Property and plant, at original cost $ 26,468 [1],[2] $ 26,154 [1],[2]
Accumulated depreciation and amortization 9,429 [1],[2] 9,194 [1],[2]
Property and plant, before construction work in progress 17,039 [1],[2] 16,960 [1],[2]
Property and Plant, Net 18,127 [1],[2] 17,853 [1],[2]
Capital lease agreements, gross asset value 229 228
Total accumulated depreciation, capital lease agreements 52 46
Electric [Member]
   
Property and plant, at original cost 24,256 [1],[2] 24,069 [1],[2]
Gas [Member]
   
Property and plant, at original cost 1,746 [1],[2] 1,661 [1],[2]
Other Energy [Member]
   
Property and plant, at original cost 466 [1],[2] 424 [1],[2]
Construction work in progress 833 [1],[2] 634 [1],[2]
Nuclear Fuel [Member]
   
Construction work in progress $ 255 [1],[2] $ 259 [1],[2]
[1] Includes amounts for Ameren registrant and nonregistrant subsidiaries as well as intercompany eliminations.
[2] Amounts in Ameren and Ameren Missouri include two electric generation CTs under two separate capital lease agreements. The gross asset value of those agreements was $229 million and $228 million at December 31, 2011 and 2010, respectively. The total accumulated depreciation associated with the two CTs was $52 million and $46 million at December 31, 2011 and 2010, respectively.