XML 112 R62.htm IDEA: XBRL DOCUMENT v2.4.0.8
Contingent Liabilities (Details) (USD $)
In Millions, unless otherwise specified
6 Months Ended
Jun. 30, 2013
Loss Contingencies [Line Items]  
Business Acquisition, Purchase Price Allocation, Environmental Liabilities Assumed $ 325
Department of Justice Lawsuit Against Pratt and Whitney [Member]
 
Loss Contingencies [Line Items]  
Loss Contingency Lawsuit Filing Date 1999
Loss Contingency Allegations As previously disclosed, the United States government sued us in 1999 in the United States District Court for the Southern District of Ohio, claiming that Pratt & Whitney violated the civil False Claims Act and common law. The claims relate to the “Fighter Engine Competition” between Pratt & Whitney's F100 engine and General Electric's F110 engine. The government alleged that it overpaid for F100 engines under contracts awarded by the U.S. Air Force in fiscal years 1985 through 1990 because Pratt & Whitney inflated its estimated costs for some purchased parts and withheld data that would have revealed the overstatements. At trial, which ended in April, 2005, the government claimed Pratt & Whitney's liability to be approximately $624 million.
Loss Contingency, Settlement Agreement, Terms On June 17, 2013, the trial court awarded the government approximately $473 million in damages and penalties, plus prejudgment interest in an amount to be determined. On July 1, 2013, the trial court, after determining the amount of prejudgment interest, entered judgment in favor of the government in the amount of approximately $664 million. The trial court also awarded postjudgment interest on the full amount of the judgment to accrue from July 2, 2013, at the federal variable interest rate determined pursuant to 28 U.S.C. § 1961. The judgment included four different components of damages: (1) common law damages of approximately $109 million; (2) prejudgment interest on common law damages of approximately $191 million; (3) False Claims Act treble damages of approximately $357 million; and (4) penalties of approximately $7 million. The penalty component of the judgment previously was affirmed by the United States Court of Appeals in 2010.
Loss Contingency Period Of Occurrence fiscal years 1985 through 1990
Loss Contingency Damages Sought 624
Loss Contingency Actions Taken By Court Arbitrator Or Mediator On August 1, 2008, the trial court held that the Air Force had not suffered any actual damages because Pratt & Whitney had made significant price concessions after the alleged overstatements were made. However, the trial court judge found that Pratt & Whitney violated the False Claims Act due to inaccurate statements contained in its 1983 initial engine pricing proposal. In the absence of actual damages, the trial court awarded the government the maximum civil penalty of approximately $7 million, or $10,000 for each of the 709 invoices Pratt & Whitney submitted in 1989 and later under the contracts.
Loss Contingency Actions Taken By Plaintiff And Defendant In September 2008, both the government and UTC appealed the decision to the United States Court of Appeals for the Sixth Circuit. On November 18, 2010, the Sixth Circuit affirmed Pratt & Whitney's liability under the False Claims Act, but remanded the case to the trial court for further proceedings on the issues of False Claims Act damages and common law liability and damages.
Loss Contingency Actions Taken By Defendant We strongly disagree with the trial court's analysis and conclusions. We will file an appeal from the judgment to the United States Court of Appeals for the Sixth Circuit on or before September 1, 2013. Based on our analysis, we continue to believe that there is no basis for any common law liability for the inaccurate statements. We also believe that the government suffered no actual damages as a result of the inaccurate statements made in 1983 and, therefore, there is no basis in fact or law for the award of common law damages, prejudgment interest or False Claims Act treble damages. If, contrary to our expectations, all or any portion of the judgment should ultimately be affirmed, we estimate a range of possible loss from approximately $24 million to $657 million in excess of amounts previously accrued, plus postjudgment interest. The outcome of this matter could result in a material adverse effect on our results of operations in the period in which a liability would be recognized and cash flows for the period in which damages would be paid.
Loss Contingency Settlement Agreement Date 6/17/2013
Loss Contingency, Range of Possible Loss, Minimum 24
Loss Contingency, Range of Possible Loss, Maximum 657
Loss Contingency Damages Awarded Value, Not Including Interest 473
Loss Contingency, Damages Awarded, Value $ 664
Department of Defense Contract Claim Against Sikorsky [Member]
 
Loss Contingencies [Line Items]  
Loss Contingency Lawsuit Filing Date December 2008
Loss Contingency Allegations As previously disclosed, in December 2008, the Department of Defense (DOD) issued a contract claim against Sikorsky to recover overpayments the DOD alleges that it made to Sikorsky since January 2003 in connection with cost accounting changes approved by the DOD and implemented by Sikorsky in 1999 and 2006. These changes relate to the calculation of material overhead rates in government contracts. The DOD claimed that Sikorsky's liability was approximately $95 million (including interest through March 31, 2013).
Loss Contingency Damages Sought $95 million (including interest through March 31, 2013)
Loss Contingency Actions Taken By Plaintiff And Defendant We believed this claim was without merit and Sikorsky filed an appeal in December 2009 with the U.S. Court of Federal Claims. Trial in the matter concluded in January 2013 and on March 22, 2013, the U.S. Court of Federal Claims issued a written decision in favor of Sikorsky determining that the DOD had failed to prove its claims because Sikorsky's calculation of material overhead complied with the cost accounting standards. While the DOD has appealed this decision, we do not believe the ultimate resolution of this matter will have a material adverse effect on our competitive position, results of operations, cash flows or financial condition.
Loss Contingency Settlement Agreement Date March 22, 2013
US Air Force Claim Against Pratt And Whitney [Member]
 
Loss Contingencies [Line Items]  
Loss Contingency Lawsuit Filing Date June 18, 2012
Loss Contingency Allegations On June 18, 2012, the trial court found that Pratt & Whitney had breached obligations imposed by common law based on the same conduct with respect to which the court previously found liability under the False Claims Act. Under the common law claims, the U.S. Air Force is entitled to seek damages for events occurring before March 3, 1989, which are not recoverable under the False Claims Act.
Loss Contingency Damages Sought 624
German Tax Office Against Otis [Member]
 
Loss Contingencies [Line Items]  
Loss Contingency Lawsuit Filing Date August 3, 2012
Loss Contingency Allegations UTC has been involved in administrative review proceedings with the German Tax Office concerning €203 million (approximately $266 million) of tax benefits that we have claimed related to a 1998 reorganization of the corporate structure of Otis operations in Germany. A portion of these tax benefits were disallowed by the local German Tax Office on July 5, 2012, as a result of the audit of tax years 1999 to 2000. The legal and factual issues relating to the denial of the tax benefits center on the interpretation and application of a German tax law.
Loss Contingency Damages Sought €203 million (approximately $266 million)
Loss Contingency Actions Taken By Defendant On August 3, 2012, the Company filed suit in the local German tax court and intends to litigate vigorously the matter to conclusion. We do not believe the resolution of this matter will have a material adverse effect on our results of operations, cash flows or financial condition.