XML 119 R59.htm IDEA: XBRL DOCUMENT v2.4.0.8
Commitments and Contingencies (Details) (USD $)
7 Months Ended 10 Months Ended 6 Months Ended
Jun. 30, 2013
Dec. 31, 2012
Oct. 31, 2013
OG&E minimum fuel purchase commitments [Member]
Oct. 31, 2013
OG&E minimum fuel purchase commitments [Member]
Jun. 30, 2013
OG&E long-term service agreement commitments [Member]
McClain Plant [Member]
Jun. 30, 2013
OG&E long-term service agreement commitments [Member]
Redbud Plant [Member]
Jun. 30, 2013
Enogex [Member]
Long-term Purchase Commitment [Line Items]              
Percentage of OG&E's Projected 2013 Requirements     55.80% 26.10%      
Factored-Fired Hours         128,000 24,000  
Factored-Fired Starts         3,600    
Operating Leases, Future Minimum Payments Due $ 0            
Commitments and Contingencies               0
Estimated Environmental Capital Costs 1,000,000,000            
Potential Penalty Under the Federal Clean Air Act $ 37,500