Commitments and Contingencies
12 Months Ended
Dec. 31, 2021
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies Commitments and Contingencies
Certain Fuel and Transportation Commitments
NRG has entered into long-term contractual arrangements to procure certain fuel and transportation services for the Company's generation assets.
As of December 31, 2021, the Company's minimum commitments under such outstanding agreements are estimated as follows:
Period(In millions)
2022$122 
202354 
202463 
202562 
202651 
Thereafter26 
Total(a)
$378 
(a)Actual fuel and transportation purchases are significantly higher than these estimated minimum unconditional long-term firm commitments with remaining term in excess of one year
For the years ended December 31, 2021, 2020 and 2019, the costs of certain fuel and transportation were $0.6 billion, $0.5 billion and $0.6 billion, respectively.
Purchased Energy Commitments
NRG has long-term contractual commitments related to electricity and natural gas products, including power purchases, gas transportation and storage of various quantities and durations, and renewable purchased power agreements under PPAs with third-party project developers, which are accounted for as NPNS. These contracts are not included in the consolidated balance sheet as of December 31, 2021. Minimum purchase commitment obligations are as follows as of December 31, 2021:
Period(In millions)
2022$1,566 
20231,036 
2024617 
2025382 
2026289 
Thereafter1,071 
Total(a)
$4,961 
(a)Actual energy purchases are significantly higher than these estimated minimum unconditional long-term firm commitments with remaining term in excess of one year
For the years ended December 31, 2021, 2020 and 2019, the costs of purchased energy were $12.8 billion, $1.8 billion and $2.6 billion, respectively.
First Lien Structure
NRG has granted first liens to certain counterparties on a substantial portion of property and assets owned by NRG and the guarantors of its senior debt. NRG uses the first lien structure to reduce the amount of cash collateral and letters of credit that it would otherwise be required to post from time to time to support its obligations under out-of-the-money hedges. To the extent that the underlying hedge positions for a counterparty are out-of-the-money to NRG, the counterparty would have a claim under the first lien program. As of December 31, 2021, hedges under the first lien were out-of-the-money for NRG on a counterparty aggregate basis.
Nuclear Insurance
STP maintains required insurance coverage for liability claims arising from nuclear incidents pursuant to the Price-Anderson Act. The current liability limit per incident is $13.8 billion, subject to change to account for the effects of inflation and the number of licensed reactors. An inflation adjustment must be made at least once every five years with the next adjustment expected to be effective no later than November 1, 2023. Under the Price-Anderson Act, owners of nuclear power plants in the U.S. are required to purchase primary insurance limits of $450 million for each operating site. In addition, the Price-Anderson Act requires an additional layer of protection through mandatory participation in a retrospective rating plan for power reactors resulting in an additional $13.3 billion in funds available for public liability claims. The current maximum assessment per incident, per reactor, is approximately $138 million, taking into account a 5% adjustment for administrative fees, payable at approximately $21 million per year, per reactor. NRG would be responsible for 44% of the maximum assessment, or $9 million per year, per reactor, and a maximum of $61 million per incident, per reactor. In addition, the U.S. Congress retains the ability to impose additional financial requirements on the nuclear industry to pay liability claims that exceed $13.8 billion for a single incident. The liabilities of the co-owners of STP with respect to the retrospective premium assessments for nuclear liability insurance are joint and several.
STP purchases insurance for property damage and site decontamination cleanup costs from Nuclear Electric Insurance Limited, or NEIL, and European Mutual Association for Nuclear Insurance, or EMANI, both of which are industry mutual insurance companies, of which STP is a member. STP has purchased $2.8 billion in limits for nuclear events and $1.0 billion in limits for non-nuclear events. The nuclear event limit remains the maximum available from NEIL. The upper $1.3 billion in nuclear events limits (excess of the first $1.5 billion in nuclear events limits) is a single limit blanket policy shared with two Diablo Canyon nuclear reactors, which have no affiliation with the Company. This shared limit is not subject to automatic reinstatement in the event of a loss. The NEIL primary policy covers both nuclear and non-nuclear property damage events, and a NEIL companion policy provides Accidental Outage coverage for the co-owners of STP's lost revenue following a property damage event, at a weekly indemnity limit of $3 million per unit up to a maximum of $274 million nuclear per unit and $184 million non-nuclear per unit, and is subject to an eight-week waiting period. NRG also purchases an Accidental Outage policy from NEIL, which provides protection for lost revenue due to an insurable event. This coverage allows for reimbursement up to $2 million per week per unit up to a maximum of $216 million nuclear and $144 million non-nuclear, and is subject to an eight-
week waiting period. Accidental Outage coverage amounts decrease in the event more than one unit at a station is out of service due to a common accident. Under the terms of the NEIL and EMANI policies, member companies may be assessed up to ten and six times their annual premiums respectively if the NEIL or EMANI Board of Directors determines their surplus has been depleted due to the payment of property losses at any of the licensed reactors in a single policy year. NEIL and EMANI require that their members maintain an investment grade credit rating or ensure their annual retrospective obligation by providing a financial guarantee, letter of credit, deposit premium, or an insurance policy. NRG has purchased an insurance policy from NEIL and EMANI to guarantee the Company's obligation; however note the NEIL aspect of this insurance will only respond to retrospective premium adjustments assessed within twenty-four months after the policy term, whereas NEIL's Board of Directors can make such an adjustment up to 6 years after the policy expires. All insurance coverage is subject to various sub limits and significant deductibles.
Contingencies
The Company's material legal proceedings are described below. The Company believes that it has valid defenses to these legal proceedings and intends to defend them vigorously. NRG records accruals for estimated losses from contingencies when information available indicates that a loss is probable and the amount of the loss, or range of loss, can be reasonably estimated. As applicable, the Company has established an adequate accrual for the applicable legal matters, including regulatory and environmental matters as further discussed in Note 24, Regulatory Matters, and Note 25, Environmental Matters. In addition, legal costs are expensed as incurred. Management has assessed each of the following matters based on current information and made a judgment concerning its potential outcome, considering the nature of the claim, the amount and nature of damages sought, and the probability of success. Unless specified below, the Company is unable to predict the outcome of these legal proceedings or reasonably estimate the scope or amount of any associated costs and potential liabilities. As additional information becomes available, management adjusts its assessment and estimates of such contingencies accordingly. Because litigation is subject to inherent uncertainties and unfavorable rulings or developments, it is possible that the ultimate resolution of the Company's liabilities and contingencies could be at amounts that are different from its currently recorded accruals and that such difference could be material.
In addition to the legal proceedings noted below, NRG and its subsidiaries are party to other litigation or legal proceedings arising in the ordinary course of business. In management's opinion, the disposition of these ordinary course matters will not materially adversely affect NRG's consolidated financial position, results of operations, or cash flows.
Environmental Lawsuits
Sierra club et al. v. Midwest Generation LLC — In 2012, several environmental groups filed a complaint against Midwest Generation with the Illinois Pollution Control Board ("IPCB") alleging violations of environmental law resulting in groundwater contamination. In June 2019, the IPCB found that Midwest Generation violated the law because it had improperly handled coal ash at four facilities in Illinois and caused or allowed coal ash constituents to impact groundwater. On September 9, 2019, Midwest Generation filed a Motion to Reconsider numerous issues, which the court granted in part and denied in part on February 6, 2020. The IPCB will hold hearings to determine the appropriate relief. Midwest Generation has been working with the Illinois EPA to address the groundwater issues since 2010.
Consumer Lawsuits
Similar to other energy service companies (“ESCOs”) operating in the industry, from time-to-time, the Company and/or its subsidiaries may be subject to consumer lawsuits in various jurisdictions where they sell natural gas and electricity.
Variable Price Cases — In the cases set forth below, referred to as the Variable Price Cases, such actions involve consumers alleging that one of the Company’s ESCOs promised that consumers would pay the same or less than they would have paid if they stayed with their default utility or previous energy supplier. The underlying claims of each case are similar and the Company continues to deny the allegations and is vigorously defending these matters. These matters were known and accrued for at the time of each acquisition.
XOOM Energy
XOOM Energy is a defendant in a putative class action lawsuit pending in New York. This case is in the discovery phase.
Direct Energy
There are three putative class actions pending against Direct Energy: (1) Linda Stanley v. Direct Energy (S.D.N.Y Apr. 2019) - The parties mediated in June and agreed on a settlement. On November 16, 2021, the Court granted preliminary approval of the settlement. The final approval hearing will be held on April 5, 2022. It may take several months to determine the final payout amount; (2) Martin Forte v. Direct Energy (N.D.N.Y. Mar. 2017) - The Court recently granted Direct Energy’s Motion for Summary Judgment effectively ending the matter at the district court level. It is likely that the plaintiff will appeal;
however, it is unlikely plaintiff will prevail; (3) Richard Schafer v. Direct Energy (W.D.N.Y. Dec. 2019; on appeal 2nd Cir. N.Y.) - The Court granted limited discovery that will end April 29, 2022. Summary judgement briefing is due on May 20, 2022.
Telephone Consumer Protection Act ("TCPA") Cases — In the cases set forth below, referred to as the TCPA Cases, such actions involve consumers alleging violations of the Telephone Consumer Protection Act of 1991, as amended, by receiving calls, texts or voicemails without consent in violation of the federal Telemarketing Sales Rule, and/or state counterpart legislation. The underlying claims of each case are similar. The Company denies the allegations asserted by plaintiffs and intends to vigorously defend these matters. These matters were known and accrued for at the time of the acquisition.
There are two putative class actions pending against Direct Energy: (1) Brittany Burk v. Direct Energy (S.D. Tex. Feb. 2019) - The Court denied Plaintiff's Motion for Class Certification and Motion for Substitution of a New Plaintiff on September 20, 2021. The parties reached a settlement of the plaintiff's individual claims and the Court has conditionally dismissed the matter; and (2) Matthew Dickson v. Direct Energy (N.D. Ohio Jan. 2018) - Direct Energy has filed a Third-Party Petition against its vendor, Total Marketing Concepts, LLC, who placed voicemails without consent from Direct Energy and in violation of the parties’ agreement. The case was stayed pending the outcome of an appeal to the Sixth Circuit based on the unconstitutionality of the TCPA during the period from 2015-2020. The Sixth Circuit found the TCPA was in effect during that period and remanded the case back to the trial court. Direct Energy refiled its motions along with supplements.
Winter Storm Uri Lawsuits
The Company has been named in certain property damage and wrongful death claims that have been filed in connection with Winter Storm Uri. At this time, the Company is unable to determine the extent or impact of these various litigation matters due to their preliminary nature. The Company intends to vigorously defend these matters.
Indemnifications and Other Contractual Arrangements
Washington-St. Tammany and Claiborne Electric Cooperative v. LaGen — On June 28, 2017, plaintiffs Washington-St. Tammany Electric Cooperative, Inc. and Claiborne Electric Cooperative, Inc. filed a lawsuit against LaGen in the United States District Court for the Middle District of Louisiana. The plaintiffs claimed breach of contract against LaGen for allegedly improperly charging the plaintiffs for costs related to the installation and maintenance of certain pollution control technology. Plaintiffs sought damages for the alleged improper charges and a declaration as to which charges were proper under the contract. In February 2020, the court dismissed this lawsuit without prejudice for lack of subject matter jurisdiction. On March 17, 2020, plaintiffs filed a lawsuit in the Nineteenth Judicial District Court for the Parish of East Baton Rouge in Louisiana alleging substantially the same matters. The Company anticipates a trial, in state court, to begin in 2023. On February 4, 2019, NRG sold the South Central Portfolio, including the entities subject to this litigation. However, NRG has agreed to indemnify the purchaser for certain losses suffered in connection therewith.