Legal and Regulatory Matters

Barnwell is routinely involved in disputes with third parties that occasionally require litigation. In addition, Barnwell is required to maintain compliance with all current governmental controls and regulations in the ordinary course of business. Barnwell’s management is not aware of any claims or litigation involving Barnwell that are likely to have a material adverse effect on its results of operations, financial position or liquidity.

In the quarter ended December 31, 2021, it was determined that a contract drilling segment well completed in the period did not meet the contract specifications for plumbness under a gyroscopic plumbness test which the contract required. While the well did pass the cage plumbness test, the contract uses the gyroscopic test as the measure of plumbness. Barnwell and the customer currently have an arrangement where Barnwell will provide for centralizers, armored cabling and a pump installation and removal test to confirm that plumbness is satisfactory. Barnwell’s management believes the plumbness deviation is not impactful to the performance of the submersible pumps that will be installed in the well. Accordingly, while costs for the centralizers, armored cabling and the pump installation and removal test have been accrued, no accrual has been recorded as of March 31, 2023 for any further costs related to this contract as there is no related probable or estimable contingent liability.