XML 108 R27.htm IDEA: XBRL DOCUMENT v2.4.0.6
Rate Matters and Regulation
12 Months Ended
Dec. 31, 2011
Regulated Operations [Abstract]  
Rate Matters and Regulation
Rate Matters and Regulation
 
Regulation and Rates

OG&E's retail electric tariffs are regulated by the OCC in Oklahoma and by the APSC in Arkansas.  The issuance of certain securities by OG&E is also regulated by the OCC and the APSC.  OG&E's wholesale electric tariffs, transmission activities, short-term borrowing authorization and accounting practices are subject to the jurisdiction of the FERC.  The Secretary of the U.S. Department of Energy has jurisdiction over some of OG&E's facilities and operations.  In 2011, 89 percent of OG&E's electric revenue was subject to the jurisdiction of the OCC, eight percent to the APSC and three percent to the FERC.

The OCC issued an order in 1996 authorizing OG&E to reorganize into a subsidiary of OGE Energy.  The order required that, among other things, (i) OGE Energy permit the OCC access to the books and records of OGE Energy and its affiliates relating to transactions with OG&E, (ii) OGE Energy employ accounting and other procedures and controls to protect against subsidization of non-utility activities by OG&E's customers and (iii) OGE Energy refrain from pledging OG&E assets or income for affiliate transactions.  In addition, the Energy Policy Act of 2005 enacted the Public Utility Holding Company Act of 2005, which in turn granted to the FERC access to the books and records of OGE Energy and its affiliates as the FERC deems relevant to costs incurred by OG&E or necessary or appropriate for the protection of utility customers with respect to the FERC jurisdictional rates.

Completed Regulatory Matters

OG&E Wholesale Agreement
 
On May 28, 2009, OG&E sent a termination notice to the Arkansas Valley Electric Cooperative that OG&E would terminate its wholesale power agreement to all points of delivery where OG&E sells or has sold power to the Arkansas Valley Electric Cooperative, effective November 30, 2011.  In December 2010, OG&E and the Arkansas Valley Electric Cooperative entered into a new wholesale power agreement whereby OG&E will supply wholesale power to the Arkansas Valley Electric Cooperative through June 2015.  On January 3, 2011, OG&E submitted this agreement to the FERC for approval.  The FERC approved the new wholesale power agreement on March 2, 2011 and the new contract was effective May 1, 2011.

OG&E Crossroads Wind Farm

On July 29, 2010, OG&E received an order from the OCC authorizing OG&E to recover from Oklahoma customers the cost to construct Crossroads, with the rider being implemented as the individual turbines are placed in service. The Crossroads wind farm was fully in service in January 2012. As part of this project, on June 16, 2011, OG&E entered into an interconnection agreement with the SPP for Crossroads which allowed Crossroads to interconnect at 227.5 MWs

OG&E 2010 Arkansas Rate Case Filing

On September 28, 2010, OG&E filed a rate case with the APSC requesting an annual rate increase of $17.7 million, to recover the cost of significant electric system expansions and upgrades, including high-voltage transmission lines, that have been completed since the last rate filing in August 2008, as well as increased operating costs. OG&E also sought recovery, through a rider, of the Arkansas jurisdictional portion of (i) costs associated with transmission upgrades and facilities that have been approved by the SPP in its regional planning processes and constructed by other non-OG&E transmission owners throughout the SPP that have been allocated to OG&E through the FERC-approved transmission rates and (ii) SPP administrative fees.  On June 17, 2011, the APSC approved a settlement agreement among all parties to the case and OG&E implemented new electric rates effective June 20, 2011. Key items of the APSC order include: (i) the recovery of and a return on significant electric system expansions and upgrades, including high-voltage transmission lines, as well as increased operating costs, totaling $8.8 million annually; (ii) authorization for OG&E to recover the actual cost of third-party transmission charges and SPP administrative fees through a rider mechanism which will remain in effect until new rates are implemented after OG&E's next general rate case (the Arkansas jurisdictional portion of the combined costs was $1.0 million in 2011); and (iii) the deferral of certain expenses associated with a customer education program in an amount not to exceed $0.3 million per year for a maximum of two years.

OG&E SPP Cost Tracker

On October 7, 2010, OG&E filed an application with the OCC seeking recovery of the Oklahoma jurisdictional portion of (i) costs associated with transmission upgrades and facilities that have been approved by the SPP in its regional planning processes and constructed by other non-OG&E transmission owners throughout the SPP that have been allocated to OG&E through the FERC-approved transmission rates and (ii) SPP administrative fees. OG&E requested authorization to implement a cost tracker in order to recover from its retail customers the third-party project costs discussed above and to collect its administrative SPP cost assessment levied under Schedule 1A of the SPP open access transmission tariff, which is currently recovered in base rates.  OG&E also requested authorization to establish a regulatory asset effective January 1, 2011 in order to give OG&E the opportunity to recover such costs that will be paid but not recovered until the cost tracker is made effective. On February 8, 2011, all parties signed a settlement agreement in this matter which would allow OG&E to recover the costs discussed in (i) above through a recovery rider effective January 1, 2011. OG&E recovered $5.1 million of incremental revenues in 2011 through the rider. Rather than including the costs of the SPP administrative fee assessment in the recovery rider, the stipulating parties agreed to allow OG&E to include the projected 2012 level of the SPP administrative fee assessment in its next Oklahoma rate case which was filed in August 2011. Pursuant to the settlement agreement in OG&E's 2011 Oklahoma general rate case filing, OG&E proposed that recovery in base rates for the costs of transmission projects it constructs and owns and that are authorized by the SPP in its regional planning processes should be limited to the Oklahoma retail jurisdictional share of the costs for such projects allocated to OG&E by the SPP.  On March 28, 2011, the OCC issued an order in this matter approving the settlement agreement.

OG&E Fuel Adjustment Clause Review for Calendar Year 2009

On October 29, 2010, the OCC Staff filed an application for a public hearing to review and monitor OG&E's application of the 2009 fuel adjustment clause.  On December 28, 2010, OG&E responded by filing the necessary information and documents to satisfy the OCC's minimum filing requirement rules. An intervenor representing a group of OG&E's industrial customers filed testimony on March 11, 2011 seeking a $15.5 million refund related to (i) a purported failure by OG&E to maximize the use of its coal-fired power plants and (ii) an inappropriate extension of the existing gas transportation and storage contract between OG&E and Enogex.  OG&E filed rebuttal testimony on April 4, 2011 in opposition to the claims of the intervenor.  On August 11, 2011, all parties to this case signed a settlement agreement in this matter, stating that (i) OG&E was prudent in its operations during 2009; (ii) a third party expert should be hired to evaluate OG&E's future gas transportation and storage needs and that OG&E should file a plan for meeting its future gas transportation and storage needs by mid-2012; and (iii) with respect to the existing gas transportation and storage contract with Enogex, OG&E will return $8.4 million to its customers in settlement for all periods under the contract through April 30, 2013. In August 2011, OG&E credited $4.9 million to its customers and will credit the remaining amount on a monthly basis through April 30, 2013. The OCC issued an order approving the settlement agreement on August 29, 2011.

OG&E Smart Grid Project

On December 17, 2010, OG&E filed an application with the APSC requesting pre-approval for system-wide deployment of smart grid technology and a recovery rider, including a credit for the Smart Grid grant awarded by the U.S. Department of Energy under the American Recovery and Reinvestment Act of 2009. On June 22, 2011, OG&E reached a settlement agreement with all the parties in this matter. OG&E and the other parties in this matter agreed to ask the APSC to approve the settlement agreement including the following: (i) pre-approval of system-wide deployment of smart grid technology in Arkansas and authorization for OG&E to begin recovering the prudently incurred costs of the Arkansas system-wide deployment of smart grid technology through a rider mechanism that will become effective in accordance with the order approving the settlement agreement; (ii) cost recovery through the rider would commence when all of the smart meters to be deployed in Arkansas are in service; (iii) OG&E guarantees that customers will receive certain operations and maintenance cost reductions resulting from the smart grid deployment as a credit to the recovery rider; and (iv) the stranded costs associated with OG&E's existing meters which are being replaced by smart meters will be accumulated in a regulatory asset and recovered in base rates beginning after an order is issued in OG&E's next general rate case. OG&E currently expects to spend $14 million, net of funds from the U.S. Department of Energy grant, in capital expenditures to implement smart grid in Arkansas pursuant to the settlement agreement. On August 3, 2011, the APSC issued an order in this matter approving the settlement agreement.

OG&E FERC Transmission Rate Incentive Filing    

On February 18, 2011, OG&E submitted to the FERC a request seeking limited transmission rate incentives for five transmission projects.  OG&E requested recovery of 100 percent of all prudently incurred construction work in progress in rate base for five 345 kilovolt Extra High Voltage transmission projects to be constructed and owned by OG&E within the SPP's region.  OG&E also requested to recover 100 percent of all prudently incurred development and construction costs if the transmission projects are abandoned or cancelled, in whole or in part, for reasons beyond OG&E's control.  On April 19, 2011, the FERC granted these incentives for the Sooner-Rose Hill, Sunnyside-Hugo and Balanced Portfolio 3E transmission projects discussed below.

OG&E Pension Tracker Modification Filing

On February 22, 2011, OG&E filed an application with the OCC requesting that OG&E's pension tracker be modified to include the difference between the level of retiree medical costs authorized in OG&E's last rate case and the current level of these expenses as a regulatory liability, effective January 1, 2011.  On June 23, 2011, a settlement agreement was filed by parties in the case stating that the pension tracker should be modified as proposed by OG&E and that the level of retiree medical costs included in base rates will be reviewed and determined in OG&E's next rate case. On September 27, 2011, the OCC issued an order in this matter approving the settlement agreement.

OG&E Demand and Energy Efficiency Program Filing

To build on the success of its earlier programs and further promote energy efficiency and conservation for each class of OG&E customers, on March 15, 2011, OG&E filed an application with the APSC seeking approval of several programs, ranging from residential weatherization to commercial lighting.  In seeking approval of these programs, OG&E also sought recovery of the program and related costs through a rider that would be added to customers' electric bills. On June 30, 2011, the APSC issued an order approving OG&E's energy efficiency plan for 2011 and approving OG&E's energy efficiency cost recovery rider for 2011. In Arkansas, OG&E's program is expected to cost $7.0 million over a three-year period and is expected to increase the average residential electric bill by $1.47 per month. 

FERC Order No. 1000, Final Rule on Transmission Planning and Cost Allocation

On July 21, 2011, the FERC issued Order No. 1000, which revised the FERC's existing regulations governing the process for planning enhancements and expansions of the electric transmission grid in a particular region, along with the corresponding process for allocating the costs of such expansions. Order No. 1000 applies only to "new transmission facilities," which are described as those subject to evaluation or reevaluation (under the applicable local or regional transmission planning process) subsequent to the effective date of the regulatory compliance filings required by the rule, which are expected to be filed during the third quarter of 2012. Order No. 1000 leaves to individual regions to determine whether a previously-approved project is subject to reevaluation and is therefore governed by the new rule.

Order No. 1000 requires, among other things, public utility transmission providers, such as the SPP, to participate in a process that produces a regional transmission plan satisfying certain standards, and requires that each such regional process consider transmission needs driven by public policy requirements (such as state or Federal policies favoring increased use of renewable energy resources). Order No. 1000 also directs public utility transmission providers to coordinate with neighboring transmission planning regions. In addition, Order No. 1000 establishes specific regional cost allocation principles and directs public utility transmission providers to participate in regional and interregional transmission planning processes that satisfy these principles.
    
On the issue of determining how entities are to be selected to develop and construct the specific transmission projects, Order No. 1000 directs public utility transmission providers to remove from the FERC-jurisdictional tariffs and agreements provisions that establish any federal "right of first refusal" for the incumbent transmission owner (such as OG&E) regarding transmission facilities selected in a regional transmission planning process, subject to certain limitations. However, Order No. 1000 is not intended to affect the right of an incumbent transmission owner (such as OG&E) to build, own and recover costs for upgrades to its own transmission facilities, and Order No. 1000 does not alter an incumbent transmission owner's use and control of existing rights of way. Order No. 1000 also clarifies that incumbent transmission owners may rely on regional transmission facilities to meet their reliability needs or service obligations. The SPP currently has a "right of first refusal" for incumbent transmission owners and this provision has played a role in OG&E being selected by the SPP to build various transmission projects in Oklahoma.
    
OGE Energy is continuing to evaluate Order No. 1000 and cannot at this time determine its precise impact on OG&E. Nevertheless, at the present time, OGE Energy has no reason to believe that the implementation of Order No. 1000 will impact OG&E's transmission projects currently under development and construction for which OG&E has received a notice to proceed from the SPP.
 
Enogex FERC Section 311 2007 Rate Case
 
On October 1, 2007, Enogex made its required triennial rate filing at the FERC to update its Section 311 maximum interruptible transportation rates for Section 311 service in the East Zone and West Zone. Enogex's filing requested an increase in the maximum zonal rates and proposed to place such rates into effect on January 1, 2008.  A number of parties intervened and some also filed protests. Enogex did not place the increased rates set forth in its October 2007 rate filing into effect but rather continued to provide interruptible Section 311 service under the maximum Section 311 rates for both zones approved by the FERC in the previous rate case. A final settlement was filed with the FERC on August 5, 2010. With the filing of Enogex's Section 311 2009 rate case discussed below, the rate period for the 2007 rate case became a limited locked-in period from January 2008 through May 2009. On October 13, 2011, the FERC issued an order in this matter approving the settlement agreement, providing that Enogex's rates from its previous rate case remain in effect and that the MEP lease agreement discussed below would be addressed in Enogex's Section 311 2009 rate case. This matter is now closed.
 
Enogex FERC Section 311 2009 Rate Case
 
On March 27, 2009, Enogex filed a petition for rate approval with the FERC to set the maximum rates for its new firm East Zone Section 311 transportation service and to revise the rates for its existing East and West Zone interruptible Section 311 transportation service. In anticipation of offering this new service, Enogex had filed with the FERC, as required by the FERC's regulations, a revised Statement of Operating Conditions Applicable to Transportation Services to describe the terms, conditions and operating arrangements for the new service.  Enogex made the Statement of Operating Conditions filing on February 27, 2009.  Enogex began offering firm East Zone Section 311 transportation service on April 1, 2009. The revised East and West Zone zonal rates for the Section 311 interruptible transportation service became effective June 1, 2009. The rates for the firm East Zone Section 311 transportation service and the increase in the rates for East and West Zone and interruptible Section 311 service were collected, subject to refund, pending the FERC approval of the proposed rates. A number of parties intervened in both the rate case and the Statement of Operating Conditions filing and some additionally filed protests. On January 4, 2010, the FERC Staff submitted an offer proposing various adjustments to Enogex's filed cost of service. On April 27, 2010, Enogex submitted comments to the FERC Staff stating that it would agree to the offer, contingent upon all parties agreeing to support or not oppose. On October 4, 2011, Enogex filed a settlement agreement with the FERC which included a proposed refund to shippers of $2.1 million related to the increase in the rates for East and West Zone and interruptible Section 311 service which were collected, subject to refund, pending the FERC approval of the proposed rates. This refund was made to shippers in January 2012. On December 16, 2011, the FERC issued an order approving the settlement agreement. Also, as discussed below, the MEP lease agreement was addressed in this rate case.

On November 13, 2007, one of the protesting intervenors filed to consolidate the Enogex 2007 rate case with a separate Enogex application pending before the FERC allowing Enogex to lease firm capacity to MEP and with separate applications filed by MEP with the FERC for a certificate to construct and operate the MEP pipeline and to lease firm capacity from Enogex. Enogex and MEP separately opposed this intervenor's protests and assertions in its initial and subsequent pleadings. On July 25, 2008, the FERC issued an order (i) approving the MEP project including the approval of a limited jurisdiction certificate and (ii) authorizing the Enogex lease agreement with MEP. Accordingly, Enogex proceeded with the construction of facilities necessary to implement this service. On August 25, 2008, a protestor sought rehearing which the FERC denied. Enogex commenced service to MEP under the lease agreement on June 1, 2009. On July 16, 2009, the protestor filed, with the United States Court of Appeals for the District of Columbia Circuit, a petition for review of the FERC's orders approving the MEP construction and the MEP lease of capacity from Enogex requesting that such orders be modified or set aside on the grounds that they are arbitrary, capricious and contrary to law.  On December 28, 2010, the Court of Appeals issued an opinion generally upholding the FERC's orders, but remanding the case for further explanation of one aspect of the FERC's reasoning.  The Court of Appeals emphasized that it was not vacating the FERC's orders and that its approval of the Enogex lease agreement with MEP remains in effect and legally binding.  On remand, the FERC was to clarify that its decision was based on a finding that the lease does not adversely affect existing customers on Enogex's system.  On January 21, 2011, Apache Corporation filed a motion asking the FERC to establish procedures on remand and to either condition the lease on Enogex's willingness to provide firm Section 311 transportation service to existing customers on all portions of its system or to establish an expedited briefing schedule.  On February 7, 2011, Enogex, MEP and Chesapeake Energy Corporation filed a joint answer asking the FERC to find, among other things, that the reduction in the amount of interruptible transportation capacity available due to the MEP lease did not have an adverse affect on Apache Corporation and to acknowledge that Apache Corporation's request to condition the lease on the provision of West Zone 311 firm transportation service has been addressed as Enogex filed a rate case on January 28, 2011 proposing to implement such service effective March 1, 2011. On March 1, 2011, Apache Corporation filed an answer seeking to refute some of the arguments presented in the joint answer filed by Enogex, MEP and Chesapeake Energy Corporation.  On March 3, 2011, the FERC issued an order on remand affirming the authorizations previously granted to Enogex and MEP and clarifying the applicable legal standard in response to the court's directive.  On April 4, 2011, Apache Corporation filed a request for rehearing of the FERC's order on remand. On September 29, 2011, the FERC issued an order denying Apache Corporation's motion for rehearing. Apache Corporation did not appeal the FERC's March 3, 2011 order on remand and/or the September 29, 2011 order denying rehearing. This matter is now closed.

Pending Regulatory Matters

OG&E 2011 Oklahoma Rate Case Filing

As part of the Joint Stipulation and Settlement Agreement reached in OG&E's 2009 Oklahoma rate case filing, the parties agreed that OG&E would file a rate case on or before June 30, 2011. On May 27, 2011, OG&E requested an extension until the end of July 2011 for filing the Oklahoma rate case. On July 28, 2011, OG&E filed its application with the OCC requesting an annual rate increase of $73.3 million, or a 4.3 percent increase in its rates. OG&E is requesting a return on equity of 11.00 percent based on a common equity percentage of 53 percent. Each 0.10 percent change in the requested return on equity affects the requested rate increase by $3.0 million. In its application, OG&E seeks to recover increases in its operating costs and to begin earning on approximately $500 million of new capital investments made on behalf of its Oklahoma customers during the previous two and one-half years. On November 9, 2011, the OCC Staff recommended a $6.2 million annual rate decrease based on a return on equity of 9.81 percent and a common equity percentage of 53 percent. The staff of the Oklahoma Attorney General recommended a return on equity of 9.818 percent and a common equity percentage of 49.5 percent. The staff of the Oklahoma Attorney General did not recommend a specific revenue requirement, but OG&E believes that adoption of the staff of the Oklahoma Attorney General's recommendations would result in a rate decrease. The Oklahoma Industrial Electric Consumers recommended a $56 million annual rate decrease based on a return on equity of 9.5 percent and a common equity percentage of 48 percent. OG&E filed rebuttal testimony on November 29, 2011 on the revenue requirement testimony filed by the parties on November 9, 2011. On November 16, 2011, the parties filed cost-of-service and rate design testimony and OG&E filed rebuttal testimony in those areas on December 2, 2011. The hearing in this matter began on December 13, 2011. OG&E expects to receive an order from the OCC in the first quarter of 2012.

OG&E Fuel Adjustment Clause Review for Calendar Year 2010
On August 19, 2011, the OCC Staff filed an application for a public hearing to review and monitor OG&E's application of the 2010 fuel adjustment clause. On October 18, 2011, OG&E responded by filing the necessary information and documents to satisfy the OCC's minimum filing requirement rules. A procedural schedule has not yet been established in this matter.
OG&E Contract and Wind Energy Purchase Agreement Filing

On December 1, 2011, OG&E filed an application with the OCC requesting approval of a 20-year agreement that is intended to provide wind power to help meet the current and future power generation needs of Oklahoma State University. The project calls for OG&E to contract with NextEra Energy to build a 60 MW wind farm near Blackwell, Oklahoma, to support the Oklahoma State University project in which NextEra will build, own and operate the wind farm and OG&E will purchase the electric output. A procedural schedule has not yet been established in this matter. OG&E expects to receive a decision from the OCC in the first quarter of 2012.

SPP Transmission/Substation Projects
The SPP is a regional transmission organization under the jurisdiction of the FERC that was created to ensure reliable supplies of power, adequate transmission infrastructure and competitive wholesale prices of electricity. The SPP does not build transmission though the SPP's tariff contains rules that govern the transmission construction process. Transmission owners complete the construction and then own, operate and maintain transmission assets within the SPP region. When the SPP Board of Directors approves a project, the transmission provider in the area where the project is needed currently has the first obligation to build; however, the process for deciding which entity constructs and owns a project may change as a result of FERC Order. No. 1000 discussed above.
There are several studies currently under review at the SPP including a 20-year plan to address issues of regional and interregional importance. The 20-year plan suggests overlaying the SPP footprint with a 345 kilovolt transmission system and integrating it with neighboring regional entities. In 2009, the SPP Board of Directors approved a new report that recommended restructuring the SPP's regional planning processes to focus on the construction of a robust transmission system, large enough in both scale and geography, to provide flexibility to meet the SPP's future needs. OG&E expects to actively participate in the ongoing study, development and transmission growth that may result from the SPP's plans.
In 2007, the SPP notified OG&E to construct 44 miles of a new 345 kilovolt transmission line which will originate at OG&E's existing Sooner 345 kilovolt substation and proceed generally in a northerly direction to the Oklahoma/Kansas Stateline (referred to as the Sooner-Rose Hill project). At the Oklahoma/Kansas Stateline, the line will connect to the companion line being constructed in Kansas by Westar Energy. Construction of the line began in early 2011 and the line is estimated to be in service by mid-2012 at an estimated cost of $45 million for OG&E.
In January 2009, OG&E received notification from the SPP to begin construction on 50 miles of a new 345 kilovolt transmission line and substation upgrades at OG&E's Sunnyside substation, among other projects. In April 2009, Western Farmers Electric Cooperative assigned to OG&E the construction of 50 miles of line designated by the SPP to be built by Western Farmers Electric Cooperative.  The new line will extend from OG&E's Sunnyside substation near Ardmore, Oklahoma, 123.5 miles to the Hugo substation owned by Western Farmers Electric Cooperative near Hugo, Oklahoma.  The project cost is estimated at $155 million for OG&E. OG&E began preliminary line routing and acquisition of rights-of-way in June 2009. Construction began in January 2011. When construction is completed, which is expected in mid-2012, the SPP will allocate a portion of the annual revenue requirement to OG&E customers according to the regional cost allocation mechanism as provided in the SPP tariff for application to such improvements.
On April 28, 2009, the SPP approved the Balanced Portfolio 3E projects.  Balanced Portfolio 3E includes four projects to be built by OG&E and includes: (i) construction of 135 miles of transmission line from OG&E's Seminole substation in a northeastern direction to OG&E's Muskogee substation at an estimated cost of $160 million for OG&E, which is expected to be in service by late 2013, (ii) construction of 96 miles of transmission line from OG&E's Woodward District Extra High Voltage substation in a southwestern direction to the Oklahoma/Texas Stateline to a companion transmission line to be built by Southwestern Public Service to its Tuco substation at an estimated cost of $145 million for OG&E, which is expected to be in service by mid-2014, (iii) construction of 39 miles of transmission line from OG&E's Sooner substation in an eastern direction to the Grand River Dam Authority Cleveland substation at an estimated cost of $60 million for OG&E, which is expected to be in service by late 2012 and (iv) construction of a new substation near Anadarko which consisted of a 345/138 kilovolt transformer and substation breakers and was built in OG&E's portion of the Cimarron-Lawton East Side 345 kilovolt line at an estimated cost of $15 million for OG&E, which was placed in service in December 2011.  On June 19, 2009, OG&E received a notice to construct the Balanced Portfolio 3E projects from the SPP.  On July 23, 2009, OG&E responded to the SPP that OG&E will construct the Balanced Portfolio 3E projects discussed above beginning in early 2011.
On April 27, 2010, the SPP approved, contingent upon approval by the FERC of a regional cost allocation methodology filed with the FERC by the SPP, a set of transmission projects titled "Priority Projects." The Priority Projects consist of several transmission projects, two of which have been assigned to OG&E. The 345 kilovolt projects include: (i) construction of 99 miles of transmission line from OG&E's Woodward District Extra High Voltage substation to a companion transmission line to be built by Southwestern Public Service to its Hitchland substation in the Texas Panhandle at an estimated cost of $185 million for OG&E, which is expected to be in service by mid-2014 and (ii) construction of 77 miles of transmission line from OG&E's Woodward District Extra High Voltage substation to a companion transmission line at the Kansas border to be built by either Mid-Kansas Electric Company or another company assigned by Mid-Kansas Electric Company at an estimated cost of $150 million to OG&E, which is expected to be in service by late 2014. On June 17, 2010, the FERC approved the cost allocation filed by the SPP and notices to construct these Priority Projects were issued by the SPP on June 30, 2010. On September 27, 2010, OG&E responded to the SPP that OG&E will construct the Priority Projects discussed above beginning in June 2012. The scope of the Woodward District Extra High Voltage substation/Kansas border Priority Project was subsequently revised and the SPP Board of Directors approved this revision in October 2010. The SPP issued a revised notice to construct for this Priority Project on November 22, 2010. On February 4, 2011, OG&E responded to the SPP that OG&E will construct the revised Priority Project.
The capital expenditures related to the Sooner-Rose Hill, Sunnyside-Hugo, Balanced Portfolio 3E and Priority Projects are presented in the summary of capital expenditures for known and committed projects in "Item 7. Management's Discussion and Analysis of Financial Condition and Results of Operations - Liquidity and Capital Resources - Future Capital Requirements and Financing Activities."
Enogex Storage Statement of Operating Conditions Filing

On August 31, 2010, Enogex filed via eTariff with the FERC a new Statement of Operating Conditions applicable to storage services that replaced Enogex's existing storage Statement of Operating Conditions effective July 30, 2010.  Among other things, the new storage Statement of Operating Conditions updates the general terms and conditions for providing storage services. A FERC order is pending.

Enogex FERC Section 311 2011 Rate Case
 
On January 28, 2011, Enogex submitted a new rate filing to the FERC to set the maximum rate for a new firm Section 311 transportation service in the West Zone of its system and to revise the currently effective maximum rates for Section 311 interruptible transportation service in the East Zone and West Zone.  Along with establishing the rate for a new firm service in the West Zone, Enogex's filing requested a decrease in the maximum interruptible zonal rates in the West Zone and to retain the currently effective rates for firm and interruptible services in the East Zone.  Enogex reserved the right to implement the higher rates for firm and interruptible services in the East Zone supported by the cost of service to the extent an expeditious settlement agreement cannot be reached in the proceeding.  Enogex proposed that the rates be placed into effect on March 1, 2011.  The deadline for interventions and protests on Enogex's filing was November 28, 2011 and no protests were filed.  On January 10, 2012, Enogex filed a settlement agreement with the FERC. The deadline for comments to the filing was January 17, 2012, and no comments opposing the settlement were filed. A FERC order is pending.
 
Enogex 2011 Fuel Filing
 
On February 28, 2011, Enogex submitted its annual fuel filing to establish the fixed fuel percentages for its East Zone and West Zone for the upcoming fuel year (April 1, 2011 through March 31, 2012).  Along with the revised fuel percentages, Enogex also requested authority to revise its Statement of Operating Conditions to permanently change the annual filing date to February 28.  The deadline for interventions and protests on Enogex's filing was March 15, 2011, and no protests were filed.  A FERC order is pending.