XML 95 R34.htm IDEA: XBRL DOCUMENT v3.20.1
Re-engineering Costs (Tables)
12 Months Ended
Dec. 28, 2019
Restructuring and Related Activities [Abstract]  
Re-engineering Charges
Pretax costs incurred related to the 2019 program by category were as follows:
(In millions)
2019
Severance
$
13.1

Other
13.3

Total re-engineering charges
$
26.4

The re-engineering charges related to the 2019 program by segment during 2019 were as follows:
(In millions)
2019
Europe
$
12.4

Asia Pacific
11.1

Other
2.9

Total re-engineering charges
$
26.4


Pretax costs incurred related to the 2017 program by category were as follows:
(In millions)
2019
 
2018
 
2017
Severance
$
4.4

 
$
3.6

 
$
48.1

Other
0.1

 
12.3

 
15.6

Total re-engineering charges
$
4.5

 
$
15.9

 
$
63.7


The re-engineering charges related to the 2017 program by segment were as follows:
(In millions)
2019
 
2018
 
2017
Europe
$
2.7

 
$
10.2

 
$
47.9

Asia Pacific
0.6

 
0.5

 
4.8

North America
1.2

 
3.8

 
11.0

South America

 
1.4

 

Total re-engineering charges
$
4.5

 
$
15.9

 
$
63.7

Schedule of Restructuring Reserve by Type of Cost
The balances included in accrued liabilities related to re-engineering and impairment charges as of December 28, 2019, December 29, 2018, and December 30, 2017 were as follows:
(In millions)
2019
 
2018
 
2017
Beginning balance
$
23.3

 
$
45.4

 
$
1.6

Provision
4.5

 
15.9

 
63.7

Adjustments and other charges
(0.3
)
 
3.0

 
(0.4
)
Cash expenditures:
 
 
 
 
 
Severance
(20.3
)
 
(27.1
)
 
(12.7
)
Other
(3.6
)
 
(12.8
)
 
(6.8
)
Currency translation adjustment
(0.5
)
 
(1.1
)
 

Ending balance
$
3.1

 
$
23.3

 
$
45.4


The balances included in accrued liabilities related to the 2019 program as of December 28, 2019 were as follows:
(In millions)
2019
Beginning balance
$

Provision
26.4

Adjustments and other charges
(1.7
)
Cash expenditures:
 
Severance
(0.9
)
Other
(10.9
)
Ending balance
$
12.9