Rate And Regulatory Matters Rate And Regulatory Matters (Tables)
6 Months Ended
Jun. 30, 2019
Public Utilities, General Disclosures [Abstract]  
Schedule of Wind Generation Facilities [Table Text Block] The following table provides information with respect to each build-transfer agreement:
 
 
Up-to 400-Megawatt Facility
 
Up-to 300-Megawatt Facility
Build-transfer agreement date
 
May 2018
 
May 2019
Wind facility developer
 
Terra-Gen, LLC
 
Enel Green Power North America, Inc.
Location
 
Northeastern Missouri
 
Northwestern Missouri
Status of certificate of convenience and necessity from the MoPSC
 
Approved October 2018
 
Requested in May 2019(a)
Status of final interconnection costs
 
Received in July 2019
 
Received in July 2019
Status of RTO transmission interconnection agreement
 
Expected by the fall of 2019
 
Expected by the fall of 2019
Status of FERC approval
 
Received December 2018
 
To be requested in the third quarter of 2019
Expected completion date
 
By the end of 2020
 
By the end of 2020
(a)
In July 2019, Ameren Missouri, the MoPSC staff, and certain intervenors filed a nonunanimous stipulation and agreement with the MoPSC regarding the requested certificate of convenience and necessity.