Rate And Regulatory Matters (Narrative-Illinois) (Details) - USD ($)
$ in Millions
1 Months Ended 3 Months Ended 9 Months Ended 12 Months Ended
Sep. 30, 2024
Dec. 31, 2023
Nov. 30, 2023
Sep. 30, 2024
Sep. 30, 2024
Sep. 30, 2023
Dec. 31, 2027
Dec. 31, 2026
Dec. 31, 2025
Dec. 31, 2024
Rate And Regulatory Matters [Line Items]                    
Capital expenditures         $ 3,029 $ 2,571        
Ameren Illinois Company                    
Rate And Regulatory Matters [Line Items]                    
Capital expenditures         1,091 $ 1,226        
Ameren Illinois Company | Natural gas                    
Rate And Regulatory Matters [Line Items]                    
Public Utilities, Requested Equity Capital Structure, Percentage   52.00%                
Public Utilities, Requested Return on Equity, Percentage   9.89%                
IETL | Ameren Illinois Company | Electric Distribution | Forecast                    
Rate And Regulatory Matters [Line Items]                    
Approved return on equity percentage             8.72% 8.72% 8.72% 8.72%
Multi-year rate plan rehearing approved revenue requirement             $ 1,397 $ 1,350 $ 1,282 $ 1,196
Approved rate base             4,700 4,500 4,300 4,000
Revised multi-year rate plan requested revenue requirement             1,444 1,385 1,299 1,215
Revised multi-year rate plan requested rate base             5,000 4,800 4,500 4,300
ICC staff revised multi-year rate plan recommended revenue requirement             1,424 1,369 1,288 1,206
ICC staff revised multi-year rate plan recommended rate base             $ 4,800 $ 4,600 $ 4,400 $ 4,200
Public Utilities, Approved Equity Capital Structure, Percentage             50.00% 50.00% 50.00% 50.00%
Public Utilities, Approved Rate Increase (Decrease), Amount                   $ 285
Public Utilities, Requested Rate Increase (Decrease), Amount                   332
ICC staff recommended rate increase                   311
IETL | Ameren Illinois Company | Electric Distribution | Forecast | Subsequent Event                    
Rate And Regulatory Matters [Line Items]                    
Multi-year rate plan ALJ proposed revenue requirement             $ 1,427 $ 1,370 $ 1,287 1,206
ALJ proposed rate base             $ 4,900 $ 4,600 $ 4,400 4,200
ALJ recommended rate increase                   $ 315
Pending Rate Case | Ameren Illinois Company | Electric Distribution                    
Rate And Regulatory Matters [Line Items]                    
Public Utilities, Requested Rate Increase (Decrease), Amount       $ 158            
Public Utilities, Requested Equity Capital Structure, Percentage       50.00%            
Pending Rate Case | Ameren Illinois Company | Electric Energy-Efficiency                    
Rate And Regulatory Matters [Line Items]                    
Public Utilities, Requested Rate Increase (Decrease), Amount         $ 26          
Pending Rate Case | Ameren Illinois Company | Natural gas                    
Rate And Regulatory Matters [Line Items]                    
Capital expenditures $ 30                  
Over-Recovery Challenged by the Attorney General $ 1                  
Final Rate Order | Ameren Illinois Company | Natural gas                    
Rate And Regulatory Matters [Line Items]                    
Approved return on equity percentage     9.44%              
Approved rate base     $ 2,850              
Public Utilities, Approved Equity Capital Structure, Percentage     50.00%              
Public Utilities, Requested Rate Increase (Decrease), Amount     $ 112              
Capital expenditures   $ 93 $ 93