XML 115 R91.htm IDEA: XBRL DOCUMENT v3.23.2
SAN ONOFRE NUCLEAR GENERATING STATION - NARRATIVE (Details) - San Diego Gas and Electric Company - USD ($)
$ in Millions
6 Months Ended
Jun. 30, 2023
Dec. 31, 2022
Jointly Owned Nuclear Power Plant    
Jointly Owned Utility Plant Interests [Line Items]    
Jointly owned utility plant, proportionate ownership share (as a percent) 20.00%  
Anticipated term of dismantlement work 10 years  
Percent of dismantlement work expense (as a percent) 20.00%  
ARO related to decommissioning costs $ 523  
SONGS 2 and 3 Decommissioning    
Jointly Owned Utility Plant Interests [Line Items]    
Nuclear decommissioning trust authorized withdrawal amount   $ 81