XML 34 R19.htm IDEA: XBRL DOCUMENT v2.4.0.6
SETTLEMENT LOSSES
12 Months Ended
Dec. 31, 2011
Settlement Losses [Abstract]  
SETTLEMENT LOSSES
On August 4, 2010, the Company was served with a complaint by Daniel Caravette, alleging the Company breached the parties’ settlement agreement dated April 24, 2008 and seeking damages in excess of $75,000.  The was tried in September of 2010 before the Circuit Court of the Nineteenth Judicial District, Lake County, Illinois. The Court awarded a final judgment in favor of Mr. Caravette in the amount of $47,140 plus approximately $31,000 in attorneys’ fees and costs.  As of December 31, 2010, the Company accrued $78,140 as a settlement amount pending appeal of the court’s decision.  During February, 2011 the court ordered the Company to post an irrevocable letter of credit in the amount of $125,000 as security towards the eventual affirmation or dismissal of the appeal.  In addition to the accrual of $78,140, the Company accrued an additional $46,860 settlement loss to encompass the irrevocable letter of credit.  On September 29, 2011, the Appellate Court ruled in favor of Mr. Caravette.  On October 27, 2011, the Company made payment of $97,500 as full and final payment for the judgment, interest thereon and attorneys’ fees.  As a result, the Company realized a settlement gain of $27,500, the difference between the final settlement of $97,500 and the $125,000 letter of credit.

During March 2011, the Company reached a settlement with a vendor regarding the costs associated with the purchase and installation of certain equipment.  This settlement of accrued invoices resulted in the recognition of a settlement gain by the Company in the amount of $34,400.

On April 13, 2011, the Company settled with a vendor relating to accrued and unpaid costs for previously utilized outside storage space.  The Company realized a settlement gain of $448.

On or about December 12, 2011, the Company was served with a complaint by LIBCO Industries, Inc., alleging the Company breached a construction contract and tortuously interfered with a business relationship, and is seeking damages in excess of $185,000.  Management believes that the allegations are frivolous and wholly without merit and will vigorously defend the claim.  Related to this matter, Process Piping, LLC, a sub-contractor for LIBCO Industries, filed a Mechanics Lien on the property leased by the Company, claiming it was owed in excess of $95,000 by LIBCO Industries.  On March 6, 2012, the Company paid $62,500 to Process Piping, LLC in exchange for a release of its lien as well as an assignment of all of its claims against LIBCO Industries.  The outcome of this matter is unknown as of the report date.  As of December 31, 2011, the Company accrued as a settlement loss, the $62,500 paid to Process Piping, LLC.