Other commitments:                    
Commitment for capital projects | $               $ 236.2    
Michiquillay                    
Other commitments:                    
Pre-operational period   12 years                
Extended pre-operational period   3 years                
Investment in projects in next five years | $   $ 20.0                
Number of meters drilled | item               140,130 140,130  
Number of core samples obtained | item               45,762 45,762  
Period of investment in projects   5 years                
Toquepala Concentrator Expansion | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               $ 118.0 S/ 445.0  
Commitment liability recorded in the balance sheet | $               27.8    
Development Fund Moquegua Region | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               $ 265.3 S/ 1,000.0  
Number of schools agreed for construction. | item               3 3  
Amount committed to funding for school projects               $ 4.8 S/ 18.2  
Amount committed for funding social and infrastructure improvement projects, build tracks and sidewalks               1.9 7.0  
Copper | Michiquillay | Peru                    
Other commitments:                    
Contingent contractual obligation | $       $ 400.0            
Estimated mineralized material (in tons) | T       2,288,000,000            
Copper grade percentage       0.43%            
Annual production ( in tons) | T       225,000            
Initial mine life       25 years            
Contractual obligation paid on project | $     $ 12.5 $ 12.5            
Remaining amount to pay if project is developed | $     $ 375.0              
Funding for Different Projects | Development Fund Moquegua Region | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               66.7 251.5  
Educational Project | Toquepala Concentrator Expansion | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               5.0 18.8  
Educational Project | Development Fund Moquegua Region | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               28.8 108.4  
Amount of investment in project               28.3   S/ 106.7
Agricultural Projects | Toquepala Concentrator Expansion | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               29.7 112.0  
Construction of Cularjahuira Dam | Toquepala Concentrator Expansion | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               4.1 15.6  
Study Of Engineering For Collazas Dam | Toquepala Concentrator Expansion | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               0.7 2.6  
Infrastructure Projects | Toquepala Concentrator Expansion | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               16.0 60.4  
Water Treatment | Development Fund Moquegua Region | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               $ 28.0 S/ 105.5  
Percentage of progress on construction               51.00% 51.00%  
Drinking Water Project | Toquepala Concentrator Expansion | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               $ 2.5 S/ 9.6  
Feasibility Studies and Minor Projects | Development Fund Moquegua Region | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               3.3 12.4  
Works For Taxes | Toquepala Concentrator Expansion | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               27.1 102.1  
Works For Taxes | Development Fund Moquegua Region | Peru                    
Other commitments:                    
Amount committed to funding for social and infrastructure improvement projects               $ 60.5 S/ 228.0  
Number of Infrastructure Projects Agreed for Construction | item               4 4  
Amount financed per-investment studies for basic sanitation               $ 0.1 S/ 0.3  
Pre investment studies for road infrastructure               $ 1.0 S/ 3.6  
Works For Taxes | Apurimac Region                    
Other commitments:                    
Number of schools agreed for construction. | item               2 2  
Amount committed to funding for school projects               $ 22.2 S/ 83.8  
Works For Taxes | Arequipa Region                    
Other commitments:                    
Number of schools agreed for construction. | item               2 2  
Amount committed to funding for school projects               $ 29.0 S/ 109.5  
Amount committed to Finance for past infrastructure project               1.7 6.3  
Works For Taxes | Cajamarca Region                    
Other commitments:                    
Amount committed for funding health projects               $ 0.2 S/ 0.7  
Electroperu S.A | Power purchase agreements | Peru                    
Other commitments:                    
Purchase agreement, contracted power capacity (in megawatts) | MW             120      
Term of power purchase agreement related to sale of power plant             20 years      
Parque Eolico de Fenicias, S. de R.L. de C.V | Power purchase agreements | Mexico                    
Other commitments:                    
Term of power purchase agreement related to sale of power plant 20 years                  
Purchase agreement, contracted power capacity (in megawatts per year) | MWh 611,400                  
Kallpa | Power purchase agreements | Peru                    
Other commitments:                    
Purchase agreement, contracted power capacity (in megawatts) | MW           120        
Term of power purchase agreement related to sale of power plant           10 years        
Kallpa | Power purchase agreements | Peru | Maximum                    
Other commitments:                    
Purchase agreement, contracted power capacity (in megawatts) | MW         80