XML 25 R14.htm IDEA: XBRL DOCUMENT v3.7.0.1
Commitments and Contingencies
6 Months Ended
Jun. 30, 2017
Commitments and Contingencies  
Commitments and Contingencies

 

NOTE 9 — Commitments and Contingencies

 

In September 1999, the Sports Authority of the County of Wilson (Tennessee) issued $25,900,000 in Variable Rate Tax Exempt Infrastructure Revenue Bonds, Series 1999, to acquire, construct and develop certain public infrastructure improvements which benefit Nashville Superspeedway, of which $16,300,000 was outstanding at June 30, 2017.  Annual principal payments range from $900,000 in September 2017 to $1,600,000 in 2029 and are payable solely from sales taxes and incremental property taxes generated from the facility.  These bonds are direct obligations of the Sports Authority and therefore have historically not been required to be recorded on our consolidated balance sheet.  If the sales taxes and incremental property taxes (“applicable taxes”) are insufficient for the payment of principal and interest on the bonds, we would become responsible for the difference.  In the event we were unable to make the payments, they would be made pursuant to a $16,573,000 irrevocable direct-pay letter of credit issued by our bank group.  We are exposed to fluctuations in interest rates for these bonds.

 

As of June 30, 2017 and December 31, 2016, $2,549,000 and $1,761,000, respectively, was available in the sales and incremental property tax fund maintained by the Sports Authority to pay the remaining principal and interest due under the bonds.  During 2016, we paid $982,000 into the sales and incremental property tax fund and $1,197,000 was deducted from the fund for principal and interest payments.  If we fail to maintain the letter of credit that secures the bonds or we allow an uncured event of default to exist under our reimbursement agreement relative to the letter of credit, the bonds would be immediately redeemable.

 

Nashville Superspeedway no longer promotes motorsports events and has not entered into sanction agreements with NASCAR since 2011.  We lease the facility on a short term basis to third parties from time to time.  In 2011 we recorded a $2,250,000 provision for contingent obligation reflecting the present value of the estimated portion of the revenue bonds debt service that may not be covered by the projected sales and incremental property taxes from the facility.  Due to changing interest rates, the provision for contingent obligation increased by $11,000 and $52,000, and $70,000 and $56,000 in the three and six-month periods ended June 30, 2017 and 2016, respectively, and is $1,854,000 at June 30, 2017.  An increase in interest rates would result in an increase in the portion of debt service not covered by applicable taxes and therefore an increase in our liability.

 

We are also a party to ordinary routine litigation incidental to our business.  Management does not believe that the resolution of any of these matters is likely to have a material adverse effect on our results of operations, financial position or cash flows.