Asset Impairments
2016 Impairment Losses

Rockford As described in Note 3, Business Acquisitions and Dispositions, on May 12, 2016, the Company entered into an agreement with RA Generation, LLC to sell 100% of its interests in the Rockford generating stations for cash consideration of $55 million. The transaction triggered an indicator of impairment as the sale price was less than the carrying amount of the assets, and, as a result, the assets were considered to be impaired. The Company measured the impairment loss as the difference between the carrying amount of the assets and the agreed-upon sale price. The Company recorded an impairment loss of $17 million during the year ended December 31, 2016, to reduce the carrying amount of the assets held for sale to the fair market value.

Mandalay and Ormond Beach On May 26, 2016, the CPUC rejected a multi-year resource adequacy contract between Mandalay and SCE. Also during the second quarter of 2016, the Statewide Advisory Committee on Cooling Water Intake Structures, or SACCWIS, issued a draft April 2016 Report noting that CAISO plans to continue to assume in its transmission studies that Ormond Beach will not operate after December 31, 2020, the deadline for Ormond Beach compliance with California regulations to mitigate once-through cooling (OTC) impacts. The Company does not anticipate that contracts of sufficient value can be secured to support the significant investment required to design, permit, construct and operate measures required for OTC compliance. As a result, on May 6, 2016, the Company notified SACCWIS that it does not expect to continue to operate Ormond Beach beyond 2020. Additionally, during the second quarter of 2016, CAISO issued its Local Capacity Requirements report for 2017 indicating unfavorable changes within the local reliability areas in which both Mandalay and Ormond Beach are located. The culmination of these events were considered to be indicators of impairment and as a result, the Company performed impairment tests for the Mandalay and Ormond Beach assets. Based on the results of the impairment tests, the Company determined that the carrying amount of these assets was higher than the estimated future net cash flows expected to be generated by the respective assets and that the Mandalay and Ormond Beach assets were impaired. The fair value of the Mandalay and Ormond Beach operating units was determined using the income approach which utilizes estimates of discounted future cash flows, which were Level 3 fair value measurements and include key inputs such as forecasted contract prices, forecasted operating expenses and discount rates. The Company measured the impairment losses as the difference between the carrying amount of the Mandalay and Ormond Beach operating units and the present value of the estimated future net cash flows for each respective operating unit. The Company recorded an impairment loss of $16 million and $43 million for Mandalay and Ormond Beach, respectively, during the second quarter of 2016.

In addition, during the fourth quarter of 2016 the declining prices for resource adequacy contracts available in the reliability sub-area which Ormond Beach operates in further reduced anticipated cash flows to be generated from Ormond Beach through its anticipated retirement in 2020. This was considered to be an indicator of impairment and as a result, the Company performed an impairment test for the Ormond Beach assets. The Company determined that the carrying amount of these assets was higher than the estimated future net cash flows expected to be generated by the assets and that the Ormond Beach assets were impaired. The fair value of the Ormond Beach operating unit was determined using the income approach which utilizes estimates of discounted future cash flows, which were Level 3 fair value measurements and include key inputs such as forecasted contract prices, forecasted operating expenses and discount rates. During the fourth quarter of 2016, the Company recorded an additional impairment loss of $28 million for Ormond Beach.

Wind Facilities — During the fourth quarter of 2016, as the Company updated its estimated future cash flows in connection with the preparation of its annual budget, the Company determined that the cash flows for the Elbow Creek and Goat Wind projects, located in Texas and the Forward project, located in Pennsylvania were below the carrying value of the related assets, primarily driven by the declining merchant power prices in post-contract periods, and the assets were considered impaired. The fair values of the facilities were determined using an income approach by applying a discounted cash flow methodology to the long-term budgets for each respective plant. The income approach utilized estimates of discounted future cash flows, which were Level 3 fair value measurements and include key inputs, such as forecasted power prices, operations and maintenance expense and discount rates. The Company measured the impairment loss as the difference between the carrying amount and the fair value of the assets and recorded impairment losses of $117 million, $60 million and $6 million for Elbow Creek, Goat Wind and Forward, respectively.
Long Beach During the fourth quarter of 2016, the Company determined that by the end of 2017 it would retire its Long Beach generation station located in Long Beach, California. The generating station was not awarded a PPA, in the SCE's capacity auction during the fourth quarter of 2016 and the current PPA will expire on July 31, 2017. The Company considered this to be an indicator of impairment and performed an impairment test. The Company measured the impairment loss as the difference between the carrying amount and the fair value of the assets and recorded an impairment loss of $36 million.
Keystone and Conemaugh Leased Interests During the fourth quarter of 2016, the Company revised its estimated future cash flows in connection with the preparation of its annual budget. The Company noted the cash flows for the leased interests in Keystone and Conemaugh were below the carrying value of the related assets, primarily driven by a reduction in long-term energy and capacity prices in PJM, and the assets were impaired. The fair value of the interests in Keystone and Conemaugh were determined using the income approach which utilizes estimates of discounted future cash flows, which were Level 3 fair value measurements and include key inputs such as forecasted power, capacity and fuel prices, forecasted operating expenses, contractual lease payments and discount rates. The Company recorded impairment losses of $97 million and $10 million for Conemaugh and Keystone respectively, for the year ended December 31, 2016.
Pittsburg — During the fourth quarter of 2016, the Company determined that it would need to retire the Pittsburg facility earlier than anticipated as it did not receive a resource adequacy contract for 2017. The Company considered this to be a triggering event and tested the assets for impairment. The fair value of the facility was determined using an income approach and the Company recorded an impairment loss of $20 million to reduce the carrying amount to the value of the underlying land.
Other Impairments — During 2016, the Company recorded other impairment losses of $153 million, which included $23 million in excess SO2 allowances, $23 million for other intangible assets, $19 million in previously purchased solar panels, $18 million in deferred marketing expenses, $22 million in other investments and $48 million of other impairment losses.

Petra Nova Parish Holdings During the first quarter of 2016, management changed its plans with respect to its future capital commitments driven in part by the continued decline in oil prices. As a result, the Company reviewed its 50% interest in Petra Nova Parish Holdings for impairment utilizing the other-than-temporary impairment model. In determining fair value, the Company utilized an income approach and considered project specific assumptions for the future project cash flows. The carrying amount of the Company's equity method investment exceeded the fair value of the investment and the Company concluded that the decline is considered to be other-than-temporary. As a result, the Company measured the impairment loss as the difference between the carrying amount and the fair value of the investment and recorded an impairment loss of $140 million.

Community Wind North and Sherbino During the fourth quarter of 2016, the Company offered several projects to NRG Yield including its interest in Community Wind North. The offer price was below its current carrying amount and this decline in fair value was determined to be other-than-temporary. Accordingly, the Company recorded an impairment loss of $36 million to reduce its carrying amount to fair value. In addition, in connection with the preparation of the annual budget, the Company noted that due to the anticipated difficulty in refinancing Sherbino’s debt that will mature in 2018, the project’s fair value had decreased significantly below its carrying amount and this decline was determined to be other-than-temporary. Accordingly, the Company determined that an other-than-temporary impairment existed and recorded an impairment loss on its investment in Sherbino of $70 million.

2015 Impairment Losses

Seward As described in Note 3, Business Acquisitions and Dispositions, on November 24, 2015, the Company entered into an agreement with Robindale Energy Services, Inc. to sell Seward for cash consideration of $75 million. The transaction triggered an impairment indicator as the sale price was less than the carrying amount of the assets, and, as a result, the assets were considered to be impaired. The Company measured the impairment loss as the difference between the carrying amount of the assets and the agreed-upon sale price. The Company recorded an impairment loss of $134 million for the year ended December 31, 2015, to reduce the carrying amount of the assets held for sale to the fair market value.

Limestone and W.A. Parish During the fourth quarter of 2015, as the Company updated its estimates of future cash flows in connection with the preparation of its annual budget, it was noted that the cash flows for the Limestone and W.A. Parish coal-fired facilities located in Texas were lower than the carrying amount, primarily driven by declining power prices as the cost of commodities continues to decline and the assets were impaired. The fair value of the Limestone and W.A. Parish plants was determined using an income approach by applying a discounted cash flow methodology to the long-term budgets for each respective plant. The income approach utilized estimates of discounted future cash flows, which were Level 3 fair value measurements, and include key inputs such as forecasted power prices, fuel costs and emissions credit expense, forecasted operating and capital expenditures and discount rates. The Company measured the impairment loss as the difference between the carrying amount and the fair value of the assets and recognized impairment losses of $1,514 million and $1,295 million related to Limestone and W.A. Parish, respectively.

Huntley On August 25, 2015, the Company filed a notice with the NYSPSC of its intent to retire Huntley's operating units on March 1, 2016. The Company considered this to be an indicator of impairment and performed an impairment test for these assets under ASC 360, Property, Plant and Equipment. On October 14, 2015, the Company filed a cost-of-service filing at FERC in anticipation that the Huntley operating units would be needed for reliability purposes, proposing a reliability must run service agreement for a four-year period beginning on March 1, 2016. On October 30, 2015, NYISO released the results of its reliability study, indicating that the Huntley operating units are not needed for bulk system reliability. The Company considered the impact of the reliability study conducted and evaluated the estimated cash flows associated with the facility. Accordingly, the Company determined that the carrying amount of the assets was higher than the estimated future net cash flows expected to be generated by the assets and that the assets were impaired. The fair value of the Huntley operating units was determined using the income approach. The income approach utilized estimates of discounted future cash flows, which were Level 3 fair value measurements, and include key inputs such as forecasted contract prices, forecasted operating expenses and discount rates. The Company recorded an impairment loss of $132 million during the year ended December 31, 2015.

Dunkirk The Company signed a ten-year agreement in November 2014 with National Grid to add natural gas-burning capabilities at the Dunkirk facility. On August 25, 2015, NRG announced that Dunkirk Unit 2 would be mothballed on January 1, 2016 at the expiration of its reliability support services agreement. The project to add natural gas-burning capabilities has been suspended, pending the outcome of litigation with respect to the gas addition contract and its validity. On October 30, 2015, NYISO released the results of its reliability study, indicating that the Dunkirk facility is not needed for system reliability. In connection with the planned mothball of the facility, the pending litigation and the latest reliability assessment completed by NYISO, the Company evaluated whether the related fixed assets were impaired. The Company determined that the carrying amount of the assets was higher than the estimated future net cash flows expected to be generated by the assets and that the assets were impaired. The fair value of the Dunkirk facility was determined using the income approach. The income approach utilized estimates of discounted future cash flows, which were Level 3 fair value measurements, and include key inputs such as forecasted contract prices, forecasted operating and capital expenditures and discount rates. The Company recorded an impairment loss of $160 million during the year ended December 31, 2015.

Gregory — During the fourth quarter of 2015, the Company determined that the carrying amount of the assets was higher than the estimated future net cash flows expected to be generated by the assets and that the assets were impaired. The fair value of the Gregory facility was determined using the income approach, which utilized estimates of discounted future cash flows, which were Level 3 fair value measurements, and include key inputs such as forecasted prices, operating and capital expenditures and discount rates. The Company recorded an impairment loss of $176 million during the year ended December 31, 2015.

Solar Panels During the fourth quarter of 2015, the Company recorded an impairment loss of $29 million to reduce the carrying value of certain solar panels to their approximate fair value.
Investments During the fourth quarter of 2015, the Company reviewed certain of its cost method and equity method investments and concluded that losses incurred by these investments were other-than-temporary. These losses were primarily driven by the sustained decline in stock price of a publicly traded investment as well as change in financing structures of certain non-publicly traded investments. As a result, the Company recorded losses related to these investments of $56 million.
         
2014 Impairment Losses

Coolwater During the fourth quarter of 2014, the Company determined that it would retire the 636 MW natural-gas fired Coolwater facility in Dagget, California. The facility faced critical repairs on the cooling towers for units 3 and 4 and, during the fourth quarter of 2014, did not receive any awards in a near-term capacity auction and no interest in a bilateral capacity deal. The Company considered this to be an indicator of impairment and performed an impairment test for these assets under ASC 360, Property, Plant and Equipment. The carrying amount of the assets was higher than the future net cash flows expected to be generated by the assets and as a result, the assets are considered to be impaired. The Company measured the impairment loss as the difference between the carrying amount and the fair value of the assets. The Company retired the Coolwater facility effective January 1, 2015. All remaining fixed assets of the station were written off resulting in an impairment loss of $22 million recorded during the fourth quarter of 2014.
Osceola During the third quarter of 2014, the Company determined that it would mothball the 463 MW natural gas-fired Osceola facility, in Saint Cloud, Florida. The Company considered this to be an indicator of impairment and performed an impairment test for these assets under ASC 360, Property, Plant and Equipment. The carrying amount of the assets was higher than the future net cash flows expected to be generated by the assets and as a result, the assets were considered to be impaired. The Company measured the impairment loss as the difference between the carrying amount and the fair value of the assets. Due to the location of the facility, it was determined that the best indicator of fair value is the market value of the combustion turbines. The Company recorded an impairment loss of approximately $60 million during the third quarter of 2014, which represents the excess of the carrying value over the fair market value.
Solar Panels During the third quarter of 2014, the Company recorded an impairment loss of $10 million to reduce the carrying value of certain solar panels to their approximate fair value.