Centrifuge Operating, LLC (ACO) utilizes a fully integrated Earned Value Management System (EVMS) in the execution of capital projects. ANSI/EIA-748-B Earned Value Management Systems and the GAO Cost Estimating and Assessment Guide serve as the basis for the ACO EVM System. The system includes: Primavera P6 as the scheduling platform, Project Management Cost Processor (PMCP) as the cost processing, reporting and change control platform, Primavera Risk as the probabilistic risk analysis platform, and Oracle as the corporate financial system.
Major components of the system include:
Integrated scope, cost and schedule Performance Measurement Baselines (PMB)
Critical Path Methodology (CPM) used in evaluating schedule performance
Probabilistic Risk Assessment (PRA) used in calculating project risks
Formal change control process for both baselines and forecasts
Monthly re-forecasting of project TEC and schedule
The EVM System and Project Controls are implemented and controlled at the corporate level of ACO and Centrus Energy Corp. ensuring continuity and consistency of its application across all projects in the Contractor’s project portfolio.”
C.Clause F.1 is deleted in its entirety and replaced with the following:
“F.1 DOE-F-1001 Delivery Schedule
The Government requires delivery to be made according to the following schedule:


Contract No: 89303519CNE000005
Modification P00014
Page 15 of #NUM_PAGES#
MILESTONE
Title
Date
00001Rescind the NRC Lead Cascade License Amendment
July 1, 2019
00002Reestablish Site Services to support the HALEU Program at Piketon
January 1. 2020
00003aAward Sub-Contract to Procure Machine Casings
October 31, 2019
00003bReceive all Machine Casings
September 1, 2020
00004
Reestablish the Vendor Supply Chain to Support the
HALEU Program
June 1, 2020
00005a,b,c,dReconstitute the Security Program for the Piketon Facilities
November 1, 2020
00006aTransfer Title of Contractor-Owned Machine Components to DOE
December 1, 2019 or mutually agreed upon date
00006bInitiate delivery of AC100M Subassemblies to Piketon
December 31, 2020
00007Complete Reconstitution of HALEU BOP and Cascade Infrastructure
November 1, 2021
00008Assemble and Dry 16 AC100M Machines
November 1, 2021
00009
Install 16 AC100M Machine in the HALEU Cascade All systems except mass spectrometer, Distributed Control System and Fissile Material Storage Area ready for operations.
December 1, 2021 March 31, 2022
00010
Complete Operational Readiness for the HALEU Cascade
Staff qualified for operations
March 1,2022 April 30, 2022
00011
Obtain NRC License Revision for COL
March 1, 2022
00012
Initiate Operation of the HALEU Cascade
March 1, 2022
00013
Operate the HALEU Cascade and Produce 19.75% Sample
By March 15, 2022
00014
Operate the HALEU Cascade and Produce a minimum of 200 Kg of UF6 HALEU and up to 600 Kg UF6 HALEU.
By June 1, 2022”
D.In accordance with Section H Clause, DOE-H-2061 Change Order Accounting (OCT 2014), DOE requires separate accounting for the incurred costs for this effort.
E.This modification will be definitized before May 22, 2022. If agreement on a definitive modification is not reached by the target date, or within any extension of it granted by the Contracting Officer, the Contracting Officer may, with the approval of the Head of Contracting Activity, determine a reasonable price or fee in accordance with Subpart 15.4 and Part 31 of the FAR, subject to Contractor appeal as provided in the Disputes clause.
The following definitization schedule applies:
    
    Action                         Date


Contract No: 89303519CNE000005 Modification P00014
Page 11 of 11
    Contractor proposal received               January 3, 2022
    Commence negotiations               April 1, 2022 Complete negotiations               May 2, 2022
Certificate of current cost or pricing May 4, 2022 data received
    Execute modification                    May 20, 2022