XML 72 R58.htm IDEA: XBRL DOCUMENT v3.3.1.900
Regulated Operations - Costs Related to Remediation of Former Operating Sites (Details)
$ in Millions
12 Months Ended
Dec. 31, 2015
USD ($)
site
Dec. 31, 2014
USD ($)
Environmental Exit Cost [Line Items]    
Number of sites | site 46  
Probabilistic model cost estimates, low estimate $ 344  
Probabilistic model cost estimates, high estimate 704  
Engineering-based estimates 87  
Amount recorded 431  
Expected costs over next 12 months $ 67 $ 87
Illinois [Member]    
Environmental Exit Cost [Line Items]    
Number of sites | site 26  
Probabilistic model cost estimates, low estimate $ 200  
Probabilistic model cost estimates, high estimate 457  
Engineering-based estimates 50  
Amount recorded 250  
Expected costs over next 12 months $ 32  
New Jersey [Member]    
Environmental Exit Cost [Line Items]    
Number of sites | site 6  
Probabilistic model cost estimates, low estimate $ 115  
Probabilistic model cost estimates, high estimate 195  
Engineering-based estimates 7  
Amount recorded 122  
Expected costs over next 12 months $ 18  
Cost recovery period 7 years  
Georgia And Florida [Member]    
Environmental Exit Cost [Line Items]    
Number of sites | site 13  
Probabilistic model cost estimates, low estimate $ 29  
Probabilistic model cost estimates, high estimate 52  
Engineering-based estimates 23  
Amount recorded 52  
Expected costs over next 12 months $ 12  
Cost recovery period 5 years  
North Carolina [Member]    
Environmental Exit Cost [Line Items]    
Number of sites | site 1  
Probabilistic model cost estimates, low estimate $ 0  
Probabilistic model cost estimates, high estimate 0  
Engineering-based estimates 7  
Amount recorded 7  
Expected costs over next 12 months $ 5  
Cost recovery period 0 years