XML 51 R41.htm IDEA: XBRL DOCUMENT v3.10.0.1
Commitments and Contingencies (Details)
$ in Millions
6 Months Ended 10 Months Ended 17 Months Ended 22 Months Ended 28 Months Ended
Jun. 30, 2018
USD ($)
bbl / d
renewal
MBbls
Jun. 30, 2017
USD ($)
Jun. 30, 2018
USD ($)
bbl / d
renewal
MBbls
Jun. 30, 2019
USD ($)
Jun. 30, 2019
USD ($)
Jan. 01, 2020
USD ($)
Dec. 31, 2017
USD ($)
Commitments and Contingencies (Textual)              
MVP Terminal construction costs $ 41,266   $ 41,266       $ 40,010
Contributions to MVP 119 $ 222          
Cost of undivided interest in pipeline $ 145 $ 72          
Terminalling Agreement [Member] | MVP Terminalling, LLC (MVP) [Member]              
Commitments and Contingencies (Textual)              
Initial term of terminal agreement 12 years            
Number of available automatic renewals | renewal 2   2        
Automatic renewal term of terminalling agreement 5 years            
MVP Terminal [Member]              
Commitments and Contingencies (Textual)              
Contributions to MVP $ 104   $ 185        
MVP Terminal [Member] | Expected [Member]              
Commitments and Contingencies (Textual)              
Contributions to MVP           $ 420  
MVP Terminal [Member] | Magellan Midstream Partners LP (Magellan) [Member]              
Commitments and Contingencies (Textual)              
Long-term liability recorded 186   186        
MVP Terminal [Member] | Construction in Progress [Member]              
Commitments and Contingencies (Textual)              
MVP Terminal construction costs $ 370   $ 370        
MVP Terminal [Member] | Minimum [Member] | Construction in Progress [Member] | Expected [Member]              
Commitments and Contingencies (Textual)              
MVP Terminal construction costs           840  
MVP Terminal [Member] | Maximum [Member] | Construction in Progress [Member] | Expected [Member]              
Commitments and Contingencies (Textual)              
MVP Terminal construction costs           $ 1,400  
Central Texas Pipeline [Member]              
Commitments and Contingencies (Textual)              
Undivided interest in project (percent) 40.00%   40.00%        
Pipeline capacity (in barrels per day) | bbl / d 150,000   150,000        
Cost of undivided interest in pipeline $ 42   $ 49        
Central Texas Pipeline [Member] | Expected [Member]              
Commitments and Contingencies (Textual)              
Cost of undivided interest in pipeline         $ 170    
Sunrise Pipeline System [Member]              
Commitments and Contingencies (Textual)              
Undivided interest in project (percent) 20.00%   20.00%        
Pipeline capacity (in barrels per day) | bbl / d 500,000   500,000        
Cost of undivided interest in pipeline $ 103            
Sunrise Pipeline System [Member] | Expected [Member]              
Commitments and Contingencies (Textual)              
Cost of undivided interest in pipeline       $ 135      
Colorado City Storage Tanks [Member]              
Commitments and Contingencies (Textual)              
Approximate storage capacity of terminal (in thousands of barrels) | MBbls 270   270        
MVP Terminalling, LLC (MVP) [Member]              
Commitments and Contingencies (Textual)              
Membership percentage in VIE (percent)     50.00%