XML 113 R87.htm IDEA: XBRL DOCUMENT v3.22.2.2
Regulatory Matters - GPC Nuclear Construction (Details) - GEORGIA POWER CO
$ in Millions
3 Months Ended 9 Months Ended 12 Months Ended
Sep. 30, 2022
USD ($)
Jun. 30, 2022
USD ($)
Sep. 30, 2022
USD ($)
Dec. 31, 2012
utility
MW
Aug. 31, 2018
Loss Contingencies [Line Items]          
Estimated cost to complete, pre-tax charge to income $ 32 $ 36      
Estimated cost to complete, pre-tax charge to income, net of tax $ 24 27      
Plant Vogtle Units 3 And 4          
Loss Contingencies [Line Items]          
Proportionate ownership share 45.70%   45.70%    
Number of construction units approved | utility       2  
Electric generating capacity in mega watts under consortium agreement | MW       1,100  
Estimated cost to complete, construction contingency estimate, financing costs $ 3,400   $ 3,400    
Estimated cost to complete, construction contingency estimate, financing costs, incurred to date 3,100   3,100    
Construction contingency estimate 170   170    
Estimated cost to complete, additional construction contingency estimate 32 $ 36 32    
Base project capital cost forecast, monthly     15    
Monthly AFUDC     $ 35    
Percentage of ownership interest required for voting for continuing construction         90.00%
Plant Vogtle Units 3 And 4 | Vogtle Owners          
Loss Contingencies [Line Items]          
Period of notice required in the event letters of credit are not renewed     30 days    
Minimum | Plant Vogtle Units 3 And 4 | COVID-19          
Loss Contingencies [Line Items]          
Loss contingency, estimate of possible loss, loss of productivity, term     3 months    
Estimate of possible loss 160   $ 160    
Maximum | Plant Vogtle Units 3 And 4 | COVID-19          
Loss Contingencies [Line Items]          
Loss contingency, estimate of possible loss, loss of productivity, term     4 months    
Estimate of possible loss $ 200   $ 200