We are involved in legal, tax, and regulatory proceedings before various courts, regulatory commissions, authorities, and governmental agencies with respect to matters that arise in the ordinary course of business, some of which involve substantial amounts of money. We believe that the final disposition of these proceedings, except as otherwise disclosed in the notes to our financial statements, will not have a material adverse effect on our results of operations, financial position, or liquidity.
See also Note 1 – Summary of Significant Accounting Policies, Note 2 – Rate and Regulatory Matters, Note 9 – Callaway Energy Center, Note 13 – Related-party Transactions, and Note 15 – Supplemental Information in this report.
Environmental Matters
Our electric generation, transmission, and distribution and natural gas distribution and storage operations must comply with a variety of statutes and regulations relating to the protection of the environment and human health and safety, including permitting programs implemented by federal, state, and local authorities. Such environmental laws regulate air emissions; protect water bodies; manage the handling and disposal of hazardous substances and waste materials; siting and land use requirements; and potential ecological impacts. Complex and lengthy processes are required to obtain and renew approvals, permits, and licenses for new, existing, or modified energy-related facilities. Additionally, the use and handling of various chemicals or hazardous materials require release prevention plans and emergency response procedures.
Environmental regulations have a significant impact on the electric utility industry and compliance with these regulations could be costly for Ameren Missouri, which operates coal-fired and natural gas-fired energy centers. Compliance obligations under the Clean Air Act include the NSPS, the MATS, emission allowance programs and the CSAPR, and the National Ambient Air Quality Standards, which are subject to periodic review for certain pollutants. Collectively, these regulations cover a variety of pollutants, such as SO2, particulate matter, NOx, mercury, toxic metals and acid gases, and CO2 emissions. Regulations implementing the Clean Water Act govern potential impacts from our operations on water bodies including wetlands subject to the Act, as well as evaluation of the ecological and biological impact of those operations. Implementation of the Clean Air Act and the Clean Water Act requirements typically occurs through the issuance of permits by state regulators or resource agencies, and capital expenditures associated with compliance could be significant. Coal-fired energy centers must comply with management and disposal requirements for coal ash under the Resource Conservation and Recovery Act and federal regulations known as the CCR Rule. Surface impoundments at Ameren Missouri’s coal-fired energy centers are subject to closure and groundwater monitoring requirements and the implementations of corrective measures if necessary. The individual or combined effects of compliance with existing and new environmental regulations could result in significant capital expenditures, increased operating costs, or the closure or alteration of operations at some of Ameren Missouri’s energy centers. Ameren and Ameren Missouri expect that such compliance costs would be recoverable through rates, subject to MoPSC prudence review, but the timing of costs and their recovery could be subject to regulatory lag.
Additionally, Ameren Missouri’s wind generation facilities may be subject to operating restrictions to limit the impact on protected species. Since 2021, Ameren Missouri’s High Prairie Energy Center curtailed nighttime operations from April through October to limit impacts on protected species during the critical biological season. The extent and duration of future curtailments are currently unknown as assessment of mitigation technologies is ongoing. In Ameren Missouri’s 2024 electric service regulatory rate review, the MoPSC staff and the MoOPC have recommended reductions to the revenue requirement associated with the nighttime curtailment of the High Prairie Energy Center. See Note 2 – Rate and Regulatory Matters for additional information.
Ameren and Ameren Missouri estimate that they may need to make capital expenditures of $900 million to $1 billion from 2025 through 2029 to comply with environmental regulations. Additional capital expenditures for environmental controls beyond 2029 could be required. These estimates include capital expenditures that may be necessary to comply with regulations issued by the EPA in 2024 relating to CO2 emissions and MATS discussed below, assuming these regulations are not revised or overturned. This estimate of capital expenditures also includes surface impoundment closure and corrective action measures required by the 2015 CCR Rule and modifications to cooling water intake structures at existing power plants under Clean Water Act rules in place prior to 2024, all of which are discussed below. Congress and the EPA could review and revise compliance requirements. In addition to planned retirements of coal-fired energy centers that will be included in Ameren Missouri’s 2025 Change to the 2023 PRP and as noted below with respect to the NSR and Clean Air Act litigation and Illinois emissions standards, Ameren Missouri’s current plan for compliance with existing air emission regulations includes burning low-sulfur coal and installing new or optimizing existing air pollution control equipment. Accordingly, the actual amount of capital expenditures required to comply with existing environmental regulations may vary substantially from the above estimates because of uncertainty as to future permitting requirements by state regulators and the EPA, revisions to regulatory obligations, and varying cost of potential compliance strategies, among other things.
The following sections describe the significant environmental statutes and regulations and environmental enforcement and remediation matters that affect or could affect our operations. The EPA periodically amends and revises its regulations and proposes amendments to regulations and guidelines, which could ultimately result in the revision of all or part of such regulations.
Clean Air Act
Federal and state laws, including the CSAPR, regulate emissions of SO2 and NOx through the reduction of emissions at their source and the use and retirement of emission allowances. In April 2022, the EPA proposed the Good Neighbor Rule of the Clean Air Act, which includes additional NOx emission reductions from power plants in Missouri, Illinois, and other states through revisions to the CSAPR. In January 2023, the EPA issued its final disapproval of Missouri’s proposed state implementation plan for addressing the transport of ozone under the Good Neighbor Rule of the Clean Air Act. The disapproval of the state plan allowed the EPA to implement revisions to the CSAPR through a federal implementation plan that reduced the amount of NOx allowances available for state budgets and imposed NOx emission limits on electric generating units for Missouri, Illinois, and other states under the Good Neighbor Rule of the Clean Air Act. In April 2023, the Missouri Attorney General and Ameren Missouri separately filed lawsuits in the United States Court of Appeals for the Eighth Circuit challenging the EPA’s disapproval of the Missouri state plan. Ameren expected a decision on Missouri’s proposed state implementation plan under the Good Neighbor Rule by the United States Court of Appeals for the Eighth Circuit in 2025, but, in February 2025, the EPA requested that the appellate court suspend the case indefinitely and indicated it was reviewing the basis for the disapproval of the state implementation plans, including Missouri’s. Ameren Missouri complies with the current CSAPR requirements by minimizing emissions through the use of low-sulfur coal, operation of two scrubbers at its Sioux Energy Center, and optimization of existing NOx air pollution control equipment. Reducing the amount of state budget NOx allowances for compliance with NOx emission limits under the Good Neighbor Rule could result in additional controls being required on Ameren Missouri’s generating units and/or the reduction of operations. Any costs for compliance are expected to be recovered from customers, subject to MoPSC prudence review, through the FAC or higher base rates.
CO2 Emissions Standards
In April 2024, the EPA issued a final rule that sets CO2 emission standards for existing coal-fired and new natural gas-fired power plants based on the emissions expected from adoption of carbon capture technology and/or natural gas co-firing for coal-fired power plants and carbon capture technology for new natural gas-fired power plants. Affected power plants are required to comply with the rule through a phased-in approach or retire. Compliance with the new rule could be required as early as 2030 for certain existing coal-fired power plants and 2032 for certain new natural gas-fired power plants. In December 2024, the United States Court of Appeals for the District of Columbia Circuit heard arguments from various stakeholders including the EPA, environmental organizations, state attorney generals, and industry groups regarding the legal merits of the final rule. In February 2025, the EPA requested that the appellate court suspend the case for 60 days and not issue an opinion so the EPA can decide how to proceed. Ameren and Ameren Missouri estimate capital expenditures of approximately $580 million may be necessary to comply with the final rule assuming it is not revised or overturned. Ameren and Ameren Missouri are monitoring the legal challenges and assessing the impacts of the final rule and, at this time, cannot predict the final impacts on their results of operations, financial position, and liquidity.
MATS
In April 2024, the EPA revised the MATS by establishing a more stringent standard for emissions of particulate matter, as well as requiring the use of continuous emissions monitoring systems. Compliance with the revised rule is required by July 2027, with a possible one-year extension if certain conditions are met. Requests for a stay of the revised rule have been denied by the United States Court of Appeals for the District of Columbia Circuit and the United States Supreme Court. Arguments regarding the legal merits of the revised rule will be considered by the United States Court of Appeals for the District of Columbia Circuit. Ameren and Ameren Missouri estimate capital expenditures of approximately $320 million may be necessary to comply with the final rule assuming it is not revised or overturned. Ameren and Ameren Missouri are monitoring the legal challenges and, at this time, cannot predict the final impacts on their results of operations, financial position, and liquidity.
NSPS
In November 2024, the EPA issued a proposed rule revising the NSPS to limit emissions of NOx from natural gas-fired stationary CTs. If adopted as proposed, the rule would require such natural gas facilities which began construction after December 13, 2024, to install certain pollution control equipment to limit emissions of NOx. In addition, the EPA proposed to maintain the current limits for SO2 at such natural gas facilities. Ameren and Ameren Missouri cannot predict the potential impacts of any such rule on their results of operations, financial position, and liquidity until a final rule is adopted.
NSR and Clean Air Act Litigation
In January 2011, the United States Department of Justice, on behalf of the EPA, filed a complaint against Ameren Missouri in the United States District Court for the Eastern District of Missouri alleging that projects performed in 2007 and 2010 at the coal-fired Rush Island Energy Center violated provisions of the Clean Air Act and Missouri law. In January 2017, the district court issued a liability ruling against Ameren Missouri and, in September 2019, entered a remedy order that required Ameren Missouri to install a flue gas desulfurization system at the Rush Island Energy Center. In September 2023, the district court modified the remedy order to allow the early retirement of the Rush Island Energy Center in lieu of installing a flue gas desulfurization system. Ameren Missouri retired the Rush Island Energy Center on
October 15, 2024. In December 2024, the United States District Court for the Eastern District of Missouri issued an order resolving all outstanding claims in this case. The order requires Ameren Missouri to fund a program to provide electric buses and charging stations to schools in the metro St. Louis area and a program to provide air purifiers to eligible Ameren Missouri electric residential customers. These programs are estimated to cost approximately $64 million. As of December 31, 2024, Ameren and Ameren Missouri each recorded liabilities of $40 million and $24 million in “Other current liabilities” and “Other deferred credits and liabilities”, respectively, on their consolidated balance sheets and recorded charges of $59 million in “Other operations and maintenance” on their consolidated statements of income in 2024 related to the cost of these programs.
In connection with the accelerated retirement of the Rush Island Energy Center, the MoPSC issued an order in June 2024 authorizing Ameren Missouri to finance the costs associated with the retirement, including the remaining unrecovered net plant balance associated with the facility, through the issuance of securitized utility tariff bonds pursuant to Missouri’s securitization statute. Costs associated with the retirement exclude any additional mitigation relief ordered in the NSR and Clean Air Act litigation discussed above. The securitized tariff bonds were issued in December 2024. See Note 2 – Rate and Regulatory Matters for additional information.
Clean Water Act
Among other items, the Clean Water Act requires power plant operators to evaluate cooling water intake structures and identify measures for reducing the number of aquatic organisms impinged on a power plant’s cooling water intake screens or entrained through the plant’s cooling water system. All of Ameren Missouri’s coal-fired and nuclear energy centers are subject to this cooling water intake structures rule. Requirements of the rule are implemented by state regulators through the permit renewal process of each power plant’s water discharge permit. Permits for Ameren Missouri’s coal-fired and nuclear energy centers have been issued or are in the process of renewal.
In April 2024, the EPA issued new effluent limitation guidelines that established a zero discharge limit for flue gas desulfurization wastewater, bottom ash transport water, and combustion residual leachate. Ameren and Ameren Missouri expect the impacts of the new guidelines on their results of operations, financial position, and liquidity to be immaterial.
CCR Management
The EPA’s 2015 CCR Rule establishes requirements for the management and disposal of CCR from coal-fired power plants and has resulted in the closure of surface impoundments at Ameren Missouri’s energy centers, with closures of surface impoundments in process at its Sioux Energy Center and retired Meramec Energy Center. Ameren Missouri plans to substantially complete the closures of remaining surface impoundments by the end of 2026. Ameren Missouri’s CCR management compliance plan includes installation of groundwater monitoring equipment and groundwater treatment facilities. In April 2024, the EPA revised the CCR Rule to impose groundwater monitoring, and corrective action, closure, and post-closure requirements on certain active and inactive CCR surface impoundments and disposal units not previously included in the 2015 CCR Rule. Ameren and Ameren Missouri have AROs of $46 million associated with CCR storage facilities recorded on their respective balance sheets as of December 31, 2024. This amount includes an immaterial incremental ARO related to the 2024 CCR Rule, which may be revised as additional site studies are performed. Ameren and Ameren Missouri are assessing the impacts of this rule revision and, at this time, cannot predict the final impacts on their results of operations, financial position, and liquidity.
Remediation
The Ameren Companies are involved in a number of remediation actions to clean up sites impacted by the use or disposal of materials containing hazardous substances. Federal and state laws can require responsible parties to fund remediation regardless of their degree of fault, the legality of original disposal, or the ownership of a disposal site.
As of December 31, 2024, Ameren Illinois has remediated the majority of the 44 former MGP sites in Illinois with an estimated remaining obligation primarily related to three of these former MGP sites at $44 million to $91 million. Ameren and Ameren Illinois recorded a liability of $44 million to represent the estimated minimum obligation for these sites, as no other amount within the range was a better estimate. Ameren cannot estimate the completion date of the estimated remaining obligation due to site accessibility, among other things. The scope of the remediation activities at these former MGP sites may increase as remediation efforts continue. Considerable uncertainty remains in these estimates because many site-specific factors can influence the actual costs, including unanticipated underground structures, the degree to which groundwater is impacted, regulatory changes, local ordinances, and site accessibility. The actual costs and timing of completion may vary substantially from these estimates.
The ICC allows Ameren Illinois to recover MGP remediation and related litigation costs from its electric and natural gas utility customers through environmental cost riders that are subject to annual prudence reviews by the ICC.
Our operations or those of our predecessor companies involve the use of, disposal of, and, in appropriate circumstances, the cleanup of substances regulated under environmental laws. We are unable to determine whether such historical practices will result in future
environmental commitments, including additional or more stringent cleanup standards, or will affect our results of operations, financial position, or liquidity.
Illinois Emission Standards
Currently as required by the CEJA, Ameren Missouri's natural gas-fired energy centers in Illinois are subject to annual limits on emissions, including CO2 and NOx. Further reductions to emissions limits will become effective between 2030 and 2040, resulting in the closure of the Venice Energy Center by the end of 2029. The reductions could also limit the operations of Ameren Missouri's four other natural gas-fired energy centers located in the state of Illinois, and will result in their closure by 2040. These energy centers are utilized to support peak loads. Subject to conditions in the CEJA, these energy centers may be allowed to exceed the emissions limits in order to maintain reliability of electric utility service.