XML 91 R65.htm IDEA: XBRL DOCUMENT v3.22.2.2
Regulatory Matters (Tables)
9 Months Ended
Sep. 30, 2022
Regulated Operations [Abstract]  
Schedule of Cost Recovery Clauses
The recovery balances for certain retail regulatory clauses of the traditional electric operating companies and Southern Company Gas at September 30, 2022 and December 31, 2021 were as follows:
Regulatory ClauseBalance Sheet Line ItemSeptember 30,
2022
December 31, 2021
(in millions)
Alabama Power
Rate CNP ComplianceOther regulatory liabilities, deferred$4 $— 
Other regulatory assets, deferred 16 
Rate CNP PPAOther regulatory assets, deferred125 84 
Retail Energy Cost Recovery(*)
Other regulatory assets, current
93 — 
Other regulatory assets, deferred413 126 
Georgia Power
Fuel Cost RecoveryDeferred under recovered fuel clause revenues$1,697 $410 
Mississippi Power
Fuel Cost RecoveryOther customer accounts receivable$13 $
Ad Valorem Tax
Other regulatory assets, current
12 12 
Other regulatory assets, deferred
22 37 
Southern Company Gas
Natural Gas Cost RecoveryNatural gas cost under recovery$390 $266 
Other regulatory assets, deferred 207 
(*)In accordance with an Alabama PSC order issued on February 1, 2022, Alabama Power applied $126 million of its 2021 Rate RSE refund to reduce the Rate ECR under recovered balance.
Nuclear Construction Cost and Schedule
Georgia Power's approximate proportionate share of the remaining estimated capital cost to complete Plant Vogtle Units 3 and 4, including contingency, through the end of the first quarter 2023 and the fourth quarter 2023, respectively, is as follows:
(in millions)
Base project capital cost forecast(a)(b)
$10,334 
Construction contingency estimate49 
Total project capital cost forecast(a)(b)
10,383 
Net investment at September 30, 2022(b)
(9,280)
Remaining estimate to complete$1,103 
(a)Includes approximately $590 million of costs that are not shared with the other Vogtle Owners and approximately $353 million of incremental costs under the cost-sharing and tender provisions of the joint ownership agreements described below. Excludes financing costs expected to be capitalized through AFUDC of approximately $385 million, of which $275 million had been accrued through September 30, 2022.
(b)Net of $1.7 billion received from Toshiba under the Guarantee Settlement Agreement and approximately $188 million in related customer refunds.
Schedule of Infrastructure Replacement Programs and Capital Projects
Georgia Power has requested recovery of the proposed increases through its existing base rate tariffs as follows:
Tariff202320242025
(in millions)
Traditional base$762 $— $— 
ECCR
Traditional— — 
CCR ARO(a)
64 78 47 
DSM(a)
37 27 (2)
Municipal Franchise Fee21 
Total(b)
$889 $107 $45 
(a)As determined by the Georgia PSC through annual compliance filings.
(b)Totals may not add due to rounding.
Capital expenditures incurred under specific infrastructure replacement programs and capital projects during the first nine months of 2022 were as follows:
UtilityProgram
Nine Months Ended September 30, 2022
(in millions)
Nicor GasInvesting in Illinois$311 
Virginia Natural GasSAVE52 
Atlanta Gas LightSystem Reinforcement Rider51 
Chattanooga GasPipeline Replacement Program
Total$416