Rate Matters and Regulation
6 Months Ended
Jun. 30, 2012
Regulated Operations [Abstract]  
Rate Matters and Regulation
Rate Matters and Regulation
 
Except as set forth below, the circumstances set forth in Note 17 to the Company's Consolidated Financial Statements included in the Company's 2011 Form 10-K appropriately represent, in all material respects, the current status of the Company's regulatory matters.

Completed Regulatory Matters

OG&E Contract and Wind Energy Purchase Agreement Filing

On December 1, 2011, OG&E filed an application with the OCC requesting approval of a 20-year agreement that is intended to provide wind power to help meet the current and future power generation needs of Oklahoma State University. The project calls for OG&E to contract with NextEra Energy to build a 60 megawatt wind farm near Blackwell, Oklahoma, to support the Oklahoma State University project in which NextEra Energy will build, own and operate the wind farm and OG&E will purchase the electric output. The wind farm is expected to be in service by the end of 2012. On February 22, 2012, OG&E, the Attorney General and the Public Utility Division of the OCC signed a settlement agreement whereby the stipulating parties requested that the OCC issue an order approving the agreement for electric service with Oklahoma State University. On March 12, 2012, OG&E received an order from the OCC approving the settlement agreement. Pursuant to the terms of the power purchase agreement between OG&E and NextEra Energy, OG&E will purchase the electric output of the wind farm and use that power to provide service to Oklahoma State University and its other retail customers.

SPP Transmission/Substation Projects

In 2007, the SPP notified OG&E to construct 44 miles of a new 345 kilovolt transmission line originating at OG&E's existing Sooner 345 kilovolt substation and proceeding generally in a northerly direction to the Oklahoma/Kansas Stateline (referred to as the Sooner-Rose Hill project). At the Oklahoma/Kansas Stateline, the line connects to the companion line constructed in Kansas by Westar Energy. The transmission line was placed in service in April 2012. The total capital expenditures associated with this project were $45 million.

In January 2009, OG&E received notification from the SPP to begin construction on 50 miles of a new 345 kilovolt transmission line and substation upgrades at OG&E's Sunnyside substation, among other projects. In April 2009, Western Farmers Electric Cooperative assigned to OG&E the construction of 50 miles of line designated by the SPP to be built by Western Farmers Electric Cooperative.  The new line extends from OG&E's Sunnyside substation near Ardmore, Oklahoma, 123.5 miles to the Hugo substation owned by Western Farmers Electric Cooperative near Hugo, Oklahoma.  The transmission line was completed in April 2012. The total capital expenditures associated with this project were $157 million.

As discussed below, the OCC approved a settlement agreement in OG&E's 2011 Oklahoma rate case filing that included an expedited procedure for recovering the costs of the two projects.  On July 31, 2012, OG&E filed an application with the OCC requesting an order authorizing recovery for the two projects through the SPP transmission systems additions rider.

OG&E 2011 Oklahoma Rate Case Filing

As previously reported in the Company's 2011 Form 10-K, on July 28, 2011, OG&E filed its application with the OCC requesting an annual rate increase of $73.3 million, or a 4.3 percent increase in its rates. OG&E requested a return on equity of 11.0 percent based on a common equity percentage of 53.0 percent. In its application, OG&E requested recovery of increases in its operating costs and to begin earning on approximately $500 million of new capital investments made on behalf of its Oklahoma customers during the previous two and one-half years. On July 2, 2012, OG&E and other parties associated with its rate increase reached a settlement agreement in this matter. Key terms of the settlement agreement include: (i) an annual net increase of approximately $4.3 million in OG&E's rates to its Oklahoma retail customers; (ii) OG&E's Oklahoma retail authorized return on equity will be 10.2 percent; (iii) the rate of return to be used under various recovery riders previously approved by the OCC, including riders for OG&E's smart grid implementation and Crossroads wind farm will be based on OG&E's actual debt and equity ratios as reflected in OG&E's application and a 10.2 percent return on equity; (iv) depreciation rates proposed by OG&E will be implemented in the same month new customer rates go into effect; (v) the pension and postretirement medical cost tracker will remain in effect; (vi) a procedure was established to expedite the recovery of the cost of specified high-voltage transmission projects; and (vii) extension of funding for OG&E's system hardening program. On July 9, 2012, the OCC issued an order approving the settlement agreement in this matter. OG&E expects the impact of the rate increase on its customers and service territory to be minimal over the next 12 months as the rate increase will be more than offset by lower fuel costs attributable to prior fuel over recoveries from lower than forecasted fuel costs. OG&E implemented the new rates effective in early August.

Pending Regulatory Matters

OG&E Fuel Adjustment Clause Review for Calendar Year 2010

The OCC routinely reviews the costs recovered from customers through OG&E’s fuel adjustment clause. On August 19, 2011, the OCC Staff filed an application to review OG&E’s fuel adjustment clause for calendar year 2010, including the prudence of OG&E’s electric generation, purchased power and fuel procurement costs. OG&E responded by filing direct testimony and the minimum filing review package on October 18, 2011. On April 6, 2012 witnesses for the OCC Staff, the Oklahoma Attorney General and the Oklahoma Industrial Energy Consumers association filed responsive testimony. The witness for the Oklahoma Industrial Energy Consumers recommended that the OCC disallow recovery of approximately $44 million of costs previously recovered through OG&E’s fuel adjustment clause. These recommendations were based on allegations that OG&E’s lower cost coal-fired generation was underutilized, that OG&E failed to aggressively pursue purchasing power at a cost lower than its marginal cost of generation and that OG&E should be found imprudent related to an unplanned outage at OG&E's Sooner 2 coal unit in November and December 2010. The witnesses for the OCC Staff and the Oklahoma Attorney General recommended that OG&E should provide additional information to allow them to reach a conclusion on their prudence review. On May 8, 2012, OG&E filed rebuttal testimony supporting the appropriateness of OG&E's use of coal-fired generation during 2010, OG&E's practice regarding purchasing power and the appropriateness of OG&E's management actions related to the Sooner 2 outage. A hearing on the merits was conducted on July 17 and 18, 2012. The witness for the Oklahoma Attorney General offered no further testimony. The witness for the OCC Staff recommended approval of OG&E's actions related to utilization of coal plants and practices related to purchasing power but recommended that OG&E refund $3 million to customers because of the Sooner 2 outage. The administrative law judge took the matter under advisement. OG&E believes that the recommendations for the disallowances made by the witnesses for the Oklahoma Industrial Energy Consumers and the OCC Staff are without merit.

SPP Transmission/Substation Projects

On January 31, 2012, the SPP approved the Integrated Transmission Plan Near Term and Integrated Transmission Plan 10-year projects. These plans include two projects to be built by OG&E and include: (i) construction of 47 miles of transmission line from OG&E's Gracemont substation in a northwestern direction to a companion transmission line to be built by American Electric Power to its Elk City substation at an estimated cost of $75 million for OG&E, which is expected to be in service by early 2018 and (ii) construction of 126 miles of transmission line from OG&E's Woodward District Extra High Voltage substation in a southeastern direction to OG&E's Cimarron substation and construction of a new substation on this transmission line, the Mathewson substation, at an estimated cost of $210 million for OG&E, which is expected to be in service by early 2021. On April 9, 2012, OG&E received a notice to construct these projects from the SPP. On June 26, 2012, OG&E responded to the SPP that OG&E will construct the projects discussed above and is moving forward with more detailed cost estimates that must be reviewed and approved by the SPP.

Market-Based Rate Authority
On June 29, 2012, OG&E filed its triennial market power update with the FERC to retain its market-based rate authorization in the SPP's energy imbalance service market but to surrender its market-based rate authorization for any market-based rate sales outside the SPP's energy imbalance service market. A FERC order is pending.

Enogex FERC Section 311 2011 Rate Case

On January 28, 2011, Enogex submitted a new rate filing to the FERC to set the maximum rate for a new firm Section 311 transportation service in the West Zone of its system and to revise the currently effective maximum rates for Section 311 interruptible transportation service in the East Zone and West Zone.  Along with establishing the rate for a new firm service in the West Zone, Enogex's filing requested a decrease in the maximum interruptible zonal rates in the West Zone and to retain the currently effective rates for firm and interruptible services in the East Zone.  Enogex reserved the right to implement the higher rates for firm and interruptible services in the East Zone supported by the cost of service to the extent an expeditious settlement agreement in this matter cannot be reached in the proceeding.  Enogex proposed that the rates be placed into effect on March 1, 2011.  On January 10, 2012, Enogex filed a settlement agreement in this matter with the FERC. On May 4, 2012, the FERC issued an order approving the settlement agreement in this matter, subject to the submission of a compliance filing to place the settlement rates into effect as of March 1, 2011, which compliance filing was subsequently filed on May 31, 2012. The FERC also requested that Enogex file a revised statement of operating conditions, which was subsequently filed on May 31, 2012. As part of the settlement agreement in this matter, Enogex made refunds of $0.2 million to affected customers on June 15, 2012 and submitted a report to the FERC on July 6, 2012 showing the refund payment calculation. A FERC order is pending.

Enogex 2011 Fuel Filing

On February 28, 2011, Enogex submitted its annual fuel filing to establish the fixed fuel percentages for its East Zone and West for the 2011 fuel year (April 1, 2011 through March 31, 2012).  Along with the revised fuel percentages, Enogex also requested authority to revise its statement of operating conditions to permanently change the annual filing date to February 28.  The deadline for interventions and protests to Enogex's filing was March 15, 2011, and no protests were filed.  On July 6, 2012, Enogex submitted a compliance filing to synchronize the 2011 fuel filing with the revised statement of operating conditions filed on May 31, 2012 in compliance with the FERC's order approving Enogex's 2011 Section 311 rate case settlement discussed above.  A FERC order is pending.

Enogex 2012 Fuel Filing

On February 24, 2012, Enogex submitted its annual fuel filing to establish the fixed fuel percentages for its East Zone and West Zone for the 2012 fuel year (April 1, 2012 through March 31, 2013). The deadline for interventions and protests on the filing was March 27, 2012. Two parties intervened in the proceeding. On July 6, 2012, Enogex submitted a compliance filing to synchronize the 2012 fuel filing with the revised statement of operating conditions filed on May 31, 2012 in compliance with the FERC's order approving Enogex's 2011 Section 311 rate case settlement discussed above. A FERC order is pending.