EX-10.214 6 dex10214.htm AMENDMENT TO STANDARD FORM OF AGREEMENT Amendment to Standard Form of Agreement

Exhibit 10.214

 

AMENDMENT NO. 1

 

Pursuant to Section 2.2.8 of that certain Standard Form of Agreement Between Owner and Construction Manager (A1A Document A121 CMc - 2003) by and between River Ventures, LLC (“Owner”) and Bovis Lend Lease, Inc. (“Construction Manager”) dated August 30, 2005 (“Contract”), the attached Guaranteed Maximum Price (“GMP”) dated April 28, 2005, with a GMP Update dated August 11, 2005, is hereby incorporated by reference into the Contract.

 

The signatures below confirm and approve the incorporation of this Amendment No. 1 into the Contract.

 

OWNER:

      CONSTRUCTION MANAGER:

RIVER VENTURES, LLC

     

BOVIS LEND LEASE, INC.

By:

 

 


     

By:

 

 


Name:

 

 


     

Name:

 

Brad Eller

Title:

 

 


     

Title:

 

Senior Vice-President

Date:

 

 


     

Date:

 

November 10, 2005


Foundation GMP Update

 

PPD Headquarters Building

Wilmington, NC

 

August 11, 2005


PPD Corporate Headquarters

Foundation GMP Update

Wilmington, NC

 

Foundation GMP Update

 

Bovis Lend Lease is pleased to present the update to the Foundation GMP for the PPD Headquarters Building in Wilmington, NC. The update is based on our GMP submittal of April 28, 2005 and the additional clarifications presented in this document.

 

The revised GMP cost is $10,629,592 or $91.24/sf is based upon 116,506sf of Parking Deck. The cost difference between this GMP update and the April submission are the Pending Change Orders to date that we were requested to incorporate. These include increases for foundation redesign and rock excavation as well as deducts for dewatering, retaining walls, imported fill, and the subdrainage system. See the attached estimate and recap for further detail.

 

This update includes a deduct of $240,000 for the retaining wall allowance. That scope of work is in the Core and Shell GMP but the credit has been included within this foundation update to stay consistent with discussions at the jobsite. If this credit becomes part of the Foundation GMP, there will be no credit for it under the Core and Shell GMP.


Project Name:

   PPD HEADQUARTERS BUILDING    Date: August 11, 2005

Location:

   Wilmington, NC    S. F. Project Area:    116,506
     Foundation GMP Update    Project Number:    24401100

Estimate No

   3               

 

CSI

DIVISION


  

DESCRIPTION


         Current
Projected Cost


  

COST/

SQFT


   % of Total

 

02

   Site Work            $ 4,417,947    $ 37.92    41.56 %

03

   Concrete            $ 4,350,720    $ 37.34    40.93 %

04

   Masonry            $ 0    $ 0.00    0.00 %

05

   Metals            $ 0    $ 0.00    0.00 %

06

   Woods & Plastics            $ 0    $ 0.00    0.00 %

07

   Thermal & Moisture Protection            $ 168,872    $ 1.45    1.59 %

08

   Doors and Windows            $ 0    $ 0.00    0.00 %

09

   Finishes            $ 0    $ 0.00    0.00 %

10

   Specialties            $ 0    $ 0.00    0.00 %

11

   Equipment            $ 0    $ 0.00    0.00 %

12

   Furnishings            $ 0    $ 0.00    0.00 %

13

   Special Construction            $ 0    $ 0.00    0.00 %

14

   Conveying            $ 0    $ 0.00    0.00 %

15

   Mechanical Systems            $ 124,720    $ 1 07    1.17 %

16

   Electrical Systems            $ 111,510    $ 0.96    1.05 %
                  $ 0    $ 0.00    0.00 %
                 

  

  

Total Direct Cost

           $ 9,173,769    $ 78.74    86.30 %
                 

  

  

Subtotal

                $ 9,173,769    $ 78.74    86.30 %
                 

  

  

General Conditions

           $ 750,000    $ 6.44    7.06 %

Design Fees- By Owner

           $ 0    $ 0.00    0.00 %

City Building Permit -Allowance

           $ 66,000    $ 0.57    0.62 %

Escalation

        $ 0.00     $ 0    $ 0.00    0.00 %

Project Contingency

           $ 249,821    $ 2.14    2.35 %

General Liability Insurance

     1.230 %   $ 130,744    $ 1.12    1.23 %

Builder’s Risk Insurance-By Owner

     0     $ 0    $ 0.00    0.00 %
                 

  

  

Subtotal

                $ 10,370,334    $ 89.01    97.56 %

Fee

          2.500 %   $ 259,258    $ 2.23    2.44 %

Preconstruction

     L.S     $ 0    $ 0.00    0.00 %

Bond- Not Required

     0.00 %   $ 0    $ 0.00    0.00 %

Total Building Construction Budget Amount

           $ 10,629,592    $ 91.24    100.00 %
                 

  

  


PPD HEADQUARTERS BUILDING                   
Foundation GMP Update    8/10/2005              
                     Total

 
Item

       

Description


   Takeoff Qty

    Unit Cost

    Amount

 
01 Foundation GMP                   
02000 SITEWORK & DEMOLITION                   
02160        

Excav Support Systems

                  
        Excavation sheeting system-Cape Fear    1.00  all   309,000.00  /all   309,000  
         

Excav Support Systems

                  
                          

                           309,000  
02220        

Bulk Excavation

                  
        Building Excavation-Cape Fear    1.00  sub   1,019,341.00  /sub   1,019,341  
        Paving                   
        Fill at building-Cape Fear Paving    0.00  cy            
        Laydown Area for Staging    1.00  ls   103,000.00  /ls   103,000  
        Site Layout & Certification    1.00  ls   82,400.00  /ls   82,400  
        Reduce amount of offsite fill    -1.00  ls   420,000.00  /ls   (420,000 )
        Rock Excavation    1.00  cy   1.00  /cy   1  
       

Cape Fear Paving

   4,200.00  cy   44.25  /cy   185,850  
       

East Coast Drilling

   4,200.00  cy   29.10  /cy   122,220  
       

BLL Equipment and Labor

   1.00  ls   22,000.00  /ls   22,000  
                          

         

Bulk Excavation

               1,114,812  
02241        

Dewatering

                  
     ob02    Dewatering Allowance                   
        Reduce dewatering allowance                   
         

Dewatering

                  
         

1.374 Labor Hours

                  
         

  0.46 Equipment Hours

                  
02280        

Soil Treatment

   76,910.00  sqft            
     010    Soil Termite Treatment by Concrete Sub                   
         

76.91 Labor Hours

                  
02290        

Foundation Redesign

                  
        Stone fill    10,400.00  ton   24.75  /ton   257,400  
        Lean Concrete    3,300.00  cy   134.45  /cy   443,685  
        Concrete revisions to foundation    1.00  ls   921,560.00  /ls   921,560  
        CMU at waterproofing    30,300.00  sf   19.30  /sf   584,790  
        Waterproofing    106,000.00  sf   4.60  /sf   487,600  
                          

         

Foundation Redesign

               2,695,035  
02580         Pavement Marking    0.00  Each            
        Pavement Markings-Cape Fear Paving                   
02710        

Sub Drainage

                  
     ob10    Perimeter Drain 6” (delete)    1,440.00  lnft            
         

Includes trench, gravel & filter fabric.

                  
     ob50    6” Under Slab Drain (delete)    5,225.00  lf            
         

Includes trench, gravel & filter fabric.

                  
         

Sub Drainage

                  
         

646.941 LaborHours

                  
         

168.625 Equipment hours

                  
02838        

Retaining Walls

                  
          Reduce retaining walls allowance    -1.00  ls   240,000.00  /ls   (240,000 )
         

This is actually a Core and Shell item. Retaining Walls

                  
                          

                           (240,000 )


PPD HEADQUARTERS BUILDING                 
Foundation GMP Update    8/10/2005            
                     Total

Item

       

Description


   Takeoff Qty

    Unit Cost

    Amount

          SITEWORK & DEMOLITION                4,417,947
         

725,225 Labor hours

                
         

169,083 Equipment hours

                
3000 CONCRETE                 
03050        

Excavate for Concrete

                
     010    Wall Footing Excavation by Machine    1,686.00  cuyd          
     020    Column Footing Excavation by Machine    2,057.00  cuyd          
     030    Interior Backfill & Compact Footings    3,500.00  cuyd          
     055    Fine Grade Mat Footings    10,723.00  sqft          
     055    Fine Grade Wall Footings    11,785.00  sqft          
     dew1    Dewater/Demuck Foundations    1.00  allo   36,050.00  /allo   36,050
                          
         

Excavate for Concrete

               36,050
         

3,729.664 Labor hours

                
         

1,839.44   Equipment hours

                
03100        

Concrete Forms & Access

                
     220    Wall Footing Forms (4 Use)    6,308.00  sqft          
     255    Column Footing Forms (4 Use)    6,944.00  sqft          
     527    Keyway In Footing    3,154.00  lnft          
     626    Wall Forms to 20’ (4 Use)    34,996.00  sqft          
     642    Const Joints/ Bulkheads @ Walls    151.00  lnft          
     703    Edge Forms on Grade (6’) (3 use)    155.00  lnft          
     733    SOG Bulkheads <12’    1,000.00  lnft          
     736    Turn Down Slab Edge Form    155.00  lnft          
     739    Screed Forms    74,924.00  sqft          
     804    Column Forms (4 use)    10,268.00  sqft          
     840    Column Forms - 42” dia. Tubes    80.00  loft          
     903    Beam Forms (4 use)    31,469.00  sqft          
     905    Beam Bottom Form - 3/4” Plywood    17,427.00  sqft          
     920    Flat Slab Forms (4 use)    66,591.00  sqft          
     926    Bulkhead Flat Slab Forms    402.00  lnft          
     940    Elevated Edge Forms 8”    1,736.00  lnfl          
     1120    Topping Screeds    66,591.00  sqft          
          Concrete Forms & Access                 
         

24,141.011 Labor hours

                
03200         Concrete Reinforcement                 
     010    Rebar Column Footings    116.00  ton          
     010    Rebar Wall Footings    89.00  ton          
     010    RebarSOG    5.00  ton          
     010    Grade8oupcharge    15.00  ton          
     010    Rebar Column    42.00  ton          
     010    RebarWalls    61.00  ton          
     010    Rebar Beams    229.00  ton          
     010    Rebar Elevated Slab    50.00  ton          
     028    Welded wire mesh-6x6 - w2.9 x w2.9 #6    82,587.00  sqft          
          Concrete Reinforcement                 
         

13,348.454 Labor hours

                
03300        

Place Concrete

                
     015    Place Concrete Wall Footings    1,636.00  cuyd          
     020    Place Concrete Column Footings    1,971.00  cuyd          
     045    Place Concrete Wall    981.00  cuyd          
     050    Gravel/stone Fill Under Slab    1,609.00  cuyd          
     065    Fine Grade Slab-on-Grade Subgrade    75,079.00  sqft          
     070    Place Concrete Slab On Grade    1,609.00  cuyd          


PPD HEADQUARTERS BUILDING                 
Foundation GMP Update    8/10/2005            
                     Total

Item

       

Description


   Takeoff Qty

    Unit Cost

    Amount

03300        

Place Concrete

                
     080    Place Concrete Columns Rectangular    234.00  cuyd          
     090    Place Concrete Beams    1,311.00  cuyd          
     095    Place Concrete Flat Slab    1,139.00  cuyd          
     115    Blow off/clean area to be poured    66,591.00  sqft          
     175    Concrete Stairs Complete    78.00 each          
     180    Place Concrete Steps On Grade Complete    12.00 each          
     180    Metal Pan Stair Fill    32.00 each          
         

Place Concrete

                
         

11,401.65 Labor hours

                
         

     272.32 Equipment hours

                
03310        

CIP Conc (Isum unit cost)

                
          Cast in place Concrete Foundation    1.00  sub   4,314,670.00  /sub   4,314,670
                          
         

CIP Conc (Isum unit cost)

               4,314,670
03345        

Concrete Finishing

                
     901    Steel Trowel Finish SOG    75,079.00  sqft          
     901    Steel Trowel Finish Elevated Slab    66,591.00  sqft          
     904    Rub and Patch Concrete    100,000.00  sqft          
     908    Cure Concrete (curing compound)    161,67000  nqft          
    

Concrete Finishing

                
         

6,373.40 Labor hours

                
03365        

Post-tensioned Concrete

                
     104    Furnish PT Cables w/Support Bars (per sqft)    66,591.00  sqft          
     105    Install PT Cables w/Pocket Patching (S/C per sqft)    66,591.00  sqft          
03380        

Concrete Hoisting/Equip.

                
ob05         Concrete pump (per cuyd total)    8,881.00  cuyd          
obO5         Crane Pads    2.00  each          
obO5         Cranes    4.00  mnth          
ob15         Concrete Equipment    8,881.00  cuyd          
          shy Safety    1.00  ls          
         

Concrete Hoisting/Equip.

                
         

8,887.00 Labor hours

                
         

8,887.00 Equipment hours

                
03385        

Concrete Mgmnt. & Lay-out

                
     10    Field Engineer    17.00 week          
     20    Rodman    17.00 week          
     30    Lay-out Crew (L&E)    17.00 week          
     40    Concrete Foreman    17.00 week          
     50    Assistant Project Manager    17.00 week          
     60    Assistant Superintendent    17.00 week          
         

Concrete Mgmnt. & Lay-out

                
         

4,760.00 Labor hours

                
         

   680.00 Equipment hours

                
03390        

Ready-mix Concrete

                
40rg         5,000 psi regular weight Footings    3,607.00  cuyd          
40rg         4,000 psi regular weight SOG    1,609.00  cuyd          
40rg         4,000 psi regularweight Walls    981.00  cuyd          
70rg         8,000 psi regular weight -Columns    234.00  cuyd          
70rg         5,000 psi regular weight Elevated Slab    1,139.00  cuyd          
add         Admixtures    8,881.00  cuyd          
03395        

Misc Concrete Access.

                
a005         Vapor Barrier 6 Mil Poly    75,079 00  sqft          


PPD HEADQUARTERS BUILDING                 
Foundation GMP Update    8/10/2005            
                Total

Item

  

Description


   Takeoff Qty

    Unit Cost

    Amount

03395   

Misc. Concrete Access.

                
a040    Waterstop - Rubber - 8”    2,914.00  lnft          
a075    Expansion Joint 1/2 x 6’    4,000.00  lnft          
    

Misc. Concrete Access.

                
    

561.163 Labor hours

                
                     
    

CONCRETE

               4,350,720
    

73,202.34 Labor hours

                
    

11,678.76 Equipment hours

                
7000 MOISTURE PROTECTION                 
07100   

Dampproof & Waterproof

                
     Waterproof Foundation Walls    1.00  SUB   168,872.00  /SUB   168,872
                     
    

Dampproof & Waterproof

               168,872
                     
     MOISTURE PROTECTION                168,872
15000 MECHANICAL                 
15400   

Plumbing

                
   Plumbing Systems Rough in Garage    116,328.00  sqft   1.072  /sqft   124,720
                     
    

Plumbing

               124,720
    

116,328.00 Labor hours

                
                     
     MECHANICAL                124,720
    

116,328.00 Labor hours

                
16000 ELECTRICAL                 
16100   

Electrical

                
   Electrical Systems Rough In Garage    116,328.00  sqft   0.96  /sqft   111,510
                     
    

Electrical

               111,510
    

116,328.00 Labor hours

                
                     
     ELECTRICAL                111,510
    

116,328.00 Labor hours

                
                     
     01 Foundation GMP                9,173,769
    

306,583.563 Labor hours

                
    

  11,847.84   Equipment hours

                


FOUNDATION GMP

 

PPD HeadQuarter Building

Wilmington, NC

 

April 28, 2005


PPD Corporate HeadQuarters

Wilmington, NC Summaries and Priorities

 

Executive Summary

 

This GMP for the Foundation Package is the first of three GMP’s that will be produced to complete the project. It is based upon the Parking Deck CD documents dated April 14, 2005 and the qualifications presented in this GMP proposal. The GMP cost of $8,665,592 or $74.38/sf is based upon 116,506sf of Parking Deck including contingency. Scope not covered in this GMP will be pick-up in the Shell and Core or Tennant GMP’s

 

Our GMP does not include any monies for cost impacts or delays incurred for soil and water issues encountered.

 

The Foundation GMP is a limited scope of work and is intended to only be for the following scope of work

 

Excavation and backfill required for foundation

 

Concrete foundation and elevated slab up to but not including elevation 37

 

Ebeds, raceways, under slab rough in required for foundation.

 

The foundation GMP does not include the following:

 

Site Work other than garage excavation for Phase 1 or 2

 

Unit Masonry

 

Metal Fabrication, Metal Stairs, Rails or Grating

 

Steel Doors or Frames

 

Overhead Coiling Grills

 

Door Hardware

 

Glazing

 

Parking Control Equipment

 

Loading Dock Equipment

 

Elevators

 

Louvers

 

Any work not noted as specially included herein

 

In additions to the GMP there are other funding requirements that will require us to be released prior to the completion of the 2nd GMP on the Core and Shell. We ask that we be permitted to commit to contracts for those scopes of work, in addition to the GMP.

 

Foundation GMP

     8,665,592

Precast Purchase

     2,800,000

Long Lead Metals

     1,000,000

Elevators

     1,750,000

Glazing Purchase

     7,708,064

Concrete Frame

     8,763,724

Long Lead Mechanical Equipment

     2,000,000

Long Lead Electrical Equipment

     750,000

Total Requested funding

   $ 33,437,380


PPD Corporate HeadQuarters

Wilmington, NC Summaries and Priorities

 

Bovis Lend Lease recommends a thorough review of this document by the Project Team. We have developed a project schedule that establishes a 20 month duration for the project, with no weather delays assuming a phased bid package approach and a 40 hour work week.


PPD Corporate HeadQuarters

Wilmington, NC Basis of Estimate

 

General Clarifications

 

The following definition represents the basis of our estimate. The estimated costs were developed based upon the Space Programming Report and Document drawings prepared to date by Cline Design Associates and Cooper Carry Inc. as indicated in the document log and the assumptions and clarifications updated under this section, along with project description and schedule data presented under other sections of this report.

 

1. Subcontractor bonds are included for all trades valued in excess of $100,000.

 

2. The pricing included does not anticipate any stoppage of construction work as a result of present PPD Operations. If interruptions in work are foreseeable with regards to interfacing with existing facilities or business decisions to perform only a portion of the work, a separate allowance will need to be defined.

 

3. We have included a 3% design contingency in this analysis.

 

4. It is understood that since the documents are not yet complete, the Owner, Architect and Bovis will work together to monitor completion of the design, in accordance with the intent and scope of the documents that form the basis of the budget. Should an increase in the budget be indicated due to deviations from such intent and scope during document completion, Bovis will recommend possible economies in order to protect the budget from increasing. If these economies are not accepted, the budget shall be increased to cover the increased cost and the associated General Conditions and Fee.

 

5. Any economies accepted by the Owner will also be accepted by the Architect and will be incorporated into the construction drawings and specifications as if they were part of the original design.

 

6. The GMF line item costs include items of work that will be subcontracted, as well as Bovis’ reimbursable costs. No guarantee exists on any separate line, Savings in any line item may be transferred to cover possible overruns of other line items.

 

7. The GMP is based on the premise that the design will meet alt codes, laws, ordinances, rules, and regulations in effect at the time that the budget was prepared. The budget shall be adjusted should any discrepancies between design and the aforementioned codes, laws or ordinances result in, or require, an increase in the Cost of the Work.

 

8. No testing is included.

 

9. The budget does not include Builders Risk insurance. General Liability insurance is included. The cost of a Payment and Performance Bond from Bovis Lend Lease is not included.

 

10. The budget includes a 12-month warranty of all work that begins the date of the temporary certification of occupancy or date of first service of equipment which ever comes first. Any extended warranties required by the Specifications will be exclusively managed by and contracted between the manufacturer/subcontractor and the Owner.

 

11. This proposal is based on mutually agreeable contract terms.

 

12. Sales Tax is included.

 

13. The additional cost for schedule compression, out-of-sequence operations, wage premiums for non-standard working timeframes, and associated operations are not included in the individual Trade Budget Estimates.


PPD Corporate HeadQuarters

Wilmington, NC Basis of Estimate

 

14. We have included the Town of Wilmington Building Permit Fee. All other fees and escrows are excluded and assumed budgeted separately by PPD.

 

15. No Costs is included for parking fees, shuttles or any other requirements due to lack of parking during normal work hours.

 

16. The following costs are not included in our estimate:

 

a. Any Preconstruction costs

 

b. Document Reproduction

 

c. Security Systems

 

d. FF&E

 

e. Usage/Tap Fees

 

f. Planning Fees

 

g. Architectural Fees

 

h. lmpact/Development Fees

 

Allowances:

 

1. Dewatering

   $ 870,000

2. Excavation Support

   $ 300,000

3. Under slab piping

   $ 78,131

4. Utility Consumption

   $ 25,000

5. Building Permit

   $ 66,000


PPD Corporate HeadQuarters

Wilmington, NC Basis of Estimate

 

Assumptions and Clarifications

Building Area

 

        PPD

       
  Mechanical   6,073.00        
  12   19,004.00        
  11   18,868.00        
  10   28,540.00        
  9   28,540.00        
  8   28,540.00        
  7   28,540.00        
  6   28,540.00        
  5   28,540.00        
  4   28,540.00        
  3   32,176,00        
  2   38,918.00        
  1   61,231,00        
  P2   25,490.00   40,059.00    
  P1   —     76,447.00    
     
 
   
  GSF Office Building   401,540.00   116,506.00   GSF Garage

 

Site

 

1. The work included in this GMP is generally limited to Excavation of the Structure, Sheeting and Shoring of excavation, Concrete Frame to the top of the underside of elevation 37, Back fill of building, Mechanical & Electrical Sleeving, Mechanical and electrical path ways in concrete slab or under foundation slabs

 

2. We have not included electrical duct banks.

 

3. We have not included any work for Phase Two

 

4. Excavation will be shored to prevent cave in by sheeting and shoring.

 

5. Dewatering is included as an allowance.

 

6. Due to the uncertainty of the Phase two site work we are not including any keystone retaining walls on the south side of the building at this time.

 

7. We have included termite treatment for the slab on grade.

 

8. We do not include any handling, treatment, or disposal of characteristically hazardous material, soil, water etc. or unsuitable material.

 

9. We do not include excavation of rock, existing foundations, piping or other utility structures.

 

10. We have included 5,225lnft of under slab drainage piping for an allowance of $78,131. This piping is not shown on the drawings.


PPD Corporate HeadQuarters

Wilmington, NC Basis of Estimate

 

Concrete

 

1. We have assumed that concrete in the garage will not be architectural in nature and that the finish will be the natural finish that a grade b plywood will leave when the forms are pulled.(Class D Finish)

 

2. We have provided a floor finish of between F(F) 20 and F(L) 25 in lieu of 1/8” tolerance in10’-0” or similar forms of measure.

 

3. Curing of floor slabs will be with Kurex-DR VOX curing compound or equal in lieu of moisture cure.

 

4. Formwork is based on use of 23/32” thick SB exterior grade plywood

 

5. Rubbing cast-in-place concrete is excluded

 

6. In exposed ceiling areas we are grinding only the plywood seams.

 

7. We do not include the sealing of chamfered wall construction or control joints as Indicated on detail 4 on S0.1.

 

8. Our GMP is based on using wood formed pans.

 

9. Specification call for a class B finish on exposed concrete, pan slabs will be a Class D finish not class B.

 

10. We have not included precast embeds.

 

11. We have not included additional pricing for concrete referenced in email from Uzan and Case dated 4/25/05

 

Masonry

 

1. All masonry walls in the garage will be priced under the Core and Shell GMP.

 

Miscellaneous Metals

 

1. All metal stair will be priced under the Core and Shell GMP.

 

2. We have included cable rail at the garage area ramps.

 

Woods and Plastics

 

1. Not required.

 

Thermal and Moisture Protection

 

1. We have included a waterproofing system for the foundation walls.

 

2. No under slab waterproofing system is included. Section 5 & 6 on S0.2 are assumed to be in error.

 

Glass & Glazing

 

1. All Doom and Frames will be priced in the Core and Shell GMP

 

2. All glazing will be priced in the Core & Shell GMP.


PPD Corporate HeadQuarters

Wilmington, NC Basis of Estimate

 

3. Overhead coiling doors will be priced in the Core and Shell GMP.

 

Finishes

 

1. All Finishes will be priced in the Core And Shell GMP

 

2. Specialties

 

1. All specialties will be priced in the Core & Shell GMP.

 

Equipment

 

1. The parking gate and controller will be priced in the Core & Shell GMP.

 

2. Dock levelers will be priced in the Core & Shell GMP.

 

Furnishings

 

1. Not Required.

 

Conveying:

 

1. We assume the hydraulic elevator will be a hole less type not requiring a jack hole.

 

Mechanical:

 

1. We have included an allowance of $124,720 for all Plumbing, HVAC & Sprinkler sleeving or embedded in walls columns or slabs, no other work has been included

 

Electrical:

 

1. We have included an allowance of $111,510 electrical sleeving or conduit embedded in walls columns or slabs, no other work has been included.