Environmental Matters
9 Months Ended
Sep. 30, 2012
Environmental Matters Disclosure [Abstract]  
Environmental Matters
Environmental Matters

NRG is subject to a wide range of environmental regulations across a broad number of jurisdictions in the development, ownership, construction and operation of domestic and international projects. These laws and regulations generally require that governmental permits and approvals be obtained before construction and during operation of power plants. Environmental regulations have become increasingly stringent and NRG expects this trend to continue. The electric generation industry is likely to face new requirements to address various emissions, including greenhouse gases, as well as combustion byproducts and water use. In general, future laws and regulations are expected to require the addition of emissions controls or other environmental quality equipment or the imposition of certain restrictions on the operations of the Company's facilities, which could have a material effect on the Company's operations or competitive position.

Environmental Capital Expenditures
 
Based on current rules, technology and plans as well as preliminary plans based on proposed rules, NRG has estimated that environmental capital expenditures from 2012 through 2016 to meet NRG's regulatory environmental commitments will be approximately $440 million. These costs are primarily associated with mercury controls to satisfy the Mercury and Air Toxics Standards, or MATS, on the Company's Big Cajun II, W.A. Parish and Limestone facilities and a number of intake modification projects across the fleet under state or proposed federal 316(b) rules. The change from our previous estimate of $553 million reflects a decrease in costs related to changes in technology related to MATS compliance, completing projects below budget, and shifts in compliance schedules based on regulatory changes.

NRG continues to explore cost effective compliance alternatives to reduce costs. While this estimate reflects anticipated schedules and controls related to the proposed 316(b) Rule (the EPA pushed back the final 316(b) rule from July 2012 to July 2013), the full impact on the scope and timing of environmental retrofits from any new or revised regulations cannot be determined until these rules are final and any legal challenges are reviewed. However, NRG believes it is positioned to meet more stringent environmental regulations through its planned capital expenditures, existing controls, and increasing generation from renewable resources.
 
NRG's current contracts with the Company's rural electric cooperative customers in the South Central region allow for recovery of a portion of the region's environmental capital costs incurred as the result of complying with any change in environmental law. Cost recoveries begin once the environmental equipment becomes operational and include a capital return. The actual recoveries will depend, among other things, on the timing of the completion of the capital projects and the remaining duration of the contracts.
Northeast Region
In January 2006, NRG's Indian River Operations, Inc. received a letter of informal notification from Delaware Department of Natural Resources and Environmental Control, or DNREC, stating that it may be a potentially responsible party with respect to Burton Island Old Ash Landfill, a historic captive landfill located at the Indian River facility. On October 1, 2007, NRG signed an agreement with DNREC to investigate the site through the Voluntary Clean-up Program. On February 4, 2008, DNREC issued findings that no further action is required in relation to surface water and that a previously planned shoreline stabilization project would satisfactorily address shoreline erosion. The landfill itself will require a further Remedial Investigation and Feasibility Study to determine the type and scope of any additional work required. Until the Remedial Investigation and Feasibility Study is approved, the Company is unable to predict the impact of any required remediation. On May 29, 2008, DNREC requested that NRG's Indian River Operations, Inc. participate in the development and performance of a Natural Resource Damage Assessment, or NRDA, at the Burton Island Old Ash Landfill. NRG is currently working with DNREC and other trustees to close out the assessment phase.
South Central Region
On September 7, 2012, LaGen received a Consolidated Compliance Order & Notice of Potential Penalty, or CCO&NPP, from the LDEQ.  The CCO&NPP alleges that there were opacity exceedance events from the three electric generating units at the Big Cajun II power plant facility on certain dates and times during the years 2007-2012.  On October 8, 2012, LaGen filed a Request for Administrative Adjudicatory Hearing in response to the CCO&NPP.  Pending this hearing, LaGen is cooperating with the LDEQ and responding in good faith to the CCO&NPP.  NRG is unable to predict the outcome of this matter at this preliminary stage of the proceeding.
On February 11, 2009, the U.S. DOJ acting at the request of the U.S. EPA commenced a lawsuit against LaGen in federal district court in the Middle District of Louisiana alleging violations of the CAA at the Big Cajun II power plant. This is the same matter for which NOVs were issued to LaGen on February 15, 2005, and on December 8, 2006. On October 17, 2012, prior to the start of liability-phase trial which had been temporarily adjourned, the parties notified the court that they had reached an agreement on terms of a settlement which requires final approval by the U.S. DOJ. The terms of the agreement generally require LaGen to install certain emission control equipment technologies, which are not expected to have an adverse impact on NRG's planned environmental capital expenditures. Further discussion on this matter can be found in Note 14, Commitments and Contingencies, of this Form 10-Q.