XML 56 R23.htm IDEA: XBRL DOCUMENT v2.4.0.6
Rate Matters and Regulation
3 Months Ended
Mar. 31, 2013
Regulated Operations [Abstract]  
Rate Matters and Regulation
Rate Matters and Regulation

Except as set forth below, the circumstances set forth in Note 17 to the Company's Consolidated Financial Statements included in the Company's 2012 Form 10-K appropriately represent, in all material respects, the current status of the Company's regulatory matters.

Completed Regulatory Matter

OG&E Crossroads Wind Farm

As previously reported, OG&E signed memoranda of understanding in February 2010 for approximately 197.8 megawatts of wind turbine generators and certain related balance of plant engineering, procurement and construction services associated with the Crossroads wind farm. Also as part of this project, on June 16, 2011, OG&E entered into an interconnection agreement with the SPP for the Crossroads wind farm which allowed the Crossroads wind farm to interconnect at 227.5 megawatts. On August 31, 2012, OG&E filed an application with the APSC requesting approval to recover the Arkansas portion of the costs of the Crossroads wind farm through a rider until such costs are included in OG&E's base rates as part of its next general rate proceeding. On April 15, 2013, the APSC issued an order authorizing OG&E to recover the Arkansas portion of the cost to construct the Crossroads wind farm, effective retroactively to August 1, 2012. The costs will be recovered through the Energy Cost Recovery Rider.

Pending Regulatory Matters

OG&E Fuel Adjustment Clause Review for Calendar Year 2011

On July 31, 2012, the OCC Staff filed an application for a public hearing to review and monitor OG&E's application of the 2011 fuel adjustment clause and for a prudence review of OG&E's electric generation, purchased power and fuel procurement processes and costs in calendar year 2011. On December 19, 2012, witnesses for the OCC Staff filed responsive testimony recommending that the OCC approve OG&E's fuel adjustment clause costs and recoveries for the calendar year 2011 and recommending that the OCC find that OG&E's electric generation, purchased power, fuel procurement and other fuel related practices, policies and decisions during calendar year 2011 were fair, just and reasonable and prudent.  The Oklahoma Industrial Energy Consumers filed a statement of position on December 19, 2012 and did not challenge OG&E's application of its fuel adjustment clause or prudency.  The Oklahoma Industrial Energy Consumers reserved its right to file rebuttal testimony, cross examine witnesses and amend its statement of position should circumstances change or additional information becomes available in the course of this proceeding. On January 7, 2013, the Oklahoma Attorney General filed a statement of position stating that after reviewing the case information the Attorney General has no reason at this time to dispute the findings of the OCC Staff.  On April 9, 2013, a hearing was held in this matter, at which time the OCC administrative law judge recommended that the OCC find that for the calendar year 2011 OG&E's electric generation, purchased power and fuel procurement processes and costs were prudent. OG&E expects to receive an order from the OCC by the end of the second quarter of 2013.

Enogex 2013 Fuel Filing

On March 1, 2013, Enogex submitted its annual fuel filing to establish the fixed fuel percentages for its East Zone and West Zone for the upcoming fuel year (April 1, 2013 through March 31, 2014). The deadline for interventions and protests on the filing was March 18, 2013 and no protests were filed. A FERC order is pending.