XML 31 R14.htm IDEA: XBRL DOCUMENT  v2.3.0.11
ASSET RETIREMENT OBLIGATION:
6 Months Ended
Jun. 30, 2011
ASSET RETIREMENT OBLIGATION:  
ASSET RETIREMENT OBLIGATION:

NOTE 9 - ASSET RETIREMENT OBLIGATION:

 

The Company maintains an estimated asset retirement obligation for its mining properties in Peru, as required by the Peruvian Mine Closure Law.  In accordance with the requirements of this law the Company’s closure plans have been approved by the Peruvian Ministry of Energy and Mines (“MINEM”).  As part of the closure plans, commencing in January 2010 the Company provides annual installments of $2.6 million over a 34 year period to guarantee the availability of funds to meet this obligation.  Therefore, as of January 2011 the Company has made installments on the guarantee of $5.2 million, in the form of a lien on its Lima office building.  The accepted value of the Lima office building, for this purpose, is $17 million.

 

The closure cost recognized for this liability includes the cost as outlined in its closure plans, which includes the physical, geochemical and hydrological stabilization of the mine pits and dumps as well as the tailings facility, the dismantling and demolition of the Toquepala and Cuajone concentrators, the smelter and refinery in Ilo, and the shops and auxiliary facilities at the three operating areas.

 

The following table summarizes the asset retirement obligation activity for the six months ended June 30, 2011 and 2010 (in millions):

 

 

 

2011

 

2010

 

Balance as of January 1

 

$

59.1

 

$

48.9

 

Changes in estimates

 

 

8.7

 

Additions

 

 

 

Accretion expense

 

1.7

 

1.6

 

Balance as of June 30,

 

$

60.8

 

$

59.2