6-K 1 drd_activities.htm Page 1
background image
SECURITIES AND EXCHANGE COMMISSION
Washington, D.C. 20549
______________________
FORM 6-K
REPORT OF A FOREIGN PRIVATE ISSUER
PURSUANT TO RULE 13a-16 OR 15d-16
UNDER THE SECURITIES EXCHANGE ACT OF 1934
For August 2006
Commission File Number 0-28800
______________________
DRDGOLD Limited
EBSCO House 4
299 Pendoring Avenue
Blackheath
Randburg, South Africa, 2195
(Address of principal executive offices)
______________________
Indicate by check mark whether the registrant files or will file annual reports under cover of Form
20-F or Form 40-F.
Form 20-F
Form 40-F _
Indicate by check mark whether the registrant by furnishing the information contained in this Form
is also thereby furnishing the information to the Commission pursuant to Rule 12g3-2(b) under the
Securities Exchange Act of 1934.
Yes _          No
If ''Yes'' is marked, indicate below the file number assigned to the registrant in connection with Rule
12g3-2(b): N/A
background image
Attached to the Registrant Form 6-K filing for the month of August 2006, incorporated
by reference herein:
Exhibit
99.1
Release dated August 24, 2006, entitled “REPORT ON ACTIVITIES FOR THE FOURTH
QUARTER ENDED 30 JUNE 2006 ”
background image
SIGNATURES
Pursuant to the requirements of the Securities Exchange Act of 1934, the registrant has duly caused
this report to be signed on its behalf by the undersigned, thereunto duly authorized.
DRDGOLD LIMITED
Date: August 24, 2006
By: /s/ Themba Gwebu
Name: Themba Gwebu
Title: Company Secretary
background image
Report on activities for the fourth quarter ended
30 June 2006
(Incorporated in the Republic of South Africa) Registration No.1895/000926/06
ARBN 086 277616 JSE trading symbol: DRD ISIN Code: ZAE 000058723
Issuer code: DUSM NASDAQ trading symbol: DROOY
( DRDGOLD or the company )
KEY FEATURES
KEY RESULTS SUMMARY
Group
Quarter
30 Jun 2006
Quarter
31 Mar 2006
%
Change
12 months to
30 Jun 2006
12 months to
30 Jun 2005
Attributable gold production *
Australasian operations
oz
41 676
42 979
(3)
211 425
317 134
kg
1 296
1 337
(3)
6 578
9 864
South African operations
oz
90 181
86 678
4
315 976
251 902
kg
2 805
2 696
4
9 828
7 835
Discontinued operations
oz                                             -                        -                        -                        -
199 850
kg                                             -                        -                        -                        -
6 216
Group
oz
131 857
129 657
2
527 401
768 886
kg
4 101
4 033
2
16 406
23 915
Cash operating costs
Australasian operations
US$ per oz
329
514
36
362
231
ZAR per kg
68 758
102 217
33
74 775
46 289
South African operations
US$ per oz
507
511
1
480
439
ZAR per kg
105 117
103 519
(2)
99 301
87 895
Discontinued operations
US$ per oz                                -                        -                        -                        -
508
ZAR per kg                                -                        -                        -                        -
101 701
Group
US$ per oz
452
512
12
433
372
ZAR per kg
93 627
103 136
9
89 475
74 404
Capital expenditure (net)
US$ million
13.7
5.4
(154)
36.6
24.9
ZAR million
87.9
32.8
(168)
235.1
154.8
* Attributable Emperor Mines Limited ("Emperor") consolidated 100% from 6 April 2006 (previously 39.52% attributable) and Crown Gold Recoveries (Pty)
Limited ("CGR") consolidated 100% from 1 December 2005 (previously 40% attributable)
Group Results
· Total attributable gold production for the quarter steady at 131 857oz
· 4% improvement from SA operations for the quarter; 25% for the year
· Porgera production for the quarter up 11%; west wall remediation now 60% complete
· 35% increase in attributable reserves to 8.8 million ounces
· New Boards for Emperor and DRDGOLD SA
· Emperor transaction closed
· DRDGOLD holds 78.9% of new Emperor
· Group cash operating costs down to US$452/oz (R93 627/kg)
DRDGOLD LIMITED
2006 FINANCIAL YEAR
background image
2
STOCK
Issued capital
320 035 078 ordinary no par value shares
5 000 000 cumulative preference shares
Total ordinary no par value shares issued and committed:
     352 210 334
Stock traded
JSE
NASDAQ
FRANKFURT
Average volume for the 3 months per day ('000)
471
4 900
91
% of issued stock traded (annualised)
38
400
7
Price
·High
R11.70
US$1.98
Euro 1.47
·Low
R7.71
US$1.11
Euro 0.92
·Close
R10.00
US$1.37
Euro 1.09
OVERVIEW
Dear shareholder
Safety
I am sad to report that two employees died in mine-related accidents,
both at ERPM, in the quarter ended 30 June 2006. Phalali Silase, a team
leader, died in a seismically related rockfall on 4 April and Matjoesa
Samuel, a stope team member, in a similar incident on 27 June. Seven
fatalities for the year as a whole compares with 10 in the previous year.
Two of the seven occurred at Empero s Vatukoula operation in Fiji,
while the balance was in the South African operations of DRDGOLD. In
the previous year, all 10 fatalities occurred in the operations of
DRDGOLD in South Africa.
While the Fatality Frequency Rate for the year within DRDGOLD South
African Operations (Pty) Limited ("DRDGOLD SA") showed a slight
improvement from 0.25 per million man hours to 0.22, the Lost Time
Injury Frequency Rate ("LTIFR") deteriorated from 9.55 to 10.81 and the
Reportable Injury Frequency Rate from 3.44 to 3.81. While this is not an
acceptable performance by the company as a whole for the year,
Blyvooruitzicht Gold Mining Company Limited ("Blyvoor"), which
showed commendable improvements in respect of all three measures,
won the West Rand Mine Managers Safety Competition for the eighth
year in succession, and achieved one million fatality-free shifts shortly
before year end.
Within Empero s managed operations, Vatukoula s LTIFR for the year
deteriorated from 1.6 to 2.2 and its Disabling Injury Frequency Rate
("DIFR") from 5.6 to 7.8 while at Tolukuma Gold Mines Limited
("Tolukuma") both the LTIFR and DIFR worsened from 2.1 to 2.6.
Needless to say, a range of initiatives is in place at both the South African
and Australasian operations to effect the necessary improvements.
Particularly noteworthy is a broad-spectrum safety awareness campaign
dubbed Before You Work currently being implemented at both ERPM and
Blyvoor, and the Accelerated Development and Training Plan ("ACDTP")
at Vatukoula. As its title implies, the ACDTP has a major focus on training
and this includes safety matters.
Production
Total attributable gold production for the quarter was 2% higher at
131 857 ounces oz ), reflecting a 4% increase from the South African
operations to 90 181oz. Australasian gold production was 3% lower at
41 676oz.
Ongoing west wall remediation work at Porgera, the negative impacts of
underground flooding and bad weather at Tolukuma and a planned
shutdown at Vatukoula to implement ACDTP were all contributors to
lower Australasian production.
In South Africa, the upswing in production can be attributed to a
generally steady-state performance from Crown and indeed from the
surface recovery operations as a whole, to better production at ERPM
notwithstanding
faulting encountered and increased seismicity 
experienced towards the end of the June quarter and to the start of
Blyvoor's implementation of its new, volume-driven plan.
For the year, total attributable gold production was 31% lower at
527 401oz than in the previous year, reflecting the impact of a 33%
decline in Australasian gold production to 211 425oz. South African gold
production rose by 25% to 315 976oz.
Cash operating costs
Group cash operating costs for the quarter decreased by 12% to
US$452/oz. For the year, group cash operating costs were 16% higher at
US$433/oz than in the previous year. The driver was Australasian cash
operating costs, which were 57% higher at US$362/oz. South African
cash operating costs rose by 9% to US$480/oz.
Corporate developments
In April 2006 the vending of DRDGOLD s Australasian operations into
Emperor was concluded and Emperor now ranks as the fourth largest
gold producer listed on the Australian Stock Exchange. Consequences of
the transaction for DRDGOLD were an increased stake in Emperor
(now 78.9%) and US$30 million in cash.
The Emperor transaction, with another earlier in the year that fully
incorporated Blyvoor, Crown and ERPM into a new entity, DRDGOLD
SA
85% owned by DRDGOLD and 15% by a wholly owned 
subsidiary of its black economic empowerment partner, Khumo Bathong
Holdings Limited ("KBH")
concluded a thorough and meticulous re- 
positioning of DRDGOLD s gold mining assets.
These are now housed in two, distinct regional entities
one Pacific Rim-
focused and the other South Africa- and Africa-focused. An enormously
important consequence is that there will be no cross-subsidisation of one
by the other going forward, a factor that, in the past, caused value-
destruction and consequently, enormous and understandable shareholder
irritation.
DRDGOLD was removed from the official list of the Australia Stock
Exchange Limited as from the close of trading on Friday, 28 July 2006,
pursuant to the de-listing arrangement described in the letter to
shareholders dated 21 April 2006 and the attachments to that letter and
in accordance with listing rule 17.11
background image
3
3
Appointments
Injections of fresh board and senior management capacity are vital to the
future success of both Emperor and DRDGOLD SA, and it is very
pleasing to report that huge progress in this respect was made during
the quarter and into the start of the new financial year.
At Emperor, Brad Gordon
former Managing Director of Placer Dome
Nuigini Limited and General Manager of Porgera joined as Chief
Executive Officer and an executive director. Clyde Moore was
appointed as Chief Financial Officer and executive director.
Geoffrey Campbell, Chairman of DRDGOLD, and Ilja Graulich, Strategic
Development Officer for DRDGOLD, both joined the board as non-
executive directors. Geoffrey was also appointed as Chairman.
Bob McDonald was also appointed an independent non-executive
director. Frazer Bourchier
former Manager: Mining at Porgera was 
appointed General Manager at Vatukoula and John Wallace former
HR Manager at Porgera joined as General Manager: Human Resources
based at Empero s corporate office in Brisbane. Brad Sampson was
appointed General Manager: Tolukuma.
At DRDGOLD SA, Niel Pretorius acting Chief Executive Officer and
DRDGOLD s Group Legal Counsel was confirmed as Chief Executive 
Officer in place of Dr Paseka Ncholo, who stood down in January due
to other business commitments. Craig Barnes, former DRDGOLD
Group Financial Accountant, was appointed Chief Financial Officer and
an executive director. Thulo Mogotsi, an executive director of KBH, and
Louisa Zondo, General Counsel for South African Airways, joined as
non-executive directors. Ben Nyirenda, Head of New Business for
DRDGOLD, was appointed as an alternate director. At Blyvoor, Collie
Russouw
former Mine Manager at Harmony s Virginia operations takes 
over as General Manager in place of Mark Munroe who will head
up a new entity, DRDGOLD Capital, focusing on the company s growth
in Africa.
Looking ahead
A year of extremely hard work has produced a way forward for
DRDGOLD and its key investments, Emperor and DRDGOLD SA, that
will be enormously challenging but, at the same time, encouraging. I say
encouraging, because the way forward is clear and filled with new
brown- and greenfields growth opportunities, and because our perennial
confidence in our product, gold, is being rewarded with renewed and
seemingly sustained price buoyancy.
In South Africa, Blyvoor is proceeding with its new plan that is expected to
deliver fewer but more profitable ounces, and a new approach provides
impetus to its No 2 Sub-shaft project. At ERPM, seismicity remains a
challenge but risk will be all the better managed through more mining of
less active, though lower grade, areas above 70 level. ERPM s great
promise, of course, lies in the extension of high-grade mining into the
adjacent Sallies lease area, for which exploration is already under way. For
Crown, much in the medium term depends on a successful outcome to its
application to mine the Top Star dump in central Johannesburg. Thanks to
the current gold price, we are able, also, to look afresh at the Argonaut
Project to the south of Johannesburg, albeit on a smaller scale.
In Australasia, management of the Porgera Joint Venture is in the capable
hands of the new majority shareholder, Barrick, and there is every
reason to be confident that turnaround forecasts will be met. At
Tolukuma, a range of infrastructural improvements, coupled with mining
of recently discovered bonanza Zine deposits, should lead to significant
operating and financial improvements. At Vatukoula, long the problem
child , a shift in focus to high-grade mining, long overdue infrastructural
improvements and employee re-training mean there is at last the very
real prospect of profitable mining into the future.
Lastly, indicative of DRDGOLD s longer term prospects, is the healthy
increase in the company s attributable reserve and resource position.
The former has increased by 35% to 8.8 million ounces and the latter by
30% to 47.6 million ounces.
We like to say 'we do what we say'. At various times in the recent past,
however, not everyone liked hearing about our intentions, not least
because they often meant pain and discomfort of some sort. Looking
down the track, I believe all of our stakeholders should feel more
enthused, both about our ambitions and our ability to deliver.
MARK WELLESLEY-WOOD
Chief Executive Officer
24 August 2006
background image
4
KEY OPERATING AND FINANCIAL RESULTS
Australasian Operations
Porgera (20% Share of Joint Venture)
Quarter
30 Jun 2006
Quarter
31 Mar 2006
%
Change
12 months to
30 Jun 2006
12 months to
30 Jun 2005
Ore milled
t'000
305
241
27
1 097
1 200
Yield
g/t
2.77
3.15
(12)
3.64
5.07
Gold produced
oz
27 215
24 410
11
128 238
195 394
kg
846
760
11
3 990
6 079
Cash operating costs
US$ per oz
123
455
73
277
186
ZAR per kg
25 811
90 355
71
57 148
37 291
ZAR per tonne
72
285
75
208
189
Capital expenditure (net)
US$ million
4.7
1.1
(327)
14.5
16.1
ZAR million
30.0
5.8
(417)
93.1
100.2
Attributable gold production for the quarter ended 30 June 2006 was 11% higher at 27 215oz, reflecting a 27% increase in ore milled to 305 000 tonne
t ). Average yield was 12% lower at 2.77 grams per ton g/t ). Low grade, long term stockpiles continued to provide the primary ore feed at Porgera
during the quarter. Cash operating costs were 73% lower at US$123/oz, reflecting higher gold production and an adjustment to deferred stripping cost
capitalised during the quarter.
Remediation of the west wall cutback continues and is now 60% complete. The JV expects mining of ore from the open pit to begin later in 2006, after
which both production levels and cash costs are expected to improve.
Tolukuma
Quarter
30 Jun 2006
Quarter
31 Mar 2006
%
Change
12 months to
30 Jun 2006
12 months to
30 Jun 2005
Ore milled
t'000
45
47
(4)
193
211
Yield
g/t
8.58
7.70
11
8.83
11.24
Gold produced
oz
12 408
11 659
6
54 790
76 314
kg
386
362
6
1 704
2 372
Cash operating costs
US$ per oz
781
637
(23)
561
346
ZAR per kg
161 858
127 122
(27)
116 042
69 348
ZAR per tonne
1 388
979
(42)
1 025
780
Capital expenditure (net)
US$ million
0.8                      -                       -
4.4
3.4
ZAR million
5.1
(0.4)
(1 375)
28.4
21.3
Gold production for the quarter was 6% lower at 12 408oz. While the average yield improved by 11% to 8.58g/t, ore milled was 4% lower at 45 000t.
Poor weather prevented continuous freight movement to the mine site by helicopter, resulting in several plant shutdowns during the quarter. To
overcome this in the future, strategic stocks of consumables at the mine site will be increased.
Improved flexibility is expected as initial production areas along the newly discovered Zine structure are developed and brought into the mine plan.
Lower gold production was the main contributor to a 23% increase in cash operating costs to US$781/oz.
Vatukoula ("Old" Emperor)
100% consolidated from 6 April 2006
(Previously 39.52% attributable)
Quarter
30 Jun 2006
Quarter
31 Mar 2006
%
Change
12 months to
30 Jun 2006
12 months to
30 Jun 2005
Ore milled
t'000
23
36
(36)
161
213
Yield
g/t
2.78
5.97
(53)
5.49
6.63
Gold produced
oz
2 053
6 910
(70)
28 397
45 426
kg
64
215
(70)
884
1 413
Cash operating costs #
US$ per oz
333
690
52
588
434
ZAR per kg
74 953
137 002
45
121 515
86 527
ZAR per tonne
209
809
74
697
584
Capital expenditure (net) #
US$ million
3.5
1.6
(119)
9.5
8.4
ZAR million
22.2
9.9
(124)
60.8
52.0
# Represents total operation
Implementation of the mine's new ACDTP involved a temporary shutdown of the mine on 20 April and a gradual start-up early in June.
Consequently, gold production for the quarter was only 2 053oz compared with 17 485oz in the previous quarter (DRDGOLD attributable portion 6 910oz). Ore milled was 75% lower at 23 000t and average yield 53% lower at 2.78g/t. The ACDTP has been designed to introduce flexibility to production areas, improve infrastructure and increase the productivity of the workforce. The plan includes development of higher
grade areas at Philip Shaft and upgrading of associated shaft infrastructure. In addition, the entire workforce will undergo comprehensive
assessment, re-skilling and retraining. During the quarter, work continued on various infrastructure
-related improvements at Philip Shaft.
Production from Smith Shaft has now stopped.
background image
5
South African Operations
Blyvoor
Quarter
30 Jun 2006
Quarter
31 Mar 2006
%
Change
12 months to
30 Jun 2006
12 months to
30 Jun 2005
Ore milled
Underground
t'000
178
171
4
674
587
Surface
t'000
920
927
(1)
3 634
2 932
Total
t'000
1 098
1 098
4 308
3 519
Yield
Underground
g/t
5.26
4.59
15
5.55
7.31
Surface
g/t
0.33
0.38
(13)
0.34
0.25
Total
g/t
1.13
1.03
10
1.15
1.43
Gold produced
Underground
oz
30 124
25 238
19
120 178
137 958
kg
937
785
19
3 738
4 291
Surface
oz
9 806
11 221
(13)
39 515
23 920
kg
305
349
(13)
1 229
744
Total
oz
39 930
36 459
10
159 693
161 878
kg
1 242
1 134
10
4 967
5 035
Cash operating costs
Underground
US$ per oz
607
692
12
551
468
ZAR per kg
126 037
138 084
9
113 789
93 715
ZAR per tonne
663
634
(5)
631
685
Surface
US$ per oz
276
233
(18)
248
272
ZAR per kg
57 289
46 553
(23)
51 245
54 331
ZAR per tonne
19
18
(6)
17
14
Total
US$ per oz
526
551
5
476
439
ZAR per kg
109 155
109 914
1
98 314
87 895
ZAR per tonne
123
114
(8)
113
126
Capital expenditure (net)
US$ million
2.2
2.4
8
8.8
2.1
ZAR million
14.3
15.1
5
56.8
12.9
The generally improved underground results reflect the start of implementation of the new plan, key features of which are a reduction in mining from the
seismically active, high-grade No 5 Shaft area in the interests of safety and an increase in production from the No 4 Shaft and lower-grade No 6 Shaft
areas.
A target of 70 000t per month from underground was expected by the end of September 2006 but could be delayed by up to a month because of the
required overhaul of the No 6 Shaft winder and shaft repairs.
For the quarter ending June 2006, underground gold production was 19% higher as a result of a 15% increase in average yield to 5.26g/t. Surface gold
production was 13% lower at 9 806oz, as a result of a 1% decrease in ore milled to 920 000t and a 13% decrease in average yield to 0.33g/t. Lower
throughput reflects slower recovery of hard material from the slimes dam project and downtime during the relocation of a pump station to access higher
grade slimes. Lower yield was mainly a factor of a foreseen decline in the grade of rock dump material treated.
Total cash operating costs were 5% lower at US$526/oz, reflecting higher underground gold production. Underground cash operating costs declined by
12% to US$607/oz, while surface cash operating costs rose by 18% to US$276/oz.
A re-assessment of Phase 2 of the No 2 Sub-shaft project has indicated that accessing the ore body between 27 and 35 level from No 6 Shaft will be 
considerably more cost effective than from the No 2 Sub-shaft, as originally envisaged. This approach is expected to lower the total capital cost of the project from R100 million to R40 million. Work on Phase 2, according to the new approach, began in July and is expected to be completed in two years.
Drilling to determine the extent of the Alpha Dyke in the No 5 Shaft high-grade area, intercepted in the previous quarter some 40m further to the west
than anticipated, continued throughout the quarter under review. Indications thus far are that the dyke is at least 30m thick.
Crown
100% consolidated from 1 Dec 2005
(Previously 40% attributable)
Quarter
30 Jun 2006
Quarter
31 Mar 2006
%
Change
12 months to
30 Jun 2006
12 months to
30 Jun 2005
Ore milled
t'000
2 070
1 946
6
6 165
3 552
Yield
g/t
0.36
0.37
(2)
0.38
0.40
Gold produced
oz
23 823
23 213
3
75 959
45 424
kg
741
722
3
2 362
1 413
Cash operating costs #
US$ per oz
489
502
3
432
395
ZAR per kg
101 456
99 841
(2)
89 329
78 890
ZAR per tonne
36
37
3
35
31
Capital expenditure (net) #
US$ million
1.6
1.3
(23)
4.9
1.5
ZAR million
10.6
7.8
(36)
31.6
9.6
# Represents total operation
A 6% increase in ore milled to 2 070 000t for the quarter compensated for a 2% decline in average yield to 0.36g/t. Gold production rose by 3% to
23 823oz. Drier weather conditions contributed to the increase in throughput. Cash operating costs were 3% lower at US$489/oz, reflecting higher gold
production.
background image
6
A R3.2 million upgrade of the residue pipeline, scheduled for completion by the end of August 2006, a R6.8 million upgrade of the CMR reclamation site
pipeline, scheduled for completion by the end of the September quarter, and a R17.4 million refurbishment of the Knights plant mills are all expected to
improve efficiencies.
In respect of the planned recovery of material from the Top Star dump in central Johannesburg, mining authorisation application procedures are
under way.
ERPM
100% consolidated from 1 Dec 2005
(Previously 40% attributable)
Quarter
30 Jun 2006
Quarter
31 Mar 2006
%
Change
12 months to
30 Jun 2006
12 months to
30 Jun 2005
Ore milled
Underground
t'000
77
72
7
225
145
Surface
t'000
474
537
(12)
1 598
752
Total
t'000
551
609
(10)
1 823
897
Yield
Underground
g/t
8.17
8.86
(8)
8.29
7.59
Surface
g/t
0.41
0.38
8
0.40
0.38
Total
g/t
1.49
1.38
8
1.37
1.55
Gold produced
Underground
oz
20 223
20 512
(1)
59 999
35 392
kg
629
638
(1)
1 866
1 101
Surface
oz
6 205
6 494
(4)
20 325
9 208
kg
193
202
(4)
633
286
Total
oz
26 428
27 006
(2)
80 324
44 600
kg
822
840
(2)
2 499
1 387
Cash operating costs #
Underground
US$ per oz
479
470
(2)
461
381
ZAR per kg
99 514
93 624
(6)
95 293
76 303
ZAR per tonne
813
830
2
785
578
Surface
US$ per oz
537
563
5
499
527
ZAR per kg
111 451
112 010
103 109
105 288
ZAR per tonne
45
42
(7)
41
40
Total
US$ per oz
493
493
471
411
ZAR per kg
102 316
98 045
(4)
97 289
82 287
ZAR per tonne
153
135
(13)
134
127
Capital expenditure (net) #
US$ million
0.7
0.7
2.1
(1.1)
ZAR million
4.8
4.4
(9)
13.7
(7.5)
# Represents total operation

Total gold production for the quarter was 2% lower at 26 428oz, reflecting a 10% decrease in total ore milled to 551 000t. The overall average yield was
8% higher at 1.49g/t.

While underground ore milled was 7% higher at 77 000t, the average underground yield was 8% lower at 8.17g/t, leading to slightly lower underground
gold production of 20 223oz. Lower grade reflects increased mining from lower grade panels above 70 level. Underground production was also
adversely affected by the exclusion from the mine plan of stopes in the 73 West area due to seismicity.

Targeted available face above 70 level of 150m has now been achieved. Traversing of the 16m, up-throw fault in the 70 East area is continuing. Work to
split the 70 level decline conveyor into two sections thus reducing wear and tear is under way and is scheduled for completion by December 2006.

The four-year, ERPM Extension (Sallies) exploration drilling programme has begun, with the drilling of the first of three holes on 70 level in progress. An
application to the Department of Minerals and Energy for a prospecting permit over an extension to the existing exploration area has been accepted.

With respect to the pumping upgrade project, water pumping plans are currently under review, while mud pumping feasibility work is continuing. Phase 2
of the plugging project is on schedule and planning of Phase 3 has been completed. The total plugging project is scheduled for completion by June 2007.

Surface gold production was 4% lower at 6 205oz, reflecting a 12% decline in surface ore milled to 474 000t. Average surface yield was 8% higher at
0.41g/t. Lower throughput was the result of mill breakdowns in the ERPM plant. The commissioning of two additional mills at the Knights plant neared
completion at the end of the quarter, slightly behind schedule due to various teething problems.
background image
7
Discontinued Operations
North West (Hartebeestfontein and
Buffelsfontein mines)
Quarter
30 Jun 2006
Quarter
31 Mar 2006
%
Change
12 months to
30 Jun 2006
12 months to
30 Jun 2005
Ore milled
Underground
t'000                                       -                       -                        -                        -
986
Surface
t'000                                       -                       -                        -                        -
884
Total
t'000                                       -                       -                        -                        -
1 870
Yield
Underground
g/t                                          -                       -                        -                        -
5.44
Surface
g/t                                          -                       -                        -                        -
0.96
Total
g/t                                          -                       -                        -                        -
3.32
Gold produced
Underground
oz                                           -                       -                        -                        -
172 522
kg                                           -                       -                        -                        -
5 366
Surface
oz                                            -                      -                        -                        -
27 328
kg                                           -                       -                        -                        -
850
Total
oz                                           -                       -                        -                        -
199 850
kg                                           -                       -                        -                        -
6 216
Cash operating costs
Total
US$ per oz                               -                       -                        -                        -
508
ZAR per kg                              -                       -                        -                        -
101 701
ZAR per tonne                          -                       -                        -                        -
338
Capital expenditure (net)
US$ million                               -                       -                        -                        -
3.3
ZAR million                              -                       -                        -                        -
20.3
EXPLORATION AND DEVELOPMENT
Australasian Operations
Vatukoula
On 20 April 2006, Emperor announced the implementation of the new ACDTP. The plan includes the development of higher grade areas in the vicinity
of Philip Shaft and upgrading the associated shaft infrastructure. On 26 April, Emperor entered into an agreement with the Government of Fiji, the Mine
Workers Union of Fiji and the Vatukoula Mine Workers Staff Association to give effect to a major reorganization to ensure the long term future of the
mine. In addition, the entire workforce is undergoing a comprehensive assessment, re-skilling and retraining programme. Over the next 18 months,
Emperor will invest F$27 million in capital expenditure. A Workers Relief Fund of F$300 000 has been committed by the Fijian Government to assist
employees.
Tolukuma
A comprehensive review of the regional exploration database has outlined several new high priority prospects. Work will begin on these in the next few
months.
In late April, Emperor announced the discovery of two zones of high-grade gold mineralisation in the Zine structure, a significant regional structure that is
parallel to the main Tolukuma Structure. This structure has continued to return encouraging results from both drilling and underground development
with a considerable strike length of high-grade material being identified. Drilling and development is in progress to bring the area into a resource category
as quickly as possible.
South African Operations
Argonaut
A prospecting right for 969 hectares was granted on 6 February. An application to extend this prospecting right by an additional 4 002 hectares was
submitted to the Department of Minerals and Energy (DME) on 26 June. The application has been accepted, and response is awaited.

ERPM Extension 1
The ERPM Extension 1 Mineral Resource as at 30 June is as follows:
Category
Mt
g/t
Contents gold t
Contents gold Moz
Measured
0.07
11.84
0.81
0.03
Indicated
2.66
13.18
35.04
1.13
Inferred
34.03
7.96
270.99
8.71
Total
36.76
8.35
306.84
9.87
The first prospect borehole has been completed. No geological structures, water or gas have been intersected. Results are encouraging, and the hole has
been sampled under the supervision of an independent consultant. Preliminary results of the assay, which will be subject to a second confirmation, indicate
that the reef is very well-developed, with a channel width of 162cm, and a value of 26.7g/t at that width, equating to 23.1g/t over a mining width of 188cm.
ERPM Extension 2
An application covering an area of 5 500.23 hectares was submitted to the DME on 6 July. The application has been accepted, and a response is awaited.
The area has an exploration target of some 7-11 million ounces.

Public Participation Meetings in respect of ERPM Extensions 1 and 2 were held on 28 July and 4 August respectively, and the reports arising from these
meetings have been submitted to the DME. Environmental Management Plans (EMPs) must be submitted to the DME by 4 and 11 September
respectively. On receipt of the EMP, the DME has 120 days to approve or reject the application.
background image
8
DRDGOLD LIMITED
DIRECTORS
Directors (* British) (** Australian) (*** American)
Executives:
MM Wellesley-Wood (Chief Executive Officer)*
Independent non-executive s:
Group Company Secretary:
JWC Sayers (Chief Financial Officer)
RP Hume
T Gwebu
GC Campbell* (Non-Executive Chairman)
Non-executives:
D Blackmur**
J Turk***
INVESTOR RELATIONS
For further information, contact Ilja Graulich at:
Tel: (+27-11) 219-7800 Fax: (+27-11) 476-2637 e-mail: ilja.graulich@za.drdgold.com website: http://www.drdgold.com
Ebsco House 4, 299 Pendoring Avenue, Blackheath, Randburg, South Africa PO Box 390, Maraisburg, 1700, South Africa