XML 47 R40.htm IDEA: XBRL DOCUMENT  v2.3.0.11
SEMPRA UTILITIES' REGULATORY MATTERS (Details) (USD $)
3 Months Ended
Jun. 30, 2011
Jun. 30, 2010
Mar. 31, 2010
San Diego Gas and Electric Company and Subsidiary [Member] | Wind Farm Project [Member]
     
Schedule Of Utility Projects [Line Items]      
Estimated Project Cost, Maximum $ 250,000,000    
Investment As Percentage Of Total Estimated Project Cost 64.99%    
San Diego Gas and Electric Company and Subsidiary [Member]
     
Schedule Of Regulatory Amounts [Line Items]      
Renewable Portfolio Standards, Penalty Per Kilowatt Hour Of Renewable Energy Underdelivery 0.05    
General Rate Case, Annual Revenue Requirement Increase 231,000,000    
Unrecorded Energy Efficiency Incentive Mechanism Award 15,100,000    
Regulatory Recovery, Deductible Per Event 5,000,000    
Incremental insurance costs incurred related to catastrophe for 2009-2010 policy period 29,000,000    
Incremental insurance costs incurred related to catastrophe for 2010-2011 policy period 63,000,000    
General Rate Case, Decrease In Revenue Requirement Increase Request 22,000,000    
Southern California Gas Company [Member]
     
Schedule Of Regulatory Amounts [Line Items]      
General Rate Case, Annual Revenue Requirement Increase 263,000,000    
Unrecorded Gas Cost Incentive Mechanism Award 6,200,000 6,000,000  
Recognized Energy Efficiency Incentive Mechanism Award     12,000,000
Unrecorded Energy Efficiency Incentive Mechanism Award 2,000,000    
General Rate Case, Decrease In Revenue Requirement Increase Request $ 17,000,000