Lease Arrangements

On December 9, 2013, the Company entered into a Lease Agreement, as amended on December 23, 2013, April 15, 2014, and January 29, 2021 (the “Lease Agreement”), for its corporate headquarters, which occupies approximately 36,350 square feet of office, storage and light manufacturing space and is classified as an operating lease for financial reporting purposes. The expiration date of the base term of the Lease Agreement in effect as of December 31, 2023 is October 31, 2026 and the terms of the Lease Agreement contain no early termination provisions. Provided there is no outstanding uncured event of default under the Lease Agreement, the Company has an option to extend the lease term for a period of five years. The Company’s option to extend the term of the Lease Agreement must be exercised in writing on or before 270 days prior to expiration of the then-current term. If the option is exercised, the monthly minimum rent for each of the extended terms will be adjusted to the then prevailing fair market rate.

The Company took possession of the leased property on May 23, 2014, once certain improvements to the leased space were completed and did not have access to the property before this date. Upon execution of the third amendment to the Lease Agreement (the “Lease Amendment”) on January 29, 2021, the Lease Amendment included a rent abatement in the amount of approximately $214,000, which is reflected in the rent payments used in the calculation of the right-of-use (“ROU”) asset and lease liability once remeasured upon the execution of the Lease Amendment to extend the lease term. The Lease Amendment also included an allowance for leasehold improvements offered by the landlord in an amount not to exceed approximately $545,000. As of the quarter ended December 31, 2023, the Company has been reimbursed approximately $506,000 by the landlord for qualified leasehold improvements in accordance with the terms of the Lease Amendment. This reimbursement by the landlord reduced the remaining ROU asset by the same amount and is being recognized prospectively over the remaining term of the lease.

The Company has no other material operating leases and is not party to leases that would qualify for classification as a finance lease, variable lease, or short-term lease.

As of December 31, 2023, the Company’s balance sheet classifications of its leases are as follows:

Operating Leases:
     
Noncurrent operating lease ROU assets
 
$
1,872,832
 
 
       
Current operating lease liabilities
 
$
892,147
 
Noncurrent operating lease liabilities
   
1,631,724
 
Total operating lease liabilities
 
$
2,523,871
 

The Company’s total operating lease cost for the three months ended December 31, 2023 and 2022 was approximately $175,000 for each period. The Company’s total operating lease cost for the six months ended December 31, 2023 and 2022 was approximately $349,000 for each period.

As of December 31, 2023, the Company’s estimated incremental borrowing rate used and assumed discount rate with respect to operating leases was 2.81% and the remaining operating lease term was 2.83 years.

As of December 31, 2023, the Company’s remaining future payments under operating leases for each fiscal year ending June 30 are as follows:

2024
 
$
450,852
 
2025
   
918,236
 
2026
   
943,487
 
2027
   
317,327
 
Total lease payments
  $
2,629,902
 
Less: imputed interest
   
106,031
 
Present value of lease payments
   
2,523,871
 
Less: current lease obligations
   
892,147
 
Total long-term lease obligations
 
$
1,631,724
 

The Company makes cash payments for amounts included in the measurement of its lease liabilities. During the three months ended December 31, 2023 and 2022, cash paid for operating leases was approximately $241,000 and $235,000, respectively. During the six months ended December 31, 2023 and 2022, cash paid for operating leases was approximately $479,000 and $466,000, respectively.

Purchase Commitments

On December 12, 2014, the Company entered into an exclusive supply agreement (the “Supply Agreement”) with Wolfspeed, Inc. (“Wolfspeed”), formerly known as Cree, Inc. Under the Supply Agreement, subject to certain terms and conditions, the Company agreed to exclusively purchase from Wolfspeed, and Wolfspeed agreed to exclusively supply, 100% of the Company’s required SiC materials in quarterly installments that must equal or exceed a set minimum order quantity. The initial term of the Supply Agreement was scheduled to expire on June 24, 2018, unless extended by the parties.

Effective June 22, 2018, the Supply Agreement was amended to extend the expiration date to June 25, 2023. The Supply Agreement was also amended to (i) provide the Company with one option, subject to certain conditions, to unilaterally extend the term of the Supply Agreement for an additional two-year period following expiration of the initial term; (ii) establish a process by which Wolfspeed may begin producing alternate SiC material based on the Company’s specifications that will give the Company the flexibility to use the materials in a broader variety of its products; and (iii) permit the Company to purchase certain amounts of SiC materials from third parties under limited conditions.

Effective June 30, 2020, the Supply Agreement was further amended to extend the expiration date to June 29, 2025, which may be extended again by mutual agreement of the parties. The Supply Agreement was also amended to, among other things, (i) spread the Company’s total purchase commitment under the Supply Agreement in the amount of approximately $52.95 million over the term of the Supply Agreement, as amended; (ii) establish a process by which Wolfspeed has agreed to accept purchase orders in excess of the agreed-upon minimum purchase commitment, subject to certain conditions; and (iii) permit the Company to purchase revised amounts of SiC materials from third parties under limited conditions.

The Company’s total purchase commitment under the Supply Agreement, as amended, until June 2025 is approximately $52.95 million, of which approximately $24.75 million remains to be purchased as of December 31, 2023. Over the life of the Supply Agreement, as amended, the Company’s future minimum annual purchase commitments of SiC crystals range from approximately $4.00 million to $10.00 million each year.

During the six months ended December 31, 2023 the Company made no purchases of SiC crystals. During the six months ended December 31, 2022 the Company purchased $1.80 million of SiC crystals from Wolfspeed pursuant to the terms of the Supply Agreement, as amended.

The Company has made no purchases of SiC crystals during the twelve-month period ended December 31, 2023. while engaged in discussions regarding the terms of the Supply Agreement.

On July 28, 2023, Wolfspeed initiated a confidential arbitration against the Company for breach of contract claiming damages, plus interest, costs, and attorneys’ fees. Wolfspeed has alleged that the Company failed to satisfy the purchase obligations provided in the Supply Agreement for Fiscal 2023 in the amount of $4.25 million and failed to pay for $3.30 million of SiC crystals Wolfspeed delivered to the Company. Wolfspeed further alleges that the Company intends to breach its remaining purchase obligations under the Supply Agreement, representing an additional $18.5 million in alleged damages.

While the Company is evaluating Wolfspeed’s claims, the Company disputes the amount sought, and intends to vigorously defend its position, including by asserting rights and defenses that the Company may have under the Supply Agreement at law and in equity. A hearing has been scheduled for September 30, 2024. The final determinations of liability arising from this matter will be made following comprehensive investigations, discovery and arbitration processes.