XML 36 R17.htm IDEA: XBRL DOCUMENT v3.3.1.900
Commitments and Contingencies
12 Months Ended
Dec. 31, 2015
Commitments and Contingencies [Abstract]  
Commitments and Contingencies

10.COMMITMENTS AND CONTINGENCIES 

COMMITMENTS 

Leases 

The Company leases certain facilities and certain equipment under non-cancelable operating leases for periods ranging from one to 45 years, with renewal options for certain leases.  The Company’s total rent expense under operating leases during the years ended December 31, 2015, 2014 and 2013, was $26,858,  $27,466 and $30,893, respectively. 

As of December 31, 2015, future minimum lease payments, by calendar year, are as follows: 

 

 

 

2016

$

16,416 

2017

 

14,100 

2018

 

10,967 

2019

 

9,080 

2020

 

7,903 

Thereafter

 

50,478 

 

$

108,944 

 

Financial Surety Bonds 

The Company uses financial surety bonds for a variety of corporate guarantees.  The two largest uses of financial surety bonds are for municipal contract performance guarantees and asset closure and retirement requirements under certain environmental regulations.  Environmental regulations require demonstrated financial assurance to meet final capping, closure and post-closure requirements for landfills.  In addition to surety bonds, these requirements may also be met through alternative financial assurance instruments, including insurance, letters of credit and restricted asset deposits. 

At December 31, 2015 and 2014, the Company had provided customers and various regulatory authorities with surety bonds in the aggregate amount of approximately $353,828 and $342,591, respectively, to secure its asset closure and retirement requirements and $121,687 and $94,385, respectively, to secure performance under collection contracts and landfill operating agreements. 

The Company owns a 9.9% interest in a company that, among other activities, issues financial surety bonds to secure landfill final capping, closure and post-closure obligations for companies operating in the solid waste industry.  The Company accounts for this investment under the cost method of accounting.  There have been no identified events or changes in circumstances that may have a significant adverse effect on the carrying value of the investment.  This investee company and the parent company of the investee have written financial surety bonds for the Company, of which $185,753 and $179,204 were outstanding as of December 31, 2015 and 2014, respectively.  The Company’s reimbursement obligations under these bonds are secured by a pledge of its stock in the investee company. 

Unconditional Purchase Obligations

At December 31, 2015, the Company’s unconditional purchase obligations consist of multiple fixed-price fuel purchase contracts under which it has 19.1 million gallons remaining to be purchased for a total of $50,198.  These fuel purchase contracts expire on or before December 31, 2017.

As of December 31, 2015, future minimum purchase commitments, by calendar year, are as follows: 

 

 

 

2016

$

33,242 

2017

 

16,956 

 

$

50,198 

 

CONTINGENCIES 

Environmental Risks

The Company expenses costs incurred to investigate and remediate environmental issues unless they extend the economic useful lives of the related assets.  The Company records liabilities when it is probable that an obligation has been incurred and the amounts can be reasonably estimated.  The remediation reserves cover anticipated costs, including remediation of environmental damage that waste facilities may have caused to neighboring landowners or residents as a result of contamination of soil, groundwater or surface water, including damage resulting from conditions existing prior to the Company’s acquisition of such facilities.  The Company’s estimates are based primarily on investigations and remediation plans established by independent consultants, regulatory agencies and potentially responsible third parties.  The Company does not discount remediation obligations.  At December 31, 2015 and 2014, the current portion of remediation reserves was $2,328 and $3,023, respectively, which is included in Accrued liabilities in the Consolidated Balance Sheets.  At December 31, 2015 and 2014, the long-term portion of remediation reserves was $12,049 and $725, respectively, which is included in Other long-term liabilities in the Consolidated Balance Sheets.  The 2015 long-term remediation reserve amount includes $11,301 of remediation reserves which the Company established after assuming certain remedial liabilities in the Rock River acquisition during the year ending December 31, 2015.  Any substantial increase in the liabilities for remediation of environmental damage incurred by the Company could have a material adverse effect on the Company’s financial condition, results of operations or cash flows. 

Legal Proceedings

In the normal course of its business and as a result of the extensive governmental regulation of the solid waste and E&P waste industries, the Company is subject to various judicial and administrative proceedings involving federal, state or local agencies.  In these proceedings, an agency may seek to impose fines on the Company or to revoke or deny renewal of an authorization held by the Company, including an operating permit.  From time to time, the Company may also be subject to actions brought by special interest or other groups, adjacent landowners or residents in connection with the permitting and licensing of landfills, transfer stations, and E&P waste treatment, recovery and disposal operations, or alleging environmental damage or violations of the permits and licenses pursuant to which the Company operates. 

In addition, the Company is a party to various claims and suits pending for alleged damages to persons and property, alleged violations of certain laws and alleged liabilities arising out of matters occurring during the normal operation of the waste management business.  Except as noted in the matters described below, as of December 31, 2015, there is no current proceeding or litigation involving the Company or its property that the Company believes could have a material adverse impact on its business, financial condition, results of operations or cash flows.

Madera County, California Materials Recovery Facility Contract Litigation

The Company’s subsidiary, Madera Disposal Systems, Inc. (“MDSI”) was named in a complaint captioned County of Madera vs. Madera Disposal Systems, Inc., et al, filed in Madera County Superior Court (Case No. MCV 059402) on March 5, 2012, and subsequently transferred to Fresno County Superior Court.  Madera County (the “County”) alleged in the complaint that from 2007 through 2010, MDSI breached a contract with the County for the operation of a materials recovery facility by withholding profits from facility operations in excess of those authorized by the contract.  The County further alleged that the breach gave the County the unilateral right to terminate all of its contracts with MDSI, including contracts for (1) the collection of residential and commercial waste in the unincorporated parts of the County, (2) operation of the materials recovery facility, (3) operation of the North Fork Transfer Station and (4) operation of the Fairmead Landfill.  MDSI answered the complaint and asserted a claim against the County for wrongful termination of the contracts.  On October 31, 2012, MDSI ceased providing services and vacated the County premises.  In 2015 the County amended its complaint to add a claim for breach of the covenant of good faith and fair dealing and to amend its damage claim to cover the period from January 1, 2008 through November 1, 2012.  The County sought monetary damages of $2,962 from MDSI, plus pre-judgment interest at 10% per annum.

The case was settled through mediation in January 2016.  The settlement resolves all claims between the parties amicably without any admission of liability, includes full mutual releases of claims between the parties and deems the contracts between the MDSI and the County to have terminated by mutual agreement effective November 1, 2012.  The Company also agreed to make an immaterial payment to the County that the Company estimates to be less than the cost of trial.

Lower Duwamish Waterway Superfund Site Allocation Process

The Company’s subsidiary, Northwest Container Services, Inc. (“NWCS”), has been named by the U.S. Environmental Protection Agency, Region 10 (the “EPA”), along with more than 100 others, as a potentially responsible party (“PRP”) under the Comprehensive Environmental Response, Compensation and Liability Act (also known as CERCLA or the “Superfund” law) with respect to the Lower Duwamish Waterway Superfund Site (the “LDW Site”).  Listed on the National Priorities List in 2001, the LDW Site is a five-mile stretch of the Duwamish River flowing into Elliott Bay in Seattle, Washington.  A group of PRPs known as the Lower Duwamish Working Group or the “LDWG” and consisting of the City of Seattle, King County, the Port of Seattle, and Boeing Company conducted a Remedial Investigation/Feasibility Study for the LDW Site.  On December 2, 2014, the EPA issued its Record of Decision (“ROD”) describing the selected clean-up remedy, and therein estimated that clean-up costs (in present value dollars as of November 2014) would total about $342,000.  However, it is possible that additional costs could be incurred based upon various factors. The EPA estimates that it will take seven years to implement the clean-up. The ROD also requires ten years of monitoring following the clean-up, and provides that if clean-up goals have not been met by the end of this period, then additional clean-up activities, at additional cost, may be required at that time.  Implementation of the clean-up will not begin until after the ongoing Early Action Area (“EAA”) clean-ups have been completed.  While three of the EAA clean-ups have been completed to date, some work remains to be done on three other EAAs.  The EPA estimates that one of these three will be completed in mid-2016; for the other two, work remains to be done and the EPA has not estimated the dates of completion.  Implementation of the clean-up also must await additional baseline sampling throughout the LDW Site and the preparation of a remedial design for performing the clean-up.

On September 30, 2015, the EPA formally initiated negotiations with the LDWG to amend the LDWG’s existing Administrative Order on Consent with the EPA (the “LDWG AOC”) a third time to require the LDWG to perform the additional baseline sediment sampling and certain technical studies needed to prepare the actual remedial design.  The EPA calls this work “Phase 1 of the Remedial Design,” and the EPA’s proposed statement of work for it indicates that it will take at least two years to complete, or into early 2018.  The EPA and the LDWG are reportedly negotiating this third amendment to the LDWG AOC.  The EPA also has indicated that once the work under the third amendment to the LDWG AOC is complete, it plans to negotiate with all of the PRPs a “global settlement” to cover performance of the remainder of the remedial design not covered by the proposed amendment to the LDWG AOC and the clean-up itself. There is no assurance, however, that a global settlement will be reached.

In August 2014, NWCS entered into an Alternative Dispute Resolution Memorandum of Agreement with several dozen other PRPs and a neutral allocator to conduct a confidential and non-binding allocation of certain past response costs allegedly incurred at the LDW Site as well as the anticipated future response costs associated with the clean-up.  The allocation process is designed to develop evidence relating to each PRP’s nexus, if any, to the LDW Site (whether or not that PRP is participating in the allocation process), for the allocator to hear arguments as to how each PRP’s nexus affects the allocation of response costs, and to determine each PRP’s share of the past and future response costs.  The goal of the allocation process is to reach agreement on a division of responsibility between and amongst the PRPs so that the PRPs then will be in a position to negotiate a global settlement with the EPA.  NWCS is defending itself vigorously in this confidential allocation process.  At this point the Company is not able to determine the likelihood of the allocation process being completed as intended by the participating PRPs nor the likelihood of the parties then negotiating a global settlement with the EPA, and thus cannot determine the likelihood of any outcome in this matter.

Chiquita Canyon Landfill Expansion Complaint

The Company’s subsidiary, Chiquita Canyon, LLC (“CCL”), is in the process of seeking approval to expand the lateral footprint and vertical height of its Chiquita Canyon Landfill in California.  In response to its published draft environmental impact report (“EIR”) regarding the proposed expansion, on June 8, 2015 two individuals and two organizations filed an administrative complaint with the California Environmental Protection Agency, the California Department of Resources Recycling and Recovery and the California Air Resources Board against the County of Los Angeles, alleging that the county has committed racial discrimination under California law through its permitting policies and practices. Among other things, the complaint alleges that the County of Los Angeles failed to provide equal opportunities for residents of all races to participate in the draft EIR process.  The complaint seeks, among other things, a suspension of the draft EIR process, the institution of hearings regarding the draft EIR that follow specified procedures and the implementation of certain surveys, notices and other hearings.  CCL is not a party to this complaint, although CCL may participate in any hearing on the complaint if the agencies elect to schedule such a hearing.  At this point the Company is not able to determine the likelihood of any outcome in this matter, including whether it may result in a delay of the permitting process for the proposed expansion of CCL’s facility.

Collective Bargaining Agreements 

Eleven of the Company’s collective bargaining agreements have expired or are set to expire in 2016.  The Company does not expect any significant disruption in its overall business in 2016 as a result of labor negotiations, employee strikes or organizational efforts.