XML 103 R12.htm IDEA: XBRL DOCUMENT v2.4.0.6
Changes in Operations
12 Months Ended
Dec. 31, 2012
Changes in Operations [Abstract]  
Changes in Operations
CHANGES IN OPERATIONS:
United States
RailAmerica, Inc.: On October 1, 2012, the Company acquired 100% of RailAmerica, Inc.'s (RailAmerica) outstanding shares for cash at a price of $27.50 per share and in connection with such acquisition, the Company repaid RailAmerica's term loan and revolving credit facility. The calculation of the total consideration for the RailAmerica acquisition is presented below (dollars in thousands, except per share amount):
RailAmerica outstanding common stock as of October 1, 2012
49,934

Cash purchase price per share
$
27.50

Equity purchase price
$
1,373,184

Payment of RailAmerica's outstanding term loan and revolving credit facility
659,198

Cash consideration
2,032,382

Impact of pre-acquisition share-based awards
9,400

Total consideration
$
2,041,782


The Company financed the $1.4 billion cash purchase price for RailAmerica's common stock, the refinancing of $1.2 billion of the Company's and RailAmerica's outstanding debt prior to the acquisition, as well as transaction and financing related expenses with approximately $1.9 billion of debt from a new five-year Senior Secured Credit Syndicated Facility Agreement (the New Credit Agreement) (See Note 9, Long-Term Debt), $475.5 million of gross proceeds from the Company's public offerings of Class A common stock and Tangible Equity Units (TEUs) (see Note 4, Earnings Per Share) and $350.0 million through a private issuance of mandatorily convertible Series A-1 Preferred Stock to affiliates of Carlyle Partners V, L.P. (collectively, Carlyle) (see Note 4, Earnings Per Share and Note 10, Derivative Financial Instruments).
The shares of RailAmerica were held in a voting trust while the United States Surface Transportation Board (STB) considered the Company's control application, which application was approved with an effective date of December 28, 2012. Accordingly, the Company accounted for the earnings of RailAmerica using the equity method of accounting while the shares were held in the voting trust and the Company's preliminary allocation of the purchase price to the acquired assets and assumed liabilities is included in the Company's consolidated balance sheet at December 31, 2012 and is included in the Company's North American and European Operations segment.
In accordance with U.S. GAAP, a new accounting basis was established for RailAmerica on October 1, 2012 for its stand-alone financial statements. Condensed consolidated financial information for RailAmerica as of and for the period ended December 28, 2012 is included in Note 8, Equity Investment.
During the year ended December 31, 2012, as discussed more fully under Contingent Forward Sale Contract in Note 10, Derivative Financial Instruments, the Company recorded a $50.1 million non-cash mark-to-market expense related to an investment agreement governing the sale of the Series A-1 Preferred Stock to Carlyle in connection with the funding of the RailAmerica acquisition (the Investment Agreement). The expense resulted from the significant increase in the Company's share price between July 23, 2012 (the date the Company entered into the Investment Agreement) and September 28, 2012 (the last trading date prior to issuing the stock).
The Company also incurred $18.6 million of acquisition-related costs and $11.5 million of integration costs related to this transaction during the year ended December 31, 2012. The Company recognized $15.6 million of net income from the equity investment in RailAmerica during the three months ended December 31, 2012. The income from equity investment included $3.5 million of after-tax acquisition/integration costs incurred by RailAmerica in the three months ended December 31, 2012.
Headquartered in Jacksonville, Florida with approximately 2,000 employees, RailAmerica owned and operated 45 short line freight railroads in North America with approximately 7,100 miles of track in 28 U.S. states and three Canadian provinces as of the acquisition date.
Columbus & Chattahoochee Railroad, Inc.: In April 2012, the Company's newly formed subsidiary, the Columbus & Chattahoochee Railroad, Inc. (CCH), signed an agreement with Norfolk Southern Railway Company (NS) to lease and operate a 26-mile segment of NS track that runs from Girard, Alabama to Mahrt, Alabama. Operations commenced on July 1, 2012. The CCH interchanges with NS in Columbus, Georgia where the Company's Georgia Southwestern Railroad, Inc. also has operations. The results from CCH’s operations have been included in the Company’s statement of operations effective July 1, 2012 and are included in the Company’s North American & European Operations segment.
Hilton & Albany Railroad, Inc.: In November 2011, the Company's newly formed subsidiary, the Hilton & Albany Railroad, Inc. (HAL), signed an agreement with NS to lease and operate a 56-mile segment of NS track that runs from Hilton, Georgia to Albany, Georgia. Operations commenced on January 1, 2012. The HAL handles primarily overhead traffic between NS and the Company's following railroads: The Bay Line Railroad, L.L.C.; Chattahoochee Bay Railroad, Inc.; Chattahoochee Industrial Railroad; and Georgia Southwestern Railroad, Inc. In addition, the HAL serves several local agricultural and aggregate customers in southwest Georgia. The results from HAL’s operations have been included in the Company’s statement of operations since January 1, 2012 and are included in the Company’s North American & European Operations segment.
Arizona Eastern Railway Company: On September 1, 2011, the Company acquired all of the capital stock of Arizona Eastern Railway Company (AZER). The Company paid the seller $89.5 million in cash at closing, which included a reduction to the purchase price of $0.6 million based on the estimated working capital adjustment. Following the final working capital adjustment, the Company recorded an additional $0.8 million of purchase price in December 2011, which was paid to the seller in January 2012. The Company incurred $0.6 million of acquisition costs related to this transaction through December 31, 2011, which were expensed as incurred. The results from AZER’s operations have been included in the Company’s statement of operations since September 1, 2011, and are included in the Company’s North American & European Operations segment.
Headquartered near Miami, Arizona, with 43 employees and 10 locomotives, AZER owned and operated two rail lines totaling approximately 200 track miles in southeast Arizona and southwest New Mexico connected by 52 miles of trackage rights over the Union Pacific Railroad as of the acquisition date. The largest customer on AZER is Freeport-McMoRan Copper & Gold Inc. (Freeport-McMoRan). AZER provides rail service to Freeport-McMoRan’s largest North American copper mine and its North American smelter, hauling copper concentrate, copper anode, copper rod and sulfuric acid. In conjunction with the transaction, AZER and Freeport-McMoRan have entered into a long-term operating agreement.
Australia
Arrium Limited: In July 2012, GWA announced that it had expanded two existing rail haulage contracts with Arrium Limited (formerly OneSteel) to transport an additional 2.7 million tons per year of export iron ore in South Australia. To support the increased shipments under the two contracts, GWA invested A$52.1 million (or $54.1 million at the exchange rate on December 31, 2012) in 2012 to purchase narrow gauge locomotives and wagons, as well as to construct a standard gauge rolling-stock maintenance facility. GWA expects to invest an additional A$17.9 million (or $18.7 million at the exchange rate on December 31, 2012) in 2013 to support the increased shipments.
Alice Springs and Cook: In May 2012, the Company's subsidiary, Genesee & Wyoming Australia Pty Ltd (GWA), entered into an agreement with Asciano Services Pty Ltd (AIO), a subsidiary of Asciano Pty Ltd, whereby GWA agreed to purchase an intermodal and freight terminal in Alice Springs, Northern Territory from AIO and the Company agreed to sell AIO certain assets in the township of Cook, South Australia that included its third-party fuel-sales business. The Company completed the purchase of the Alice Springs intermodal and freight terminal in June 2012 for A$9.0 million (or $9.2 million at the exchange rate on June 30, 2012) plus A$0.5 million (or $0.6 million at the exchange rate on June 30, 2012) tax liability for stamp duty (an Australian asset transfer tax). Previously, GWA had leased the facility from AIO. The sale of the assets in Cook closed in the third quarter of 2012. The Company received A$4.0 million (or $4.1 million at the exchange rate on September 30, 2012) in pre-tax cash proceeds from the sale and recognized an after-tax book gain of A$1.3 million (or $1.3 million at the exchange rate on September 30, 2012), or approximately $0.03 per share.
FreightLink: On December 1, 2010, the Company completed the acquisition of the assets of FreightLink Pty Ltd, Asia Pacific Transport Pty Ltd and related corporate entities (together, FreightLink) for A$331.9 million (or $320.0 million at the exchange rate on December 1, 2010) (FreightLink Acquisition). The Company has included the results from GWA (North) Pty Ltd (GWA North), the Company’s subsidiary that acquired certain assets of FreightLink, in its statement of operations since December 1, 2010 and are included in the Company's Australian Operations segment. Pursuant to the Business Sale Agreement, the Company acquired FreightLink’s freight rail business between Tarcoola, South Australia and Darwin in the Northern Territory of Australia, certain material contracts, equipment and property leases, as well as FreightLink’s plant, equipment and business inventory and the assumption of debt with a carrying value of A$1.8 million (or $1.7 million at the exchange rate on December 1, 2010), which represented the fair value of an A$50.0 million (or $48.2 million at the exchange rate on December 1, 2010) non-interest bearing loan due in 2054.
As a result of the acquisition, GWA North is now the concessionaire and operator of the Tarcoola to Darwin rail line, which links the Port of Darwin to the Australian interstate rail network in South Australia. The rail line is located on land leased to GWA North by the AustralAsia Railway Corporation (a statutory corporation established by legislation in the Northern Territory) under a concession agreement that expires in 2054. GWA North is both a provider of rail haulage to customers on its railroad (above rail services), as well as a track access provider, charging access fees to any rail operators that run on its track (below rail services). The track access rights are regulated under a statutory access regime established by legislation in the Northern Territory and South Australia. The Company’s subsidiary, GWA, has historically operated FreightLink’s rail haulage services and provided its crews, managed its train operations and also leased locomotives and wagons to FreightLink.
The Company incurred $28.2 million of acquisition costs related to this transaction in 2010, which were recorded in earnings as follows: $16.4 million within stamp duty (an Australian asset transfer tax), $11.0 million within other expenses and $0.8 million within labor and benefits.
The Company financed the purchase of FreightLink’s assets through a combination of cash on hand and borrowing $100.0 million and A$97.0 million (or $94.0 million at the December 1, 2010 exchange rate) under the United States and Australian revolving loans, respectively, of the Company's credit agreement then in effect.
Canada
Tata Steel Minerals Canada Ltd.: On August 2, 2012, the Company announced that its newly formed subsidiary, KeRail Inc. (KeRail), entered into a long-term agreement with Tata Steel Minerals Canada Ltd. (TSMC), for KeRail to provide rail transportation services to the direct shipping iron ore mine TSMC is developing near Schefferville, Quebec in the Labrador Trough (the Mine). In addition, KeRail will construct an approximately 21-kilometer rail line (Rail Line) that will connect the Mine to the Tshiuetin Rail Transportation (TSH) interchange point in Schefferville. Operated as part of the Company's Canada Region, KeRail will haul unit trains of iron ore from its rail connection with the Mine, which will then travel over three privately owned railways to the Port of Sept-Îles for export primarily to Tata Steel's European operations. The agreement and construction are contingent on certain conditions being met, including the receipt of necessary governmental permits and approvals. Once the track construction has commenced, the Rail Line is expected to be completed three to six months thereafter.
Huron Central Railway Inc.: In June 2009, the Company announced that its subsidiary, Huron Central Railway Inc. (HCRY), intended to cease its operations in the third quarter of 2009. Consequently, in the second quarter of 2009, the Company recorded charges of $5.4 million after-tax associated with HCRY. These charges reflected a non-cash write-down of non-current assets of $6.7 million and restructuring charges of $2.3 million and were partially offset by a tax benefit of $3.6 million. In September 2010, the governments of Canada and the Province of Ontario agreed to provide C$30 million (or $30 million at the December 31, 2012 exchange rate) to fund infrastructure improvements that, combined with certain customer agreements, will enable HCRY to continue operations on a long-term basis. In addition, HCRY committed to fund approximately C$3 million (or $3 million at the December 31, 2012 exchange rate) of infrastructure improvements. As a result, the Company reversed $2.3 million ($1.5 million after-tax) of accrued restructuring charges related to HCRY in September 2010, as HCRY no longer intends to cease its operations. Because of the substance of the temporary agreement HCRY was operating under from August 15, 2009 through December 31, 2010, HCRY’s net operating earnings were included within non-freight revenues as other operating income. On January 1, 2011, HCRY began operating under a new agreement with certain customers. Because of the substance of the new arrangement, on January 1, 2011, the Company resumed reporting HCRY’s operating revenues, including freight revenues and corresponding carloads, and operating expenses within each respective line item of the statement of operations.
Purchase Price Allocation
The Company accounted for the RailAmerica, AZER and FreightLink acquisitions using the acquisition method of accounting under U.S. GAAP. Under the acquisition method of accounting:
The assets and liabilities of RailAmerica were recorded at their respective estimated acquisition-date fair values by RailAmerica as of October 1, 2012, which is referred to as the application of push-down accounting, and were included in G&W's consolidated balance sheet in a single line item following the equity method of accounting as of that date (see RailAmerica as of October 1, 2012 column in the following table).
Upon approval of the STB to control RailAmerica, the preliminary allocation of fair value to the acquired assets and assumed liabilities were consolidated with the Company's assets and liabilities as of December 28, 2012 (see RailAmerica as of December 28, 2012 column in the following table). Between October 1, 2012 and December 28, 2012, the Company recognized income from its equity investment in RailAmerica of $15.6 million and other comprehensive loss of $2.0 million primarily resulting from foreign currency translation adjustments. In addition, the Company recognized $21.8 million, representing the change in RailAmerica's cash and cash equivalents from October 1, 2012 to December 28, 2012, as a reduction in net cash paid for the acquisition. The final allocation of fair value to RailAmerica's assets and liabilities is subject to completion of an assessment of the acquisition-date fair values of acquired non-current assets, deferred taxes and other tax matters, and contingent liabilities.
The assets and liabilities of AZER and FreightLink were recorded at their respective acquisition-date fair values and were consolidated with those of G&W as of their respective acquisition dates (see AZER and FreightLink columns in the following table). The foreign exchange rate used to translate the FreightLink balance sheet to United States dollars was $0.96 for one Australian dollar (which was the exchange rate on December 1, 2010).
The fair values assigned to the acquired net assets of RailAmerica, AZER and FreightLink were as follows (dollars in thousands):
 
 
RailAmerica
 
 
 
FreightLink
 
 
As of
October 1, 2012
 
As of
December 28, 2012
 
AZER
 
AUD
 
USD
 
 
 
 
 
 
Purchase Price Allocations:
 
 
 
 
 
 
 
 
 
 
Cash and cash equivalents
 
$
86,102

 
$
107,922

 
$

 
$

 
$

Accounts receivable, net
 
104,839

 
91,424

 
3,096

 
161

 
155

Materials and supplies
 
6,406

 
7,325

 

 
3,328

 
3,209

Prepaid expenses and other
 
15,146

 
14,815

 
2,319

 
101

 
97

Deferred income tax assets, net
 
49,074

 
49,074

 

 

 

Property and equipment
 
1,579,321

 
1,588,612

 
90,129

 
331,201

 
319,311

Goodwill
 
474,115

 
474,115

 

 

 

Intangible assets, net
 
451,100

 
446,327

 

 

 

Other Assets, net
 
116

 
116

 

 

 

Total assets
 
2,766,219

 
2,779,730

 
95,544

 
334,791

 
322,772

Accounts payable and accrued expenses
 
143,790

 
135,117

 
5,212

 
731

 
705

Long-term debt
 
12,158

 
12,010

 

 
1,806

 
1,741

Deferred income tax liabilities, net
 
542,210

 
551,856

 

 
318

 
307

Other long-term liabilities
 
20,754

 
19,618

 

 

 

Noncontrolling interest
 
5,525

 
5,525

 

 

 

Net assets
 
$
2,041,782

 
$
2,055,604

 
$
90,332

 
$
331,936

 
$
320,019


Discontinued Operations
In August 2010, the Company recognized income from net insurance proceeds of $2.8 million ($2.8 million after-tax) within discontinued operations related to damages incurred as a result of Hurricane Stan in 2005 by the Company's Mexican operating subsidiary, Ferrocarriles Chiapas-Mayab, S.A. de C.V. (FCCM), which was sold in August 2009. The Company utilized capital loss carryforwards, which were previously subject to a full valuation allowance, to offset the tax on this gain.
The net assets, results of operations and cash flows of our remaining Mexican subsidiary, GW Servicios S.A. (Servicios), which were classified as discontinued operations, were not material as of and for the years ended December 31, 2012, 2011 and 2010. The Company does not expect any material future adverse financial impact from its remaining Mexican subsidiary. See Note 22, Discontinued Operations, for additional information regarding the Company’s discontinued operations.
Results from Continuing Operations
When comparing the Company’s results from continuing operations from one reporting period to another, it is important to consider that the Company has historically experienced fluctuations in revenues and expenses due to changing economic conditions, acquisitions, competitive forces, changes in foreign currency exchange rates, one-time freight moves, fuel price fluctuations, customer plant expansions and shut-downs, sales of property and equipment, derailments and weather-related conditions, such as hurricanes, cyclones, tornadoes, droughts, heavy snowfall, unseasonably warm or cool weather, freezing and flooding. In periods when these events occur, results of operations are not easily comparable from one period to another. Finally, certain of the Company’s railroads have commodity shipments that are sensitive to general economic conditions, such as steel products, paper products and lumber and forest products, as well as product specific economic conditions, such as the availability of lower priced alternative sources of power generation (coal). Other shipments are relatively less affected by economic conditions and are more closely affected by other factors, such as inventory levels maintained at customer plants (coal), winter weather (salt and coal) and seasonal rainfall (grain). As a result of these and other factors, the Company’s operating results in any reporting period may not be directly comparable to its operating results in other reporting periods.
Pro Forma Financial Results (unaudited)
The following table summarizes the Company’s unaudited pro forma operating results for the years ended December 31, 2012, 2011 and 2010, as if the acquisition of RailAmerica had been consummated as of January 1, 2011 and the FreightLink Acquisition was consummated as of January 1, 2009. The following pro forma financial statements do not include the impact of any potential operating efficiencies, savings from expected synergies, costs to integrate the operations or costs necessary to achieve savings from expected synergies or the impact of derivative instruments that the Company has entered into or may enter into to mitigate interest rate or currency exchange rate risk (dollars in thousands, except per share amounts): 
 
2012
 
2011
 
2010
Operating revenues
$
1,472,438

 
$
1,376,070

 
$
717,306

Net income attributable to Genesee & Wyoming Inc.
$
57,478

 
$
127,408

 
$
107,420

Series A-1 Preferred Stock dividend
17,500

 
17,500

 

Net income available to common stockholders
$
39,978

 
109,908

 
$
107,420

Earnings per common share attributable to Genesee & Wyoming Inc. common shareholders:
 
 
 
 
 
Basic earnings per common share from continuing operations
$
0.94

 
$
2.35

 
$
2.70

Diluted earnings per share from continuing operations
$
0.88

 
$
2.22

 
$
2.50


The 2012 and 2011 unaudited pro forma operating results include the acquisition of RailAmerica adjusted, net of tax, for depreciation and amortization expense resulting from the property and equipment and amortizable intangible assets based on the assignment of fair values, the inclusion of interest expense related to borrowings used to fund the acquisition, the amortization of debt issuance costs related to amendments to the Company’s prior credit agreement and the elimination of RailAmerica's interest expense related to debt not assumed in the acquisition.
The unaudited pro forma statements of operations for the years ended December 31, 2012 and 2011 were based upon the Company’s historical consolidated statements of operations for the years ended December 31, 2012 and 2011 and RailAmerica's consolidated statements of operations for the nine months ended September 30, 2012, the three months ended December 28, 2012 and the year ended December 31, 2011. Since the pro forma financial results for 2012 and 2011 assume the acquisition of RailAmerica was consummated on January 1, 2011, the 2011 results included $14.5 million, net of tax, of acquisition-related costs incurred by the Company during the year ended December 31, 2012, $12.9 million, net of tax, of acquisition-related costs incurred by RailAmerica during the year ended December 31, 2012 and approximately $9 million, net of tax, of fees associated with the financing transactions associated with the acquisition. In addition, the pro forma results for 2012 included approximately $55 million of costs incurred by RailAmerica associated with the redemption of senior secured notes in January 2012. As a result of these charges, the numerator used in the calculation of pro forma diluted earnings per share from continuing operations was reduced by the Series A-1 Preferred Stock dividend and the denominator excluded approximately 6.0 million "if-converted" shares related to the Series A-1 Preferred Stock.
The 2010 unaudited pro forma operating results include the FreightLink Acquisition adjusted, net of tax, for depreciation and amortization expense resulting from the property and equipment assets based on the assignment of fair values, an adjustment to interest income for the reduction in available cash and cash equivalents due to the use of cash on hand to fund the acquisition, the inclusion of interest expense related to borrowings used to fund the acquisition, the amortization of debt issuance costs related to amendments to the Company’s prior credit agreement, the elimination of FreightLink’s deferred grant income for a liability not acquired and the elimination of FreightLink’s interest expense related to debt not assumed in the acquisition. In addition, 2010 unaudited pro forma operating results included an additional tax provision to report FreightLink as a tax paying entity using the Australian statutory income tax rate of 30%.
The Company’s 2010 results included $11.6 million of revenues and a net loss of $10.3 million from GWA North for the month of December. The $10.3 million net loss included A$11.8 million, net of tax ($11.5 million, net of tax, at the December 1, 2010 exchange rate) of stamp duty (an Australian asset transfer tax), which was directly attributable to the acquisition. Since the pro forma financial results assume the FreightLink Acquisition was consummated on January 1, 2009, the 2010 unaudited pro forma operating results excluded A$11.8 million, net of tax ($11.5 million, net of tax, at the December 1, 2010 exchange rate) of stamp duty and $7.8 million, net of tax, of other FreightLink acquisition costs incurred in the year ended December 31, 2010.
FreightLink’s fiscal year end was June 30 and the Company’s fiscal year end is December 31. Since FreightLink and the Company had different fiscal year end dates, the unaudited pro forma condensed financial statements were prepared based on comparable periods. The unaudited pro forma statement of operations for the year ended December 31, 2010, was based upon the Company’s consolidated statement of operations, which includes one month of GWA North’s results and the sum of FreightLink’s historical quarterly statements of operations for the three months ended March 31, June 30, September 30, 2010, and two months ended November 30, 2010. The foreign exchange rates used to translate FreightLink’s statements of operations to United States dollars were $0.90, $0.88, $0.91 and $0.99 for one Australian dollar for the three months ended March 31, June 30, September 30, 2010, and two months ended November 30, 2010, respectively (which were calculated based on average daily exchange rates during each of those periods).
The pro forma financial information does not purport to be indicative of the results that actually would have been obtained had the transactions been completed as of the assumed dates and for the periods presented and are not intended to be a projection of future results or trends.