XML 17 R9.htm IDEA: XBRL DOCUMENT v2.4.0.6
Vessel Acquisitions and Dispositions
3 Months Ended
Mar. 31, 2012
Vessel Acquisitions and Dispositions [Abstract]  
Vessel Acquisitions and Dispositions

(2) VESSEL ACQUISITIONS AND DISPOSITIONS

As of May 3, 2012, we have one vessel that is being held for sale that is not included in our fleet numbers. We have assessed the value of the vessel during this quarter and at this time we believe that it is recorded at fair value. However, we will continue to assess the value on a quarterly basis and make the proper adjustment, if needed.

Interest is capitalized in connection with the construction of vessels. During the three month period ended March 31, 2012, we capitalized $0.7 million of interest. We did not capitalize any interest during the three month period ended March 31, 2011.

In January 2012, we purchased a vessel for operation in the Americas region for a total price of $22.5 million, and we sold one of our Americas vessels and recorded a gain of $1.2 million. In May 2012, we sold two of our Americas vessels and recorded a combined gain of approximately $4.2 million.

In the third quarter of 2011, our Board of Directors approved the initiation of a new-build construction program. We began the program in the North Sea region where we contracted with three shipyards to build a total of six new platform supply vessels. The estimated total cost of these initial six vessels is $245.0 million. In addition, in late 2011, we exercised an option with one of the shipyards to build an additional vessel at an estimated cost of $60.9 million. The first of these vessels is scheduled to be delivered in the second quarter of 2013 and the last is scheduled to be delivered in the first quarter of 2014.

 

In May 2012, we entered into a letter of agreement with a shipyard to negotiate a contract to build two U.S. flagged platform supply vessels for the U.S. Gulf of Mexico. The vessels will be 270 foot, dynamic positioning (“DP2”) capability, fire fighting certified, multi-service platform supply vessels. The estimated total cost of these two vessels is approximately $73.0 million with expected deliveries in the second and third quarters of 2013.

The following tables illustrate the details of the vessels under construction, the vessels acquired, the vessels disposed of and the vessels classified as held for sale as indicated.

 

                                                         

Construction Yard

  Region     Type(1)     Expected
Delivery
    Length
(feet)
    BHP(2)     DWT(3)     Expected
Cost
 
                                        (millions)  

Remontowa

    North Sea       LgPSV       Q2 2013       291       9120       5100     $ 41.0  

Remontowa

    North Sea       LgPSV       Q3 2013       291       9120       5100     $ 41.1  

Remontowa

    North Sea       LgPSV       Q3 2013       260       9120       4000     $ 37.7  

Rosetti Marino

    North Sea       LgPSV       Q4 2013       246       7483       3000     $ 32.1  

Rosetti Marino

    North Sea       LgPSV       Q1 2014       246       7483       3000     $ 32.1  

Simek

    North Sea       LgPSV       Q2 2013       304       11265       4700     $ 60.9  

Simek

    North Sea       LgPSV       Q4 2013       304       11265       4700     $ 60.9  

 

(1)

LgPSV—Large Platform Supply Vessel

PSV—Platform Supply Vessel

SpV—Specialty Vessel

Crew—Crewboat

(2) 

BHP—Breakhorse Power

(3) 

DWT—Deadweight Tons

                                                         

Vessels Acquired Since December 31, 2011

 

Vessel

  Region     Type(1)     Year     Length     BHP(2)     DWT(3)     Cost  
      Built     (feet)        
                                        (in millions)  

Thomas Wainwright

    Americas       PSV       2010       242       4,200       2,700     $ 22.5  

 

                                                         

Vessels Disposed of Since December 31, 2011

 

Vessel

  Region     Type(1)     Year     Length     BHP(2)     DWT(3)     Month  
      Built     (feet)         Disposed  

Bluefin

    Americas       Crew       2008       165       7,200       337       Jan-12  

Sailfish

    Americas       Crew       2007       176       7,200       307       May-12  

Swordfish

    Americas       Crew       2009       176       7,200       307       May-12  

 

                                                 

Vessels Held for Sale (Laid Up)

 

Vessel

  Region     Type(1)     Year     Length     BHP(2)     DWT(3)  
      Built     (feet)      

Clwyd Supporter

    N. Sea       SpV       1984       266       10,700       1,350