EX-99.1 2 tm2532001d1_ex99-1.htm EXHIBIT 99.1

 

Exhibit 99.1

 

 

Diamba Sud Gold Project,

Kédougou Region, Senegal

 

Technical Report,

Effective Date: October 15, 2025

 

Prepared for Fortuna Mining Corp.

 

Prepared by

Eric Chapman

Senior Vice President of Technical Services - Fortuna Mining Corp.

 

Paul Weedon

Senior Vice President of Exploration - Fortuna Mining Corp.

 

Raul Espinoza

Director of Technical Services - Fortuna Mining Corp.

 

Mathieu Veillette

Director, Geotechnical, Tailings and Water - Fortuna Mining Corp.

 

Leendert (Leon) Lorenzen

Senior Principal Consultant (Process) - Lorenzen Consultants Pty Ltd

 

Suite 820, 1111 Melville Street, Vancouver, BC, V6E 3V6. Tel: (604) 484 4085

 

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Forward- Looking Statements

 

This Technical Report contains certain forward-looking information and forward-looking statements within the meaning of applicable securities legislation and may include future-oriented financial information (collectively, “Forward-looking Information”). Forward-looking Information in this Technical Report includes, but is not limited to, statements regarding: the Company’s plans and expectations for the Diamba Sud Project, including the estimattion of mineral resources the estimation of future mineral resources at the project; the Company’s ability to convert existing mineral resources into categories of higher geological confidence or mineral reserves; the projected yearly gold production profile, all-in sustaining costs (“AISC”), mill throughput and average grades; future plans for exploration drilling; the projected economics of the project, including total gold sales, margins, taxes, average annual production, the net present value of the project, the internal rate of return on the project, project payback period, average yearly free cash flow, life of mine unit costs, projected mine life, the total initial capital and sustaining capital required; estimated operating costs; the project design, including the location of the tailings management facility, process plant, water storage dam, infrastructure area, stockpile areas, camp; and the proposed open pit mine plans; the plans for completing the early works program; the project development timeline to production including the Company’s work relating to its environmental impact assessment statement and obtaining the permit, the permitting of future phases of the project, the timing of the completion of future studies including a feasibility study, obtaining an exploitation permit for the project, other permitting approvals including an environmental permit, and the development and construction of a mine and production at the project, including the constructing of a series of open pit mines; the timing of and future prospects for exploration and any expansion of the project, including upside associated with the project and the Company’s adjacent permits; the potential for expanding the initial mineral resource and the potential for identifying additional mineralization in areas of intercepts and conceptual areas for extension and expansion; potential recovery rates or processing techniques; the potential for a hybrid solar power plant; ongoing studies to optimize the mine design and enhance operational efficiency; the possibility of reducing capital and operating costs through engineering and optimization studies; potential to enhance socio-economic impacts of the Project; and opportunities to reduce the impact of the operations on the environment.

 

Often, but not always, these forward-looking statements can be identified by the use of words such as “anticipates”, “believes”, “plans”, “estimates”, “expects”, “forecasts”, “scheduled”, “targets”, “possible”, “strategy”, “potential”, “intends”, “advance”, “goal”, “objective”, “projects”, “budget”, “calculates” or statements that events, “will”, “may”, “shall”, “could”, “should” or “would” occur or be achieved and similar expressions, including negative variations.

 

The material factors or assumptions regarding Forward-looking Information contained in this Technical Report are discussed in this report, where applicable. Forward-looking Information is subject to known and unknown risks, uncertainties and other factors that may cause actual results and developments to differ materially from those expressed or implied by such Forward-looking Information. Relevant risks and other factors include,

 

October 15, 2025Page 2 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

without limitation: the estimation of Mineral Resources, the realization of resource estimates and mine plan, any potential upgrades of existing resource estimates, gold metal prices, the timing and amount of future exploration and development expenditures, the estimation of initial and sustaining capital requirements, the estimation of labour and operating costs; fluctuations in foreign exchange or interest rates; the possibility of material increases in costs and inflation and effects of same on the supply chain which could impact capital and operating costs; extended procurement and delivery times for key mechanical and power generation equipment may lead to delays; the ability to obtain qualified staff the availability of necessary financing and materials to continue to explore and develop the Company’s properties in the short and long-term, the progress of exploration and development activities; dependence of operations on construction and maintenance of infrastructure; the receipt of necessary regulatory approvals, the Company’s ability to maintain existing or obtain all necessary permits, licenses and regulatory approvals, including an exploitation permit and environmental permit, in a timely manner or at all; changes in laws, regulations and government practices, including environmental, tax, export and import laws and regulations; that the evolution of local content laws in Senegal which may affect contracting and recruitment; legal restrictions relating to mining; that the percentage of the taxes, royalties payable to the State and the contributions to the community development fund are consistent with the provisions of Boya’s Mining Convention; the viability, economically and otherwise of developing the Diamba Sud Project; economic and politicial risks associated with operating in foreign countries, including emerging country risks, exchange controls, and corruption; political developments in Senegal being consistent with Fortuna’s expectations; and risks relating to expropriation; increased competition in the mining industry and assumptions with respect to currency fluctuations, environmental risks including risks related to climate change; risks related to artisanal mining on the Project title disputes or claims, and other similar matters; the risk that the State of Senegal may elect to purchase up to an additional 25% interest in Boya SA at a “fair price” determined through an independent valuation upon the granting of the exploitation permit as is permissible under Senegalese mining legislation; uncertainties and hazards associated with gold exploration, development and mining, including but not limited to environmental hazards, accidents, operational stoppages, and other factors as described in the section 'Risk Factors' in Fortuna’s current Annual Information Form for the year ended December 31, 2024. Readers are cautioned that the foregoing factors are not exhaustive. Although the Company has attempted to identify important factors that could cause actual actions, events, or results to differ materially from those described in these Forward-looking Statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended.

 

Forward-looking Information is designed to help readers understand views as of that time with respect to future events and speaks only as of the date it is made. All the Forward-looking Information in this Technical Report is qualified by these cautionary statements. Except as required by applicable law, Fortuna and the Qualified Persons who authored this Technical Report assume no obligation to update publicly or otherwise revise any

 

October 15, 2025Page 3 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Forward-looking Information in this Technical Report, whether because of new information or future events or otherwise.

 

Cautionary Note to United States Investors Concerning Estimates of Reserves and Resources

 

The Company is a Canadian “foreign private issuer” as defined in Rule 3b-4 under the Exchange Act and is permitted to prepare the technical information contained herein in accordance with the requirements of the securities laws in effect in Canada, which differ from the requirements of the securities laws currently in effect in the United States.

 

Technical disclosure regarding the Diamba Sud Project included in this Technical Report was prepared in accordance with National Instrument 43-101 — Standards of Disclosure for Mineral Projects (“NI 43-101”). NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. NI 43-101 differs significantly from the disclosure requirements of the Securities and Exchange Commission (the “SEC”) generally applicable to U.S. companies. Accordingly, information contained herein is not comparable to similar information made public by U.S. companies reporting pursuant to SEC disclosure requirements.

 

Cautionary Note Regarding Non-IFRS Measures

 

This Technical Report includes certain terms or performance measures and ratios commonly used in the mining industry that are not defined under International Financial Reporting Standards (“IFRS”), including earnings before interest, tax, depreciation and amortization (“EBITDA”), cash costs and AISC per payable ounce of gold sold. Non-IFRS measures do not have any standardized meaning prescribed under IFRS and, therefore, they may not be comparable to similar measures employed by other companies. Accordingly, these measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS.

 

October 15, 2025Page 4 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Contents

 

1 Summary 20
  1.1 Introduction 20
  1.2 Property Description, Location and Access 20
  1.3 Mineral Tenure, Surface Rights and Royalties 21
  1.4 History 21
  1.5 Geology and Mineralization 22
  1.6 Exploration, Drilling and Sampling 23
  1.7 Data Verification 27
  1.8 Mineral Processing and Metallurgical Testing 27
  1.9 Mineral Resources 29
  1.10 Mineral Reserves 30
  1.11 Mining methods 30
  1.12 Processing and Recovery Methods 31
  1.13 Project infrastructure 32
  1.14 Market Studies and Contracts 32
  1.15 Environmental Studies and Permitting 32
  1.16 Capital and Operating Costs 33
    1.16.1 Capital cost estimate 33
    1.16.2 Operating cost estimate 34
  1.17 Economic analysis 35
  1.18 Conclusions 37
  1.19 Risks and Opportunities 37
  1.20 Recommendations 38
    1.20.1 Exploration 38
    1.20.2 Geotechnical 39
    1.20.3 Water Management 39
    1.20.4 Metallurgical 40
    1.20.5 Environmental and Social 40
    1.20.6 Engineering Studies 40
         
2 Introduction 42
  2.1 Report Purpose 42
  2.2 Qualified Persons 43
  2.3 Scope of Personal Inspection 43
    2.3.1 Mr. Eric Chapman 43
    2.3.2 Mr. Paul Weedon 43
    2.3.3 Mr. Mathieu Veillette 43
  2.4 Effective Dates 44
  2.5 Previous Technical Reports 44
  2.6 Information Sources and References 44

 

October 15, 2025Page 5 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

  2.7 Acronyms 44
         
3 Reliance on Other Experts 46
     
4 Property Description and Location 47
  4.1 Ownership 47
  4.2 Mineral Tenure and Surface Rights 47
    4.2.1 History of the Mining Code 47
    4.2.2 Permits 48
    4.2.3 Surface Rights 50
  4.3 Royalties 50
  4.4 Permitting 51
  4.5 Social and Environmental Considerations 51
  4.6 Comment on Section 4 51
         
5 Accessibility, Climate, Local Resources, Infrastructure and Physiography 52
  5.1 Accessibility 52
  5.2 Climate 52
  5.3 Topography, Elevation and Vegetation 52
  5.4 Local Resources and Infrastructure 53
    5.4.1 Sources of Power and Water 53
    5.4.2 Consumables 53
    5.4.3 Labor 53
    5.4.4 Infrastructure 53
  5.5 Comment on Section 5 54
         
6 History 55
  6.1 Previous Owners and Results 55
    6.1.1 Anmercosa, 1993–1996 55
    6.1.2 Ashanti Goldfields, 1997–1998 55
    6.1.3 Iamgold, 1999–2014 55
    6.1.4 Boya Gold Pty Ltd 2015–2016 55
    6.1.5 Chesser Resources Ltd. 2017–2023 56
  6.2 Geophysics 56
  6.3 Other Work 57
  6.4 Production History 57
         
7 Geological Setting and Mineralization 58
  7.1 Regional Geology 58
  7.2 Local Geology 61
    7.2.1 Lithologies 61
    7.2.2 Tectonic Setting 62
    7.2.3 Alteration 63

 

October 15, 2025Page 6 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

    7.2.4 Mineralization 63
  7.3 Deposit Geology 64
    7.3.1 Area A 66
    7.3.2 Area D 67
    7.3.3 Karakara 68
    7.3.4 Kassassoko 69
    7.3.5 Western Splay 70
    7.3.6 Moungoundi 70
    7.3.7 Southern Arc 71
  7.4 Comment on Section 7 72
       
8 Deposit Types 73
  8.1 Mineral Deposit Type 73
  8.2 Comment on Section 8 73
       
9 Exploration 74
  9.1 Historical Exploration Activities 74
  9.2 Exploration Activities Conducted by Fortuna 74
  9.3 Exploration Potential 75
    9.3.1 Bougouda 75
    9.3.2 Gamba Gamba North 75
    9.3.3 Other Prospects 76
  9.4 Comment on Section 9 76
       
10 Drilling 77
  10.1 Drilling Conducted by Chesser 77
    10.1.1 Auger Drilling 77
    10.1.2 RC and Core Drilling 78
  10.2 Drilling Conducted by Fortuna 80
  10.3 Drilling Used in the Estimation of Mineral Resources 82
  10.4 Drilling Since the Mineral Resource Database Cut-off Date 82
    10.4.1 Grade Control Drilling 89
  10.5 Extent of Drilling 89
  10.6 Drilling Techniques and Procedures 90
    10.6.1 Reverse Circulation Drilling 90
    10.6.2 Core Drilling 90
    10.6.3 Geological and Geotechnical Logging Procedures 90
    10.6.4 Photography 90
    10.6.5 Core Orientation 91
    10.6.6 Drill Core Recovery 91
    10.6.7 Collar Surveying 91
    10.6.8 Downhole Surveying 91
  10.7 Sample Length Versus True Thickness 91

 

October 15, 2025Page 7 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 
  10.8 Example of Drill Intercepts 91
  10.9 Comment on Section 10 92
       
11 Sample Preparation, Analyses, and Security 94
  11.1 Sample Preparation Prior to Dispatch of Samples 94
  11.2 Sample Collection 94
  11.3 Sample Dispatch 94
  11.4 Sample Preparation 94
  11.5 Analytical Methods 95
  11.6 Laboratory Accreditation 95
  11.7 Sample Security and Chain of Custody 95
  11.8 Bulk Density Determination 95
  11.9 Quality Assurance and Quality Control 96
    11.9.1 Database 96
    11.9.2 Certified Reference Materials 97
    11.9.3 Field Duplicates 97
    11.9.4 Blanks 97
    11.9.5 Twin holes 97
  11.10 Comment on Section 11 98
       
12 Data Verification 99
  12.1 Introduction 99
    12.1.1 Chesser 99
    12.1.2 Fortuna 99
  12.2 Database 99
  12.3 Collar and Downhole Surveys 100
  12.4 Geologic Logs and Assays 100
  12.5 Sample Type Comparison 100
  12.6 Mineral Resource Estimation 101
  12.7 Data Verification by Qualified Persons 101
    12.7.1 Mr. Eric Chapman 101
    12.7.2 Mr. Paul Weeden 102
    12.7.3 Mr. Raul Espinoza 102
    12.7.4 Mr. Mathieu Veillette 102
    12.7.5 Dr. Leon Lorenzen 103
  12.8 Comment on Section 12 103
       
13 Mineral Processing and Metallurgical Testing 105
  13.1 Introduction 105
  13.2 Sample Preparation 105
    13.2.1 Sample Selection and Identification 105
    13.2.2 Quantification of Minerals 109
  13.3 Comminution Testwork 112

  

October 15, 2025Page 8 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

    13.3.1 Abrasion Index 112
    13.3.2 Crushing Index 112
    13.3.3 Ball Mill Work Index 113
    13.3.4 SMC Testwork 113
  13.4 Leach and Cyanidation Testwork 114
    13.4.1 Gravity Concentration 115
    13.4.2 Grind Size Optimization 116
    13.4.3 Effect of Lead Nitrate on Cyanidation 118
    13.4.4 Effect of Air on Cyanidation 119
    13.4.5 Carbon in Leach 120
    13.4.6 Effect of Cyanide Concentration on Cyanidation 120
    13.4.7 Effect of Solid Concentration on Cyanidation 122
    13.4.8 Bulk Leach Testwork 123
    13.4.9 Carbon Testwork 125
  13.5 Rheology 127
  13.6 Diagnostic Leach 128
  13.7 Testwork on Prospects 129
    13.7.1 Comminution Testwork 129
    13.7.2 Gold Leaching Testwork 129
    13.7.3 Gravity Leach Testing 129
  13.8 Metallurgical Variability 130
  13.9 Recovery Estimates 131
  13.10 Deleterious Elements 133
  13.11 Comments on Section 13 133
       
14 Mineral Resource Estimates 136
  14.1 Introduction 136
  14.2 Supplied Data, Data Transformations and Data Preparation 136
    14.2.1 Data Transformations 136
    14.2.2 Software 136
    14.2.3 Data Preparation 136
  14.3 Geological Interpretation and Domaining 136
    14.3.1 Probabilistic Grade Shells 136
    14.3.2 Statistical Analysis of Composites 137
  14.4 Exploratory Data Analysis 138
    14.4.1 Sub-Domaining 140
    14.4.2 Grade Capping 140
  14.5 Variogram Analysis 143
    14.5.1 Continuity Analysis 143
    14.5.2 Variogram Modeling 143
  14.6 Modeling and Estimation 145
    14.6.1 Block Size Selection 145

 

October 15, 2025Page 9 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

    14.6.2 Block Model Parameters 145
    14.6.3 Sample Search Parameters 146
    14.6.4 Grade Interpolation 146
  14.7 Model Validation 146
    14.7.1 Visual Validation 147
    14.7.2 Global Estimation Validation 147
    14.7.3 Local Estimation Validation 147
    14.7.4 Mineral Resource Depletion 148
  14.8 Mineral Resource Classification 149
    14.8.1 Geological Continuity 149
    14.8.2 Data Density and Orientation 149
    14.8.3 Data Accuracy and Precision 149
    14.8.4 Spatial Grade Continuity 149
    14.8.5 Classification 150
  14.9 Mineral Resource Reporting 151
    14.9.1 Reasonable Prospects for Eventual Economic Extraction 151
    14.9.2 Mineral Resource Statement 151
    14.9.3 Comparison to Previous Estimate 153
  14.10 Comment on Section 14 153
       
15 Mineral Reserve Estimates 154
     
16 Mining Methods 155
  16.1 Overview 155
  16.2 Hydrogeology 155
  16.3 Mine Geotechnical 157
  16.4 Pit Optimizations 158
    16.4.1 Block Model 158
    16.4.2 Optimization Parameters 158
    16.4.3 Optimization Outcomes 161
  16.5 Mine Design 162
    16.5.1 Pit Design 162
    16.5.2 Pit Design Parameters 162
    16.5.3 Waste Rock Storage Facilities 164
  16.6 Mining Operations 165
    16.6.1 Drill and Blast, Excavate, Load and Haul 165
    16.6.2 Ancillary and Support Fleet 166
    16.6.3 Other Mining Infrastructure 166
    16.6.4 Equipment and Personnel Requirements 166
  16.7 Mining and Production Schedule 168
  16.8 Comments on Section 16 170
       
17 Recovery Methods 171

 

October 15, 2025Page 10 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

  17.1 Processing Plant Design 171
  17.2 Processing Design Philosophy 172
  17.3 Process Plant Feed 173
  17.4 Comminution Circuit Design Basis 173
    17.4.1 Design Criteria 173
    17.4.2 Comminution Circuit Selection 174
  17.5 Process Plant Description 174
    17.5.1 Primary Crushing 174
    17.5.2 Grinding and Classification Circuit 175
    17.5.3 Pebble Crushing 176
    17.5.4 Gravity Recovery Circuit and Pre-leach Thickener 176
    17.5.5 Carbon in Leach Circuit 177
    17.5.6 Elution, Electrowinning and Smelting 177
    17.5.7 Tailings Disposal 178
  17.6 Reagents 179
    17.6.1 Lime 179
    17.6.2 Cyanide 179
    17.6.3 Caustic Soda/Sodium Hydroxide 179
    17.6.4 Hydrochloric Acid 180
    17.6.5 Activated Carbon 180
    17.6.6 Flocculant 181
    17.6.7 Balls and Liners 181
  17.7 Control Systems 181
  17.8 Electrical Reticulation 182
  17.9 Water Supply 184
  17.10 Comments on Section 17 184
       
18 Project Infrastructure 185
  18.1 Overview 185
  18.2 Roads 187
    18.2.1 Site Access Roads and Bypass Road 187
    18.2.2 Site Haul Roads 187
  18.3 Tailing Storage Facilities 187
  18.4 Sediment Management 189
  18.5 Water Storage Dam and Water Management 189
  18.6 Aerodrome 192
  18.7 Mining Contractor’s Infrastructure 193
  18.8 Administration and Plant Buildings 193
  18.9 Accommodations Camp 195
  18.10 Waste Rock Storage Facilities 195
  18.11 Stockpiles 195
  18.12 Power Generation 195

 

October 15, 2025Page 11 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

  18.13 Fuel Supply 196
  18.14 Communications 196
  18.15 Plant Security 196
  18.16 Water Supply 197
  18.17 Comments on Section 18 197
       
19 Market Studies and Contracts 198
  19.1 Market Studies 198
  19.2 Commodity Pricing 198
  19.3 Contracts 198
  19.4 Comments on Section 19 198
       
20 Environmental Studies, Permitting and Social or Community Impact 200
  20.1 Base Line Studies 200
    20.1.1 Socio-Economic Environment 201
    20.1.2 Physical Environment 204
    20.1.3 Biological Environment 207
  20.2 Environmental Issues – Climate Change 211
    20.2.1 Physical Risks 211
  20.3 Permitting 212
  20.4 Tailings Storage Facilities 214
  20.5 Water Management 214
  20.6 Environmental Management and Monitoring 214
    20.6.1 Environmental and Social Management System 214
  20.7 Community Relations 216
    20.7.1 Stakeholder Engagement 216
    20.7.2 Social Investment 217
    20.7.3 Land Acquisition 217
    20.7.4 Artisanal Small-Scale Mining (ASM) 218
    20.7.5 Community Development Fund 219
  20.8 Mine Closure Plan 220
    20.8.1 National Framework 220
    20.8.2 Conceptual Closure Costs 220
  20.9 Comments on Section 20 221
       
21 Capital and Operating Costs 222
  21.1 Capital Cost Estimates 222
    21.1.1 Estimate Assumption and Clarifications 223
    21.1.2 Estimate Exclusions 224
    21.1.3 Capital Estimate 224
    21.1.4 Mine Development 228
    21.1.5 Mine Rehabilitation 228
  21.2 Operating Cost Estimates 228

 

October 15, 2025Page 12 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

    21.2.1 Mine Operating Costs 230
    21.2.2 Operating Cost Exclusions 231
  21.3 Sustaining Capital Costs 231
    21.3.1 Mine Development 231
    21.3.2 Equipment and Infrastructure 231
    21.3.3 Mine Closure and Rehabilitation 231
  21.4 Comment on Section 21 231
       
22 Economic Analysis 233
  22.1 Methodology Used 233
  22.2 Assumptions 233
  22.3 Summary 234
  22.4 Forecast Production and Mill Feed 235
  22.5 Cost Estimates 236
    22.5.1 Capital and Operating Costs 236
    22.5.2 Closure and Salvage Value 236
    22.5.3 Working Capital 236
    22.5.4 All-in Sustaining Unit Cost Estimates 236
  22.6 Taxes and Royalties 237
    22.6.1 Government Royalty 237
    22.6.2 Social Fund 237
    22.6.3 Duties and Levies 237
    22.6.4 Value Added Tax 237
    22.6.5 Corporate Income Tax 238
    22.6.6 Withholding Taxes 238
  22.7 Government-Carried Interest 238
  22.8 Economic Results 239
  22.9 Sensitivity Analysis 241
  22.10 Comment on Section 22 243
       
23 Adjacent Properties 244
     
24 Other Relevant Data and Information 245
     
25 Interpretation and Conclusions 246
  25.1 Mineral Tenure, Surface Rights, Royalties and Agreements 246
  25.2 Geology and Mineralization 246
  25.3 Exploration, Drilling and Analytical Data Collection in Support of Mineral Resource Estimation 247
  25.4 Data Verification 247
  25.5 Metallurgical Testwork 247
  25.6 Mineral Resource Estimation 248
  25.7 Mine Plan 248

 

October 15, 2025Page 13 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

  25.8 Recovery 249
  25.9 Infrastructure 249
  25.10 Markets and Contracts 249
  25.11 Environmental, Permitting and Social Considerations 250
  25.12 Capital and Operating Costs 250
  25.13 Economic Analysis 251
  25.14 Risks and Opportunities 251
       
26 Recommendations 253
  26.1 Overview 253
  26.2 Exploration 253
  26.3 Geotechnical 253
  26.4 Water Management 254
  26.5 Metallurgical 255
  26.6 Environmental and Social 255
  26.7 Engineering Studies 255
       
27 References 256

 

Certificates     258

 

October 15, 2025Page 14 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Tables

 

Table 1.1 Mineral Resources for the Diamba Sud Project 29
Table 1.2 Summary of Projected Major Capital Costs for the LOM 34
Table 1.3 Summary of Projected Major Sustaining Capital Costs for the LOM 34
Table 1.4 Life-of-Mine Operating Costs 35
Table 1.5 PEA Summary 35
Table 2.1 Acronyms 44
Table 4.1 Diamba Sud Permit Coordinates in Longitude and Latitude 50
Table 10.1 Reverse Circulation and Core Drilling Conducted by Chesser 79
Table 10.2 Reverse Circulation and Core Drilling Conducted by Fortuna 80
Table 10.3 Number of Holes and Meters Used in the Estimation by Deposit 82
Table 10.4 Intervals of Interest in Holes Drilled Post Data Cut-off Date 82
Table 10.5 Example of Typical Drill Results at the Diamba Sud Project 92
Table 11.1 Density Measurements by Lithology and Weathering Horizon 96
Table 12.1 Database Checklist Summary 99
Table 13.1 Samples taken for metallurgical testing 105
Table 13.2 Summary of XRD Analysis for Area D 110
Table 13.3 Summary of XRD Analysis for Area A and Karakara 111
Table 13.4 Bond Crushing Work Index Results 112
Table 13.5 SMC Results 113
Table 13.6 Gravity Recovery Results 115
Table 13.7 Grind Size Optimization Results 116
Table 13.8 CIL vs Leach Only Cyanidation 120
Table 13.9 Effect of Cyanide Concentration on Gold Recovery and Reagent Consumption after 24 hours 121
Table 13.10 Average Reagent Consumption after 24 hours at 1,000 ppm Cyanide Between Fresh and Oxide Mineralization 122
Table 13.11 Bulk Leach Testwork Summary 124
Table 13.12 Bulk Leach Testwork Summary - Variability Tests 124
Table 13.13 Carbon Concentrations and Loading 125
Table 13.14 Carbon Triple Contact Test Results 126
Table 13.15 Summary of Vane Yield Stress Test Results 127
Table 13.16 Summary of Bohlin Viscometry Testwork 128
Table 13.17 Diagnostic Leach Results 128
Table 13.18 Gold Recovery Formula 131
Table 13.19 Gold Recovery at Cutoff Grade and Overall Plant Performance 132
Table 13.20 Proposed Process Design Values Based on Testwork 134
Table 13.21 Proposed Comminution Model Inputs 134

 

October 15, 2025Page 15 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 14.1 Univariate Statistics of Au Composites for Each Deposit 138
Table 14.2 Top Cut Thresholds 141
Table 14.3 Variogram Model Parameters 143
Table 14.4 Block Model Parameters by Deposit 145
Table 14.5 Mineral Resources for the Diamba Sud Project 152
Table 16.1 Maximum Predicted Dewatering (average over one quarter) 156
Table 16.2 Geotechnical Slope Design Parameters for all Diamba Sud Pits 157
Table 16.3 Financial Parameters and Selling Costs Applied Inpit Optimization 158
Table 16.4 Mining Parameters Costs Applied Inpit Optimization 158
Table 16.5 Waste Load and Haul Costs in US$/t 159
Table 16.6 Mill Feed Material Load and Haul Costs in US$/t 160
Table 16.7 ROM Costs Applied in Pit Optimization 160
Table 16.8 Optimizations Results 161
Table 16.9 WRSF Capacities 165
Table 16.10 Drill and Blast Assumptions 165
Table 16.11 LOM Mining Equipment Requirements 166
Table 16.12 LOM Personnel Requirements 167
Table 16.13 Proposed Mining and Production Schedule 169
Table 17.1 Proposed LOM Feed Composition 173
Table 17.2 Fresh Mill Feed Material Comminution Characteristics 173
Table 18.1 Tailings Storage Facility Design Parameters 189
Table 18.2 Water Storage Dam Design Parameters 191
Table 20.1 Key Community Infrastructure 203
Table 20.2 Summary of Key Permits and Authorisations Required for the Diamba Sud Project 213
Table 20.3 Key Air Quality, Noise and Water Standards and Legal Requirements 214
Table 20.4 Summary of Closure Costs 221
Table 21.1 Summary of Projected Capital Costs 222
Table 21.2 Summary of Projected Major Capital Costs (US$M) 222
Table 21.3 Exchange Rates Used for Capital Cost Estimates 228
Table 21.4 Life-of-Mine Operating Costs 228
Table 21.5 Oxide Mill Feed Material Operating Cost Estimates 229
Table 21.6 Fresh Mill Feed Material Operating Cost Estimates 229
Table 21.7 Summary of projected major sustaining capital costs for the LOM 231
Table 22.1 Key Economic Assumptions 233
Table 22.2 Preliminary Economic Assessment Summary 234
Table 22.3 Estimate of Recovered Gold for Diamba Sud Project 236

 

October 15, 2025Page 16 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 22.4 Life of Mine All-in Sustaining Cost and All-in Cost 237
Table 22.5 PEA Cash Flow Estimate 240
Table 22.6 After-Tax NPV Sensitivity to Discount Rate and Gold Price ($M) 241
Table 22.7 After-Tax IRR Sensitivity to Gold Price 241
Table 22.8 After-Tax NPV5% Sensitivity to Capital Costs and Operating Costs ($M) 241

 

October 15, 2025Page 17 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figures

 

Figure 2.1 Map Showing the Location of the Diamba Sud Project 42
Figure 4.1 The Diamba Sud Permit Boundary and Location in Eastern Senegal 49
Figure 6.1 Second Vertical Derivative, Total Magnetic Intensity (TMI) at the Diamba Sud Project 56
Figure 6.2 Magnetic Analytical Signal for the Diamba Sud Project 57
Figure 7.1 Regional Geological Map of the Leo–Man Shield and Kedougou–Kenieba Inlier, West Africa Craton 58
Figure 7.2 Geological Map of Diamba Sud DS1 Block Showing Deposits and Prospects 65
Figure 7.3 Schematic Cross-Section of Area A Looking North 66
Figure 7.4 Schematic Cross-Section of Area D Looking North 67
Figure 7.5 Schematic Cross-Section of Karakara Looking North 68
Figure 7.6 Schematic Cross-Section of Kassassoko Looking North 69
Figure 7.7 Schematic Cross-Section of Western Splay Looking North 70
Figure 7.8 Schematic Cross-Section of Moungoundi Looking North 71
Figure 7.9 Schematic Cross-Section of Southern Arc Looking Northeast 72
Figure 9.1 Fortuna Auger Sampling Results Across Portion of Northern Block of Daimba Sud Property 75
Figure 10.1 Contoured Auger Sampling Results Across the DS1 and DS2 Blocks of the Diamba Sud Project. 78
Figure 10.2 Location Map of RC and Core Drill Holes Completed by Chesser 79
Figure 10.3 Map Showing Location of RC and Core Drilling Conducted by Fortuna 81
Figure 13.1 Map Showing Location of Metallurgical Samples for Area A and Area D 107
Figure 13.2 Metallurgical Sample Location for Area A and Area D – Section C 108
Figure 13.3 Map Showing Location of Metallurgical Samples for Karakara 108
Figure 13.4 Metallurgical Sample Location for Karakara – Section B 109
Figure 13.5 Diamba Sud A*b vs SMC Database 114
Figure 13.6 Grind Size Optimization of Area A, Area D and Karakara Deposits 118
Figure 13.7 Lead Nitrate vs Au Recovery of DC Fresh-1 119
Figure 13.8 Oxygen vs Air Sparging 119
Figure 13.9 Effect of NaCN Concentration on Cyanidation 121
Figure 13.10 Effect of Solid Mass Fraction (%) – Oxides 122
Figure 13.11 Effect of Solid Mass Fraction (%) – Fresh 123
Figure 14.1 Cross-Section Showing Mineralized Wireframes for Area A 137
Figure 14.2 Cross-Section of Estimated Gold Grade Block Model vs Top Cut Drill Hole Composites in Area D 147
Figure 14.3 Swath Plot Analysis for Area D and Comparative Log-Probability Plot 148
Figure 14.4 Cross-Section Showing Mineral Resource Classification for Area D 151

 

October 15, 2025Page 18 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 16.1 Diamba Sud Project Proposed Mining Area Layout 163
Figure 16.2 Mineralization Mined by Deposit 169
Figure 17.1 Schematic of Proposed Processing Flowsheet for the Diamba Sud Project 172
Figure 18.1 Plan View of Mine Infrastructure 186
Figure 18.2 Water Balance Modelling Block Model Diagram 192
Figure 20.1 Diamba Sud Project Study Area in DS1 Block 201
Figure 20.2 Creeks in and Around the Diamba Sud Project 205
Figure 22.1 Diamba Sud PEA Production Profile 235
Figure 22.2 After-Tax NPV5% Sensitivities to Key Input Parameters 242
Figure 22.3 After-Tax IRR Sensitivity to Key Input Parameters 242

 

October 15, 2025Page 19 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

1Summary

 

1.1Introduction

 

This Technical Report (the Report) was prepared by Mr. Eric Chapman, P.Geo., Mr. Paul Weedon, MAIG, Mr. Raul Espinoza, FAusIMM (CP), Mr. Mathieu Veillette, P.Eng., and Dr. Leendert (Leon) Lorenzen, FAusIMM (CP) for Fortuna Mining Corp. (Fortuna) on the Diamba Sud Project (the Project) located in the Kédougou Region of Senegal.

 

The Diamba Sud Project is operated by Boya S.A. (Boya), a 100% indirectly owned Fortuna subsidiary. The Government of Senegal will assume a 10% free carried ownership interest in Boya when an exploitation permit is granted.

 

The Report discloses Mineral Resource estimates for the Project and a Preliminary Economic Assessment (PEA) based on those estimates.

 

Costs are in US dollars (US$) unless otherwise indicated.

 

1.2Property Description, Location and Access

 

The Diamba Sud Project is located within the Department of Saraya in the Kédougou Region and within the Arrondissement of Bembou. It is situated approximately 50 km north of the Senegal-Guinea border, and is approximately 7 km to the west of the Falémé River which, in this region, defines the international border between Senegal and Mali. The Project is approximately 665 km southeast of the Senegalese capital Dakar and 83 km northeast from the nearest town, Kédougou.

 

The Project comprises two blocks: DS1 and DS2 linked by a narrow strip of some 25 m width in order for the two blocks to be classed as contiguous and one permit area. DS1 is centered upon co-ordinates 11° 28’ 23.17” W and 12° 55’ 46.55” N. DS2, the southern block some 20 km to the south is centered upon co-ordinates 11° 26’ 2.68” W and 12° 45’ 13.61” N.

 

Elevations range between 100 m and 380 m above mean sea level. The region features low to moderate relief, consisting of broad lateritic plateaus, eroded valleys, and gentle slopes.

 

The landscape primarily comprises forested savanna with patches of grassland and forest. Notable flora include Baobab (Adansonia digitata), Madd (Saba senegalensis), Jujube (Ziziphus mauritania), and the Locust Bean Tree (Parkia biglobosa). Larger trees are often localized along river channels where seasonal rivers flow and the lateritic plateau has eroded, while vegetation in the area is predominantly grasses and small shrubs, characteristic of the climate.

 

From Dakar the Project site is accessed via the all-weather paved N1 highway southeast to the city of Tambacounda, the regional center of Senegal. From Tambacounda, the N7 can be taken southeast to Kédougou where it joins the Kédougou–Saraya road which connects Kédougou to the village of Saraya. From Saraya the paved N24 road is frequented by trucks taking goods to and from Mali, passes through the Diamba Sud permit area, and continues through to the Senegal-Mali border. Due to frequent use by trucks carrying heavy loads, road conditions can be locally very poor. However, in almost all cases the main roads remain open to vehicles throughout the year. Access throughout the permit area is taken via a combination of paved and laterite roads and dirt tracks.

 

October 15, 2025Page 20 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Access by air is possible via an asphalt airfield in Kédougou. The Government has announced numerous plans to transform the airport into an international airport with regular scheduled flights, but development of the airport is yet to take place. Thus, the only currently available options for flights are two charter companies that operate from Dakar with flights taking approximately 2–3 hours.

 

1.3Mineral Tenure, Surface Rights and Royalties

 

The Diamba Sud permit is an exploration permit (permis de recherche) which was granted to Boya in June 2015 under the 2003 Mining Code before the 2016 Mining Code came into effect, and therefore it remains subject to the 2003 Mining Code for its duration and validity. The exploration permit was granted for an initial period of three years, subject to being renewed twice for additional periods of three years. It was last renewed on June 9, 2021, for a period of three years, being the second and final renewal and which expired on June 9, 2024. However, Fortuna obtained a special two-year retention period to complete the works necessary for a PEA, and to conduct the environmental studies that are required in support of an application for a mining license. This retention period is valid until June 21, 2026, and requires the submission of a request for an exploitation permit before this date and at least four months before the expiry of the exploration permit.

 

The permit comprises two blocks, the northern block, DS1 is approximately 46.56 km2 and the southern block, DS2, some 20 km to the south is approximately 6.31 km2, for a total permit area of 53.46 km2 (including the corridor of land connecting the two parcels.

 

Mineral exploration permits, within their boundaries, entitle the holder within the boundaries of its perimeter, on surface and indefinitely in depth, the exclusive rights to explore for the nominated mineral commodities specified (in this case, gold), as well as encumbrance-free disposal of materials extracted during the exploration process. Such permits allow for beneficial ownership to be held by a foreign entity, such as Fortuna, through Boya, its wholly-owned Senegalese subsidiary.

 

Boya has full and unrestricted surface rights to the land covered by the exploration permit. The perimeter of the exploration permit is free to access and is not subject to any kind of restriction, subject to the applicable mining regulation.

 

The Diamba Sud Project is not subject to any back-in rights, liens, payments or encumbrances.

 

There are royalties attached to the mineral concessions; however, the only royalties that affect the Mineral Reserves and have been considered in the economic analysis are:

 

·A 3% royalty on the “carreau-mine value” of gold produced. The carreau-mine value of a mineral substance is calculated as the difference between its sale price and the total costs incurred between the mine site and the point of delivery.

 

·A contribution to a local development fund of 0.5% of Boya’s annual turnover (excluding taxes) dedicated to promote the economic and social development of local communities.

 

1.4History

 

Prior to 1993 there is no known or recorded systematic mineral exploration carried out on the property, although regionally the area was surveyed by the Bureau de Recherches Géologiques et Minières (BRGM) as part of the Senegal Plan minerale in 1983. The first

 

October 15, 2025Page 21 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

recorded exploration activities were carried out by Anmercosa Exploration (a subsidiary of Anglo American plc) from 1993 to 1996, as part of a joint venture agreement with Iamgold Corporation (Iamgold). This work was carried out over the larger Bambadji permit which at that time included the area currently referred to as Diamba Sud.

 

Between 1997 to 1998, Ashanti Goldfields completed further exploration activities as part of a similar joint venture with Iamgold.

 

Between 1999 to 2014, Iamgold conducted exploration activities at the Diamba Sud Project, either individually or as part of a joint venture. The area was relinquished as part of a renewal process for Bambadji and acquired by Boya in 2015.

 

1.5Geology and Mineralization

 

The Diamba Sud Project is a part of the West Africa craton (WAC) within the Loulo Mining district.

 

The geology local to the Diamba Sud Project is dominated by plutons belonging to the Falémé Volcanic Belt as well as roof pendants and xenolith screens of the Bambadji Formation which also uncomformably overly the Kofi series sediments that subcrop to the east.

 

At the westernmost extent of the Kofi series, north striking altered marbles and strongly abilitized lithologies with identified and unidentified protoliths are prevalent. The Kofi series in the area is dominated by undifferentiated sandstones and siltstones with minor conglomerate and breccia. Several dolerite dykes of various orientations intrude the Kofi series and plutonic rocks of the Falémé Volcanic Belt.

 

The Falémé Volcanic Belt within and surrounding the permit area is made up of the Highway pluton and a range of smaller plugs and dykes. The Balangouma Pluton and heterogeneous granitoids adjacent to it occur to the north of the permit, with the Boboti and Garaboureya plutons outcropping to the south of the permit. The Bambadji Formation is also mapped to subcrop within and surrounding the permit, forming xenolithic screens and roof pendants within the Falémé Volcanic Belt, as well as unconformably overlying the Kofi series to the east.

 

Iron endo- and exoskarns, some structurally controlled along faults, occur within the Falémé Volcanic Belt, the Bambadji Formation and on western portions of the Kofi series. A genetic link between iron skarn mineralization and gold mineralization has been proposed based on the proximal locations of these deposits, the involvement of high temperature FeCl2-rich brine and from mineral paragenesis at the Sadiola deposit. Additionally, the Karakaéné Ndi iron skarn, north of Afrigold’s Karakaéné mine, has been a target of significant artisanal workings. Named iron skarns inside and within the vicinity of the project include the Karakaéné Mbah, Karakaéné Ndi and Kouroudiako iron skarns, with other unnamed skarns of various volumes also outcropping in the region.

 

Sedimentary sequences not confirmed to belong to the Bambadji Formation and possibly belonging to the Kofi series or part of the Diale-Dalema Basin are also present within the permit. These consist of marls, carbonates, polymictic matrix-supported conglomerates and intensely hydrothermally altered lithologies, some of which the protoliths cannot be identified. Granites belonging to the Falémé batholith intrude into these sedimentary units.

 

October 15, 2025Page 22 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Both the Falémé batholith and sedimentary sequences are intruded by late predominantly sub-vertical diorite dykes. A number of iron endo and exoskarns also occur in the area and these form prominent topographic highs inside and outside of the permit area.

 

Exploration has identified seven gold deposits and several prospects located in the DS1 block. These include the deposits of Area A, Area D, Karakara, Kassassoko, Western Splay, Moungoundi, and Southern Arc, as well as the Gamba Gamba North, Area A North, Area D South, and Kouroudiako prospects.  These deposits all form part of a single mineralizing system with local variability influenced mainly by intensity of brecciation, alteration and later supergene processes. The Bougouda prospect is located in the DS2 block.

 

Mineralization at Diamba Sud is relatively simple, consisting dominantly of pyrite with minor chalcopyrite and magnetite.

 

There does not appear to be a preferential host lithology, with gold mineralization hosted in most rock types, except for weakly altered fine grained sedimentary rocks. Most of the mineralization is hosted in a combination of disseminated pyrite, minor veinlets and hydrothermal breccia cement.

 

The predominant mineralization style is orogenic lode gold with supergene enriched saprolite zones specifically in Area D. This style of mineralization can occur as veins or disseminations in altered (often silicified) host rocks or as pervasive alteration over a broad zone. Across Diamba Sud gold mineralization is controlled by a variety of minor structures and often along lithological boundaries.

 

Gold mineralization is both structurally and lithologically controlled and can occur within granites, argillites, conglomerates, marls and carbonates. Supergene enrichment of the orogenic gold deposits (saprolitic) has also taken place within the permit, with significant mineralization of this style present within Area D.

 

Most of the mineralization at Diamba Sud is hosted within sedimentary units, where structures that acted as fluid conduits intersected the units allowing fluid flow. Hydrothermal breccia zones within Area A host some of the highest grades within the hypogene mineralized zones from Diamba Sud. The high permeability and porosity of these rocks, in addition to friction and attrition generated at clast boundaries due to strain, allowed fluid to move into this unit and deposit the auriferous pyrite. A precursor phase of albitization and hematization prepared the breccias for a later phase of auriferous pyrite–hematite–albite–carbonate–quartz mineralization.

 

Mineralized structures also occur throughout the intrusions in the area, with auriferous pyrite ± carbonate veins exploiting shear zones that cut through the granitoids.

 

Gold mineralization at Diamba Sud is considered to be of the orogenic type.

 

1.6Exploration, Drilling and Sampling

 

From 1993 to 1996, Anmercosa conducted regional exploration activities over the Bambadji, Daorala and Boto Project areas as part of a joint venture agreement with Iamgold. These activities included airborne geophysical surveys along with regional and local geochemistry and early drilling activity. No drilling was conducted on the Diamba Sud area.

 

Ashanti Goldfields also worked on the Bambadji, Daorala and Boto areas and continued to focus on geochemical data acquisition of and conducted some preliminary trenching and pitting in 1997 and 1998.

 

October 15, 2025Page 23 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

From 1999 to 2014, Iamgold conducted limited prospecting activity over the Bambadji permit: the majority of the work conducted was on the eastern portion of the permit and not on the Diamba Sud area. The western part of the Bambadji permit was relinquished in 2014.

 

The Diamba Sud exploration permit was granted in April 2015 to Boya, a subsidiary of Boya Gold PTY Ltd. (Boya Gold). During the period 2015-2016, Boya conducted regional soil geochemistry for gold using a 400 x 400 m grid, later infilled to 200 x 100 m in places, collecting 1,552 soil samples. Outcrop mapping was completed over an area of 37 km2 and 96 grab samples were collected.

 

Air core and reverse circulation (RC) drilling was conducted by Minerex drilling. A total of 334 air core holes with depths from 2–56 m were drilled for a total meterage of 3,358 m with 1,160 samples, including quality control samples, sent to the SGS laboratory in Bamako (SGS Bamako) for analysis. In addition, 9 RC holes, with maximum depths ranging from 40–86 m, were drilled over two target areas in the south of DS1 at Dembakholi and Southern Arc for a total meterage of 650 m with 338 samples, including quality control samples, sent to SGS Bamako for analysis.

 

Boya Gold was acquired by Chesser Resources Ltd. (Chesser) in 2017. Chesser commenced RC drilling in 2019 using several different drilling contractors during various campaigns through to July 2023. A total of 10 geochemical targets were drilled by RC or RC with a core tail, totaling 493 holes and 58,960 m. In total, 127 diamond drill (DD) holes totaling 19,805 m were drilled between November 2019 and July 2023. All holes were sampled at 1- or 2-m intervals in the oxide material and at 1-m intervals in the fresh rock and all samples were submitted to SGS Bamako or to the ALS laboratory in Burkina Faso.

 

After acquiring Chesser in 2023, Fortuna began an extensive program of verification and infill drilling across nine of the advanced target areas with the aim of collecting sufficient data to support the estimation of Mineral Resources. A total of 532 RC holes totaling 59,701 m, 425 DD holes totaling 56,672 m and 15 RC with DD tail holes totaling 1,830 m were drilled between October 2023 and October 31, 2025.

 

RC drilling was conducted using an Atlas Copco T3W rig with a 950CFM compressor and an Atlas Copco Hurricane booster. All holes were cased with PVC to 6 m and then drilled using a 5.5-inch RC hammer bit. Samples were collected at 1-meter intervals from an onboard cyclone then split on site to produce two 1.5 kg samples, the first sample was submitted for analysis, the second stored as a duplicate sample.

 

Diamond drilling was conducted with Atlas Copco CS14 and CT14 diamond drill rigs, dependent upon the contractor. The majority of this drilling is drilled to HQ (63.5 mm core diameter) and NQ (47.6 mm) sizes. In Area D where the oxide material can be difficult to keep holes from collapsing, holes are drilled PQ (85 mm) from surface to fresh rock before stepping down to HQ and NQ as appropriate to conditions and depth.

 

Proposed surface drill hole collar coordinates, azimuths and inclinations were designed based on the known orientation of mineralization and the planned depth of intersection using geological plan maps and sections as a guide. The location of the collar is defined in the field using differential global positioning system (GPS) instruments. The drill pad is then prepared at this marked location. Upon completion of the drill hole, a survey of the collar is performed using Total Station equipment, with results reported in the collar coordinates using reference Datum WGS84, UTM Zone 29N.

 

October 15, 2025Page 24 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The geologist in charge of drilling is responsible for orienting the azimuth and inclination of the hole at the collar using a compass clinometer. Downhole surveys for RC holes are completed every 10 m by the drilling contractor using a Reflex Gyro Sprint IQ survey tool. Downhole surveys of the DD holes were conducted using a variety of survey tools, as there were several rigs operating at the same time in different areas. These included a Reflex EZ Shot TM, the Reflex Gyro Sprint IQ and an Axis Champ gyro. Readings were collected every 30 m down the hole. Boya assesses the downhole survey measurements as a component of data validation.

 

Drill holes are typically drilled on sections spaced 25 to 50 m apart along the strike of the mineralized structures.

 

The Area A deposit has been drilled over an approximate area of 700 m (north to south) and 500 m (east to west) to depths around 280 m from surface. Exploration drilling has increased in depth to the south.

 

The Area D deposit has been drilled over an approximate area of 600 m (north to south) and 700 m (east to west) to depths around 250 m from surface. Exploration drilling has increased in depth to the south.

 

The Karakara deposit has been drilled over a strike length of approximately 1,000 m (north–northeast to south–southwest) and to depths of 230 m from surface. Exploration drilling has increased in depth in response to the plunge of the mineralization to the southwest.

 

The Kassassoko deposit has been drilled over an approximate area of 700 m (southwest to northeast) and 200 m (southeast to northwest) to depths around 150 m from surface. Exploration drilling has increased in depth to the south.

 

The Western Splay deposit has been drilled over an approximate area of 500 m (north to south) and 700 m (east to west) to depths around 280 m from surface. Exploration drilling has increased in depth to the south.

 

The Moungoundi deposit has been drilled over a strike length of approximately 400 m (north to south) and to depths around 150 m from surface.

 

The Southern Arc deposit has been drilled over a strike length of approximately 800 m (northwest to southeast) and to depths of 200 m from surface.

 

The Bougouda prospect has been drilled over a strike length of approximately 1,800 m (northeast to southwest) and to depths of 150 m from surface.

 

The Gamba Gamba North prospect drilled by Chesser is split into two main mineralized zones. The eastern zone has been drilled over a strike length of 300 m (north–northeast to south–southwest) to a depth of 150 m from surface; the western zone has been drilled over a strike length of 300 m (north to south) to a depth of 125 m from surface. The drilling follows the plunge of the mineralization, generally getting deeper towards the south–southwest.

 

The Bougouda prospect has been drilled over a strike length of approximately 1,800 m (northeast to southwest) and to depths of 150 m from surface.

 

The relationship between the sample intercept lengths and the true width of the mineralization varies in relation to the intersect angle and sometimes can be difficult to determine based on the various orientations of the mineralized structures. Calculated estimated true widths (ETWs) are always reported together with actual sample lengths by

 

October 15, 2025Page 25 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

taking into account the angle of intersection between drill hole and the mineralized structure.

 

RC chips were collected and logged at the drill site and stored in standard chip trays for further investigation as appropriate.

 

Core is logged in detail at the field camp, using LogChief software and transferred electronically to DataShed 5 for database management. As is the norm with exploration drilling, geological logging is undertaken at several different times to ensure that a level of consistency is maintained. Lithologies, alteration, mineralization and structures are all logged to industry standards. Geotechnical information collected routinely is at a rudimentary exploration level, however 14 holes (2,100 m) were fully logged to higher geotechnical standards as part of geotechnical studies.

 

The sampling methodology, preparation, and analyses differ depending on whether it is DD core or RC chip samples.

 

Sampling of RC holes is conducted at the drilling rig with one split sample collected for routine analysis and the second sample split again for duplicate sample submission.

 

Sampling of diamond core is conducted after geological logging and marking of the core for sampling. Core is split using a diamond saw. The half core that does not contain the orientation line is then selected for sampling. Intervals are based upon geology with nominal sample lengths of 1 meter due, although this may be variable, but standard sampling procedures dictate a minimum sample length of 0.4 m and a maximum of 1.2 m. For duplicate samples only, the remaining half core is cut in half again for submission to the laboratory.

 

PQ core is sampled as quarter core for routine sample submission and the second quarter is collected for duplicate sample submission.

 

All samples are combined into batches for submission to the laboratory. Nominally each batch should represent a specific hole, however the preferred batch size at the laboratory is 100 samples, thus longer holes tend to be split into two or three batches. Once sampled and labelled samples are packed into large sacks and sealed ready for transportation.

 

Sample collection and transportation of drill core and chip samples is the responsibility of Boya exploration and must follow strict security and chain of custody requirements established by Fortuna. Samples are retained in accordance with the Fortuna corporate sample retention policy.

 

The preparation of both RC and DD samples is conducted by ALS Global at their preparation facilities in Kédougou, Senegal or Bamako, Mali.

 

Samples from Diamba Sud are assayed for gold at ALS Global’s analytical facility in Ouagadougou, Burkina Faso or the SGS Mineral Services laboratory in Bamako, Mali. The assay method used for all the drill samples is a fire assay fusion with atomic absorption spectroscopy (AAS) finish. Both the ALS Global and SGS Mineral Services laboratories are certified for the preparation and assaying of gold samples.

 

Implementation of a quality assurance/quality control (QAQC) program is current industry best practice and involves establishing appropriate procedures and the routine insertion of certified reference material (CRMs), blanks, and duplicates to monitor the sampling, sample preparation and analytical process. Fortuna implemented a full QAQC program to monitor the sampling, sample preparation and analytical process for all drilling campaigns in accordance with its companywide procedures. The program involved the routine insertion of CRMs, blanks, and duplicates. Evaluation of the QAQC

 

October 15, 2025Page 26 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

data indicates that the data are sufficiently accurate and precise to support Mineral Resource estimation.

 

1.7Data Verification

 

Site visits were completed. The QPs individually reviewed the information in their areas of expertise, and concluded that the information supported Mineral Resource estimation, and could be used in mine planning and in the preliminary economic analysis that supports the PEA.

 

1.8Mineral Processing and Metallurgical Testing

 

Maca Interquip Mintrex (MIQM), previously Mintrex, was engaged by Chesser in May 2022 and subsequently by Fortuna to manage metallurgical testwork for the Diamba Sud Project. The testwork was undertaken by ALS Metallurgy Pty Ltd (ALS) in Perth, Western Australia. A testwork program developed by MIQM aimed to build upon the initial scoping study level testwork competed in 2022. The testwork was conducted on samples selected by MIQM and Fortuna across three initial deposits: Area A, Area D, and Karakara. The purpose of the testwork program was to provide inputs to future studies for a gold processing plant.

 

Testwork was to be conducted in five stages. The first stage was comminution testwork, which was used to determine the mineralization properties. Optimization tests were then conducted in the second stage to determine optimum conditions for cyanidation. The third stage of testwork determined cyanidation at the optimized conditions and carbon testing across a number of samples. The final two stages consisted of variability testing. Bulk mineral analysis (BMA), rheology and diagnostic leach tests were added during the program to investigate flow properties and speciation. Additional testwork was commissioned and managed by Fortuna covering the Western Splay, Kassassoko, Moungoundi and Southern Arc deposits, as well as some supporting testwork identified during review. This additional testwork was completed in phases through 2024 and 2025.

 

The testwork program indicated favorable grinding and leaching characteristics for the oxide mineralization and most samples of the fresh mineralized material:

 

·Various comminution tests were undertaken on the composites. Bond abrasion (Ai), Bond Ball mill (BWi) indices and semi-autogenous grind (SAG) mill comminution (SMC) tests were undertaken. Initial modelling confirmed that single-stage SAG mill (SSAG) and SAG and ball mill crushing (SABC) comminution flowsheets are both suitable for this material. Unfortunately, the oxide composites were too friable to be reliably tested with these methods. Initial size screening indicated the unmilled mineralization is mostly fine and close to the milling product P80.

 

·Comminution testing results indicated the following:

 

oAi (average ~0.18 for fresh domain) indicates that the material is not abrasive.

oBWi and SMC results indicate that the material is moderate to hard (10–22 kWh/t), except the oxide composite, which was not compatible with the test. The friability of the composite shows that the oxide is very soft.

oThe SMC testwork indicates that the mineralized material is amenable to both single-stage crushing followed by SAG milling (SSAG), or alternatively SABC (average A*b of 27–53 for fresh mineralization) in closed circuit with or without a pebble crusher.

 

October 15, 2025Page 27 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Gravity testwork has indicated that the mineralized material contains a large proportion of free/gravity-recoverable gold. The proportion of gravity recoverable gold varied from 19–40% for selected oxide samples and 27–81% for selected fresh mineralized material. Broadly, the higher gold grade fresh materials had higher fractions of gravity gold, while the lower-grade samples had comparatively lower gravity recoveries. Intensive leach results indicate gold recoveries from the gravity concentrate >99%.

 

·Leaching optimization tests on two oxide and seven fresh samples found the leaching parameters that were suitable for these types of mineralized material:

 

oOptimal grind size selected at 106 µm,

oOnly one sample exhibited recovery below 90%, at 74%. The addition of 200 g/t lead nitrate did not improve gold recovery.

oUse of air instead of oxygen for sparging did not impact gold recovery significantly.

oCyanide concentration initially at 1,000 ppm (maintained at 500 ppm) showed marginal improvement over 500 ppm initial and 250 maintained, and 250 initial and 100 ppm maintained.

oVarying the carbon in leach (CIL) oxide solids concentration between 25–40% did not show major impact with increasing solids density in this range. Varying the fresh solids concentration between 35–45% likewise showed no major impact.

oBased on the majority of tests, longer leach times in excess of 24 hrs were not considered to be necessary.

oGold leaching kinetics on gravity tailings samples after gravity gold recovery are relatively fast and mostly complete within 8 hours.

oThe samples did not display any preg-robbing characteristics or carbon fouling.

 

·Applying the optimized leach conditions to bulk composites, including 19 additional variability samples, found that the leach recovery of gold (that is, head grade minus gravity) varied significantly between 20–98%. Overall, the composites tested demonstrated high to very high total gold recoveries (including gravity) of 70–99%t after 24 hrs. Both oxide and fresh mineralization samples tested showed overall recovery with an average of 91%.

 

·Rheology testwork was undertaken on fresh and oxide samples, with the oxide samples showing elevated viscosity above 45% w/w solids.

 

·Diagnostic leaching was undertaken on several samples that had lower overall recovery (70–74%). These tests indicated that a portion of the gold (24–31%) was locked in sulfides.

 

·Thickener testwork indicated good thickening behavior for fresh material and poor thickening behavior for oxide material.

 

·Based on the above, metallurgical grade versus recovery relationship formulas were developed for oxide/transitional rock (all deposits) and separate formulas for fresh rock in each of the seven deposits. The overall recovery is estimated to be 90.4% for oxide/transitional rock and 93.4% for fresh rock for Area A; 85.2% for fresh rock for Area D; 94.9% for fresh rock for Karakara; 88.3% for fresh rock for Western Splay; 90.3% for fresh rock for Kassassoko; 82.7% for fresh rock for Moungoundi; and 86.4% for fresh rock for Southern Arc.

 

October 15, 2025Page 28 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

1.9Mineral Resources

 

Mineral Resource estimates used diamond and RC drill hole information obtained by Boya since 2019. Mineralized domains identifying potentially economically extractable material were modeled and used to code drill hole samples for geostatistical analysis, block modeling and grade interpolation. Gold and copper grades were estimated into a geological block model consisting of either 5 x 5 x 5m or 10 x 10 x 5 m selective mining units (SMUs), depending on the level of data density. Grades were estimated by ordinary kriging (OK) and constrained within an ultimate pit shell based on estimated long term metal prices, projected operating costs, geotechnical constraints, and metallurgical recoveries. Estimated grades were validated globally, locally, and visually prior to tabulation of the Mineral Resources.

 

Resource confidence classification considers a number of aspects affecting confidence in the resource estimation including; geological continuity and complexity; data density and orientation; data accuracy and precision; and grade continuity. Mineral Resources are categorized as Indicated or Inferred. The criteria used for classification includes the number of samples, spatial distribution, distance to block centroid, kriging efficiency (KE) and slope of regression (ZZ).

 

The Qualified Person for the Mineral Resource estimate is Mr. Eric Chapman, P.Geo., a Fortuna employee. Mineral Resources for the Diamba Sud Project are reported insitu, using the 2014 CIM Definition Standards, and have an effective date of July 7, 2025. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The estimate is detailed in Table 1.1.

 

Table 1.1 Mineral Resources for the Diamba Sud Project

 

Category Deposit Tonnes (000) Au (g/t) Au (koz)
Indicated Area A 3,891 1.47 184
Area D 4,877 1.75 274
Karakara 2,476 1.79 143
Western Splay 1,615 1.65 86
Kassassoko 1,294 0.90 38
Total 14,153 1.59 724
Inferred Area A 61 1.02 2
Area D 600 1.10 21
Karakara 510 1.61 26
Western Splay 101 2.11 7
Kassassoko 123 0.85 3
Southern Arc 3,854 1.57 194
Moungoundi 922 1.06 31
Total 6,171 1.44 285

 

Notes to accompany Mineral Resource table:

 

·Mr. Eric Chapman, P.Geo., is the Qualified Person responsible for Mineral Resources, and is a full-time employee of Fortuna.
·Mineral Resources are reported using the 2014 CIM Definition Standards.
·Mineral Resources are reported insitu, on a 100% basis as of July 7, 2025. The Government of Senegal will assume a 10% free-carried ownership interest in the Project when an exploitation permit is granted, and may elect to purchase up to an additional 25% interest in Boya SA at a “fair price” as determined through an independent valuation upon the granting of the exploitation permit.
·Mineral Resources are reported from a regularized block model derived from the original sub-blocked model to account for mining dilution.

 

October 15, 2025Page 29 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
·Mineral Resources are reported inside constraining pit shells using selective mining unit block sizes and at an incremental gold cutoff grade for oxide/transitional material of 0.31 g/t Au, with fresh material reported based on a cutoff of 0.35 g/t Au for Area A, 0.42 g/t Au for Area D, 0.35 g/t Au for Karakara, 0.41 g/t Au for Western Splay, 0.35 g/t Au for Kassassoko, 0.37 g/t Au for Southern Arc, and 0.39 g/t Au for Moungoundi in accordance estimated average base mining costs of US$4.57/t for all material mined, average processing and G&A costs of US$21.45/t milled, and sales and transportation costs of US$7.00/oz of gold. Pit slope angles applied are 33° for weathered material and 46° for fresh rock. The long-term gold price was US$2,600/oz. Metallurgical recoveries are estimated using grade versus recovery relationship formulas developed for oxide/transition rock (all deposits) and separate formulas for fresh rock in each of the seven deposits A royalty of 3.5% has been considered in the generation of the pit shell and cut-off grade determination.
·Totals may not add due to rounding.

 

Factors that may affect the estimates include metal price and exchange rate assumptions; changes to the assumptions used to generate the cut-off grades; changes in local interpretations of mineralization geometry and continuity of mineralized zones; changes to geological and mineralization shape and geological and grade continuity assumptions; variations in density and domain assignments; geometallurgical assumptions; changes to geotechnical, mining, dilution, and metallurgical recovery assumptions; change to the input and design parameter assumptions that pertain to the conceptual open pit constraining the estimates; extent of artisanal mining; and assumptions as to the continued ability to access the site, retain mineral and surface rights titles, maintain environment and other regulatory permits, and maintain the social license to operate.

 

There are no other known environmental, legal, title, taxation, socioeconomic, marketing, political or other relevant factors that would materially affect the estimation of Mineral Resources that are not discussed in this Report.

 

1.10Mineral Reserves

 

The Diamba Sud Project has no defined Mineral Reserves

 

1.11Mining Methods

 

The mine plan is partly based on Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the PEA based on these Mineral Resources will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

 

Mining is proposed for Mineral Resources defined inside an ultimate pit shell based on a long term gold metal price of US$2,300/oz, by conventional open pit mining methods and equipment, using the services of a mining contractor.

 

There will be seven open pits (Area A, Area D, Karakara, Western Splay, Kassassoko, Moungoundi and Southern Arc). The Area D pit will be mined in two stages, the other pits will be mined in a single stage.

 

The overall mining and production strategy is to maintain a mill processing throughput of 2.0–2.5 Mtpa. The processing plant design capacity is 2.0 Mtpa of fresh rock, with capacity to process up to 2.5 Mtpa where the blend is 80% fresh rock and 20% oxidized rock. The pits were sequenced to maximize the amount of oxide mined early in the schedule to maximize processing rate and cashflow early in the schedule. The mine life based on Indicated and Inferred Mineral Resources is 8.1 years.

 

October 15, 2025Page 30 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Drilling and blasting are planned for oxide, transitional and fresh mineralized material and waste, followed by conventional excavator and truck operations within the pits for the movement of mineralized material and waste. Free digging will be conducted in the oxide zones if practical, otherwise blasting has been assumed for all the weathering horizons. Bench heights for extraction of mineralized material and waste material is 5 m taken in two digging flitches of 2.5 m. Where possible in high waste stripping pit stages, 10 m bench heights will be used at an appropriate standoff distance from known mineralization.

 

Mining costs and equipment requirements are predominantly based on a request for pricing conducted in 2025 with five mining contractors submitting proposals however only three were used for pricing after outliers were removed. The mining equipment is proposed to be 120 t and 200 t excavators, along with 100 t haul trucks. The annual rate of mining movement peaks at 9 million bank cubic meters (BCM). A common pool of equipment will be used and scheduled across all of the active pits so that movement between the pits is minimized.

 

A tender process will be used to select the mining contractor.

 

Run of mine (ROM) material will be trucked from the pits to the ROM pad and tipped onto the ROM pad to be reclaimed and loaded to the crusher feed bin using front-end loaders that will be operated by the mining contractor.

 

1.12Processing and Recovery Methods

 

The process plant design is based on a metallurgical flowsheet envisioned for the production of gold doré at optimum recovery while minimizing initial capital expenditure and operating costs. The flowsheet comprises a conventional crushing, milling, gravity recovery, a CIL, carbon elution and gold recovery circuit.

 

The key project design criteria for the plant are:

 

·Initial nominal throughput of 2.5 Mtpa mineralized material in years 1 to 3 (high quantities of oxide feed), decreasing to 2 Mtpa thereafter (predominantly fresh rock feed). This flexibility is achieved through the upgrading and sizing of key components, such as pipes and pumps, to support higher throughput, minimize potential bottlenecks, and ensure planned throughputs can be met.

 

·Crushing plant availability of 75%.

 

·Plant availability of 91.3% for grinding, gravity concentration, leach plant and gold recovery operations.

 

The proposed process design is comprised of the following circuits:

 

·Primary jaw crushing of ROM material.

 

·A coarse material stockpile to provide buffer capacity ahead of the grinding circuit.

 

·Grinding circuit: single-stage SAG mill in closed circuit with cyclones.

 

·Gravity recovery of cyclone underflow by a semi-batch centrifugal gravity concentrator, followed by intensive cyanidation of the gravity concentrate and electrowinning of the pregnant leach solution in a dedicated cell located in the gold room.

 

October 15, 2025Page 31 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Trash screening and thickening of cyclone overflow prior to leaching.

 

·Gold leaching in a CIL circuit.

 

·Acid washing of loaded carbon and split AARL type elution followed by electrowinning and smelting to produce doré. Carbon regeneration by rotary kiln.

 

·Disposal of tailings to a tailings storage facility (TSF).

 

1.13Project Infrastructure

 

The Project has sufficient surface area to accommodate all infrastructure requirements to support the open pit life-of-mine (LOM) and sufficient studies have been completed to ascertain reasonable locations for all major infrastructure to PEA study level.

 

The proposed TSF will be located approximately 5 km to the north of the process plant. The Stage 1 tailings facility has a design capacity of 2.4 Mt, sufficient to handle tailings for 12 months based on design production levels, expansion of the facility has been designed annually thereafter. There is sufficient room for expansion of the tailings facility for the proposed life of mine (17.8 Mt), based on the design production rates.

 

The recommended power option for the operation is heavy fuel oil (HFO) generator(s) power for the site. Senegal does not have a feasible grid connection within proximity of the Project. As studies progress the addition of solar photovoltaic and a hybrid power solution will be assessed. Under average conditions, water demand is estimated at 66 L/s. Approximately 80% of the water in the slurry deposited into the TSF can be recovered from the TSF and pumped back to the plant for reuse in the process.

 

1.14Market Studies and Contracts

 

No market studies have been performed as part of this PEA. Diamba Sud will produce gold doré, which is readily marketable on an ‘ex-works’ or delivered basis to several refineries in Europe and Africa. There are no indications of the presence of penalty elements that may impact on the price or render the product unsalable.

 

The long-term gold price used for estimating potential mineralized material in the LOM plan was US$2,300/oz, based on the mean consensus prices from 2026 to 2028 of US$2,726/oz weighted at 40% and a 5-year historical average of $2,023/oz weighted at 60%. An elevated gold price of US$2,600/oz, using a 15% upside was used for Mineral Resource estimation. The economic analysis conducted in October 2025 used a base case gold price of US$2,750/oz.

 

The QP has reviewed the information provided by Fortuna on marketing, contracts, metal price projections and exchange rate forecasts and notes that the information provided support for the assumptions used in this Report and are consistent with the source documents, and that the information is consistent with what is publicly available within industry norms.

 

1.15Environmental Studies and Permitting

 

In April 2015, Boya entered into a Mining Convention (Mining Agreement) with the State of Senegal. This was followed by the grant of the Diamba Sud exploration permit in June 2015. The exploration permit was granted for an initial period of three years, subject to being renewed twice for additional periods of three years. It was last renewed on June 9,

 

October 15, 2025Page 32 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

2021, for a period of three years, being the second and final renewal which expired on June 9, 2024. However, Boya obtained a special two-year retention period until June 21, 2026 in order to complete the works necessary for a PEA, and to conduct the environmental studies that are required in support of an application for a mining license. Boya must submit an application for an exploitation permit before the aforementioned date and at least four months before the expiry of the exploration permit.

 

The environmental and social baseline has been established for the Project with field studies undertaken by Earth Systems, an environmental and social science and engineering company based out of Australia and registered in Senegal since 2022, with support from Oryx Expertise in 2024, a specialized biodiversity consultancy firm. These studies have included those related to socio-economic conditions, land and water use, surface and groundwater resources, terrestrial and aquatic ecology and biodiversity, air quality, noise and vibration, climate change, traffic and transportation, as well as archaeology and cultural heritage.

 

Senegalese law requires an Environmental Permit for the Diamba Sud Project before an Exploitation Permit can be obtained. Earth Systems was commissioned to prepare an Environmental and Social Impact Assessment (ESIA) in compliance with Senegalese regulatory requirements, and in accordance with international best practices such as the Equator Principles and International Finance Corporation (IFC) Performance standards.

 

The ESIA identifies and assesses the potential impacts of the Project and develops environmental and social management plans designed to mitigate impacts and enhance local benefits, such as environmental and social management plan, stakeholder engagement plan, capacity building plan, livelihood restoration program, mine rehabilitation and closure plan and a voluntary environmental and social investment program.

 

Regular consultations with Senegalese government authorities, local communities and other stakeholders have been conducted since the start of the Project to ensure that stakeholders' interests are taken into account in the planning and development of the project. In 2025, formal consultations were held to present the Project as defined in this Report.

 

The ESIA was submitted to the Direction de la Réglementation Environnementale et du Contrôle (DiREC), a division of the Ministry of the Environment and Sustainable Development of Senegal on October 6, 2025, for approval, with a decision expected in early 2026.

 

From an environmental perspective, artisanal mining is identified as the main threat to biodiversity in the study area. Artisanal mining activities have decreased over the past years in the Project area due to the current legal exploration activities ongoing. There are no artisanal mining activities or settlement in the Project development or fenced in area at the effective date of the Report.

 

1.16Capital and Operating Costs

 

1.16.1Capital Cost Estimate

 

The capital cost estimate is based upon an engineering, procurement and construction management (EPCM) approach where the Owner assumes the builder’s risk. As a result, the cost estimate does not include a builder’s margin. The estimate is considered to have an accuracy range of ±25 to –30%.

 

October 15, 2025Page 33 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Capital and operating cost estimates are based on established cost experience gained from engineering house experience, projected budget data and quotes from manufacturers and suppliers.

 

Capital costs include all investments in ongoing mine development, infill drilling, mine equipment overhaul and components, and infrastructure necessary to sustain the continuity of the operation.

 

Mine development includes the main development and infrastructure of the mine as this activity has the objective of increasing confidence in currently defined Mineral Resources.

 

Mine closure costs are attributed to site rehabilitation costs required to remediate the area where the mine is located and to meet mine closure requirements.

 

Equipment and infrastructure costs are attributed to all departments of the Project including mine, plant, tailing facilities, maintenance and energy, safety, information technology, administration and human resources, logistics, camps, geology, planning, laboratory and environmental.

 

The capital cost estimate is summarized in Table 1.2.

 

Table 1.2 Summary of Projected Major Capital Costs for the LOM

 

Area Capital Cost (US$M)
Process plant and infrastructure 180.4
Mining 19.9
Owner’s costs 31.9
With Holding Tax, duties, levies 4.5
Contingency (20%) 46.4
Total 283.2

 

Projected sustaining capital costs for the proposed LOM are summarized in Table 1.3, and total US$48 million.

 

Table 1.3 Summary of Projected Major Sustaining Capital Costs for the LOM

 

Capital Cost Item (US$M) * Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Mine development (access and haul roads) - 2.1 0.2 - - 0.1 0.3 -
 
Surface water management - 1.0 0.9 - - - 0.3 -
Tailings storage facility 4.5 - 7.3 - 11.7 - 11.1 -
Equipment and infrastructure 4.5 3.1 8.4 - 11.7 0.1 11.7 -
 
Mine closure & site rehabilitation - - 0.6 0.6 0.6 0.6 0.6 5.3
 
Total capital expenditure 4.5 3.1 9.1 0.6 12.3 0.7 12.4 5.3
*Numbers may not total due to rounding

 

1.16.2Operating Cost Estimate

 

Long-term projected operating costs are based on the LOM mining and processing requirements.

 

Operating costs include site costs and operating expenses to maintain the operation. These operating costs are analyzed on a functional basis, and the cost structure is not similar to the operating costs reported by the financial statements published by Fortuna.

 

October 15, 2025Page 34 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Site costs relate to activities performed on the property including mine, plant, general services, and administrative service costs. Other operating expenses include costs associated with transportation and community support activities.

 

Direct operating costs are estimated as $51.16/t of material milled or $1,081/oz of gold produced, as summarized in Table 1.4.

 

Table 1.4 Life-of-Mine Operating Costs

 

Operating Cost $M $/t milled $/payable oz
Mining 542 30.54 646
Processing 247 13.91 294
G&A 119 6.70 142
Total operating costs excluding Royalties and Social Fund 908 51.16 1,081
Refining 3 0.14 3
Royalties* 69 3.90 83
Social Fund* 12 0.65 14
Total Operating costs including Royalties and Social Fund 992 55.85 1,180
*The PEA assumes a 3% royalty payable to the State and 0.5% contribution to a Social Development Fund

 

1.17Economic Analysis

 

The PEA is preliminary in nature, and it includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and, as such, there is no certainty that the PEA results will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

 

The Diamba Sud Project has been evaluated on a discounted cash flow (DCF) basis. The results of the analysis show the project to potentially be economically very robust (Table 1.5). The economic analysis assumes that Fortuna will provide all development funding via inter-company and shareholder loans to the mine operating entity, which will be repaid with interest from future gold sales.

 

Table 1.5 PEA Summary

 

Metrics Units Results

Gold Price

Life of mine

$/oz

years

2,750

8.1

Processing Duration years 7.9
Total mineralized material mined kt 17.8
Contained gold in mineralized material mined koz 932
Strip ratio Waste: Mineralized material 5.5
Throughput initial 3 years (primarily oxide) Mtpa 2.5
Throughput after 3 years (primarily fresh) Mtpa 2.0
LOM grade g/t 1.63
Recoveries % 90
Gold production    
Total production over LOM koz 840
Average annual production over LOM koz 106
Average annual production over first 3 years koz 146
Per Unit Costs LOM    
Mining $/t, mined 4.82
Processing $/t, processed 13.9
G&A $/t, processed 6.7
Cash costs 1    
Average operating cash costs over LOM $/oz 1,081

 

October 15, 2025Page 35 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Metrics Units Results
Average operating cash costs over first 3 years $/oz 759
AISC 1    
Average AISC over LOM $/oz 1,238
Average AISC over first 3 years   $/oz 904
Capital costs    
Initial capital expenditure $M 283
Sustaining capital expenditure + infrastructure (includes closure costs) $M 48
Returns    
NPV5%, pre-tax (100% Project basis) $M 772
Pre-tax IRR % 86
NPV5%, after-tax (100% Project basis) $M 563
After-tax IRR % 72
After Tax Payback Period years 0.8
     
Annual EBITDA 1    
Average EBITDA over LOM $M 167
Average EBITDA over first 3 years   $M 277

 

Note: (1)  This is a non-IFRS financial measure. The definition and purpose of this non-IFRS financial measure is included under the heading “Cautionary Note on Non-IFRS Measures” in this Report. Non-IFRS financial measures have no standardized meaning under IFRS and therefore, may not be comparable to similar measures presented by other issuers.

 

·The pit optimization shells used for the mine plan were generated using a gold price of $2,300 per ounce.
·Average operating cash costs and average AISC represent costs for projected production for the LOM at the time of gold sales.
·The PEA is presented on a 100% project basis. However, upon the granting of the exploitation permit, the State of Senegal is entitled to a 10% free-carried interest Boya, with the right for the State to acquire an additional contributory interest of up to 25%.
·The economic analysis was carried out using a discounted cash flow approach on a pre-tax and after-tax basis, based on the gold price of $2,750/oz.
·The IRR on total investment that is presented in the economic analysis was calculated assuming a 100% ownership in Diamba Sud.
·The NPV was calculated from the after-tax cash flow generated by the Project, based on a discounted rate of 5% and an effective date of October 10, 2025.
·The PEA assumes that the percentage of certain royalties and taxes payable to the State, the percentage of the investment tax credit available to the company and the percentage payable to the social development fund will be in accordance with the provisions of the Mining Convention between Boya S.A. and the State of Senegal dated April 8, 2015. It should be noted, however, that the State retains the sovereign prerogative to review or revisit certain fiscal terms during the exploitation permit approval process, and as such, the current framework may be subject to amendment.
·The PEA is preliminary in nature, and it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and, as such, there is no certainty that the PEA results will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability

 

The pre-tax net present value with a 5% discount rate (NPV5%) is $772 million and with an IRR of 86% using a base gold price of $2,750/oz. The post-tax Project NPV5% is $563 million, with an IRR of 72% and a payback period of less than one year at a gold price of $2,750/oz. The payback period is defined as the time after process plant start-up that is required to recover the initial expenditures incurred developing the Diamba Sud Project.

 

Like most gold mining projects, the key economic indicators of NPV5% and internal rate of return (IRR) are most sensitive to changes in gold price. A $250/oz reduction in the gold price reduces Fortuna’s after-tax NPV5% by $119 million and the IRR by 13%. A $250/oz increase in the gold price increases Fortuna’s NPV5% by $119 million and the IRR by 13%.

 

Project IRR is most sensitive to changes in revenue parameters (i.e. gold price and gold grade) and operating costs, while changes to recovery and capital costs are secondary.

 

October 15, 2025Page 36 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

1.18Conclusions

 

The PEA was based on Mineral Resources that have been estimated using industry-recognized methods, and estimated operational costs, capital costs, and plant performance data. The economic analysis indicates a positive cash flow using the assumptions and parameters detailed in this Report.

 

1.19Risks and Opportunities

 

A number of opportunities and risks were identified by the QPs during the evaluation of the Diamba Sud Project.

 

Opportunities include:

 

·Ongoing work aimed at optimizing the process flowsheet to enhance recoveries and operating efficiencies.

 

·Significant exploration upside following the initial resource estimates at Moungoundi and Southern Arc.

 

·Untested prospective targets across the broader Diamba Sud tenement package.

 

·Ongoing geological interpretation and modelling to improve understanding of the Diamba Sud deposits and to identify additional drill targets.

 

·Evaluation of a hybrid solar power system that could reduce operating costs and lower the project’s environmental footprint.

 

·Ongoing optimization of mine design and scheduling to potentially enhance operational efficiency.

 

·Opportunities to further reduce capital and operating costs through detailed engineering and optimization studies.

 

·Opportunity to enhance the socio-economic impacts of the Project by developing partnerships with local institutions, such as for local employment, and by further optimizing the design of the Project to reduce the impacts on the environment, such as greenhouse gas (GHG) emissions and footprint on critical habitats.

 

Risks include:

 

·Local Content Compliance: The evolving implementation of Senegal’s local content regulations may affect contracting and recruitment. Mitigation includes regular engagement with authorities, maintaining strong relationships with relevant government parties, dedicated local content specialists, and early alignment of procurement and staffing strategies to ensure compliance.

 

·Material Cost Increases and Inflation: Global inflation and supply chain pressures could impact capital and operating costs. Mitigation includes proactive cost tracking, early contractor engagement, and appropriate contingencies within cost estimates. Advancing detailed mining studies and investment decision timeline is also expected to help limit exposure to inflationary pressures.

 

·Long Lead Times for Critical Equipment: Extended procurement and delivery times for key mechanical and power generation equipment pose schedule risks. Mitigation measures include early identification, prioritization, and ordering of long-lead items during future more detailed studies.

 

October 15, 2025Page 37 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Taxes and Royalties: Certain taxes and royalties included in the economic analysis have been based upon the provisions included in the Mining Convention between Boya and the State of Senegal dated April 8, 2015, and the Mining Code of 2003. It should be noted, however, that the State retains the sovereign prerogative to review or revisit certain fiscal terms during the exploitation permit approval process, and as such, the current framework may be subject to amendment.

 

·Interest of the State: The State of Senegal is entitled to a 10% free-carried interest in Boya upon the granting of the exploitation permit, with the right for the State to acquire an additional contributory interest of up to 25%. There can be no assurance that the State will not increase its interest above 10%. The economic analysis in this Report is presented on a 100% project basis.

 

1.20Recommendations

 

The following recommendations outline the key activities required to advance the Diamba Sud Project from the PEA to a more advanced study level. The focus is on resource expansion and infill, technical de-risking, design optimization, and confirmation of environmental, permitting, and social frameworks. The next phase of work is broken into activities relating to exploration, growth and infill, and those optimizing and advancing technical studies to support project development. All recommended programs are independent and may be executed concurrently unless otherwise stated.

 

1.20.1Exploration

 

An exploration and infill drilling program is recommended to expand the existing deposits that have not been fully defined and potentially support upgrading of Inferred Mineral Resources to Indicated Mineral Resources.

 

Key priorities for the exploration program include:

 

·Ongoing step-out and expansion drilling at the Southern Arc and Moungoundi deposits.

 

·Continued infill drilling at the Moungoundi, Southern Arc, Area A, Area D and Karakara deposits to potentially support upgrades in Mineral Resource classification and improve geological confidence.

 

·Continuing regional auger, geochemical, and geophysical surveys across the Diamba Sud permit to generate new drill targets.

 

·Detailed structural mapping and surface sampling of untested high-priority targets to refine the geological model and guide future drill programs.

 

The budget to execute the exploration and infill program is estimated at approximately US$10.1 million based on current contracted drill rates and in-country expenses. The program for 2026 will include, but not be limited to:

 

·11,300 m of infill and resource extension drilling (RC and core) across the Project area, guided by the next iteration of Mineral Resource estimation and provision for advancing emerging prospects.

 

·24,000 m of target generation RC and core drilling at Southern Arc, Gamba Gamba, Moungoundi North and other emerging targets generated from 2025

 

October 15, 2025Page 38 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

auger and geophysical campaigns, as well as deep stratigraphic diamond core drilling to validate certain geological concepts and to examine likely geological targets for future underground mining potential.

 

1.20.2Geotechnical

 

Recommendations to improve geotechnical data confidence and support pit design optimization for the Western Splay, Kassassoko, Southern Arc, and Moungoundi pits as follows:

 

·Undertake a dedicated geotechnical-specific drilling program, including the infill of selected resource drill holes, to obtain representative geotechnical data across key deposit areas.

 

·Conduct geotechnical logging at the drill rig to minimize mechanical breakage and preserve core integrity during handling and transport.

 

·Collect geotechnical samples for laboratory testing (direct shear on natural joints, unconfined compressive strength, tensile compressive strength, Brazilian, and undrained triaxial tests) to characterize joint and intact rock strengths, as well as saprolite behavior.

 

·Perform point load index testing in fresh zones to improve understanding of variability in rock strength.

 

·Install piezometers or standpipes to monitor and quantify hydrogeological conditions within pit walls and surrounding areas.

 

·Integrate ATV and optical televiewer (OTV) surveys into the geotechnical program to enhance structural characterization and refine the geotechnical model.

 

An allocation of approximately US$500,000 has been made for the geotechnical investigation program, comprising both technical studies and physical drilling activities.

 

Technical studies and analysis are budgeted at approximately US$250,000, covering project supervision and reporting, televiewing, laboratory rock strength testing, and interpretation of results.

 

Physical drilling is budgeted at approximately US$200,00, consisting of 11 geotechnical drill holes totaling approximately 1,250 m, at an estimated all-in cost of US$160/m.

 

These programs are designed to improve pit design confidence and ensure adequate data coverage across newly-defined Mineral Resource areas. The combined dataset will provide critical input for refining slope design parameters, improving overall pit stability assessments, and reducing geotechnical risk for any future open-pit development.

 

1.20.3Water Management

 

A minimum catchment yield of 13% is required in the area upstream of the proposed water harvest dam between the months of June and October to eliminate the need for abstraction from the Falémé River to a water storage dam. Ongoing monitoring of flow in the Gamba Gamba Creek (Karakaka watercourse) should continue to further refine the yield of the catchment upstream of the proposed water harvest dam and confirm its suitability as a sustainable raw water source for the project.

 

Additional drilling, pump testing, and technical assessments are required for the pits Western Splay, Kassassoko, Southern Arc, and Moungoundi pits to confirm the

 

October 15, 2025Page 39 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

availability of supplementary site water supplies and to support accurate estimation of pit dewatering requirements.

 

An allocation of approximately US$270,000 has been made for technical work and analysis, excluding additional funds allocated for the physical drilling of hydrogeological holes associated with these studies.

 

These activities will refine the understanding of groundwater conditions, improve pit dewatering designs, and ensure the adequacy and sustainability of a long-term process water supply.

 

1.20.4Metallurgical

 

Additional metallurgical testwork is recommended for the Southern Arc and Moungoundi deposits under process design conditions to confirm metallurgical recoveries in line with the plant’s design criteria. An allocation of approximately US$270,000 has been made for additional metallurgical testwork, reporting, and analysis to support these studies.

 

1.20.5Environmental and Social

 

It is recommended to use the next study stage to optimize the Project by reducing its environmental footprint and potential impacts while enhancing opportunities for local communities where possible. In parallel, it is also recommended to explore renewable energy options, such as solar hybrid power solutions, to improve project sustainability and reduce long-term operating costs. This work is expected to be completed using in-house resources and part of normal operating costs for Fortuna’s West Africa regional office.

 

1.20.6Engineering Studies

 

In addition to addressing these key gaps, it is further recommended that the following studies be completed to optimize and advance the project:

 

·Mining Study Preparation and Integration. An allowance of approximately US$700,000 has been included for engineering, trade-off studies, discipline inputs, and integration of all technical workstreams to support estimation of Mineral Reserves. This scope will also consolidate the outcomes of ongoing technical and optimization studies.

 

·Integration of Solar PV and Renewable Power Options. This work is estimated at approximately US$150,000 and will be integrated into the mining studies to evaluate hybrid HFO–solar configurations aimed at reducing operating costs and enhancing overall project sustainability.

 

·Mining Cost Optimization Study. This is budgeted at approximately US$240,000, and covers updated pit optimizations, mine design revisions, detailed mine planning and scheduling, Mineral Reserve estimation, and supporting mining studies.

 

·Local Content and Procurement Studies. Completion of these studies is estimated at approximately US$100,000. These studies will ensure full compliance with Senegal’s evolving local content framework and identify in-country participation opportunities across construction and operations.

 

·Tailings and Water Storage Optimization Review. This is estimated at approximately US$150,000. The work will confirm capacity, sequencing, and

 

October 15, 2025Page 40 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

design integration with early works and mine layouts, and ensure alignment between storage infrastructure, water balance, and process plant requirements.

 

·Operational Readiness and Implementation Planning. Estimated at approximately US$70,000, this study will define resource requirements, schedules, and execution strategies.

 

October 15, 2025Page 41 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

2Introduction

 

2.1Report Purpose

 

This Technical Report (the Report) was prepared by Mr. Eric Chapman, P.Geo., Mr. Paul Weedon, MAIG, Mr. Raul Espinoza, FAusIMM (CP), Mr. Mathieu Veillette, P.Eng., and Dr. Leendert (Leon) Lorenzen, FAusIMM (CP) for Fortuna Mining Corp. (Fortuna)on the Diamba Sud Project (the Project).

 

The Project is located in the east of Senegal, close to the border of Mali (Figure 2.1).

 

Figure 2.1 Map Showing the Location of the Diamba Sud Project

 

 

Figure prepared by Fortuna, 2024, sourced from Senegal - Geospatial, location data for a better world

 

The Diamba Sud Project is operated by Boya S.A. (Boya), a company incorporated, registered, and operating in accordance with the laws of Senegal, which is a 100% indirectly wholly-owned subsidiary of Fortuna. The Government of Senegal will assume a 10% free carried ownership interest in Boya when an exploitation permit is granted, and may elect to purchase, for itself or the national private sector, up to an additional 25%

 

October 15, 2025Page 42 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

interest in Boya at a “fair price” determined through an independent valuation upon the granting of the exploitation permit.

 

The Report discloses a preliminary economic assessment (PEA) based on Mineral Resource estimates for the Diamba Sud Project.

 

Mineral Resources are reported using the 2014 CIM Definition Standards - for Mineral Resources and Mineral Reserves (the 2014 CIM Definition Standards).

 

Costs are in US dollars (US$) unless otherwise indicated.

 

2.2Qualified Persons

 

The following Qualified Persons are responsible for the preparation of this Report:

 

·Mr. Eric Chapman, P.Geo., Senior Vice President of Technical Services – Fortuna Mining Corp.

 

·Mr. Paul Weedon, MAIG, Senior Vice President of Exploration – Fortuna Mining Corp.

 

·Mr. Raul Espinoza, FAusIMM (CP), Director of Technical Services – Fortuna Mining Corp.

 

·Mr. Mathieu Veillette, P.Eng., Director, Geotechnical, Tailings and Water – Fortuna Mining Corp.

 

·Dr. Leendert (Leon) Lorenzen, FAusIMM (CP), Senior Principal Consultant (Process) - Lorenzen Consultants Pty Ltd.

 

2.3Scope of Personal Inspection

 

2.3.1Mr. Eric Chapman

 

Mr. Eric Chapman visited the Project from October 19–22, 2023. During his site visit Mr. Chapman reviewed data collection, drill core, storage facilities, database integrity, procedures, and geological model construction. Discussions on Geology and mineralization were held with Boya personnel, and field site inspections were performed including inspection drill core and operating surface drill machines. He worked with site geological personnel reviewing aspects of data storage (database) and analytical quality control.

 

2.3.2Mr. Paul Weedon

 

Mr. Paul Weedon visited the Project on multiple occasions since 2023, most recently from April 11-15, 2025. During these visits, Mr. Weedon reviewed drilling performance, sample and data collection, site quality assurance and quality control (QA/QC) records and geological model development for the Diamba Sud mineralization.

 

2.3.3Mr. Mathieu Veillette

 

Mr. Mathieu Veillette visited the property from October 19–22, 2023 when he performed a field visit to the proposed location of the tailings storage facility (TSF), waste rock storage facilities (WRSFs) and water management facilities. He also reviewed and discussed with Boya site personnel, designs and procedures for the TSFs, WRSFs, geotechnical model and water balance.

 

October 15, 2025Page 43 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

2.4Effective Dates

 

The Report has a number of effective dates, as follows:

 

·July 7, 2025: date of database cut-off for assays used in the Mineral Resource estimate for the Diamba Sud Project.

 

·August 31, 2025: date of the Mineral Resource estimate.

 

·October 15, 2025: date of the economic analysis in the PEA.

 

·October 15, 2025: date to which drilling has been reported.

 

The overall effective date of the Report is the date of the most recent supply of information on the ongoing drilling program, and the date of the PEA, which is October 15, 2025.

 

2.5Previous Technical Reports

 

There have been no previous technical reports filed by Fortuna on the Diamba Sud Project.

 

2.6Information Sources and References

 

The main information source referenced in this Report is:

 

·Arthur, J., 2021. Mineral Resource Estimate at the Diamba Sud Gold Project, Senegal, West Africa, prepared for Chesser Resources Ltd., dated November 16, 2021.

 

Additional information was obtained from Boya site personnel including social, environmental and permitting guidance.

 

2.7Acronyms

 

The more commonly used acronyms used in the Report are detailed in Table 2.1.

 

Table 2.1 Acronyms

 

Acronym Description
Au gold
cm centimeters
COG cut-off grade
g grams
g/t grams per tonne
ha hectares
kg kilograms
km kilometers
kV kilovolts
kW kilowatts
l liter
LOM life-of-mine
m meters
Ma millions of years
masl meters above sea level
Moz million troy ounces

 

October 15, 2025Page 44 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Acronym Description
Mn manganese
Mt million metric tonnes
MVA megavolt ampere
MW megawatt
n/a not applicable
NI national instrument
nr not recorded
NSR net smelter return
OK ordinary kriging
oz troy ounce
ppm parts per million
Pb lead
psi pounds per square inch
QAQC quality assurance/quality control
RMR rock mass rating
RQD rock-quality designation
s second
t metric tonne
t/m3 metric tonnes per cubic meter
tpd metric tonnes per day
tph metric tonnes per hour
yd yard
yr year
Zn zinc
US$/t United States dollars per tonne
US$/g US dollars per gram
US$/% US dollars per percent

 

October 15, 2025Page 45 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

3Reliance on Other Experts

 

The QPs have not independently reviewed ownership of the Diamba Sud Project or any underlying agreements, mineral tenure, or surface rights. The QPs have fully relied upon, and disclaim responsibility for, information derived from Fortuna and legal experts retained by Fortuna for this information through the following documents:

 

·Fall Maname., 2025. Legal Opinion prepared by Societe de Conseils Juridiques et Fiscaux for Fortuna dated January 23, 2025, 11 p.

 

This information is used in Section 4 of the Report. The information is also used in support of the Mineral Resource estimate in Section 14.

 

October 15, 2025Page 46 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

4Property Description and Location

 

The Diamba Sud Project is located within the Department of Saraya in the Kédougou Region and within the Arrondissement of Bembou.

 

The Project is situated approximately 50 km north of the Senegal-Guinea border and approximately 7 km to the west of the Falémé River which, in this region, defines the international border between Senegal and Mali. The Project is approximately 665 km southeast of the Senegalese capital Dakar and 83 km northeast of the nearest town, Kédougou.

 

The Diamba Sud exploration camp is located within the permit area and centered upon co-ordinates 11° 27’ 58.73” W and 12° 55’ 5.04” N. All field activities are managed from that camp.

 

4.1Ownership

 

The Project is owned 100% by Fortuna. Fortuna acquired the Project pursuant to its acquisition of Chesser Resources Ltd. (Chesser) in September 2023. The Project is operated by Boya S.A. (Boya), a 100% indirectly owned subsidiary of Fortuna.

 

The Senegalese Government is entitled to a 10% free carried interest in Boya upon the granting of an exploitation permit for the Project, and may elect to purchase for itself or local applicants up to an additional 25% interest in Boya at an agreed commercial price upon the granting of the exploitation permit.

 

4.2Mineral Tenure and Surface Rights

 

4.2.1History of the Mining Code

 

Senegalese mining law provides that all mineral resources are administered by the Senegalese Ministry of Mines. A new mining code “Law No. 2016-32” (the “2016 Mining Code”) was passed by the Senegal Parliament on November 8, 2016, and published in the Official Journal on November 24, 2016. It was implemented by Decree No. 2017-458 which came into effect on March 20, 2017. The 2016 Mining Code applies to new applications for mining permits, while the previous mining law (Law No. 2003-36) effective as of November 24, 2003 (the “2003 Mining Code”) remains applicable to existing mining permits until their expiry as provided under Article 141 of the 2016 Mining Code as follows:

 

Mining titles granted before the date of entry into force of this code remain subject, for the duration and for the substances for which they were issued, to the law and regulations applicable to them on the date of entry into force of this code. (…) Holders of mining conventions linked to a mining title signed prior to the date of entry into force of the present code remain subject to the stipulations contained in the said conventions for the entire duration of their validity.

 

The 2016 Mining Code reformed the mining sector in Senegal in line with other countries in West Africa to include an increase in transparency and control over mining activities by the State, increased taxes, reduced scope of exemption and advantages for investors.

 

October 15, 2025Page 47 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

4.2.2Permits

 

Background

 

The 2016 Mining Code provides that no one can undertake or conduct a mining activity in Senegal without holding a mining title according to the terms of the Code.

 

There are two levels of permitting required to undertake mineral exploration and development and mining in Senegal. First, an exploration permit (permis de recherche) allows for exploration to be undertaken, including resource estimates and feasibility studies. Secondly, a small-scale mining permit (limited to an area of 500 ha with a term of five years, renewable for five years each time, or, a mining permit or exploitation permit (permis d’exploitation) intended for large-scale mining projects an initial term of between 5 to 20 years, and are renewable as many times as is necessary until the resource is exhausted.

 

In all cases, the mining title must be held by a Senegal registered company. The holder of a mining title must also enter into a “Mining Convention” or “Mining Agreement” with the State. Under the 2003 Mining Code, a Mining Convention regulates the relationship between the parties for the entire duration of mining operations. A Mining Convention entered into under the 2003 Mining Code covers the exploration and exploitation phases of a project (article 87 of the 2003 Mining Code) and specifies the rights and obligations of the parties, which gives the title holder a stable legal and fiscal framework within which to operate.

 

Diamba Sud Exploration Permit

 

The Diamba Sud permit is an exploration permit (permis de recherche) which was granted to Boya in June 2015 under the 2003 Mining Code before the 2016 Mining Code came into effect and therefore it remains subject to the 2003 Mining Code for its duration and validity. The exploration permit was granted for an initial period of three years, subject to being renewed twice for additional periods of three years. It was last renewed on June 9, 2021, for a period of three years, being the second and final renewal which expired on June 9, 2024. However, Boya obtained a special two-year retention period to complete the works necessary for a PEA, and to conduct the environmental studies that are required in support of an application for a mining license. This retention period is valid until June 21, 2026, and requires the submission of a request for an exploitation permit before this date and at least four months before the expiry of the exploration permit.

 

The Diamba Sud exploration permit was granted before the 2016 Mining Code came into effect and therefore it remains subject to the 2003 Mining Code for its duration and validity, except for procedural documents (related to renewals, authorizations and permit applications) which are under 2016 Mining Code.

 

Boya Mining entered into a Mining Convention with the State of Senegal dated April 8, 2015. Under the 2003 Mining Code, the Mining Convention between the State and the titleholder regulates the relationship between the parties during the exploration and exploitation periods. It should be noted, however, that the State retains the sovereign

 

October 15, 2025Page 48 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

prerogative to review or revisit certain fiscal terms during the exploitation permit approval process, and as such, the current framework may be subject to amendment.

 

The permit comprises two blocks, referred to as the DS1 and DS2 blocks, which are linked by a narrow strip of some 25 m width. This allows the two blocks to be classed as contiguous and form one permit area (Figure 4.1). Corner point (apex) co-ordinates for the concession in degrees, minutes and seconds are detailed in Table 4.1.

 

Figure 4.1 The Diamba Sud Permit Boundary and Location in Eastern Senegal

 

 

Figure prepared by Fortuna, 2024

 

October 15, 2025Page 49 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 4.1 Diamba Sud Permit Coordinates in Longitude and Latitude

 

Apex ID Longitude
(degrees, minutes
and seconds
)
Latitude
(degrees, minutes
and seconds
)
D1 11° 29' 50.0388'' W 12° 57' 57.4632'' N
D2 11° 27' 11.3796'' W 12° 57' 55.3140'' N
D3 11° 27' 09.7416'' W 12° 53' 59.6508'' N
D4 11° 26' 31.6536'' W 12° 53' 59.1360'' N
D5 11° 26' 30.6564'' W 12° 52' 58.3500'' N
D6 11° 27' 49.8456'' W 12° 52' 58.1088'' N
D7 11° 27' 49.8276'' W 12° 51' 31.7232'' N
D8 11° 25' 51.5064'' W 12° 51' 31.7448'' N
D9 11° 25' 51.2364'' W 12° 45' 58.3128'' N
D10 11° 25' 24.4632'' W 12° 45' 58.5180'' N
D11 11° 25' 23.3976'' W 12° 44' 30.3936'' N
D12 11° 26' 41.5932'' W 12° 44' 30.3072'' N
D13 11° 26' 41.7408'' W 12° 45' 57.3372'' N
D14 11° 25' 52.0680'' W 12° 45' 58.2912'' N
D15 11° 25' 52.3452'' W 12° 51' 30.8988'' N
D16 11° 27' 50.7204'' W 12° 51' 30.8808'' N
D17 11° 27' 50.7168'' W 12° 53' 00.8988'' N
D18 11° 29' 54.1680'' W 12° 53' 01.5216'' N

 

The northern block, DS1, is approximately 46.56 km2 in area. The southern block, DS2, is approximately 6.31 km2 in area. The total area of the permit is 53.46 km2 (including the corridor of land that connects the two blocks). The DS1 block is centered upon co-ordinates 11° 28’ 23.17” W and 12° 55’ 46.55” N. The DS2 block, which is some 20 km to the south, is centered upon co-ordinates 11° 26’ 2.68” W and 12° 45’ 13.61” N.

 

4.2.3Surface Rights

 

Mineral exploration permits, within their boundaries, entitle the holder on surface and indefinitely at depth, the exclusive rights to explore for the nominated mineral commodities specified (in this case, gold), as well as encumbrance-free disposal of materials extracted during the exploration process. Such permits allow for beneficial ownership to be held by a foreign entity, such as Fortuna, through Boya, its wholly owned Senegalese subsidiary.

 

Fortuna has full and unrestricted surface rights to the land covered by the exploration permit. The perimeter of the exploration permit is free to access and is not subject to any kind of restriction, subject to the applicable mining regulation.

 

The PEA assumes the granting of an exploitation permit which will provide Boya, within the boundaries of its perimeter, on surface and indefinitely in depth, with the exclusive rights to explore, extract and dispose of the nominated mineral commodities specified (in this case, gold).

 

4.3Royalties

 

Under the Diamba Sud Mining Convention, and based on the 2003 Mining Code, the State of Senegal is entitled to a 3% royalty on the “carreau-mine value” of gold produced. The carreau-mine value of a mineral substance is calculated as the difference between its sale price and the total costs incurred between the mine site and the point of delivery.

 

October 15, 2025Page 50 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

It should be noted, however, that the State retains the sovereign prerogative to review or revisit certain fiscal terms during the exploitation permit approval process, and as such, the current framework may be subject to amendment.

 

Additionally, under the 2016 Mining Code, holders of exploitation permits are required to contribute 0.5% of their annual turnover (excluding taxes) to a local development fund dedicated to promoting the economic and social development of local communities.

 

An annual surface fee is payable by holders of exploration permits as follows:

 

·First period of validity – 5,000 West African CFA francs per km2 per year.

·First renewal period – 6,500 West African CFA francs per km2 per year.

·Second renewal period – 8,000 West African CFA francs per km2 per year.

 

Boya is currently paying a surface fee of 8,000 West African CFA francs per km2 per year related to the Diamba Sud exploration permit.

 

4.4Permitting

 

Permitting is discussed in Section 20 of this Report.

 

4.5Social and Environmental Considerations

 

Environmental and social considerations are discussed in Section 20 of this Report.

 

4.6Comment on Section 4

 

In the opinion of the QPs:

 

·The QPs were provided with a legal opinion that supported that the mining tenure held by Boya for the Diamba Sud Project is valid and that Boya has a legal right to exploration.

 

·The QPs were provided with a legal opinion that supported that Boya has unrestricted surface rights to the land covered by the exploration permits held by Boya. Surface rights are sufficient in area for mining operation infrastructure and tailings facilities if the Project advances to a more advanced stage.

 

·Fortuna is not aware of any environmental issues that may impact exploration or potential future operational activities at the Diamba Sud Project.

 

Fortuna advised the QPs that to the extent known, there are no other significant factors and risks that may affect access, title or right or ability to perform work at the Project.

 

October 15, 2025Page 51 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

5Accessibility, Climate, Local Resources, Infrastructure and Physiography

 

5.1Accessibility

 

From Senegal’s capital city Dakar, the Project site is accessed via the all-weather paved N1 highway east–southeast 489 km to the regional center of Tambacounda. From Tambacounda, the paved N7 can be taken southeast 234 km to Kédougou where it joins the Kédougou–Saraya Road that connects Kédougou to the municipality of Saraya. From Saraya the paved N24 road, frequented by trucks taking goods to and from neighboring Mali, passes through the Diamba Sud permit area and continues through to the Senegal–Mali border. Due to frequent use by trucks carrying heavy loads, road conditions can be locally very poor. However, in almost all cases the main roads remain open to vehicles throughout the year. Access throughout the permit area is via a combination of paved and laterite roads, and dirt tracks.

 

Access by air is possible via an asphalt airfield in Kédougou. The Senegalese government has announced numerous plans to transform the airfield into an international airport with regular scheduled flights, but development of the airport is yet to take place. Thus, the only currently available options for flights are two charter companies that operate from Dakar with flights taking between 1.5 and 3 hours, depending on aircraft type.

 

5.2Climate

 

Senegal lies within the semi-arid Sahel region of Africa, with the Project situated in the tropical savanna climate zone of southern Senegal, classified as Tropical Savanna (Aw) under Köppen-Geiger’s climate classification (Peel et al., 2007). This region experiences two distinct seasons: a dry winter from November to May and a wet summer from June to October, driven by the movement of the intertropical convergence zone (ITCZ). The wet season typically extends from June to September, peaking in August with high annual rainfall variability. Average annual precipitation is approximately 1,000–1,200 mm, distributed over 65 days, with very little to no rainfall during the dry season. Evaporation rates are higher, averaging around 1,900 mm annually.

 

The dry season is dominated by the warm, dust-laden east-northeast harmattan winds from the Sahara. Temperatures are hottest from February to June, averaging 24–41°C, and milder from July to January, ranging between 16–34°C. Daylight hours are relatively stable, varying from 11.4 hours in December to 12.9 hours in June.

 

The climate supports year-round mining and processing; however, the wet season can complicate surface exploration activities due to excessive vegetation growth, surface water, electrical storms, and abundant insects. Consequently, field exploration typically ceases between July and September.

 

5.3Topography, Elevation and Vegetation

 

The Project is located in the Kédougou region in the southeast corner of Senegal, with an elevation ranging between 100–380 meters above sea level (masl). The highest point is Kouroudiako, a prominent ironstone hill in the southeast of the DS1 area, reaching 380 m AMSL. The region features low to moderate relief, consisting of broad lateritic plateaus, eroded valleys, and gentle slopes.

 

October 15, 2025Page 52 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The Project lies approximately 7 km from the western bank of the Falémé River, with drainage into three major streams that flow into the Falémé River, which drains into the Senegal River and ultimately the north Atlantic Ocean at St. Louis, approximately 180 km northeast of Dakar at the Senegal-Mauritania border.

 

The landscape primarily comprises forested savanna with patches of grassland and forest. Notable flora include baobab (Adansonia digitata), madd (Saba senegalensis), jujube (Ziziphus mauritania), and the locust bean tree (Parkia biglobosa). Larger trees are often localized along river channels where seasonal rivers flow and the lateritic plateau has eroded, while vegetation in the area is predominantly grass and small shrubs, characteristic of the climate.

 

5.4Local Resources and Infrastructure

 

Gamba Gamba (population c. 640) is the closest village to the Project and the only village located within the permit area. The settlement of Karakaéné (population c. 3,253) is located 2.4 km west of the DS1 block boundary and is the largest local village. It largely consists of informal lodgings for artisanal miners in the area. Five very small rural settlements occur within 2 km of the tenement boundaries and these chiefly consist of wood and thatch huts connected by laterite roads and dirt paths.

 

There is a permanent Gendarme base camp (police post) approximately 2.4 km from Fortuna’s Gamba Gamba field camp. Barrick Gold also operates an exploration camp, Bambadji, adjacent to the Gendarme base camp.

 

5.4.1Sources of Power and Water

 

There is no electricity from the national grid to this area of the country. Electricity is supplied to the exploration camp via diesel generators. Fresh water is pumped from underground aquifers and is treated at an in-house water treatment facility for use at the exploration camp.

 

5.4.2Consumables

 

Apart from some fresh produce and supplies that can be sourced locally from Karakaéné and Gamba Gamba, most consumables and supplies are transported by road to the Project site either from Kédougou or Dakar (depending on availability).

 

5.4.3Labor

 

Of all the nearby settlements, the town of Saraya and the village of Gamba Gamba are the two main sources of laborers. Skilled and professional workers can be sourced from other areas of Senegal.

 

5.4.4Infrastructure

 

Infrastructure at the Project is limited to Boya’s Gamba Gamba field camp. This consists of a series of semi-permanent block accommodations and office buildings, a kitchen and mess hall, laundry, and ablution facilities. Temporary containerized accommodation and ablution units supplement the semi-permanent buildings during periods of increased exploration activities. Partially-enclosed drill core and sample preparation facilities and a basic workshop are also located within the camp boundary.

 

An Orange mobile network cellular tower is located at Karakaéné, and a booster tower has been installed outside of Barrick’s Bambadji camp, some 2.4 km to the northwest of the Boya exploration camp. Cellular signal is generally unavailable across the Project area, although 4G is available occasionally and in certain more favorable locations.

 

October 15, 2025Page 53 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Section 15 discusses the infrastructure assumptions for the PEA.

 

5.5Comment on Section 5

 

In the opinion of the QP, there is sufficient surface area within the granted permit for the open pit, WRSFs, plant, TSFs, associated infrastructure and other operational requirements for the planned life-of-mine and mine plan discussed in this Report.

 

October 15, 2025Page 54 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

6History

 

Prior to 1993 there is no known or recorded systematic mineral exploration carried out on the property, although regionally the area was surveyed by the Bureau de Recherches Géologiques et Minières (BRGM) as part of the Senegal Plan Mineral in 1983.

 

The first recorded exploration activities were carried out by Anmercosa Exploration (Anmercosa, a subsidiary of Anglo American plc) from 1993–1996, as part of a joint venture agreement with Iamgold Corporation (Iamgold). This work was carried out over the larger Bambadji permit which at that time included the area currently referred to as Diamba Sud.

 

From 1997–1998, Ashanti Goldfields Corporation (Ashanti Goldfields) completed further exploration activities as part of a similar joint venture with Iamgold.

 

From 1999–2014, Iamgold conducted exploration activities at the Diamba Sud Project, either individually or as part of a joint venture. The area was relinquished as part of a renewal process for Bambadji and acquired by Boya in 2015.

 

6.1Previous Owners and Results

 

6.1.1Anmercosa, 1993–1996

 

From 1993–1996, Anmercosa conducted regional exploration activities over the Bambadji, Daorala and Boto Project areas. These activities included airborne geophysical surveys along with regional and local geochemistry and early drilling activity. No drilling was conducted on the Diamba Sud area.

 

6.1.2Ashanti Goldfields, 1997–1998

 

Ashanti Goldfields also worked on the Bambadji, Daorala and Boto Project areas and continued to focus on the acquisition of geochemical data and, in addition, conducted some preliminary trenching and pitting in 1997 and 1998.

 

6.1.3Iamgold, 1999–2014

 

From 1999–2014, Iamgold conducted limited prospecting activity over the Bambadji permit. The majority of the work conducted was in the eastern portion of the permit and not on the Diamba Sud area. The western part of the Bambadji permit was relinquished in 2014.

 

6.1.4Boya Gold Pty Ltd 2015–2016

 

The Diamba Sud permit was granted in June 2015 to Boya, a subsidiary of Boya Gold Pty Ltd. (Boya Gold). From 2015 to 2016, Boya conducted regional soil geochemistry for gold using a 400 x 400 m grid, later infilled to 200 x 100 m in places, collecting 1,552 soil samples. Outcrop mapping was completed over a 37 km2 area, and 96 grab samples were collected.

 

Aircore and reverse circulation (RC) drilling was conducted by Minerex drilling. A total of 334 aircore holes with depths between 2 and 56 m were drilled for a total meterage of 3,358 m with 1,160 samples, including quality control samples, sent to the SGS laboratory in Bamako (SGS Bamako) in Mali for analysis. In addition, 9 RC holes, with maximum depths between 40 and 86 m, were drilled over two prospect areas in the south of the DS1 block at Dembakholi and Southern Arc for a total meterage of 650 m with 338 samples, including quality control samples. These samples were sent to SGS Bamako for analysis.

 

October 15, 2025Page 55 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

6.1.5Chesser Resources Ltd. 2017–2023

 

On July 12, 2017, Chesser completed the 100% acquisition of the issued capital of Boya Gold. As a result, Boya became an indirectly wholly-owned subsidiary of Chesser. During the period from 2017–2023, Chesser completed the drilling of 3,848 auger holes, totaling 34,174 m, targeting areas of potential gold mineralization.

 

Chesser commenced RC drilling in 2019. A total of 10 geochemical targets were RC drilled, totaling 476 holes and 58,396 m. The first core drilling at Diamba Sud was conducted in November 2019 over Areas A and D. In total, 127 core holes totaling 19,805 m were drilled between November 2019 and July 2023.

 

6.2Geophysics

 

Chesser’s in-house geophysics team collected resistivity, conductivity and chargeability data over a large part of the DS1 block. In addition to induced polarization (IP), Chesser acquired high resolution magnetic data for the DS1 and DS2 blocks (Figure 6.1 and Figure 6.2). Whilst these datasets provided numerous additional prospects, Chesser had only drilled the surface geochemical prospects prior to the Project acquisition by Fortuna.

 

Figure 6.1 Second Vertical Derivative, Total Magnetic Intensity (TMI) at the Diamba Sud Project

 

 

Figure prepared by Fortuna, 2025

 

October 15, 2025Page 56 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 6.2 Magnetic Analytical Signal for the Diamba Sud Project

 

 

Figure prepared by Fortuna, 2025

 

6.3Other Work

 

Given the geological complexities encountered in the RC and core drilling campaigns Chesser commissioned petrographic studies of selected samples to be conducted by Dr. James Lambert-Smith at Cardiff University, UK.

 

A structural study of selected cores was also conducted by TECT Consulting, Cape Town. Both studies assisted with the understanding of the mineralization models and target selection during various drilling campaigns.

 

A mineral resource estimate was prepared in 2021. Chesser also began extensive environmental studies as well as community and stakeholder engagement programs.

 

6.4Production History

 

There has been no commercial production at the Diamba Sud Project as at the effective date of this Report.

 

October 15, 2025Page 57 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

7Geological Setting and Mineralization

 

7.1Regional Geology

 

The Diamba Sud Project is located within the West African Craton (WAC). The WAC consists of three domains:

 

·The Northern African Reguibat Shield.

 

·The Leo–Man Shield of sub-Saharan West Africa.

 

·The Kedougou–Kenieba Inlier (KKI) northwest of the Leo–Man Shield in the Sahel region, which hosts the Diamba Sud deposits.

 

Regional geology is shown in Figure 7.1.

 

Figure 7.1 Regional Geological Map of the Leo–Man Shield and Kedougou–Kenieba Inlier, West Africa Craton

 

 

West African Craton, Sourced from Masurel et al. (2022).

 

October 15, 2025Page 58 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The WAC had a number of deformation events and a complicated metamorphic history with evidence of two main Paleoproterozoic orogenic cycles. The first phase of deformation (D1) between ca. 2,140–2,135 Ma was the Eoeburnean cycle, which caused region-wide contractional deformation and metamorphism. This was followed by the Eburnean cycle (D2), which commenced with basin formation between ca. 2,135 and 2,105 Ma. Basin formation continued into contractional deformation, basin inversion and predominantly greenschist metamorphism from ca. 2,105–2,100 Ma. Most of the gold mineralization in the region is associated with the Eburnean deformational event (Lambert-Smith et al., 2020). The Eburnean cycle ended at ca. 2,100–2,095 Ma with wrench-style deformation (Masurel, Quentin et al. (2022)). Docking of the Archean Kenema-Man Domain with the Paleoproterozoic rocks also occurred ca. 2,095 Ma. Reverse, normal and strike-slip faulting occurred throughout the western and southern parts of the WAC, both during and after high potassium-magmatism, between ca. 2,095–2,060 Ma (Masurel, Quentin et al. (2022)).

 

The Birimian of West Africa consists of shear-bounded, linear and arcuate trending volcanic belts/arcs that have north to north–northeast trends separated by wide metasedimentary basins. Large granitic batholiths intrude the volcanic and sedimentary rocks, which were accreted, deformed, and underwent greenschist metamorphism during the Eburnean Orogeny at about ~2.1 Ga (Masurel, Quentin et al. (2022)).

 

The Diamba Sud Project is located northwest of the Leo–Man Shield in the Kedougou–Kenieba Inlier (KKI). The KKI, an area of around 15,000 km2 is separated from the Leo–Man Shield by the overlying Neoproterozoic Taoudeni sandstones. These sediments unconformably overly all of the margins of the inlier apart from the western margin that is bounded by the Pan-African Mauritanides Belt (Lambert-Smith et al., 2016).

 

Evidence for the two main Paleoproterozoic orogenic cycles was observed in the KKI, with the first orogeny (D1) associated with reverse faulting and recumbent and overturned folding, and the second orogeny (D2) associated with a period of transcurrent deformation which involved upright folding and sinistral displacement along north-striking shear zones (Allibone et al., 2020). A third phase of transtensional deformation (D3) was identified to the east of the Falémé River, the timing of which coincides with gold mineralization at Barrick Gold’s Loulo deposit (Lawrence et al., 2013).

 

In the KKI, two major crustal shear zones were identified in the region, with both having proximal relationships to gold deposits. Additionally, other smaller, less continuous structures were identified or speculated upon in the inlier (Allibone et al., 2020; Diallo et al., 2020).

 

The northeast-striking Main Transcurrent Zone (MTSZ) forms a tectonic contact between the Dialé-Daléma Basin to the east and the Mako Volcanic Belt to the west. A number of gold deposits are associated with the MTZ, including Tomboronkoto, Massawa and Makabingui, with the Petowal and Sabodala deposits occurring further to the west but still within the structural vicinity of the MTZ.

 

The north-striking Senegal-Mali Shear Zone (SMSZ) initiated as a sinistral transpressional brittle-ductile shear zone during the phase of D2 deformation (Lawrence et al., 2013; Lambert-Smith et al., 2016). It is a 1–10 km wide corridor of varying deformation styles that bounds the western contact of the Kofi Series. It was a major conduit for hydrothermal fluids in the region with several gold deposits recognized on either side of the shear zone including the Gounkoto, Fékola and Boto deposits within the Kofi series to the east, and the Karakaéné deposit within the Falémé Volcanic Belt to the west. Although the presence of the SMSZ has been questioned recently (Allibone et al., 2020

 

October 15, 2025Page 59 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

and Lambert-Smith et al., 2020), the possibility of the Falémé Batholith intruding and stitching a pre-existing regional structure where the SMSZ was delineated has also been postulated as a possible reason why this regional-scale lineament is not observed today (Allibone et al., 2020). Additionally, discontinuous structures observed today along where the SMSZ is interpreted to strike, may be the result of tectonic sealing of this regional-scale feature.

 

From east to west, the stratigraphy of the KKI consists of the following:

 

·The Kofi series: consists of sedimentary rocks which are made up of a monotonous package of argillites, siltstones, and sandstones with subordinate volcaniclastic rocks, marbles, polymictic conglomerates and immature sandstones (Allibone et al., 2020; Lambert-Smith et al., 2016). The series is carbonate-rich, predominantly consisting of dolomitic marls, to the west of the series in close proximity to the Falémé Volcanic Belt (Lambert-Smith et al., 2016). The age of the Kofi series was constrained using detrital zircons to between ca. 2,153 and 2,113 ± 7 Ma with a maximum depositional age of 2120 Ma (Allibone et al., 2020). Dips of units within the Kofi series vary from 40˚ to greater than 50˚ and the units strike from north–-northwest to north–northeast within the Loulo mining district. The series is intruded by dolerite to monzodiorite dykes and small stocks of quartz–feldspar porphyry as well as smaller dykes belonging to the Falémé Volcanic Belt (Lambert-Smith et al., 2016). The larger Gamaye (2,045 ± 27 Ma) and Yatea monzogranite plutons also intrude into the Kofi series (Lambert-Smith et al., 2016).

 

·The Falémé Volcanic Belt: subdivided into the plutonic and volcanic Falémé batholith and volcaniclastic and sedimentary Bambadji Formation (Allibone et al., 2020; Lambert-Smith et al., 2020). It is a ~16 km wide, north–northeast-trending belt that is bounded by the Kofi series to the east and the Dialé-Daléma Series to the west (Lambert-Smith et al., 2016). The eastern margin of the belt is composed of porphyritic monzonite, quartz monzonite, and minor granite of Highway pluton with dated ages of 2,076 ± 25 and 2,080 ± 11 Ma and the >100 km2 quartz monzodiorite and granodiorite Balangouma pluton with ages of 2,118 ± 16 Ma (Allibone et al., 2020). To the center–south of the belt, the >100 km2 Boboti pluton with an age of 2,080 ± 0.9 Ma outcrops alongside the South Falémé pluton composed of albitized diorites and magmatic breccias (2082 ± 1.1 Ma) and the Garaboureya pluton (Lambert-Smith et al., 2016). Volcanic and subvolcanic rhyolites with ages ranging from 2,064 ± 30 Ma to 2,099 ± 4 Ma also occur within the belt (Lambert-Smith et al., 2016). The western margin is composed of dioritic, granodioritic, granitic and leucogranitic rocks (Allibone et al., 2020). Other smaller plugs, stocks and dykes also occur throughout (Lambert-Smith et al., 2016; Allibone et al., 2020). Within the belt, the Bambadji Formation is composed of sandstones, siltstones, carbonates, volcaniclastic, conglomeratic, and fine-grained massive rocks which make up xenolith screens and roof pendants within the Falémé batholith (Allibone et al., 2020; Lambert-Smith et al., 2016). These rocks have dips <35˚ and unconformably overlie the Kofi series (Allibone et al., 2020). The Bambadji Formation rocks were deposited between ca. 2,085–2,071 Ma (Allibone et al., 2020). The Falémé Volcanic belt hosts hypogene magnetite and supergene enriched iron skarn deposits (Lambert-Smith, 2014).

 

·The Dialé-Daléma series: Made up of predominantly volcaniclastic, siliciclastic, and subordinate carbonate rocks that are isoclinally folded (Lambert-Smith et al.,

 

October 15, 2025Page 60 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

2016). It is bounded by the Falémé Volcanic Belt to the east. The Main Transcurrent Zone forms a tectonic contact in the west with the Mako Volcanic Belt. Zircon dating of basalts from the series return an age of 2,165 ± 0.9 Ma (Lambert-Smith et al., 2016). The peraluminous two-mica S-type Saraya Batholith intrudes into the southern–central part of the KKI and into the Dialé-Daléma series. The batholith covers an area of ~2,000 km2 and is made up of several plutonic bodies of granodiorite to granite composition, which were emplaced between 2,079 ± 2 Ma and 2,061 ± 15 Ma (Lambert-Smith et al., 2016).

 

·The Mako Volcanic belt: The 20–40 km wide north–northeast-trending Mako Volcanic Belt is composed of bimodal volcanic rocks and forms the westernmost outcrop of Paleoproterozoic rocks in the KKI (Lambert-Smith et al., 2016). It is bounded by the Mauritanides belt to the west and shares a tectonic contact (MTZ) with the Dialé-Daléma series to the east. The belt is composed of pillowed tholeiitic basalts, dolerites, and gabbro’s intercalated with pyroclastics, rhyolites, felsic tuffs and subordinate ultramafic rocks, and clastic and carbonaceous rocks (Dioh et al., 2006). The 120 km long and 20 km wide Kakadian plutonic complex intrudes into the Mako Volcanic Belt on the western edge of the belt (Dioh et al., 2016). It consists of four main units; (1) the tonalitic to dioritic Sandikounda amphibolite-gneiss complex (SAG) with an age of 2,205 ± 15 Ma; (2) the hornblende-gabbro, diorite, migmatite and hornblendite Sandikounda layered plutonic complex (SLPC) with a crystallization age of 2,171 ± 9 to 2,158 ± 8 Ma; (3) the tonalite and granodiorite Laminia dated at 2,138 ± 12 to 2,105 ± 8 Ma and monzogranite Kaourou (2,079 ± 6 Ma) plutonic complex (LKPC); and (4) the biotite-granodiorite Badon pluton to the south of the complex with an age of 2,198 ± 2 Ma (Lambert-Smith et al., 2016).

 

7.2Local Geology

 

7.2.1Lithologies

 

The Project is located within the Loulo Mining district within the Kofi series. Numerous gold deposits held by third parties occur within the vicinity of the Diamba Sud permit, including the Karakaéné, Gounkoto, Yalea, and Gara deposits alongside several other satellite deposits.

 

Lateritic weathering and duricrust formation is still active in the region. Apart from hills and resilient lithologies, much of the terrain is covered by lateritic material resulting in limited exposure of sub-cropping geology.

 

Oxidation depth in the region is highly variable, but is generally several tens of meters, occasionally down as far as 70–80 m. In some areas near major drainages, thick colluvial material cover large tracts of land and close to the Falémé River, small lenses of lateritized alluvial deposits can be observed. Additionally, colluvium is also observed on the slopes of the Falémé iron skarn hills.

 

The SMSZ runs adjacent to the contact between the Falémé Volcanic Belt and the Kofi series to the east of the permit. Faults in the local area are generally north- to northeast-striking, with predominantly north-striking bedding and foliation (Allibone et al., 2020).

 

The geology local to the Diamba Sud Project is dominated by plutons belonging to the Falémé Volcanic Belt as well as roof pendants and xenolith screens of the Bambadji Formation. This formation also uncomformably overlies the Kofi series sediments that subcrop to the east (Allibone et al., 2020).

 

October 15, 2025Page 61 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

At the westernmost extent of the Kofi series, north-striking altered marbles and strongly albilitized lithologies with identified and unidentified protoliths are prevalent (Allibone et al., 2020). The Kofi series in the area is dominated by undifferentiated sandstones and siltstones with minor conglomerate and breccia (Lambert-Smith et al., 2020). Several dolerite dykes of various orientations intrude the Kofi series and plutonic rocks of the Falémé Volcanic Belt.

 

The Falémé Volcanic Belt within and surrounding the permit area is made up of the Highway pluton and a range of smaller plugs and dykes. The Balangouma pluton and heterogeneous granitoids adjacent to it occur to the north of the permit, with the Boboti and Garaboureya plutons outcropping to the south of the permit. The Bambadji Formation is also mapped to subcrop within and surrounding the permit, forming xenolithic screens and roof pendants within the Falémé Volcanic Belt, as well as unconformably overlying the Kofi series to the east (Allibone et al., 2020).

 

Iron endo- and exoskarns, some structurally controlled along faults, occur within the Falémé Volcanic Belt, the Bambadji Formation and on western portions of the Kofi series (Lambert-Smith et al., 2020). A genetic link between iron skarn mineralization and gold mineralization has been proposed based on the proximal locations of these deposits, the involvement of high temperature FeCl2-rich brine, and from mineral paragenesis at the Sadiola deposit (Allibone et al., 2020). Additionally, the Karakaéné Ndi iron skarn, north of Afrigold’s Karakaéné mine, has been a target of significant artisanal workings. Named iron skarns inside and within the vicinity of the Project include the Karakaéné Mbah, Karakaéné Ndi and Kouroudiako iron skarns, with other unnamed skarns of various volumes also outcropping in the region (Lambert-Smith et al., 2020).

 

Sedimentary sequences not confirmed to belong to the Bambadji Formation and possibly belonging to the Kofi series or part of the Diale-Dalema basin are also present within the permit area. These consist of marls, carbonates, polymictic matrix-supported breccias and intensely hydrothermally altered lithologies, some of the protoliths for these lithologies cannot be identified. Granites belonging to the Falémé batholith intrude into these sedimentary units.

 

Both the Falémé batholith and sedimentary sequences are intruded by late, predominantly sub-vertical, diorite dykes. A number of iron endo- and exoskarns also occur in the area and these form prominent topographic highs, inside and outside of the permit.

 

7.2.2Tectonic Setting

 

The Birimian rocks of the Kédougou-Kéniéba inlier have been affected by a polycyclic deformation and metamorphic history related to the Eburnean Orogeny Three major deformation phases were identified: a collisional phase (D1) associated with the initial accretion of the Birimian, and two transcurrent phases (D2–D3) associated with the formation regional-scale north-south shear zones. At the scale of the Kédougou-Kéniéba inlier, the D2–D3 deformation is clearly related to the two regional transcurrent ductile structures i.e.: the northeast-trending MTZ, and the SMZ

 

The tectonic history of the region can be summarized as follows:

 

·Early Proterozoic: deposits of clastic, pelitic, greywacke, carbonate, and volcano-sedimentary units.

 

·Eburnean Orogeny: metamorphism (greenschist facies) of sediments to form quartzites, schists, and marbles, (Birimian D1, D2, D3).

 

·Late Proterozoic: uplift, erosion, and peneplanation of Birimian rocks.

 

October 15, 2025Page 62 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Late Proterozoic to Carboniferous: deposition of clastic sediments (mostly sandstones) of the Taoudeni Basin.

 

7.2.3Alteration

 

Alteration at Diamba Sud is dominated by at least two successive phases of albite ± carbonate ± hematite alteration, with localized potassium (K)-feldspar alteration in mineralized and intensely altered samples. Several lithologies also display albitization, tourmalinization, and sericite–chlorite alteration.

 

Albitization has affected the host rocks at Diamba Sud. This early phase of albitization is generally relatively iron poor, producing more muted pale orange or beige colors than later albite–hematite–carbonate alteration. Similarly, an early phase of tourmalinization is also seen.

 

In general, moderate to intense albite–hematite–carbonate ± quartz–chlorite–tourmaline–pyrite alteration has affected most lithologies to varying degrees.

 

Almost all lithologies exhibit (relatively) late carbonate alteration in the form of carbonate (mostly dolomite) porphyroblasts that overprint the host lithologies. The precise paragenesis of these porphyroblasts is unclear but they are likely related to the later stage of carbonate ± quartz–chlorite–tourmaline–pyrite veining and breccia cement that affects a significant number of mineralized zones

 

Sericitization of feldspars is also widespread and is likely to post-date the main phase of alteration.

 

7.2.4Mineralization

 

Mineralogy related to mineralization at Diamba Sud is relatively simple, consisting dominantly of pyrite with minor pyrrhotite, chalcopyrite and magnetite. Primary gold is generally associated with pyrite or as free millimeter scale grains.

 

There does not appear to be a preferential host lithology, with gold mineralization (>1 g/t Au) hosted in most rock types, except for weakly-altered fine grained sedimentary rocks, although there is a bias towards hydrothermally brecciated carbonate units. Most of the mineralization is hosted in a combination of disseminated pyrite, minor veinlets and hydrothermal breccia cement.

 

The predominant mineralization style is orogenic lode gold with supergene enriched saprolitic zones specifically in Area D. This style of mineralization can occur as veins or disseminations in altered (often silicified) host rocks or as pervasive alteration over a broad zone.

 

Gold mineralization is both structurally and lithologically controlled and can occur within granites, argillites, tectonic breccias and carbonates. Supergene enrichment of the near surface in some deposits has also taken place with significant mineralization of this style present within Area D.

 

Most of the mineralization at Diamba Sud is hosted within variably brecciated sedimentary, predominantly carbonate units, where structures that acted as fluid conduits intersected the units allowing fluid flow. Hydrothermal breccia zones within Area A host some of the highest grades within the hypogene mineralized zones from Diamba Sud. The high permeability and porosity of these rocks, in addition to friction and attrition generated at clast boundaries due to strain, allowed fluid to move into this unit and deposit the auriferous pyrite. A precursor phase of albitization and hematization prepared

 

October 15, 2025Page 63 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

the breccias for a later phase of auriferous pyrite-hematite-albite-carbonate-quartz mineralization.

 

Mineralized structures also occur throughout the intrusions in the area, with auriferous pyrite ± carbonate veins exploiting shear zones that cut through the granitoids.

 

In Area D, mineralization which occurs within carbonate lithologies exploits styolites that were opened and acted as fluid conduits for auriferous pyrite-bearing fluids. Altered marls, sandstones and tectonic breccias also host mineralization. However, supergene enrichment appears to occur predominantly over the altered and bleached marls. Mineralization within the oxide is associated with goethite, hematite and kaolinite alteration assemblages.

 

7.3Deposit Geology

 

Exploration has identified seven gold deposits and several prospects located in the DS1 block. These include the Area A, Area D, Karakara, Kassassoko, Western Splay, Moungoundi, and Southern Arc deposits, as well as the Gamba Gamba North, Area A North, Area D South, and Kouroudiako prospects. These deposits all form part of a single mineralizing system with local variability influenced mainly by intensity of brecciation, alteration and later supergene processes. The Bougouda prospect is located in the DS2 block. The deposits and prospects within the DS1 block are shown in Figure 7.2. The location of the Bougouda prospect is provided in Figure 10.1.

 

The relationship between the different structural regimes present remains unclear with work continuing to resolve the relationship and timing with the broader SMSZ and intrusion related history. Strong metasomatism and phases of hydrothermal and tectonic brecciation have complicated determining key associations.

 

The paragenetic sequence has been divided into two main stages based on consistently overprinting relationships. During stage I early fluids cause hematite carbonate silica ± albite ± tourmaline alteration and is associated with fine fractures, brecciation and disseminated pyrite. Tectonic breccias were also active at this time as evidence by fragments of hematite altered dolomite.

 

The early fluids are interpreted as being oxidizing (hematization) and slightly alkaline (albitization). If the early fluid was not CO2 rich to start with, it would have become so after equilibration with the carbonate rich sedimentary sequence.

 

Stage II carbonate ± quartz veins and hydrothermal breccia always overprint Stage I parts of the paragenesis (including tectonic breccias). These breccias formed during interpreted explosive decompression which resulted in significant dilation and intense carbonate alteration/replacement. The carbonate alteration can be locally intense and texturally destructive to the point where it can be difficult to identify the protolith.

 

The bulk of the gold was deposited during Stage II with gold mineralization associated with late carbonate ± quartz veining and hydrothermal breccia overprinting dolomite, monzonite intrusive and tectonic breccia. Gold mineralization is closely associated with finely-disseminated pyrite.

 

It is also recognized that, in contrast to much of the typical Birimian style mineralization, mineralization is preferentially hosted in breccia bodies and does not generally follow simple planar structures. Determining the path of these breccia bodies (fluid pathways) is a focus for further exploration. Much of what presents as broad-scale fault and fracture zones is generally post mineralization.

 

October 15, 2025Page 64 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 7.2 Geological Map of Diamba Sud DS1 Block Showing Deposits and Prospects

 

 

Figure prepared by Fortuna, 2025

 

October 15, 2025Page 65 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

7.3.1Area A

 

Area A comprises volcano-sedimentary, sedimentary rocks and hydrothermal breccias that appear to be tightly folded into an antiformal structure sandwiched between granodioritic intrusions (Figure 7.3).

 

Figure 7.3 Schematic Cross-Section of Area A Looking North

 

 

 

Figure prepared by Fortuna, 2025

 

Gold mineralization coincides with the breccia–carbonate and breccia–-intrusive contact zones, with brecciation providing conduits for mineralizing fluids, and further enhanced by alteration and degradation of some of the carbonate units, likely associated with emplacement of acidic mineralizing fluids. The mineralization trends north–south and at depth is moderately dipping (40–50º) to the west. Near surface, there is evidence to suggest that the antiform is refolded towards the east and the mineralized zones are more shallow dipping towards the west. Mineralization has been drill-defined along an approximate 500 m strike with a cumulative width of up to 200 m across strike. Mineralization continuity tends to reflect the underlying distribution of brecciated carbonate units with individual zones able to be traced over several tens to hundreds of meters, and remains open at depth and will be subject to future drilling.

 

Mineralization is largely represented by pods and agglomerations of pyrite–gold with occasional chalcopyrite–galena, hosted in strongly albite–hematite ± potassic feldspar–quartz-altered hydrothermal breccias. Higher-grade zones appear to be related to fluids damming up against less permeable rocks at the top of the structure. Although there is a

 

October 15, 2025Page 66 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

strong geochemical anomaly above Area A, most of the mineralization is seen at depth in fresh rock and there is very little oxide mineralization.

 

Structurally Area A is located on the south side of a northeast–southwest-trending splay of the SMSZ.

 

7.3.2Area D

 

The Area D deposit is dominated by carbonates (marls, limestone), sandstones, greywackes, tectonic and hydrothermal breccias (Figure 7.4) with granodioritic intrusions to the immediate southeast.

 

Figure 7.4 Schematic Cross-Section of Area D Looking North

 

 

Figure prepared by Fortuna, 2025

 

These rocks dip gently (30–45º) to the northwest, but some localized folding is noted. Granodiorite lithologies are seen at depth to the east of the zone where it merges with the western extension of Area A. Structurally Area D is on the northern side of the SMSZ splay, and locally the rocks appear less fractured and deformed than at Area A, however Area D is notable for the depth of weathering which reaches 70 m in places.

 

Similar to Area A, gold mineralization coincides with the hydrothermal and tectonic breccia-carbonate zones, with brecciation providing conduits for mineralizing fluids, and further enhanced by alteration of some of the carbonate units. Mineralization is largely represented by pods and agglomerations of pyrite–gold, hosted in strongly albite–hematite ± potassic feldspar–silica altered hydrothermal breccias, although the extensive oxidation and supergene enhancement to a depth of up to 70 m makes identification of the host lithology and original sulfide species difficult.

 

Mineralization is continuous as a series of lenticular zones across several drill sections, for 50 to 150 m and has been drill defined along a 500- m strike with a cumulative cross-

 

October 15, 2025Page 67 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

strike width of 500 m. Mineralization occurs at depth within the fresh rock, but it is more sporadic and lower grade.

 

7.3.3Karakara

 

The Karakara deposit is located 1.2 km southwest of Area D coincident with the interpreted northeast–southwest-trending structure associated with Area A and Area D.

 

The geology of Karakara is structurally complex but at its simplest it is a series of intercalated carbonate sediments, sandstones and volcaniclastic rocks with a variable dip to the east, and sandwiched to the east and west by granitic intrusions. Folding of the sediments is observed and this may be a control on the mineralization (Figure 7.5). Unlike Area D, the weathering profile is shallow at generally less than 5 m.

 

Figure 7.5 Schematic Cross-Section of Karakara Looking North

 

 

Figure prepared by Fortuna, 2025

 

Gold mineralization is predominantly associated with quartz–carbonate–hematite–albite–pyrite alteration within hydrothermally-altered and brecciated sedimentary rocks near intrusive contacts, with these interpreted as favorable sites for increased deformation and brecciation and hydrothermal fluid flow. Some mineralization in the granites has also been observed as small scale shear zones. Pyrite is the dominant sulfide species with minor associated pyrrhotite.

 

Mineralization at Karakara has been drill defined along a 400 m by 50 m zone and remains partially open at depth.

 

October 15, 2025Page 68 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

7.3.4Kassassoko

 

The Kassassoko deposit is located 2.5 km south of Karakara and has been exploited by artisanal miners since 2022. Mineralization at Kassassoko was discovered via several altered granite rock chips recovered from artisanal pits returning elevated gold grades. Weathering is shallow at less than 5 m below surface.

 

The geology at Kassassoko is characterized by a series of late-stage northeast–southwest-oriented aphanitic diorite dykes, clearly delineated within the high-resolution magnetic images. These dykes intrude near-vertically into the granite host. There is also an amorphous porphyritic diorite that appears to have intruded sub-horizontally from the southeast of the area and an extensive carbonate sequence is noted to the west (Figure 7.6).

 

Figure 7.6 Schematic Cross-Section of Kassassoko Looking North

 

 

Figure prepared by Fortuna, 2025

 

Mineralization is hosted within the granite, which has undergone alteration to varying degrees of intensity by albite–hematite–pyrite–silica alteration minerals. Mineralization is typically observed adjacent to the diorite dykes within granite, indicative of a relationship between these intrusive contacts and the distribution of gold within the deposit.

 

Mineralization has been drill defined along a 600 m strike and 150 m across strike and remains open at depth. Further drilling is planned to test the depth extensions.

 

Geological mapping in the area has delineated the weathered granite host at surface adjacent to aphanitic diorite dykes. Northeast- to southwest-trending features evident in high-resolution magnetic images support the extension of this zone along a strike of approximately 700 m to the northeast, towards the Southern Arc prospect and to the southeast of Kassassoko, towards the permit boundary.

 

October 15, 2025Page 69 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

7.3.5Western Splay

 

The Western Splay deposit is located approximately 5 km to the southwest of Area A. This deposit was first recognized by grab sample anomalies in 2016 and has been subject to some artisanal mining since discovery.

 

Geology is dominated by granite and diorite/gabbro rocks intruding a suite of volcanoclastic tectonic breccias and sedimentary rocks including carbonates, resulting in the rocks being locally brecciated and highly altered. A late phase porphyritic diorite intrusion crosscuts all earlier lithologies. Gold mineralization is associated with the granite/metasediment contact and also hosted in silica–hematite–albite–carbonate-altered limestones and hydrothermal breccias (Figure 7.7).

 

Figure 7.7 Schematic Cross-Section of Western Splay Looking North

 

 

Figure prepared by Fortuna, 2025

 

Mineralization is largely represented by pods and agglomerations of pyrite–gold hosted in strongly albite–hematite ± potassic feldspar–quartz-altered hydrothermal breccias. Drill defined continuity has been shown along strike for 350 m, extending across strike for an aggregate of up to 250 m. Several sections remain open at depth beyond the deepest drilling to 150 m, with further deeper drilling planned.

 

7.3.6Moungoundi

 

The Moungoundi deposit is located approximately 1.7 km to the southwest of Karakara. It was discovered by soil geochemistry and was subject to artisanal mining activities from 2018 to 2022.

 

The main lithologies encountered are carbonates, often associated with magnetized ferrous skarn, tectonic breccias, sandstones and hydrothermal breccia, and granite. These assemblages are crosscut by later sub-horizontal diorite dykes.

 

October 15, 2025Page 70 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Gold mineralization is interpreted to strike northeast and dip to the northwest, becoming subvertical in the east. Mineralization is associated with strong silica–carbonate–-hematite–albite alteration, accompanied by pyrite, and is mostly hosted by tectonic breccias, carbonates and hydrothermal breccias along the contact zones of the intrusive bodies (Figure 7.8).

 

Figure 7.8 Schematic Cross-Section of Moungoundi Looking North

 

 

Figure prepared by Fortuna, 2025

 

7.3.7Southern Arc

 

Located approximately 4 km south of Area A, Southern Arc was one of the earliest identified targets at Diamba Sud, located by soil and grab sampling in 2015. It has been subject to some artisanal mining since discovery.

 

The main lithologies comprises an intercalated sequence of variably porphyritic diorite, volcaniclastics and carbonate/limestone units with extensive tectonic and hydrothermal breccia development, and extensive metasomatism and hematitic alteration making identification of the protolith complicated at times. The carbonate sequences are generally preferentially mineralized, especially where brecciated, hosting extensive pyrite (plus gold) development (Figure 7.9). Weathering is shallow to generally less than 5 m depth.

 

Gold mineralization is interpreted to strike northeast and dip 30–50º to the northwest, in the east. Mineralization is associated with strong silica–carbonate–-hematite–albite alteration, accompanied by pyrite, and is mostly hosted by tectonic breccias, carbonates and hydrothermal breccias.

 

Mineralization has been drill defined over an area of 750 x 300 m to a depth of approximately 150 m where it remains open at depth and along strike indicating potential for further extension. Additional drilling is planned to better define the full extent of Southern Arc mineralization, both along strike and at depth.

 

October 15, 2025Page 71 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 7.9 Schematic Cross-Section of Southern Arc Looking Northeast

 

 

Figure prepared by Fortuna, 2025

 

7.4Comment on Section 7

 

In the opinion of the QP, knowledge of the settings, lithologies, and structural and alteration controls on mineralization at the Area A, Area D, Karakara, Kassassoko, Western Splay, Moungoundi and Southern Arc deposits is sufficient to support Mineral Resource estimation.

 

October 15, 2025Page 72 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

8Deposit Types

 

8.1Mineral Deposit Type

 

In keeping with the majority of the gold deposits found in the KKI, gold mineralization at Diamba Sud is considered to be of the orogenic type.

 

The KKI is associated with Paleoproterozoic-aged epigenetic gold deposits which occur in 2.25 Ga to 1.90 Ga granite-greenstone belts of the Birimian which were deformed and metamorphosed during the Paleoproterozoic Eburnean orogeny. Despite the abundance of known deposits, much of the region remains poorly explored.

 

The orogenic gold deposits in the Birimian Province have been classified into three groups: (pre-, syn-, and post-orogenic). The characteristics of the mineralization seen at Diamba Sud are most similar to those of the post-orogenic class.

 

Orogenic gold deposits exhibit a range of styles depending on metamorphic grade, setting, fluid type, and fluid/confining pressure. They often include spatially associated quartz shear veins, extension vein arrays, shear zone and disseminated sulfide styles. Vein dominated styles contain quartz–carbonate ± albite ± K-feldspar with up to 10% sulfides (pyrite with minor base metals) and associated Fe-carbonate albite, chlorite, scheelite, fuchsite and tourmaline as associated vein and hydrothermal alteration assemblages. Vein systems and shear zones are often semi-brittle in style, including both brittle veining styles (extension veins and fault hosted brecciated shear veins), which alternate with periods of ductile deformation, producing sequences of early folded and younger less strained vein systems during latter periods of regional deformation at peak to immediate post-peak metamorphic timing. Sigmoidal extension vein arrays are often present and are typical of the deposit style. This deposit type often also has great vertical extent providing potential for discovery of significant down dip and down plunge continuations of mineralized zones. Globally orogenic deposits are typically localized adjacent to major faults (shear zones) in second and third order shear zones within volcano-sedimentary (greenstone and sedimentary) belts between granitic domains. Fluid sources for these systems are often controversial: they generally involve a dominant metamorphic fluid component, consistent with their setting and relative timing, however in many districts, there is evidence for a contributing magmatic fluid inducing early oxide-rich alteration assemblages.

 

8.2Comment on Section 8

 

The gold deposits in Diamba Sud are classified as Birimian-style mesothermal orogenic gold deposits. Although not formally classified as such, the gold deposits of Diamba Sud show similarities to the post-collisional, atypical orogenic Loulo/Falémé-style deposits (Thebaud et al., 2020). This tentative classification is based on the correlation between the mineral assemblages, geochemistry and the structural and lithological controls on mineralization with that of the nearby deposits classed as the same type which sit in close proximity to the SMSZ.

 

In the QP’s opinion an exploration model that uses an orogenic deposit model is reasonable as a regional targeting tool.

 

October 15, 2025Page 73 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

9Exploration

 

9.1Historical Exploration Activities

 

Exploration activities conducted by owners of Diamba Sud prior to Fortuna are detailed in Section 6 of this Report.

 

9.2Exploration Activities Conducted by Fortuna

 

Since Fortuna’s acquisition of Chesser in September 2023, exploration work has focused primarily on resource definition and extension drilling at the nine advanced prospect areas within the permit as detailed in Section 10 of this Report.

 

Auger geochemistry is ongoing, with a small program of infill auger conducted in early 2025 between Karakara and the southern boundary of the DS1 block. A total of 645 holes were completed for 4,169 m. Auger collars are recorded with a hand-held DGPS, samples are logged into a portable device and samples analyzed by Olympus Vanta portable X-ray fluorescence (XRF) analyzer, using Portable ppb’s proprietary DetectORE process. A total of 22 samples returned results >100 ppb Au. One sample located ~300 m northwest of Western Splay returned 510 ppb Au. Sample locations with their assays are shown on Figure 9.1.

 

October 15, 2025Page 74 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 9.1 Fortuna Auger Sampling Results Across Portion of Northern Block of Daimba Sud Property

 

 

 

Figure prepared by Fortuna, 2025

 

9.3Exploration Potential

 

9.3.1Bougouda

 

The Bougouda prospect is located in the DS2 block, approximately 20 km south of Areas A and D.

 

The main lithology at Bougouda is an altered dioritic intrusive crosscut by multiple northeast trending shear zones. Gold mineralization is hosted by steeply dipping quartz-hematite-pyrite carbonate veins within the shear zones.

 

As of the effective date of this Report, four such quartz veins with a total length of 1,800 m have been discovered at Bougouda but artisanal mining activities on several other quartz veins indicate further potential.

 

9.3.2Gamba Gamba North

 

The Gamba Gamba North prospect is located in the far west of the DS1 block and abuts the boundary with the adjacent Afrigold mining license.

 

The prospect is divided into two areas, west and east, with the west area being the most interesting, dominated by granite and volcaniclastics. The target area is approximately

 

October 15, 2025Page 75 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

250 m long and 150 m wide. In the western part of the tenement the geology comprises volcaniclastic lenses within a granitic intrusion with late north south trending diorite dykes. Gold mineralization is sporadic and hosted in the north–south-striking and steeply west dipping volcanoclastic/granite contact. The eastern zone is dominated by carbonates and volcaniclastics and is yet to be evaluated.

 

9.3.3Other Prospects

 

The other prospects identified to date including Area A North, Area D South and Kouroudiako have been identified as extensions of existing mineralized trends and, as of the effective date of this Report have received limited or no additional exploration work.

 

Potential for further mineralization is good within the Diamba Sub permit, with several surface geochemical anomalies still untested by drilling, several others have been drilled with encouraging results but not sufficiently to estimate resources and a wide variety of geophysical targets generated by Chesser are yet to be drill tested.

 

The structurally complex nature of the permit area dictates that potential mineralization is likely to be of a similar nature and size as the deposits already drilled. Thus far the majority of the drilling conducted has been on near-surface geochemical anomalies. There is some evidence to support mineralization at depth and the possibility of blind mineralization that does not reach surface also exists.

 

9.4Comment on Section 9

 

In the opinion of the QP:

 

·The mineralization style and setting of the Diamba Sud Project is sufficiently well understood to support the Mineral Resource estimation.

 

·Exploration methods are consistent with industry practices and are adequate to support continuing exploration and Mineral Resource estimation.

 

·Exploration results support Fortuna’s interpretation of the geological setting and mineralization.

 

·Continuing exploration may identify additional mineralization that may warrant drill testing.

 

October 15, 2025Page 76 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

10Drilling

 

10.1Drilling Conducted by Chesser

 

10.1.1Auger Drilling

 

Within the Diamba Sud permit, a first pass auger drill program on a 400 x 100 m grid was completed. Follow up auger infill programs on a 200 x 25 m grid, and later 25 x 25 m grids were completed, targeting zones that produced anomalous gold from the first pass auger drill program. During both the first pass and infill programs, auger drilling was routinely halted at 3 m into the weathered bedrock/saprolite. Typically, each auger hole was drilled through three layers:

 

·Ferricrete.

 

·The mottled zone between ferricrete and saprolite.

 

·Saprolite.

 

A representative sample of each of these layers was collected, with samples from the saprolite and mottled zone sent to the SGS Bamako laboratory for analysis.

 

In total 3,848 auger holes were drilled, totaling 34,174 m. All samples were assayed for gold at SGS Bamako, and the majority were also analyzed with a Niton XL5 Pxrf for a variety of other elements.

 

The resulting gold anomalism map is shown in Figure 10.1. A total of 10 drill targets were defined and drilled between 2019 and 2023.

 

Chesser drilled Area A and discovered near-surface mineralization in highly-altered hydrothermal breccias. Drilling then moved to Area D where mineralization was also discovered in the near-surface oxide material.

 

October 15, 2025Page 77 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 10.1 Contoured Auger Sampling Results Across the DS1 and DS2 Blocks of the Diamba Sud Project.

 

 

 

Figure prepared by Fortuna, 2025

 

10.1.2RC and Core Drilling

 

Chesser commenced RC drilling in 2019. Drill contractors included Minerex Drilling Contractors Ltd (MINEREX), International Drilling Company (IDC) and Forage Technique Eau Drilling (FTE) during various campaigns through to July 2023. A total of 10 geochemical targets were RC or RC with core tail (RC-DDT) drilled, totaling 493 holes and 60,213 m. All holes were sampled at 1- or 2-m intervals in the oxide material and at 1-m intervals in the fresh rock. All samples were submitted to SGS Bamako or the ALS laboratory in Burkina Faso, (ALS Burkina Faso).

 

The first core drilling at Diamba Sud was conducted in November 2019 over Areas A and D. In total, 116 core holes totaling 18,263 m were drilled between November 2019 and July 2023.

 

Figure 10.2 shows the collar locations for the Chesser drilling. Table 10.1 details the number of holes and meters drilled by prospect.

 

October 15, 2025Page 78 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 10.2 Location Map of RC and Core Drill Holes Completed by Chesser

 

 

 

Figure prepared by Fortuna, 2025

 

Table 10.1 Reverse Circulation and Core Drilling Conducted by Chesser

 

Area Core RC RC-DDT Total
No.
Holes
Meters No.
Holes
Meters No.
Holes
Meters
RC
Meters
Core
No.
Holes
Meters
Area A 22 4,835 174 21,716 23 3,898 1,028 219 31,477
Area D 70 8,602 106 12,299 3 122 225 179 21,248
Karakara 22 4,508 52 6,973 - - - 74 11,481
Western Splay - - 43 4,617 - - - 43 4,617
Kassassoko 2 318 13 1,274 - - - 13 1,274
Bougouda - - 12 1,214 - - - 12 1,214
Southern Arc - - 22 2,356 - - - 24 2,674
Gamba Gamba North - - 14 1,310 - - - 14 1,310
Moungoundi - - 31 3,181 - - - 31 3,181
Total 127 19,805 467 54,940 26 4,020 1,253 609 78,475

 

October 15, 2025Page 79 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

10.2Drilling Conducted by Fortuna

 

After acquiring Chesser in 2023, Fortuna began an extensive program of verification and infill drilling across nine of the advanced prospect areas with the aim of collecting sufficient data to support the estimation of Mineral Resources for those deposits (Table 10.2). A total of 972 drill holes totaling 119,490 m were drilled between October 2023 and October 31, 2025.

 

Table 10.2 Reverse Circulation and Core Drilling Conducted by Fortuna

 

Area Core RC RC-DDT Total
No.
Holes
Meters No.
Holes
Meters No.
Holes
Meters
RC
Meters
Core
No.
Holes
Meters
Area A 18 3,471 24 2,788 9 1,141 379 51 7,779
Area D 101 10,334 51 2,884 - - - 152 13,218
Karakara 74 10,615 62 8,137 - - - 136 18,752
Western Splay 50 7,551 57 6,495 6 689 908 113 15,643
Kassassoko 23 2,892 53 5,441 - - - 76 8,333
Bougouda 19 2,332 45 5,128 - - - 64 7,460
Southern Arc 117 16,854 112 14,664 - - - 229 31,518
Moungoundi 17 1,999 73 8,221 - - - 90 10,220
Moungoundi North 6 626 23 2,442 - - - 29 3,068
Geophysical targets - - 25 2,745 - - - 25 2,745
Geochemical targets - - 7 756 - - - 7 756
Total 425 56,672 532 59,701 15 1,830 1,287 972 119,490

 

The location of the holes by drilling methodology is shown in Figure 10.3.

 

October 15, 2025Page 80 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 10.3 Map Showing Location of RC and Core Drilling Conducted by Fortuna

 

 

Figure prepared by Fortuna, 2025

 

October 15, 2025Page 81 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

10.3Drilling Used in the Estimation of Mineral Resources

 

The number of DD, RC, and RC_DDT used in the geologic interpretation of deposits with estimated Mineral Resources are summarized in Table 10.3. The drilling comprises a mix of that conducted by Chesser and Fortuna with a data cut-off date of July 7, 2025, and excludes twin holes, holes abandoned prior to any samples being taken and one hole where concerns were raised regarding potential downhole contamination.

 

Table 10.3 Number of Holes and Meters Used in the Estimation by Deposit

 

Deposit Core RC RC-DDT Total
No. Holes Meters No. Holes Meters No. Holes Meters No. Holes Meters
Area A 35 7,586 197 24,460 32 6,788 264 38,833
Area D 141 16,692 123 13,932 3 347 267 30,971
Karakara 73 12,622 112 14,900 0 0 185 27,522
Western Splay 50 7,551 94 10,534 6 1,597 150 19,682
Kassassoko 21 2,650 66 7,340 0 0 87 9,990
Southern Arc 62 7,694 102 12,177 0 0 164 19,871
Moungoundi 17 1,999 102 11,156 0 0 119 13,155
Total 399 56,793 796 94,499 41 8,732 1,236 160,023

 

10.4Drilling Since the Mineral Resource Database Cut-off Date

 

As at the effective date of this Report, an additional 153 drill holes totaling 20,211 m (excluding 2 abandoned holes) were completed after July 7, 2025, the database cut-off date. All drilling was conducted from surface. Assay results for intercepts of interest (>0.7 g/t Au) are summarized in Table 10.4.

 

Table 10.4 Intervals of Interest in Holes Drilled Post Data Cut-off Date

 

Hole ID Easting Northing Elevation EOH
Depth
Azimuth
(°)*
Dip
(°)*
From
(m)
To
(m)
Drilled
Interval
(m)
ETW**
(m)
Au
(g/t)
Hole
Type
Deposit
DSDD460 232810 1426257 143 183 150 -50 167 180.7 13.7 10.96 1.7 DD Southern Arc
DSDD461 232869 1426207 143 185 150 -50 78 87 9 7.2 6.2 DD Southern Arc
          including 81 83 2 1.6 20.1 DD Southern Arc
              155 175 20 16 0.9 DD Southern Arc
DSDD462 232913 1426251 143 159 150 -50 117 143 26 20.8 9.7 DD Southern Arc
          including 120.3 123 2.7 2.16 21.9 DD Southern Arc
            and 124 127 3 2.4 18.4 DD Southern Arc
            and 129 130 1 0.8 13.4 DD Southern Arc
            and 133 134 1 0.8 14.2 DD Southern Arc
            and 140 142 2 1.6 16.8 DD Southern Arc
DSDD463 232889 1426230 143 149 150 -50 83 94 11 8.8 4.2 DD Southern Arc
          including 90 91 1 0.8 26.9 DD Southern Arc
              116 132.4 16.4 13.12 5.0 DD Southern Arc
          including 124 125 1 0.8 10.1 DD Southern Arc
            and 130 132.4 2.4 1.92 17.0 DD Southern Arc
DSDD464 232467 1426355 147 108 150 -50 NSI         DD Southern Arc
DSDD465 232807 1426213 144 169.5 150 -50 9 15 6 4.8 1.4 DD Southern Arc
              68 75 7 5.6 2.1 DD Southern Arc
              92 103 11 8.8 1.1 DD Southern Arc
DSDD466 232949 1426170 143 168 150 -50 NSI         DD Southern Arc
DSDD467 232797 1426118 144 184 150 -50 NSI         DD Southern Arc
DSDD468 232694 1426082 144 185 150 -50 126 137 11 8.8 1.0 DD Southern Arc
              162 166 4 3.2 5.2 DD Southern Arc
          including 162 163 1 0.8 11.0 DD Southern Arc

 

October 15, 2025Page 82 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Hole ID Easting Northing Elevation EOH
Depth
Azimuth
(°)*
Dip
(°)*
From
(m)
To
(m)
Drilled
Interval
(m)
ETW**
(m)
Au
(g/t)
Hole
Type
Deposit
DSDD469 232842 1426105 144 131 150 -50 73.5 88.5 15 12 8.4 DD Southern Arc
          including 80 83 3 2.4 21.6 DD Southern Arc
            and 86 87.2 1.2 0.96 11.8 DD Southern Arc
              92 99 7 5.6 3.4 DD Southern Arc
DSDD470 232763 1426110 144 157 150 -50 138 141 3 2.4 3.7 DD Southern Arc
DSDD471 232860 1426076 143 161 150 -50 36.3 46 9.7 7.76 1.5 DD Southern Arc
              55.85 75.45 19.6 15.68 3.3 DD Southern Arc
DSDD472 232960 1426216 143 161 150 -50 133 149 16 12.8 6.5 DD Southern Arc
          including 135 138 3 2.4 17.8 DD Southern Arc
            and 139 140 1 0.8 20.7 DD Southern Arc
              154.85 159.6 4.75 3.8 2.7 DD Southern Arc
DSDD473 232554 1426339 146 231 150 -50 97 98 1 0.8 13.7 DD Southern Arc
DSDD474 232983 1426171 143 143 150 -50 NSI         DD Southern Arc
DSDD475 232969 1426254 143 140 150 -50 NSI         DD Southern Arc
DSDD476 232498 1426323 145 252 150 -50 123 126 3 2.4 1.7 DD Southern Arc
              151 161.5 10.5 8.4 0.7 DD Southern Arc
DSDD477 232879 1426094 144 166 150 -50 56.5 69.25 12.75 10.2 3.7 DD Southern Arc
          including 57 58 1 0.8 11.6 DD Southern Arc
            and 66 66.6 0.6 0.48 15.3 DD Southern Arc
              79.5 90 10.5 8.4 11.9 DD Southern Arc
          including 80 84 4 3.2 21.4 DD Southern Arc
            and 88 89 1 0.8 15.7 DD Southern Arc
DSDD478 232740 1426275 144 119 150 -50 31.45 38 6.55 5.24 3.5 DD Southern Arc
          including 32.3 33 0.7 0.56 10.8 DD Southern Arc
DSDD479 232274 1426433 148 243 150 -50 148 155.25 7.25 5.8 0.9 DD Southern Arc
DSDD480 232893 1426117 143 179 150 -50 22.75 35 12.25 9.8 6.4 DD Southern Arc
          Including 27 28 1 0.8 14.1 DD Southern Arc
            And 30 32 2 1.6 20.8 DD Southern Arc
              50 86.2 36.2 28.96 2.5 DD Southern Arc
              139.2 144.45 5.25 4.2 2.3 DD Southern Arc
              160.3 162 1.7 1.36 3.2 DD Southern Arc
DSDD481 232717 1426265 145 119 150 -50 53 65 12 9.6 6.1 DD Southern Arc
          Including 59 60 1 0.8 11.5 DD Southern Arc
            And 61 62 1 0.8 12.0 DD Southern Arc
            And 64 65 1 0.8 14.6 DD Southern Arc
DSDD482 232685 1426240 146 137 150 -50 72 74 2 1.6 10.8 DD Southern Arc
          Including 73 74 1 0.8 13.4 DD Southern Arc
              100.8 104.45 3.65 2.92 3.9 DD Southern Arc
DSDD483 232308 1426459 148 249 150 -50 162 171 9 7.2 1.3 DD Southern Arc
DSDD484 232923 1426118 143 161 150 -50 5 44 39 31.2 4.1 DD Southern Arc
          Including 7 8 1 0.8 13.3 DD Southern Arc
            And 15 17 2 1.6 14.6 DD Southern Arc
            And 19 20 1 0.8 18.4 DD Southern Arc
            And 32 34 2 1.6 13.2 DD Southern Arc
DSDD485 232867 1426157 143.36 179 150 -50 58 64 6 4.8 3.9 DD Southern Arc
          Including 63 64 1 0.8 14.9 DD Southern Arc
              69 92 23 18.4 1.3 DD Southern Arc
DSDD486 232278 1426476 148 249 150 -50 NSI         DD Southern Arc
DSDD487 232905 1426062 143 128 150 -50 31 59 28 22.4 7.8 DD Southern Arc
          Including 44 46 2 1.6 33.6 DD Southern Arc
            And 51 52 1 0.8 20.5 DD Southern Arc
            And 53 55 2 1.6 11.1 DD Southern Arc
              56 57 1 0.8 13.2 DD Southern Arc
DSDD488 232899 1426165 143 152 150 -50 53 80 27 21.6 22.7 DD Southern Arc

 

October 15, 2025Page 83 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Hole ID Easting Northing Elevation EOH
Depth
Azimuth
(°)*
Dip
(°)*
From
(m)
To
(m)
Drilled
Interval
(m)
ETW**
(m)
Au
(g/t)
Hole
Type
Deposit
              63 64 1 0.8 27.4 DD Southern Arc
              66 68 2 1.6 258.8 DD Southern Arc
              69 69.85 0.85 0.68 13.4 DD Southern Arc
              77 78 1 0.8 17.0 DD Southern Arc
DSDD489 232825 1426079 144 182 150 -50 NSI         DD Southern Arc
DSDD490 232390 1426463 148 123 150 -50 NSI         DD Southern Arc
DSDD491 232725 1426076 144 200 150 -50 113 118.2 5.2 4.16 3.6 DD Southern Arc
              122 147 25 20 4.8 DD Southern Arc
          Including 132 133 1 0.8 10.6 DD Southern Arc
            And 135 136 1 0.8 10.6 DD Southern Arc
            And 138 139 1 0.8 15.1 DD Southern Arc
            And 140 141 1 0.8 10.9 DD Southern Arc
              187 196 9 7.2 1.0 DD Southern Arc
DSDD492 232725 1426036 143 152 150 -50 68 84 16 12.8 3.8 DD Southern Arc
          including 68 69 1 0.8 14.3 DD Southern Arc
            and 72 73 1 0.8 15.3 DD Southern Arc
            and 75.8 77 1.2 0.96 19.0 DD Southern Arc
              96 112 16 12.8 5.7 DD Southern Arc
          including 103 106 3 2.4 16.2 DD Southern Arc
              128 139.8 11.8 9.44 3.2 DD Southern Arc
DSDD493 232347 1426500 149 207 150 -50 165 174 9 7.2 2.4 DD Southern Arc
          including 168 169 1 0.8 13.2 DD Southern Arc
DSDD494 232532 1426112 143 131 150 -50 38 49 11 8.8 1.4 DD Southern Arc
DSDD495 232310 1426500 149 186 150 -50 NSI         DD Southern Arc
DSDD496 232672 1426077 143 176 150 -50 38.3 50 11.7 9.36 2.2 DD Southern Arc
          including 44 45 1 0.8 15.5 DD Southern Arc
              95.95 102.25 6.3 5.04 2.3 DD Southern Arc
              107 119.5 12.5 10 6.8 DD Southern Arc
          including 115 116 1 0.8 19.2 DD Southern Arc
          including 117 118 1 0.8 19.8 DD Southern Arc
              135 155 20 16 1.0 DD Southern Arc
DSDD497 232884 1426027 143.764 129 150 50 108.8 121.7 12.9 10.32 3.6 DD Southern Arc
          Including 117 118 1 0.8 17.0 DD Southern Arc
DSDD498 232714 1426155 145.448 132 150 -50 84.3 89.65 5.35 4.28 1.9 DD Southern Arc
DSDD499 231944 1428373 153 161 270 -60 NSI     0   DD Karakara
DSDD500 231940 1428424 154 140 270 -60 NSI         DD Karakara
DSDD501 231886 1428375 154 140 270 -60 47.5 49 1.5 1.2 5.2 DD Karakara
              66 73 7 5.6 1.4 DD Karakara
              84 104 20 16 2.1 DD Karakara
              84 85 1 0.8 15.6 DD Karakara
              130 135 5 4 3.1 DD Karakara
DSDD502 231892 1428200 149 140 270 -55 NSI         DD Karakara
DSDD503 233384 1429573 177 120 90 -60 1 5 4 3.2 2.8 DD Area A
              15 21 6 4.8 14.7 DD Area A
              16 17 1 0.8 28.6 DD Area A
              19 21 2 1.6 23.2 DD Area A
DSDD504 231848 1428273 153 160 270 -60 123 133 10 8 0.7 DD Karakara
DSDD505 231891 1428275 152 140 270 -60 94 95 1 0.8 10.8 DD Karakara
DSDD506 233115 1429501 183 200 90 -60 NSI         DD Area A
DSDD507 231835 1428324 152 150 270 -60 NSI         DD KaraKara
DSDD508 233387 1429552 176 120 90 -60 NSI         DD Area A
DSDD509 231816 1428173.8 151 100 270 -50 11.5 26 14.5 11.6 1.7 DD Karakara
          Including 13 14 1 0.8 11.5 DD Karakara
DSDD510 233071 1429600 186 75 90 -60 NSI         DD Area D

 

October 15, 2025Page 84 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Hole ID Easting Northing Elevation EOH
Depth
Azimuth
(°)*
Dip
(°)*
From
(m)
To
(m)
Drilled
Interval
(m)
ETW**
(m)
Au
(g/t)
Hole
Type
Deposit
DSDD511 231860 1428149 150 80 270 -55 NSI         DD KaraKara
DSDD512 233000 1429602 185 60 90 -60 NSI         DD Area D
DSDD513 231653 1428122 152 90 270 -50 NSI         DD Karakara
DSDD514 232973 1429602 186 60 90 -60 0 10 10 8 1.2 DD Area D
              48 56 8 6.4 1.6 DD Area D
DSDD515 233388 1429602 178 120 90 -60 NSI         DD Area D
DSDD516 231669 1428146 152 120 270 -50 32.6 41 8.4 6.72 0.8 DD Karakara
              110 119 9 7.2 1.4 DD Karakara
DSDD517 233170 1429342 177 130 90 -60 NSI         DD Area A
DSDD518 231620 1428147 153 90 270 -50 9 16 7 5.6 1.1 DD Karakara
DSDD519 231700 1428196 152 130 270 -50 72 75 3 2.4 1.9 DD Karakara
DSDD520 233139 1429344 178 150 90 -60 111.72 125.9 14.18 11.344 6.0 DD Area A
          Including 120 121 1 0.8 15.3 DD Area A
            And 122 123 1 0.8 14.4 DD Area A
              141 148 7 5.6 6.3 DD Area A
          Including 142 144 2 1.6 12.7 DD Area A
DSDD521 231670 1428222 153 90 270 -50 15 25 10 8 2.9 DD Karakara
              62 69 7 5.6 0.9 DD Karakara
DSDD522 231672 1428245 153 80 270 -50 52 58 6 4.8 3.1 DD Karakara
          Including 57 58 1 0.8 11.5 DD Karakara
              66 70 4 3.2 2.8 DD Karakara
DSDD523 232980 1429548 184 110 90 -60 7 20 13 10.4 0.8 DD Area D
              29 36.5 7.5 6 0.9 DD Area D
DSDD524 231618 1428276 155 80 90 -60 33 38 5 4 2.5 DD Karakara
DSDD525 232890 1429551 184 60 90 -60 10 41 31 24.8 3.6 DD Area D
          Including 28 29 1 0.8 31.0 DD Area D
          Including 39 40 1 0.8 11.1 DD Area D
DSDD526 231620 1428246 154 110 270 -50 24 30 6 4.8 8.2 DD Karakara
          Including 26 27 1 0.8 22.1 DD Karakara
          Including 29 30 1 0.8 18.3 DD Karakara
DSDD527 232896 1429501 183 120 90 -70 77 85 8 6.4 7.4 DD Area D
          Including 77 78 1 0.8 28.8 DD Area D
DSDD528 231628 1428225 152 60 270 -50 25 31 6 4.8 6.0 DD Karakara
          Including 29 30 1 0.8 30.1 DD Karakara
DSDD529 231634 1428322 156 60 90 -60 NSI         DD Karakara
DSDD530 232591 1429525 181 107 90 -60 NSI         DD Area D
DSDD531 231874 1428149 150 80 270 -55 55.7 58.5 2.8 2.24 10.8 DD Karakara
          Including 55.7 56.5 0.8 0.64 35.2 DD Karakara
DSDD532 232621 1429500 181 129 90 -60 63.5 73 9.5 7.6 5.5 DD Area D
          Including 65 66 1 0.8 34.7 DD Area D
              79 95 16 12.8 0.7 DD Area D
DSDD533 231825 1428145 150 80 270 -55 NSI         DD Karakara
DSDD534 231824 1428292 153 150 270 -60 116 121 5 4 14.0 DD Karakara
          Including 118 119 1 0.8 57.4 DD Karakara
              126 130 4 3.2 3.2 DD Karakara
          Including 126 127 1 0.8 11.6 DD Karakara
              134 142 8 6.4 0.8 DD Karakara
DSDD535 232591 1429456 179 120 90 -60 62 64 2 1.6 5.0 DD Area D
              89 99 10 8 4.0 DD Area D
          Including 90 91 1 0.8 33.4 DD Area D
DSDD536 232544 1429453 179 121 90 -60 98 101 3 2.4 2.0 DD Area D
DSDD537 231767 1428450 156 120 90 -60 NSI         DD Karakara
DSDD538 232531 1429379 177 100 90 -60 21 30 9 7.2 5.3 DD Area D
          Including 22 23 1 0.8 18.2 DD Area D

 

October 15, 2025Page 85 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Hole ID Easting Northing Elevation EOH
Depth
Azimuth
(°)*
Dip
(°)*
From
(m)
To
(m)
Drilled
Interval
(m)
ETW**
(m)
Au
(g/t)
Hole
Type
Deposit
          Including 24 25 1 0.8 10.0 DD Area D
              47 51 4 3.2 1.6 DD Area D
DSDD539 232947 1429474 182 60 90 -60 NSI         DD Area D
DSDD540 233003 1429478 182 30 90 -60 NSI         DD Area D
DSDD541 232886 1429473 182 60 90 -60 26 35 9 7.2 2.4 DD Area D
              51 52 1 0.8 7.5 DD Area D
DSDD542 232432 1429402 178 69 90 -60 NSI         DD Area D
DSDD543 232951 1429454 182 30 90 -60 13 30 17 13.6 0.8 DD Area D
DSDD544 232899 1429454 182 40 90 -60 31 38 7 5.6 1.1 DD Area D
DSDD545 232484 1429374 177 120 90 -60 6 11 5 4 2.6 DD Area D
              65 68 3 2.4 25.7 DD Area D
          Including 67 68 1 0.8 69.4 DD Area D
              96 107 11 8.8 0.7 DD Area D
DSDD546 232870 1429455 182 50 90 -60 NSI         DD Area D
DSDD547 232707 1429300 178 60 90 -60 NSI         DD Area D
DSDD548 232499 1429347 177 120 90 -60 73 82 9 7.2 0.8 DD Area D
              111.2 116 4.8 3.84 2.1 DD Area D
DSDD549 232681 1429303 177 60 90 -60 3 17 14 11.2 2.2 DD Area D
DSDD550 232666 1429307 177 60 90 -60 13 16 3 2.4 1.8 DD Area D
              31 39 8 6.4 0.9 DD Area D
DSDD551 232695 1429276 177 40 90 -60 NSI         DD Area D
DSDD552 232526 1429324 176 60 90 -60 18 20 2 1.6 6.5 DD Area D
DSDD553 232641 1429276 177 50 90 -60 30 43 13 10.4 1.8 DD Area D
DSDD554 232814 1429576 183 40 90 -60 NSI         DD Area D
DSDD555 232868 1426115 144 120 150 -50 48.6 93 44.4 35.52 6.8 DD Southern Arc
          Including 65 66 1 0.8 24.0 DD Southern Arc
            And 68.5 69.5 1 0.8 13.1 DD Southern Arc
            And 74 75 1 0.8 18.5 DD Southern Arc
            And 80 87 7 5.6 18.7 DD Southern Arc
DSDD556 232738 1426053 144 201 150 -50 88 88.6 0.6 0.48 9.5 DD Southern Arc
              105 134 29 23.2 1.5 DD Southern Arc
              138 153 15 12 2.8 DD Southern Arc
DSDD557 232838 1426172 144 165 150 -50 39 57 18 14.4 1.9 DD Southern Arc
              67 73 6 4.8 1.2 DD Southern Arc
              104.7 127 22.3 17.84 3.8 DD Southern Arc
          Including 108 109 1 0.8 11.8 DD Southern Arc
            And 114 115 1 0.8 30.4 DD Southern Arc
              139 141 2 1.6 3.7 DD Southern Arc
              145 161.2 16.2 12.96 3.4 DD Southern Arc
DSDD558 232809 1426138 145 146 150 -50 25 41 16 12.8 1.8 DD Southern Arc
              96 114 18 14.4 8.8 DD Southern Arc
          Including 101 102 1 0.8 22.1 DD Southern Arc
            And 103 106 3 2.4 18.0 DD Southern Arc
            And 110 111 1 0.8 11.5 DD Southern Arc
              118 122 4 3.2 3.0 DD Southern Arc
DSDD559 232753 1426132 145 99 150 -50 NSI         DD Southern Arc
DSDD560 232789 1426174 145 170 150 -50 18 19 1 0.8 6.0 DD Southern Arc
              43 55 12 9.6 1.9 DD Southern Arc
              63 70 7 5.6 2.7 DD Southern Arc
DSDD561 232773 1425989 143 126 150 -50 59 68 9 7.2 0.7 DD Southern Arc
              79 100 21 16.8 0.7 DD Southern Arc
DSDD562 232718 1426095 144 206 150 -50 146 153 7 5.6 4.5 DD Southern Arc
              158 159 1 0.8 5.7 DD Southern Arc
              174 188 14 11.2 8.0 DD Southern Arc

 

October 15, 2025Page 86 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Hole ID Easting Northing Elevation EOH
Depth
Azimuth
(°)*
Dip
(°)*
From
(m)
To
(m)
Drilled
Interval
(m)
ETW**
(m)
Au
(g/t)
Hole
Type
Deposit
          Including 183 185 2 1.6 46.3 DD Southern Arc
DSDD563 232724 1426181 145 135 150 -50 50 76 26 20.8 5.8 DD Southern Arc
          Including 53 55 2 1.6 23.3 DD Southern Arc
            And 71 73 2 1.6 21.8 DD Southern Arc
              86 93.3 7.3 5.84 12.2 DD Southern Arc
          Including 87 88 1 0.8 14.7 DD Southern Arc
            And 90 92.8 2.8 2.24 22.1 DD Southern Arc
              106 114 8 6.4 2.7 DD Southern Arc
              118 124 6 4.8 7.0 DD Southern Arc
          Including 120 122 2 1.6 15.3 DD Southern Arc
DSDD564 232774 1426200 145 200 150 -50 12 21 9 7.2 1.2 DD Southern Arc
              30 38.3 8.3 6.64 2.9 DD Southern Arc
          Including 37.5 38.3 0.8 0.64 11.7 DD Southern Arc
              80 93 13 10.4 1.0 DD Southern Arc
              160 163 3 2.4 3.0 DD Southern Arc
DSDD565 232761 1426009 143 147 150 -50 70 79 9 7.2 0.7 DD Southern Arc
              86 106 20 16 1.5 DD Southern Arc
              121 123 2 1.6 2.6 DD Southern Arc
DSDD566 232779 1426159 145 149 150 -50 5 11 6 4.8 1.4 DD Southern Arc
              36 42 6 4.8 1.6 DD Southern Arc
              46 56 10 8 2.5 DD Southern Arc
              121.7 134 12.3 9.84 2.0 DD Southern Arc
          Including 131 132 1 0.8 14.3 DD Southern Arc
DSDD567 232790 1426141 145 146 150 -50 1.3 8 6.7 5.36 1.1 DD Southern Arc
              16 28 12 9.6 1.2 DD Southern Arc
              34 45 11 8.8 1.6 DD Southern Arc
              96.8 130 33.2 26.56 4.6 DD Southern Arc
          Including 103 104 1 0.8 15.6 DD Southern Arc
            And 105 107 2 1.6 13.6 DD Southern Arc
            And 112 113 1 0.8 11.9 DD Southern Arc
            And 114 116 2 1.6 18.3 DD Southern Arc
DSDD568 232684 1426051 143 171 150 -50 80.3 89.5 9.2 7.36 1.0 DD Southern Arc
              111 117 6 4.8 1.8 DD Southern Arc
              123 128 5 4 4.0 DD Southern Arc
              144 158 14 11.2 0.9 DD Southern Arc
DSDD569 232758 1426225 145 183 150 -50 51 58 7 5.6 1.2 DD Southern Arc
DSDD570 232600 1426187 145 231 150 -50 174 191 17 13.6 0.9 DD Southern Arc
              198 209 11 8.8 3.6 DD Southern Arc
          Including 206 208 2 1.6 14.9 DD Southern Arc
              214 217 3 2.4 1.8 DD Southern Arc
DSR923 231065 1426600 151 120 90 -60 NSI           Moungoundi
DSR924 231009 1426603 151 126 90 -60 NSI           Moungoundi
DSR961 232785 1426306 143 186 150 -50 172 174 2 1.6 3.0 RC Southern Arc
DSR962 232324 1426440 148 156 150 -50 123 127 4 3.2 3.5 RC Southern Arc
              139 145 6 4.8 3.7 RC Southern Arc
          including 140 141 1 0.8 12.2 RC Southern Arc
              153 156 3 2.4 1.7 RC Southern Arc
DSR963 232883 1426295 143 162 150 -50 NSI         RC Southern Arc
DSR964 232475 1426474 148 150 150 -50 NSI         RC Southern Arc
DSR965 232489 1426442 147 162 150 -50 NSI         RC Southern Arc
DSR966 232512 1426401 147 180 150 -50 NSI         RC Southern Arc
DSR967 232531 1426374 146 162 150 -50 NSI         RC Southern Arc
DSR968 232628 1426148 145 162 150 -50 122 123 1 0.8 8.1 RC Southern Arc
DSR969 232647 1426112 144 138 150 -50 34 51 17 13.6 1.3 RC Southern Arc

 

October 15, 2025Page 87 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Hole ID Easting Northing Elevation EOH
Depth
Azimuth
(°)*
Dip
(°)*
From
(m)
To
(m)
Drilled
Interval
(m)
ETW**
(m)
Au
(g/t)
Hole
Type
Deposit
              59 63 4 3.2 1.6 RC Southern Arc
              67 86 19 15.2 1.5 RC Southern Arc
          including 85 86 1 0.8 10.2 RC Southern Arc
DSR970 232785 1426069 143 108 150 -50 NSI         RC Southern Arc
DSR971 232844 1426032 143 144 150 -50 60 64 4 3.2 2.6 RC Southern Arc
              78 80 2 1.6 4.6 RC Southern Arc
DSR972 232813 1426019 143 120 150 -50 NSI         RC Southern Arc
DSR973 232537 1426160 143 150 150 -50 NSI         RC Southern Arc
DSR974 232474 1426264 145 162 150 -50 NSI         RC Southern Arc
DSR975 232980 1426119 143 126 150 -50 NSI         RC Southern Arc
DSR976 232962 1426110 143 126 150 -50 51 80 29 23.2 4.9 RC Southern Arc
          including 63 67 4 3.2 19.4 RC Southern Arc
DSR977 232960 1426162 143 128 150 -50 95 107 12 9.6 4.3 RC Southern Arc
DSR978 232766 1426064 143 108 150 -50 NSI         RC Southern Arc
DSR979 232746 1425990 142 120 150 -50 60 80 20 16 3.3 RC Southern Arc
          including 62 63 1 0.8 19.9 RC Southern Arc
              84 92 8 6.4 1.4 RC Southern Arc
              99 111 12 9.6 2.6 RC Southern Arc
DSR980 232748 1426033 143 108 150 -50 82 87 5 4 1.8 RC Southern Arc
              93 101 8 6.4 0.7 RC Southern Arc
DSR988 233526 1430000 183 120 90 -50 10 19 9 7.2 0.8 RC Area A North
DSR989 233478 1430001 186 90 90 -50 NSI         RC Area A North
DSR990 233301 1429999 197 90 90 -50 NSI         RC Area A North
DSR991 232693 1425987 142 126 150 -50 NSI         RC Southern Arc
DSR992 232692 1426031 142 126 150 -50 71 83 12 9.6 2.0 RC Southern Arc
          including 76 77 1 0.8 10.0 RC Southern Arc
              88 102 14 11.2 1.0 RC Southern Arc
DSR993 232443 1426350 146.63 60 150 -50 NSI         RC Southern Arc
DSR994 233299 1430198 200 120 90 -50 NSI         RC Area A North
DSR995 232161 1428650 164 126 90 -55 NSI         RC Area D South
DSR996 232104 1428649 163 114 90 -55 16 18 2   6.1 RC Area D South
          including 17 18 1   10.1 RC Area D South
DSR997 232044 1428645 160.3 86 90 -55 NSI         RC Area D South
DSR998 231533 1428602 153 108 135 -50 NSI         RC KaraKara
DSR999 231580 1428543 153 102 135 -50 NSI         RC KaraKara
DSR1002 232291 1426456.1 148.4 204 150 -50 157 158 1 0.7 8.1 RC Southern Arc
              184 198 14 9.8 1.3 RC Southern Arc
DSR1003 232619 1426169 145 162 150 -50 NSI         RC Southern Arc
DSR1004 232587 1426169 145 162 150 -50 129 133 4 3.2 3.5 RC Southern Arc
          Including 129 130 1 0.8 11.3 RC Southern Arc
              149 155 6 4.8 1.3 RC Southern Arc
DSR1005 232702 1426218 146 168 150 -50 80 86 6 4.8 3.8 RC Southern Arc
          Including 84 85 1 0.8 14.6 RC Southern Arc
DSR1006 232779 1426089 145 144 150 -50 NSI         RC Southern Arc
DSR1007 232597 1426150 144 160 150 -50 NSI         RC Southern Arc
DSR1008 232738 1426160 145 132 150 -50 NSI         RC Southern Arc
DSR1009 232819 1426120 144 144 150 -50 103 106 3 2.4 2.9 RC Southern Arc

*Azimuth and dip values taken at collar location

**ETW = Estimated True Width

NSI = No Significant Interval

 

The QP has reviewed the results against the block models and has determined that the new drilling would not materially change the Mineral Resources of Area A, Area D, Karakara, and Moungoundi, detailed in this Report. Drilling at Southern Arc (86 of the

 

October 15, 2025Page 88 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

154 holes) has identified extended mineralization to the south, east and at depth to the currently defined Mineral Resources as detailed in this Report. An updated estimate of the Southern Arc deposit is planned for the end of 2025 to assess the potential of this additional mineralization.

 

10.4.1Grade Control Drilling

 

In addition to the exploration holes drilled after the data cut-off date, Fortuna also conducted a grade control drilling program at Area D to validate the continuity of mineralization and level of grade variability. A total of 34 holes (32 RC and 2 core) totaling 1,022 m were drilled on a 10 x 10 m grid, to a depth of 30 m.

 

A grade control model was generated based on the grade control drilling and compared to the resource model described in Section 14. Results were positive, with the extent of mineralization, mineralized tonnage and grade comparing favorably between the two models. Two additional grade control drill programs are planned in 2026 for the Area A and Karakara deposits.

 

10.5Extent of Drilling

 

The extent of drilling varies for each of the deposits and prospects. Those that have been drilled sufficiently to support Mineral Resources are based on a grid of exploration holes approximately 25–50 m apart.

 

The Area A deposit has been drilled over an approximate area of 700 m (north to south) and 500 m (east to west) to depths around 280 m from surface. Exploration drilling has increased in depth to the south.

 

The Area D deposit has been drilled over an approximate area of 600 m (north to south) and 700 m (east to west) to depths around 250 m from surface. Exploration drilling has increased in depth to the south.

 

The Karakara deposit has been drilled over a strike length of approximately 1,000 m (north–northeast to south–southwest) and to depths of 230 m from surface. Exploration drilling has increased in depth in response to the plunge of mineralization to the southwest.

 

The Kassassoko deposit has been drilled over an approximate area of 700 m (southwest to northeast) and 200 m (southeast to northwest) to depths around 150 m from surface. Exploration drilling has increased in depth to the south.

 

The Western Splay deposit has been drilled over an approximate area of 500 m (north to south) and 700 m (east to west) to depths around 280 m from surface. Exploration drilling has increased in depth to the south.

 

The Moungoundi deposit has been drilled over a strike length of approximately 400 m (north to south) and to depths around 150 m from surface.

 

The Southern Arc deposit has been drilled over a strike length of approximately 800 m (northwest to southeast) and to depths of 200 m from surface.

 

The Gamba Gamba North prospect drilled by Chesser is split into two main mineralized zones (refer to Figure 10.2). The eastern zone has been drilled over a strike length of 300 m (north–northeast to south–southwest) to a depth of 150 m from surface; the western zone has been drilled over a strike length of 300 m (north to south) to a depth of 125 m from surface. The drilling follows the plunge of the mineralization generally getting deeper towards the south–southwest.

 

October 15, 2025Page 89 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The Bougouda prospect has been drilled over a strike length of approximately 1,800 m (northeast to southwest) and to depths of 150 m from surface (refer to Figure 10.3).

 

10.6Drilling Techniques and Procedures

 

Drilling techniques and procedures have remained the same under the management of Boya for the Chesser and Fortuna drill programs.

 

10.6.1Reverse Circulation Drilling

 

RC drilling was conducted using an Atlas Copco T3W rig with a 950CFM compressor and an Atlas Copco Hurricane booster. All holes were cased with PVC to 6 m and then drilled using a 5.5-inch RC hammer bit. Samples were collected at 1-m intervals from an onboard cyclone then split on site to produce two 1.5 kg samples. The first sample was submitted for analysis, the second stored as a duplicate sample.

 

10.6.2Core Drilling

 

Core drilling was conducted with Atlas Copco CS14 and CT14 core drill rigs, depending on the contractor. The majority of holes are drilled to HQ (63.5 mm core diameter) and NQ (47.6 mm) sizes. In Area D where the oxide material can be difficult to keep holes from collapsing, holes are drilled PQ (85 mm) from surface to fresh rock before stepping down to HQ and NQ as appropriate to conditions and depth.

 

Chesser completed nine twin holes over Area A, Area D and Karakara for targeting mineralized intervals for metallurgical sampling in 2022. The assay results supported the interpretations.

 

10.6.3Geological and Geotechnical Logging Procedures

 

RC chips were collected and logged at the drill site and stored in standard chip trays for further investigation as appropriate.

 

Core is logged in detail at the field camp, using LogChief software and transferred electronically to DataShed for database management. Lithologies, alteration, mineralization and structures are all logged to industry standards.

 

Geotechnical information collected routinely is at a rudimentary exploration level and includes total recovery, rock quality designation (RQD) measurements and occasional fracture frequency information. However, 14 holes (2,100 m) were fully logged to higher geotechnical standards as part of geotechnical studies on Area A, Area D, Karakara and Bougouda deposits to support rock mass classification of the various units. These specific geotechnical drill holes were logged in detail including recovery, RQD, fracture frequency, infill type, discontinuity types, roughness, thickness, and strike and dip of major structures. Intact geotechnical samples were also collected to conduct laboratory testing for deriving intact rock strength properties. The detailed geotechnical site investigation also included the usage of an acoustic televiewer (ATV) to obtain geophysical readings of the discontinuities.

 

10.6.4Photography

 

All RC chip trays were photographed wet using standard digital SLR equipment.

 

All drill core was photographed using the same digital SLR equipment with core boxes loaded into a frame apparatus to allow for consistent photography. All core was photographed both wet and dry prior to being cut for sampling.

 

October 15, 2025Page 90 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

10.6.5Core Orientation

 

Drill core orientation was recorded using an “Axis Champ Ori” Orientation tool.

 

Immediately after drilling, core was transferred from the core barrel and pieced together on a V-rail rack. The orientation line determined by the orientation tool during drilling was then drawn along the entire length of the assembled core.

 

10.6.6Drill Core Recovery

 

Drill core recoveries were measured at the drill rig prior to boxing for transportation.

 

From recovery logs, recorded weighted average recoveries were measured as 70% in the ferricrete, 88% in the saprolite, 86% in the transition zone (saprock) and 96% in fresh rock.

 

Occasional issues with recovery of core were encountered where the water table is close to surface within the weathered zones. Additionally, recovery can be poor in interpreted karst environments and fault zones.

 

10.6.7Collar Surveying

 

All drill holes are located prior to drilling by handheld global positioning system (GPS) instrument and set up by the responsible geologist. All collars are later surveyed using a differential GPS by an external service provider.

 

10.6.8Downhole Surveying

 

Downhole surveys of RC holes were conducted using a Reflex Gyro Sprint IQ survey tool. After drilling was completed the survey tool was used to take readings every 10 m down the hole and a second set of readings were taken on the way out. The average readings were calculated and used to display the drill hole trace.

 

Downhole surveys of the core holes were conducted using a variety of survey tools, as there were several rigs operating at the same time in different areas. These included Reflex EZ Shot, Reflex Gyro Sprint IQ and Axis Champ gyroscopic tools. Readings were collected every 30 m down the hole.

 

10.7Sample Length Versus True Thickness

 

The relationship between the sample intercept lengths and the true width of mineralization varies in relation to the intersect angle between the mineralized structures (that vary in both strike and dip direction) and the inclined nature of the core holes. Drilling is conducted as close to perpendicular to the mineralized structures as possible, once the orientation of mineralization has been established. Calculated estimated true widths (ETWs) are always reported together with actual sample lengths by considering the angle of intersection between drill hole and the mineralized structure. Exaggeration of the true width of mineralization does not occur during modeling as the actual contacts are modeled in three-dimensional space to create mineralized wireframes.

 

10.8Example of Drill Intercepts

 

Examples of drill hole intercepts encountered at the Diamba Sud Project at the Area A, Area D, Karakara, Kassassoko, Western Splay, Moungoundi and Southern Arc deposits are summarized in Table 10.5.

 

October 15, 2025Page 91 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 10.5 Example of Typical Drill Results at the Diamba Sud Project

 

Hole ID Easting Northing Elevation

EOH
Depth

Azimuth
(°)*

Dip
(°)*

From
(m)

To
(m)

Drilled
Interval
(m)

ETW**
(m)

Au
(g/t)

Grams
x
Meters
Deposit
DSDD395 233176 1429583 184.97 210 90 -60 65 75 10 8 12.23 122.30 Area A
           including 66 67 1 0.8 21 21 Area A
DSDD399 233139 1429384 179.08 190 90 -60 153 189 36 28.8 3.00 108.11 Area A
DSDD389 232711 1429374 177.97 100 90 -60 20 46 26 20.8 3.39 88.11 Area D
          including 41 43 2 1.6 26.55 53.1 Area D
DSDD394 232457 1429428 178.27 110 90 -60 74 81 7 5.6 2.857 20.00 Area D
DSDD393 231816 1428275 152.29 180 270 -60 119 143 24 19.2 3.39 81.36 Karakara
          including 119 120 1 0.8 17.55 17.55 Karakara
DSR868 231862 1428354 153.78 130 270 -60 62 72 10 8 0.78 7.757 Karakara
DSR881 231335 1426244 147 70 90 -50         NSI   Western Splay
DSDD362 231223 1426378 155.1 89 90 -50 39 48 9 8.1 3.155 28.40 Western Splay
DSDD363 231153 1426347 147.28 221 90 -66 156 162 6 5.4 1.29 7.74 Western Splay
DSDD376 231200 1427800 155.44 82.3 270 -50         NSI   Moungoundi
DSR825 230853 1427747 158 108 90 -50 33 40 7 4.9 5.07 35.49 Moungoundi
          including 37 38 1 0.7 32.9 32.9 Moungoundi
DSR875 231621 1425875 144.07 147 150 -53 64 77 13 10.4 1.09 14.17 Kassassoko
DSR876 231607 1425896 144.63 120 150 -53 66 88 22 17.6 2.38 52.36 Kassassoko
          including 77 78 1 0.8 28.7 28.7 Kassassoko
DSR976 232962 1426110 143 126 150 -50 51 80 29 23.2 4.95 143.53 Southern Arc
          Including 63 67 4 3.2 19.38 77.5 Southern Arc
DSDD460 232810 1426257 143.3 183 150 -50 167 180.7 13.7 10.96 1.68 23.07 Southern Arc

*Azimuth and dip values taken at collar location

**ETW = Estimated True Width

NSI = No Significant Interval

 

It should be noted that the intervals listed in Table 10.5 are a subset for example purposes only and do not represent the total mineralized intervals encountered from the 1,581 holes drilled by Chesser and Fortuna at the Diamba Sud Project.

 

10.9Comment on Section 10

 

The QP has the following observations and conclusions regarding drilling conducted at the Diamba Sud project since September 2023.

 

·Data was collected using industry standard practices.

 

·Drill orientations are appropriate to the orientation of mineralization.

 

·Core logging meets industry standards for exploration of orogenic style deposits.

 

·Geotechnical logging is sufficient to support Mineral Resource estimation.

 

·Collar surveys have been conducted using industry-standard instrumentation.

 

·Downhole surveys performed during the drill programs have used industry-standard instrumentation.

 

·Drilling information is sufficient to support Mineral Resource estimates.

 

October 15, 2025Page 92 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

There are no drilling, sampling or recovery factors that could materially impact the accuracy and reliability of the results known to the QPs that have not been discussed in the Report.

 

October 15, 2025Page 93 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

11Sample Preparation, Analyses, and Security

 

11.1Sample Preparation Prior to Dispatch of Samples

 

Other than drying splitting and bagging, no sample preparation is conducted at the Diamba Sud field camp. Samples are combined into batches; normally each hole is a batch unless they are particularly long or short. Optimal batch sizes for the analytical laboratories are in the order of 100 samples. Quality control (QC) samples are also inserted in accordance with the company’s standard batch control sheet and the samples then sealed in large sacks for dispatch.

 

11.2Sample Collection

 

Sampling of RC holes is conducted at the drilling rig with one split sample collected every meter for routine analysis and the second sample split again for duplicate sample submission.

 

Sampling of drill core is conducted after geological logging and marking of the core for sampling. Core is split using a diamond saw. The half core that does not contain the orientation line is selected for sampling. Intervals are based upon geology with nominal sample lengths of 1 m, although this may be variable. Standard sampling procedures dictate a minimum sample length of 0.4 m and a maximum of 1.2 m. For duplicate samples only, the remaining half core is quartered (cut in half again) for submission to the laboratory.

 

PQ core is sampled as quarter core for routine sample submission and the second quarter is collected for duplicate sample submission.

 

All samples are combined into batches for submission to the laboratory. Nominally each batch should represent a specific drill hole; however, the preferred batch size at the laboratory is 100 samples, thus longer drill holes tend to be split into two or three batches. Once sampled and labelled, samples are packed into large sacks and sealed ready for transportation.

 

11.3Sample Dispatch

 

Drill samples are delivered to either ALS Global’s sample preparation facility in Kédougou, Senegal or SGS Mineral Services’ facility in Bamako, Mali, by Boya personnel, normally twice a week during the drilling season. No outside interference with the samples is possible.

 

11.4Sample Preparation

 

The preparation of both RC and core samples is conducted by external laboratories ALS Global or SGS Mineral Services at their preparation facilities in Kédougou or Bamako.

 

ALS Global’s preparation code for both RC and core samples is Prep-31H. This involves crushing to 75% passing 2 mm, splitting to 500 g, and pulverizing to 85% passing 75 µm. Once complete the samples are submitted to ALS Global’s analytical laboratory in Ouagadougou, Burkina Faso. Transportation of the samples from Kédougou is managed by ALS Global.

 

SGS Mineral Services’ equivalent preparation code is PRP 87 and also involves crushing to 75% passing 2 mm, splitting to 500 g, and pulverizing to 85% passing 75 µm. Once

 

October 15, 2025Page 94 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

complete, the samples are submitted to the SGS Mineral Services analytical laboratory in Bamako. Transportation of the samples from Kédougou to Bamako is managed by SGS Mineral Services.

 

11.5Analytical Methods

 

Samples from Diamba Sud are assayed for gold only. The assay method used for all the drill samples is a fire assay fusion with an atomic absorption spectroscopy (AAS) finish. Assaying is performed at the ALS Global laboratory in Ouagadougou or the SGS Mineral Services laboratory in Bamako. The ALS Global and SGS Mineral Services codes for this method are Au-AA24 and FA505 respectively.

 

ALS Global’s lower detection limit for this method is 0.005 ppm, and the upper detection limit is 10 g/t Au, whilst SGS Mineral Services’ lower, and upper detection limits are 0.01 g/t and 100 g/t Au respectively.

 

Samples returning values above 10 g/t Au are resubmitted for fire assay fusion with a gravimetric finish (ALS Global code Au-GRA22 – reporting limit 0.05–10,000 g/t Au, SGS Mineral Services code G_FAG50V – reporting limit 0.5 –3,000 g/t Au).

 

11.6Laboratory Accreditation

 

ALS Global and SGS are independent, privately-owned analytical laboratory groups. The preparation laboratories in Kédougou and Bamako and the analytical laboratories in Ouagadougou and Bamako are supported by a Quality Management System (QMS) framework which is designed to highlight data inconsistencies sufficiently early in the process to enable corrective action to be taken in time to meet reporting deadlines. The analytical laboratories are ISO/IEC 17025:2017 accredited for chemical and physical testing for the determination of gold content using the fire assay method with an atomic absorption finish.

 

11.7Sample Security and Chain of Custody

 

All samples remain under strict control between drilling and delivery to the laboratory for sample preparation. RC samples are transported to the core shed within the field camp after each shift. Core is transported to the core storage facility daily. The core storage facility is located within the fenced field camp and under strict control. All RC and DD samples were transported by Company vehicle or commercial courier to ALS Global’s preparation laboratories in Kédougou, Senegal or the SGS Mineral Services laboratory in Bamako, Mali. Prepared sample pulps from ALS Global’s Kédougou laboratory were then transported via commercial courier to ALS Global’s analytical facility in Ouagadougou, Burkina Faso.

 

11.8Bulk Density Determination

 

Bulk density values were determined for each individual lithology via the collection of density measurements using the Archimedes method (water immersion measurements) based on drill core sampled across each of the deposits. For un-weathered core a sample 10–15 cm long is selected, weighed in air, and weighed in water, with the density then recorded in the database for the corresponding interval and lithology type. For fully or partially weathered samples, samples are dried, weighed, wrapped in clingfilm then weighed in water. Company personnel on site were responsible for the collection of this data according to standardized density data collection procedures.

 

October 15, 2025Page 95 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

There was a total of 25,762 density measurements taken by Boya and used in the estimation of Mineral Resources (Table 11.1). All samples were taken from diamond drill core, typically HQ or NQ diameter, with some PQ diameter for metallurgical holes. Statistical analysis of density measurements was performed both globally (all deposits combined) and separately by deposit. The analysis was conducted using both lithological and weathering logging data. This provides (in most cases) three mean density values: one for oxide, one for transition and one for fresh for each lithology. Area A and Area D were combined for analysis and density assignment. Karakara, Western Splay, Kassassoko, Moungoundi, and Southern Arc were assessed individually and where insufficient samples (<15) were available, the global mean for that lithology or weathering unit was assigned.

 

Table 11.1 Density Measurements by Lithology and Weathering Horizon

 

Weathering
Zone
Lithology Average Bulk
Density (g/cm3)
Oxide Laterite 2.15
Carbonate 1.50
Tectonic Breccia 1.72
Hydrothermal Breccia 1.67
Diorite 1.72
Granite 1.96
Mafic Breccia 1.89
Marl 2.02
Transition Carbonate 2.39
Tectonic Breccia 2.15
Hydrothermal Breccia 2.47
Diorite 2.27
Granite 2.44
Mafic Breccia 2.45
Marl 2.17
Fresh Carbonate 2.73
Tectonic Breccia 2.64
Hydrothermal Breccia 2.71
Diorite 2.62
Granite 2.63
Mafic Breccia 2.68
Marl 2.72

 

11.9Quality Assurance and Quality Control

 

Fortuna operates company-wide standard operational procedures for quality control of sampling and assaying. These procedures are in keeping with global industry standards for analytical QA/QC. Fortuna has a corporate procedure for monitoring laboratory performance across West Africa with regular reports on QC results submitted monthly. Strict rules are applied to processing the results from the laboratory, resulting in occasional resubmission of batches or part batches for reanalysis due to QC failures. Additional details are provided in Section 12 on these procedures.

 

11.9.1Database

 

The database for the Diamba Sud Project is currently maintained in Maxwell’s DataShed system, managed by a database administrator from the Boya exploration office. Data

 

October 15, 2025Page 96 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

collected in the field (geological logging, collar information, drill hole metadata) are collected digitally and validated daily at the end of shift by the supervising geologist, and then directly synchronized into the database to prevent transcription errors. Tough-books and MS surface tablets are used to capture data in the field using Maxwell LogChief.

 

Additional validation checks are completed regularly by the administrator for relational consistency within the data collected (from-to sample interval overlaps, data exceeding recorded holes depths, missing data intervals etc.).

 

11.9.2Certified Reference Materials

 

Certified reference materials (CRMs) are used to assess analytical accuracy.

 

Analytical values for a given standard that lie outside a tolerance of ±2 standard deviations from the reference value are considered warnings. Should two or more CRMs within a batch trigger warnings, the batch is considered to have failed with respect to accuracy. The batch is re-assayed, and an investigation is undertaken into the causes of the spurious results. If a CRM returns a value outside ±3 standard deviations from the reference value, it is deemed to have failed and the batch, or partial batch, is re-assayed, and an investigation undertaken.

 

A variety of CRMs are submitted as part of the sampling process in accordance with company standards. At Diamba Sud the CRMs used are produced by OREAS. CRMs submitted during Chesser and Fortuna drill programs are at a rate of 4 per 100 samples (4% insertion rate). Generally, the QA/QC results returned from the analysis of all CRMs from the Chesser and Fortuna programs are deemed acceptable, and the gold analyses are suitable for use in the estimation of Mineral Resources. No specific concerns are apparent from the data and control chart plots for all CRM analyses.

 

11.9.3Field Duplicates

 

Duplicates are obtained from the second core drill split or second RC split. Both original and duplicate samples are prepared and analyzed in the same batch.

 

Field duplicate samples submitted during Chesser and Fortuna drilling programs are to test the precision levels from each batch at a rate of 5 per 100 samples (5%).

 

In both the case of duplicate core and chips, although precision levels monitored via half absolute relative difference methods indicate high variability, the data show reasonable correlation coefficients and linear regressions. Duplicate results for both core and chips are deemed acceptable and indicate no concerns with sample quality at the Project.

 

11.9.4Blanks

 

Blanks submitted during the Chesser and Fortuna drill programs are at a rate of 3 per 100 samples (3%). The blank material is a barren basalt material from the Tambacounda Formation.

 

Blank results returned from the Chesser and Fortuna programs do not indicate issues with sample contamination or switching and are deemed acceptable.

 

11.9.5Twin holes

 

Chesser Resources completed 9 twin holes over Area A, Area D and Karakara for targeting mineralized intervals for metallurgical sampling in 2022. The assay results supported the geologic interpretations.

 

October 15, 2025Page 97 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

11.10Comment on Section 11

 

It is the opinion of the QP that the sample collection and preparation, analytical techniques, security and QA/QC protocols implemented by Chesser and Fortuna for the Diamba Sud Project are consistent with standard industry practices and are suitable for the reporting of exploration results and for use in Mineral Resource estimation.

 

The sampling procedures are adequate for and consistent with the style of gold mineralization under consideration.

 

Analytical results and density determinations are considered to pose minimal risk to the overall confidence level of the Mineral Resource estimates.

 

October 15, 2025Page 98 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

12Data Verification

 

12.1Introduction

 

12.1.1Chesser

 

Chesser results were verified by Fortuna relogging of historical core. Quality control results were assessed including assays for standards, blanks, duplicates and results of twin hole drilling. Additional infill drilling was conducted at all deposits to support and confirm historical drilling and geological interpretation developed by Chesser.

 

12.1.2Fortuna

 

Since taking ownership in 2023, Fortuna staff have adhered to a stringent set of procedures for data storage and validation, performing verification of its data on a monthly basis for all data relating to drilling. The Project employs a Database Administrator who is responsible for oversight of data entry, verification and database maintenance.

 

Fortuna re-logged historical drill core across Area A, Area D and Karakara to validate the historic geological models and mineralized intervals with the re-logging showing good correlation with the pre-existing interpretations. In addition, Fortuna carried out infill drilling and a trial grade-control program of 34 holes on close spaced centers of 10 x 10 m (mimicking the expected grade control drilling pattern spacing) on Area D to validate the block model interpretation. Results from these programs have confirmed geologic interpretations and provide support for resource modeling.

 

12.2Database

 

An audit of the database is conducted quarterly by the Corporate Resource Geologist. A report is filed listing any discrepancies and Boya staff are required to make the necessary corrections.

 

The database was reviewed and validated by Fortuna staff in July 2025. The data verification procedure includes specific checks to verify the data used in the Mineral Resource estimation as set out in Table 12.1.

 

Table 12.1 Database Checklist Summary

 

Collar Checks Survey Checks Geology Checks Assay Checks Density Checks
Missing assays Missing assays Missing collars Missing collars Missing collars
Missing downhole survey Missing downhole assays Missing downhole surveys Missing downhole surveys Missing downhole surveys
Missing geology Missing geology Missing geology Missing geology Depth > total collar depth
Missing density Azimuth corrected for magnetic declination Overlapping from to records Overlapping from to records  
Duplicate holes Magnetic declination checked and correctly applied Gaps between from to records Gaps between from to records  
Duplicate collar positions Survey record at collar Depth > total collar depth Depth > total collar depth  
X-Y collar locations within boundary Down plunging holes have negative dip Geocodes consistent and match set legend Modelling assay fields identified  
Total hole length Up plunging holes have positive dip Missing/unspecified intervals Units and detection limits identified  
Total hole length < any entries in other tables Duplicate survey records   Analytical data conversion, storage and conversion factors  
Initial survey direction in collar table Depth > total collar depth   Modelling grade ranges and assay methodology  

 

October 15, 2025Page 99 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Collar Checks Survey Checks Geology Checks Assay Checks Density Checks
Collars checked against surface DTM and underground solids Traces of new holes checked in plan and section   Highest grades are within stoichiometric limits  
Cross section check completed Anomalies checked and removed from traces   Zero grades do not exist  
Planned collar locations excluded Inconsistencies in alphanumeric fields   Sum of oxides =< 100%  
Spaces in data entry for collar coordinates     Missing or unspecified intervals  
Inconsistencies in Alphanumeric fields     Intervals awaiting assay results identified  
      No spaces in data entry  

 

No significant inconsistencies were discovered. Minor inconsistencies identified relating to spelling or coding errors were reported to the Database Administrator for correction in the database.

 

12.3Collar and Downhole Surveys

 

Downhole surveys were historically taken using a REFLEX EZ shot tool and more recently with the REFLEX GYRO tool. Downhole surveys are validated during the drilling campaign by exploration geologists in three dimensions using Leapfrog Geo. If significant deviation is observed the drilling contractor (IDC or FTE) will be requested to conduct a second survey to confirm. If there are issues, then the equipment will be calibrated and the hole surveyed multiple times to ensure a consistent result. A magnetic declination correction is applied to any REFLEX EZ Shot readings within DataShed.

 

12.4Geologic Logs and Assays

 

The use of Maxwell LogChief software supports the electronic collection of geological and geotechnical information in the field using a standardized system of drop-down menus to promote consistency. In addition, all information is electronically transferred to the database thereby removing the risk of transcription errors.

 

Assays received by Boya are reported in both Portable Document Format (pdf) and Microsoft Excel format. Both documents are compared and only imported into the database if they are in agreement. Importation is performed electronically without requiring transcription.

 

Assay data are verified using a comprehensive QAQC program including the insertion of CRMs, blanks and duplicates for assays reported by ALS and SGS laboratories, as described in Section 11.9.

 

12.5Sample Type Comparison

 

Reverse circulation, diamond and reverse circulation with diamond tail holes are drilled at Diamba Sud. A comparison between the different drill hole types was conducted using log probability plots for each deposit. Both separately and globally the drill hole types are considered comparable and do not require separation or omission from the database prior to estimation. All drill hole types were included within this Mineral Resource estimate.

 

October 15, 2025Page 100 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

12.6Mineral Resource Estimation

 

The Mineral Resource estimation methodology followed by Fortuna, as described in Section 14 of this Report, is based on CIM (2019) best practice guidelines.

 

Each step of the process is documented, and a checklist developed that is signed off by Fortuna staff and the corporate reviewer in this case, the QP, when completed.

 

An extensive database audit was conducted on July 7, 2025, by the Mineral Resource geologists in the Technical Services team prior to Mineral Resource estimation. The findings indicated that only minor coding errors were present that required correction.

 

Validation checks were also performed upon importation into Datamine mining software and included searches for overlaps or gaps in sample and geology intervals, inconsistent drill hole identifiers, and missing data. No significant discrepancies were identified.

 

12.7Data Verification by Qualified Persons

 

12.7.1Mr. Eric Chapman

 

Mr. Chapman performed a site visit as outlined in Section 2.3.1.

 

Mr. Chapman reviewed the database audit results and verified the database and is of the opinion that it is suitable for the estimation of Mineral Resources.

 

Mr. Chapman checked randomly selected collar and downhole survey information for each campaign against source documentation. In addition, Mr. Chapman completed a comparison of the surface collar coordinates against the surveyed topographic surface. The wireframes showed a good correlation with collar locations recorded in the database.

 

A validation of the downhole readings was performed by Mr. Chapman by randomly selecting readings taken from individual holes and assessing the level of deviation between successive data points. If significant discrepancies (e.g. >15%) existed between data points, the information was flagged and follow-up checks performed. Mr. Chapman is of the opinion that collar and downhole survey data has been determined using appropriate techniques and is suitable for usage in Mineral Resource estimation. To further verify the assay data, Mr. Chapman randomly selected assay data from the database and compared the assay results stored to those of the original assay certificates. Mr. Chapman is of the opinion that the geological and assay data stored in the database is representative of that reported from the laboratories and is suitable for usage in Mineral Resource estimation.

 

No material sample biases were identified from the QA/QC programs. Analytical data that were considered marginal were accounted for in the resource classifications.

 

Mr. Chapman reviewed the steps used in the Mineral Resource estimate and the outcome and considers the resulting estimate can be used as the basis for the PEA as summarized in this Report. The data validation included reviews of:

 

·Site visit to review core, geological interpretation and discuss estimation methodology.

 

·The database (as described above).

 

·Wireframe modelling to define geological, weathering and mineralization domains.

 

·Statistical evaluation to confirm domaining is appropriate and adheres to the geological interpretation.

 

October 15, 2025Page 101 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Variographic analysis to confirm modelled variograms correspond to experimental variography.

 

·Cross validation results.

 

·Statistical checks on each field contained in the resource block model to confirm minimum/maximum values are not exceeded.

 

·Mineral Resource classification.

 

·Depletion of mined out and remnant/isolated blocks from the model.

 

·Verification of pit shell parameters used to constrain Mineral Resources and costs for the determination of cut-off grades.

 

·Reported Mineral Resources correspond with block models.

 

12.7.2Mr. Paul Weeden

 

Mr. Weedon performed site visits as set out in Section 2.3.2.

 

During site visits Mr. Weedon conducted the following activities:

 

·Review of the geological interpretation and drill core with Boya exploration personnel.

 

·Review of exploration plans and program objectives to ensure any changes to interpretations based on results were appropriately addressed.

 

·Review of results and interpretations, and discussed changes to interpretation and understanding of the mineralization and geological controls to ensure a consistent approach to exploration.

 

·Review of external specialist consultants reports with the site geologists, and provided feedback and direction for further investigations.

 

Mr. Weedon is of the opinion that the geological and sample data collected adequately reflect deposit dimensions, true widths of mineralization, and the style of the deposits. The geological models are appropriate and reasonable and reflect the current understanding of the various Diamba Sud deposits.

 

12.7.3Mr. Raul Espinoza

 

Mr. Espinoza has conducted a comprehensive review of the project by engaging in detailed discussions with Boya mining engineers. These interactions covered review of the inputs used for cut-off grade determination, geotechnical observations, open pit optimization strategy, mine design and proposed mine and plant infrastructure, equipment selection, life of mine (LOM) and scheduling plans. Additionally, Mr. Espinoza consulted with Boya personnel with specialized knowledge regarding local environmental and social aspects of the project to address requirements related to environmental, social, and permitting aspects, and their related impact on operating and capital expenditure.

 

12.7.4Mr. Mathieu Veillette

 

Mr. Veillette performed a site visit as outlined in Section 2.3.3.

 

Mr. Veillette visited the proposed locations of the TSFs, WRSFs and water management facilities. He also reviewed and discussed with Boya site personnel, designs and procedures for the TSFs, WRSFs, geotechnical model, and water balance. He also

 

October 15, 2025Page 102 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

reviewed core logging activities and provided feedback on acquiring more geotechnical data, stream flow and pump test data for water management/balance outcomes.

 

Geotechnical data indicate that the proposed open pit mining method, and WRSF are suitable, based on rock stability. Hydrology data indicate that any future plant will have sufficient access to water to meet its requirements. Mr. Veillette reviewed Piteau’s open pit design work with respect to wall design and stability analyses. Mr. Veillette also reviewed all work performed by Knight Piésold with respect to the TSF and water management related work. He also provided input on WRSF slope designs and open pit offset requirements for slope stability.

 

12.7.5Dr. Leon Lorenzen

 

Dr. Lorenzen has held discussions with Boya exploration geologists in helping select samples for the PEA stage of metallurgical testwork. He also discussed with mining engineers proposed mine and plant infrastructure, proposed mining methods, LOM and scheduling plans.

 

Dr. Lorenzen reviewed the spatial selection of metallurgical samples for testwork to determine their representativity. Sample selection is reliant on the geological characteristics of the deposits, and he therefore collaborated with the Boya geologists on sample selection including evaluation through photos and drone videos. Dr. Lorenzen also inspected all core and samples at the laboratories prior to commencement of any testwork.

 

He has conducted reviews to verify proposed metallurgical recoveries applied in the estimation of Mineral Resources including:

 

·Mineralogical information and reports.

 

·Metallurgical testwork results.

 

·Discussions with Boya geologic staff to ensure representativity of selected metallurgical samples.

 

It is the opinion of Dr. Lorenzen that the Diamba Sud metallurgical samples tested are representative of mineralization defined for each of the deposits (covers the variability), in respect to geographical orientation, depth, mineralization, grade and metallurgical response. Differences between deposits are minimal regarding metallurgical recovery and have been accounted for. Metallurgical assessments have been conducted using tests, assays and mineralogical data appropriate for determining the proposed processing methodology.

 

He considers that the metallurgical information is acceptable to support Mineral Resource estimation and be used for PEA purposes.

 

The proposed process flowsheet selected to treat the mineralized material contained in the deposits is applicable to the type of mineralogy and gold deportment for free milling gold that is planned to be processed at Diamba Sud. The relevant testwork as detailed in Section 13 was selected to confirm the process flowsheet and mass balance as described in Section 17.

 

12.8Comment on Section 12

 

The QPs are of the opinion that the data verification programs performed on the data collected from the Project are adequate to support the geological interpretations, the analytical and database quality, geotechnical and hydrogeological considerations,

 

October 15, 2025Page 103 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

metallurgical recoveries, Mineral Resource estimation and the PEA at the Diamba Sud Project and that, to the knowledge of the QPs, there are no limitations on or failure to conduct such verification that would materially impact the results.

 

October 15, 2025Page 104 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

13Mineral Processing and Metallurgical Testing

 

13.1Introduction

 

Mintrex, now Maca Interquip Mintrex (MIQM), was engaged by Chesser in May 2022 to manage a metallurgical testwork program for Diamba Sud. Dr. Lorenzen was an employe of Mintrex and MIQM during the testwork program and process design stages. The testwork was undertaken by ALS Metallurgy Pty Ltd (ALS) in Perth, Western Australia. MIQM developed, monitored and evaluated a five-stage testwork program for the project. This testwork program was developed to build up scoping study level testwork completed in 2021. Samples were selected by MIQM and Fortuna (Chesser had also selected samples prior to the acquisition by Fortuna) and dispatched from Senegal to Perth for testing in June 2022. The first stage was comminution testwork which was used to determine the mineralization properties. Optimization tests were then conducted in the second stage to determine optimum conditions for cyanidation. The final stage of testwork determined cyanidation at the optimized conditions across a larger number of samples followed by variability testing. Bulk mineral analysis (BMA), rheology and diagnostic leach tests were added during the program to investigate flow properties and gold mineralogy. This report covers the testwork completed as of the effective date of this Report in support of the PEA study while ongoing testwork is conducted for the next phases of the project. Some additional testwork was commissioned and managed by Fortuna to cover additional deposit areas, as well as testwork to support more detailed studies.

 

13.2Sample Preparation

 

Initial testwork was based on samples taken from Area A, Area D and Karakara deposits, with additional bottle roll recovery tests performed on samples from the Kassassoko and Western Splay deposits, and the Bougouda prospect.

 

13.2.1Sample Selection and Identification

 

A total of 25 samples were composited from fresh and oxide mineralization from Area A, Area D and Karakara. Composite selection was performed by Mintrex and Fortuna. Sample selection criteria included wide geographical coverage, a range of depths, lithologies, gold grades and proximity of drill holes. Table 13.1 shows the sample ID, drill hole ID, sample mass, assay head grade and lithology of the supplied samples. Figure 13.1 shows the plan view of the metallurgical sample locations for Area A and Area D with Figure 13.2 providing a view of Section C. Figure 13.3 shows the plan view of the metallurgical sample locations for Karakara with Figure 13.4 showing Section B.

 

Table 13.1 Samples taken for metallurgical testing

 

Sample ID Drill Hole ID Total Sample
Mass (kg)
Head Grade
(g/t Au)
DA Oxide-1 DSDD051, DSDD052 77 3.81
DA Oxide-2 DSDD042 96 2.06
DA Oxide-3 DSDD034, DSDD016 44.5 0.63
DA Fresh-1 DSDD052, DSDD032 47 1.38
DA Fresh-2 DSDD042, DSDD033 57.5 1.60
DA Fresh-3 DSDD007, DSDD016 49 2.60
DB Oxide-1 DSDD040 109 6.22
DB Oxide-2 DSDD035, DSDD029 41 5.81
DB Fresh-1 DSDD014 67 1.68

 

October 15, 2025Page 105 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Sample ID Drill Hole ID Total Sample
Mass (kg)
Head Grade
(g/t Au)
DB Fresh-2 DSDD035, DSDD029 42 1.63
DC Oxide-1 DSDD036, DSDD030 28.5 3.14
DC Fresh-1 DSDD019, DSDD030 49 1.01
AA Fresh-1 DSDD020, DSDD064 72.5 3.72
AB Fresh-1 DSDD024, DSDD059 72.5 1.28
AB Fresh-2 DSDD058, DSDD003 50.5 1.15
AB Fresh-3 DSDD011 24.9 NA
AB Fresh-4 (Previously AB Oxide-1) DSDD011, DSDD059 61 0.27
AC Fresh-1 DSDD013, DSDD008 87 1.48
AC Fresh-2 DSDD060, DSDD068 63.5 2.26
AC Fresh-3 DSDD002 27 2.00
KARA Fresh-1 DSDD069, DSDD077 54 4.62
KARB Fresh-1 DSDD075, DSDD076 75 2.63
KARB Fresh-2 DSDD076 61 0.03
KARB Fresh-3 DSDD073 79 3.07
KARC Fresh-1 DSDD074 78.5 2.77
KARC Fresh-2 DSDD071 56 3.11
DAOxideVAR1 DSDD044, DSDD047 63.5 0.88
DBOxideVAR1 DSDD015, DSDD035, DSDD038, DSDD041 82 2.09
DCOxideVAR1 DSDD036 DSDD057 32 0.58
DCOxideVAR2 DSDDM098 53 3.47
DCOxideVAR3 DSDDM097 56 8.95
DCOxideVAR4 DSDDM100 50 1.67
DAFreshVAR1 DSDD044 45 6.88
DBFreshVAR1 DSDD015, DSDD018, DSDD055 77.4 1.46
DCFreshVAR1 DSDD030, DSDD054, DSDD057 39 0.9
AAFreshVAR1 DSDDM094 162 2.01
AAFreshVAR2 DSDD064 66.5 0.45
ABFreshVAR1 DSDD066, DSDD067 60.5 3.75
ABFreshVAR2 DSDD066 59 1.62
ACFreshVAR1 DSDD004, DSDD008 89.5 1.23
ACFreshVAR2 DSDD060 22 0.53
KARAFreshVAR1 DSDDM106 97 5.07
KARBFreshVAR1 DSDDM103 71 5.81
KARBFreshVAR2 DSDDM103 105 4.76
KARCFreshVAR1 DSDD070 86 1.07

 

Note: Sample IDs are named to reference the resource pit area, section, weathering and sequential sample number. For example, “DA Oxide-1” refers to pit Area “D” and section “A”, the sample is categorized as mostly “Oxide” and is the first in that area and section. Variability samples are prefixed by “Var”.

 

October 15, 2025Page 106 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 13.1 Map Showing Location of Metallurgical Samples for Area A and Area D

 

 

Figure prepared by Fortuna, 2024

 

October 15, 2025Page 107 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 13.2 Metallurgical Sample Location for Area A and Area D – Section C

 

 

Figure prepared by Fortuna, 2024

 

Figure 13.3 Map Showing Location of Metallurgical Samples for Karakara

 

 

Figure prepared by Fortuna, 2024

 

October 15, 2025Page 108 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 13.4 Metallurgical Sample Location for Karakara – Section B

 

 

Figure prepared by Fortuna, 2024

 

There was significantly more fresh than oxide mineralization samples available from the core drilling. All fresh samples were half core but due to the friability of the oxide mineralization, the samples available were too small for reliable SMC and Bond impact crushing work index (CWi) tests. These tests were therefore not conducted on oxide mineralization. Head assays conducted show a wide range of head grades from 0.8–5.5 g/t Au. The KARB Fresh-2 sample gold grade was very low and therefore the sample was not used in further leach testwork.

 

13.2.2Quantification of Minerals

 

A total of 26 samples were provided to ALS for semi-quantitative X-ray diffraction (XRD) analysis. XRD is used to analyze the samples whilst a combination of matrix flushing and reference intensity ration (RIR) derived constants were used to identify and quantify sample mineralogy. The XRD test results are shown for Area D in Table 13.2 and for Area A and Karakara in Table 13.3. Minerals identified were common for gold deposits. No major cyanide consumers or deleterious minerals were identified.

 

October 15, 2025Page 109 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 13.2 Summary of XRD Analysis for Area D

 

Mineral or Mineral Group DA_Oxide_
1
DA_Oxide_
2
DA_Oxide_
3
DA_Fresh_
1
DA_Fresh_
2
DA_Fresh_
3
DB_Oxide_
1
DB_Oxide_
2
DB_Fresh_
1
DB_Fresh_
2
DC_Oxide_
1
DC_Fresh_
1
Clay mineral 10 0 0 0 < 1 0 26 11 0 0 0 0
Kaolinite 54 46 40 0 0 0 37 43 0 0 69 0
Chlorite 0 0 0 0 1 0 0 0 0 0 0 1
Annite - biotite - phlogopite 0 1 1 0 0 0 0 0 0 0 0 1
Muscovite 1 7 5 0 1 0 3 1 0 1 1 0
Talc 0 0 0 0 0 0 0 0 0 0 0 0
Calcic amphibole 0 0 0 0 0 0 0 0 0 0 0 0
Plagioclase 5 0 0 43 19 31 8 11 34 31 0 49
K-feldspar 2 3 4 2 1 2 2 2 0 0 0 0
K-feldspar and/or rutile 0 0 0 0 0 0 0 0 0 < 1 0 1
Quartz 16 24 37 24 12 8 13 13 3 3 16 9
Rutile 2 2 0 0 0 0 2 0 0 0 2 0
Anatase 0 0 0 0 0 0 0 0 0 0 0 1
Calcite 0 0 0 0 0 0 0 0 0 < 1 0 0
Dolomite - ankerite 0 0 0 27 60 55 5 4 62 64 0 37
Siderite type carbonate 0 0 0 0 4 0 0 0 0 0 0 0
Goethite 10 14 11 0 0 0 5 15 0 0 13 0
Hematite 0 2 2 0 0 1 0 0 0 0 0 0
Magnetite 0 0 0 0 0 0 0 0 0 0 0 0
Pyrite 0 0 0 4 2 4 0 0 1 1 0 2
Pyrite and/or hematite 0 0 0 0 0 0 0 0 0 0 0 0

 

October 15, 2025Page 110 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 13.3 Summary of XRD Analysis for Area A and Karakara

 

Mineral or
Mineral Group
AA_Fresh_
1
AB_Fresh_
1
AB_Fresh_
2
AB_Fresh_
4
AC_Fresh_
1
AC_Fresh_
2
AC_Fresh_
3
KARA_Fresh_
1
KARB_Fresh_
1
KARB_Fresh_
2
KARB_Fresh_
3
KARB_Fresh_
4
KARC_Fresh_
1
KARC_Fresh_
2
Clay mineral 0 0 0 2 0 0 0 0 0 0 2 2 2 0
Kaolinite 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Chlorite 0 1 < 1 1 0 0 0 0 1 < 1 2 0 1 1
Annite - biotite - phlogopite 0 < 1 1 8 1 1 0 0 0 < 1 1 1 1 < 1
Muscovite < 1 0 0 0 0 0 0 < 1 1 0 0 0 0 0
Talc 0 0 0 1 0 0 0 0 < 1 0 < 1 2 0 0
Calcic amphibole 0 0 0 3 0 0 0 0 0 0 4 0 0 0
Plagioclase 63 61 54 68 51 63 71 68 19 68 30 23 42 56
K-feldspar 5 2 3 0 6 3 2 0 1 2 1 0 3 2
K-feldspar and/or rutile 0 0 0 1 0 0 0 1 0 0 0 1 0 0
Quartz 6 7 14 9 9 15 9 8 14 10 7 16 16 16
Rutile 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Anatase 1 1 1 1 < 1 1 1 1 0 1 0 0 < 1 0
Calcite 0 0 0 2 0 0 0 1 0 0 12 0 0 0
Dolomite - ankerite 24 27 24 1 32 14 16 21 61 19 39 48 34 22
Siderite type carbonate 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Goethite 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Hematite 0 < 1 0 0 0 0 0 0 0 0 0 0 0 0
Magnetite 0 0 0 0 0 0 0 0 0 0 0 5 0 0
Pyrite 1 1 3 2 1 3 1 1 2 0 2 2 2 2
Pyrite and/or hematite 0 0 0 0 0 0 0 0 0 < 1 0 0 0 0

 

October 15, 2025Page 111 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

13.3Comminution Testwork

 

The first stage of testwork consisted of comminution tests to help determine hardness, abrasion and breakage properties to provide input for comminution modelling. The comminution modelling will be used to provide further information on the comminution circuit selection. The testwork program included Bond abrasion index (Ai), ball mill work index (BWi), CWi, and semi-autogenous grind (SAG) mill comminution (SMC) tests.

 

13.3.1Abrasion Index

 

Ai values ranged from 0.0416–0.3333, and averaged 0.1829 in the fresh samples. These Ai values are normal for non-abrasive gold-bearing mineralized material, with three samples from Area D with slightly less abrasiveness than average. The most abrasive sample, also from Area D, was not more abrasive than normal gold-bearing mineralization. The mineralized material (irrespective of domain) is unlikely to pose any significant problems with abrasiveness.

 

13.3.2Crushing Index

 

Table 13.4 shows the CWi results for each composite.

 

CWi values below 7 kWh/t are very soft, between 7–9 kWh/t are soft while 9–14 kWh/t are considered medium, and 14–20 kWh/t hard.

 

Most testwork CWi values at Diamba Sud are between 4–8 kWh/t which indicates the majority of the mineralized material is either very soft or soft. The CWi for one Area A sample (15.1 kWh/t) indicates hard mineralization. This isolated sample is an outlier and either indicates variability or a spurious result in Area A.

 

Table 13.4 Bond Crushing Work Index Results

 

Sample ID Average CWi
(kWh/t)
Category
AA FRESH-1 15.1 Hard
AB FRESH-1 4.5 Very soft
AB FRESH-2 6.3 Very soft
AB FRESH-4 5.7 Very soft
AC FRESH-1 4.4 Very soft
AC FRESH-2 5.3 Very soft
AC FRESH-3 5.9 Very soft
DA FRESH-1 6.8 Very soft
DA FRESH-2 5.6 Very soft
DA FRESH-3 4.0 Very soft
DB FRESH-1 4.4 Very soft
DB FRESH-2 7.6 Soft
DC FRESH-1 6.6 Very soft
KARA FRESH-1 6.1 Very soft
KARB FRESH-1 6.3 Very soft
KARB FRESH-2 7.3 Soft
KARB FRESH-3 4.2 Very soft
KARC FRESH-1 6.4 Very soft
KARC FRESH-2 6.0 Very soft

 

October 15, 2025Page 112 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

13.3.3Ball Mill Work Index

 

BWi values between 14–20 kWh/t indicate mineralization that is moderate to hard. BWi values above 20 kWh/t indicate mineralization that is very hard. The results of the testwork shows a range of BWi values from 10.4–22.1 kWh/t for fresh mineralized material to reach a P80 of ~60 µm. Therefore, mineralization is primarily moderate to hard. Compared to typical gold ores this material is moderate. Only one sample, from Karakara, showed a BWi value above 20 kWh/t, while six samples, five from Area D and one from Karakara, showed BWi values below 14 kWh/t.

 

Oxide samples were too friable to be tested, which is typical for weathered composites. Generally, blending weathered mineralization with fresh mineralization is recommended during operation to decrease the impact of variability. Area D contains significant mineralized oxide material without easily available fresh mineralization for blending and therefore a comminution circuit capable of processing only soft oxide mineralization for periods of time will be crucial.

 

13.3.4SMC Testwork

 

The oxide mineralized samples were too friable for SMC testwork and were thus excluded – this is not considered material at this stage of Project evaluation. Table 13.5 shows the results of the SMC testwork with the attributes reported represented as follows:

 

·A is the resistance of breaking larger particles.

 

·b is breakage of smaller particles.

 

·A*b allows comparison of different mineralization types – the smaller the value the greater the resistance to comminution.

 

·ta is a measure of resistance to abrasion grinding.

 

The A*b values, ranging from 27–53 from this testwork indicate mostly hard composites with few outliers. The SAG circuit specific energy (SCSE) value is derived from simulations of a “standard” circuit of a single-stage SAG mill in closed circuit. The SCSE results for these composites indicate that the mineralized material could be suitable for single-stage crushing followed by SAG mill or a SAG–ball mill–crusher comminution (SABC) circuit in agreement with the BWi data. The results for ta compared well with the Ai values indicating that the material will be hard to very hard regards to abrasion (0.25 to 0.42), which is higher than the Ai indicated.

 

Table 13.5 SMC Results

 

Sample Info SMC
A b A x b DWi
(kWh/m3)
DWi
(%)
ta Mia
(kWh/t)
Mic
(kWh/t)
Mih
(kWh/t)
SCSE
(kWh/t)
AA FRESH-1 86.7 0.34 29.5 9.4 82 0.28 24.9 10.2 19.7 11.60
AA FRESH VAR-1 73.3 0.46 33.7 8.1 68 0.33 22.7 17.4 9.0 10.65
AB FRESH-1 91.4 0.34 31.1 8.6 74 0.30 23.7 9.5 18.4 11.16
AB FRESH-2 92.9 0.33 30.7 9.0 78 0.29 24.4 9.9 19.2 11.26
AB FRESH-4 65.5 0.61 40.0 6.6 50 0.39 19.7 7.5 14.5 9.78
AB FRESH VAR-1 63.8 0.68 43.4 6.2 44 0.42 18.3 13.4 6.9 9.51
AC FRESH-1 89.4 0.37 33.1 7.9 66 0.33 23.0 9.1 17.6 10.62
AC FRESH-2 91.5 0.33 30.2 9.0 79 0.29 24.7 10.0 19.4 11.29
AC FRESH-3 93.1 0.32 29.8 9.1 80 0.29 24.9 10.1 19.6 11.37

 

October 15, 2025Page 113 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Sample Info SMC
A b A x b DWi
(kWh/m3)
DWi
(%)
ta Mia
(kWh/t)
Mic
(kWh/t)
Mih
(kWh/t)
SCSE
(kWh/t)
AC FRESH VAR-1 59.3 0.89 52.8 5.1 30 0.50 15.6 11.0 5.7 8.76
DA FRESH-1 81.8 0.40 32.7 8.4 72 0.30 22.7 9.1 17.6 11.06
DA FRESH-2 75.0 0.58 43.5 6.6 49 0.39 18.0 6.9 13.3 9.85
DA FRESH-3 80.2 0.50 40.1 7.1 56 0.36 19.4 7.5 14.5 10.19
DB FRESH-1 69.0 0.64 44.2 6.8 52 0.38 17.8 6.8 13.2 10.02
DB FRESH-2 93.7 0.36 33.7 8.2 69 0.32 22.3 8.9 17.2 10.82
DB FRESH VAR-1 61.7 0.82 50.6 5.6 36 0.5 16.0 11.4 5.9 9.11
DC FRESH-1 100.0 0.27 27.0 10.5 90 0.25 26.8 11.2 21.7 12.26
KARA FRESH-1 71.7 0.61 43.7 6.1 42 0.42 18.2 6.8 13.2 9.45
KARB FRESH-1 76.6 0.45 34.5 8.1 68 0.32 21.7 8.6 16.7 10.86
KARB FRESH-2 85.8 0.35 30.0 8.8 77 0.29 24.4 9.9 19.1 11.27
KARB FRESH-3 73.1 0.45 32.9 8.8 77 0.30 22.8 9.20 17.80 11.32
KARC FRESH-1 75.7 0.51 38.6 6.9 53 0.37 20.0 7.70 14.90 10.00
KARC FRESH-2 83.3 0.41 34.2 8.0 67 0.33 22.3 8.80 17.10 10.63

 

Figure 13.5 is an extract from the SMC report which compares the A*b of the Diamba Sud tested composites to the SMC database of over 1,300 different deposits which confirms the mineralized material is average to harder than average. Material competency will influence the comminution design towards more energy efficiency circuits.

 

Figure 13.5 Diamba Sud A*b vs SMC Database

 

 

 

Figure prepared by JKTech, 2024

 

13.4 Leach and Cyanidation Testwork

 

The second stage of testwork was focused on optimizing the conditions for leaching the gold from the mineralized material by cyanidation including some gravity separation

 

October 15, 2025Page 114 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

testwork. The first step for this testwork was to determine how much gold was recoverable by gravity before the leach. This was done on all 24 composites. Next, nine composites were selected to determine the optimum leaching conditions. Two oxides from Area D and seven fresh samples from Area A, Area D and Karakara were selected. The effect of various conditions and parameters on gold recovery during cyanide leaching were then examined using the selected samples, namely:

 

·Grind size.

·Use of air or oxygen.

·Addition of lead nitrate.

·Inclusion of carbon in the leach.

·Cyanide concentration.

·Mass fraction of solids.

 

Finally, nine composites were selected for bulk gravity, leaching at optimized conditions, and carbon testwork.

 

13.4.1Gravity Concentration

 

The composite samples were initially subjected to gravity concentration testwork to determine the gravity gold component that can be expected from the various domains. Gravity concentration was tested using a laboratory-scale Knelson concentrator, followed by intensive leach. This preliminary gravity testwork comprised 24 3-kg samples. Optimization testwork involved a selection of nine samples each weighing 14 kg. An additional 12 samples were tested during the bulk leach phase. Table 13.6 shows the results of the initial gravity recovery tests, gravity testwork for optimization and gravity concentration for the bulk leach testwork.

 

Gravity testwork indicated that the mineralized material contains a large proportion of free/gravity-recoverable gold. The proportion of gravity-recoverable gold varied from 19–40% for selected oxide samples and 27–81% for selected fresh samples. Broadly, the higher gold grade fresh samples had higher fractions of gravity gold, while the lower-grade samples had comparatively lower gravity recoveries. Intensive leach results indicate gold recoveries from the gravity concentrate as being >99%.

 

Similar results were indicated with the optimization and gravity concentration for bulk leach testwork with marginally lesser gravity-recoverable gold mostly attributed to the lower proportion of mass pull. The available gravity-recoverable gold remains high, and this provides further support for inclusion of a gravity circuit.

 

Table 13.6 Gravity Recovery Results

 

Sample ID Gravity Screening Optimization Testwork Gravity Concentration for Bulk Leach
Calculated
Gold Grade
(g/t)
Gold Gravity
Recovery
(%)
Calculated
Gold Grade
(g/t)
Gold Gravity
Recovery
(%)
Calculated
Gold Grade
(g/t)
Gold Gravity
Recovery
(%)
DA OXIDE-1 3.13 14.1 2.9 8.7 2.87 27.5
DA OXIDE-2 1.84 40.7        
DA OXIDE-3 0.82 31.8        
DB OXIDE-1 5.70 40.7 5.8 39.0 5.82 44.2
DB OXIDE-2 6.25 37.4        
DB FRESH-1 1.28 51.6     1.17 48.2
DB FRESH-2 1.84 59.1     1.71 63.4

 

October 15, 2025Page 115 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Sample ID Gravity Screening Optimization Testwork Gravity Concentration for
Bulk Leach
Calculated
Gold Grade
(g/t)
Gold Gravity
Recovery
(%)
Calculated
Gold Grade
(g/t)
Gold Gravity
Recovery
(%)
Calculated
Gold Grade
(g/t)
Gold Gravity
Recovery
(%)
DC OXIDE-1 3.43 31.1        
DC FRESH-1 1.07 42.0 1.2 31.6 1.18 32.1
AA FRESH-1 2.96 72.6 3.3 69.1 3.27 70.1
AB FRESH-1 1.13 65.3 1.4 68.8    
AC FRESH-1 2.09 68.4 1.5 67.6    
KARA FRESH-1 2.84 80.0 3.5 74.3 3.71 81.1
KARB FRESH-1 1.77 72.9        
KARB FRESH-3 3.10 77.4 3.3 60.1 3.30 67.0
KARC FRESH-1 2.78 58.6        
KARC FRESH-2 3.81 63.7 4.6 58.2 4.05 67.2
DA FRESH-1 0.79 34.0     0.83 34.0
DA FRESH-2 1.77 57.0     1.94 53.9
DA FRESH-3 2.46 55.8     2.49 56.7
AB FRESH-2 0.96 60.5        
AC FRESH-2 1.25 64.7        
AC FRESH-3 2.30 55.1        
KARB FRESH-4 2.44 58.6        

 

13.4.2Grind Size Optimization

 

Tails from the bulk gravity testwork were ground to particle sizes of P80 180 µm, 150 µm, 106 µm and 75 µm to investigate the optimum grind size. Oxide samples were not tested at 180 µm due to initial particle size reporting mostly finer than 180 µm with screen sizing. Samples were leached under standard cyanidation conditions with solution samples extracted at 1, 2, 4, 8, 12, 24, and 48 hour intervals at 40% w/w with oxygen sparging. A summary of results of the tests is shown in Table 13.7. Note that the total recovery column includes gravity recovery.

 

Table 13.7 Grind Size Optimization Results

 

Sample ID Grind Size
P80
(µm)
Total Recovery
After 12h
(%)
Total Recovery
After 24h
(%)
Total Recovery
After 48h
(%)
DA OXIDE-1 150 93.2 94.9 97.4
DA OXIDE-1 106 93.0 93.0 97.1
DA OXIDE-1 75 92.2 93.1 96.6
DB OXIDE-1 150 95.5 96.7 98.2
DB OXIDE-1 106 96.7 96.7 98.3
DB OXIDE-1 75 90.4 97.7 99.1
DC FRESH-1 180 65.9 66.5 67.1
DC FRESH-1 150 71.8 71.8 71.8
DC FRESH-1 106 73.6 74.2 74.2
DC FRESH-1 75 79.1 79.1 79.1
AA FRESH-1 180 94.9 95.7 96.7
AA FRESH-1 150 95.5 96.3 97.4
AA FRESH-1 106 95.9 97.1 97.7

 

October 15, 2025Page 116 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Sample ID Grind Size
P80
(µm)
Total Recovery
After 12h
(%)
Total Recovery
After 24h
(%)
Total Recovery
After 48h
(%)
AA FRESH-1 75 96.2 97.0 98.0
AB FRESH-1 180 93.5 94.4 95.3
AB FRESH-1 150 94.3 94.8 94.8
AB FRESH-1 106 95.5 96.0 96.0
AB FRESH-1 75 95.2 95.2 96.1
AC FRESH-1 180 95.7 97.0 97.0
AC FRESH-1 150 95.8 96.2 97.0
AC FRESH-1 106 96.9 98.2 98.2
AC FRESH-1 75 97.8 98.2 98.2
KARA FRESH-1 180 97.4 97.5 97.7
KARA FRESH-1 150 96.6 96.5 96.7
KARA FRESH-1 106 98.0 98.1 98.1
KARA FRESH-1 75 98.4 98.4 98.6
KARB FRESH-3 180 93.9 94.1 94.4
KARB FRESH-3 150 94.8 95.5 95.9
KARB FRESH-3 106 95.7 96.5 96.5
KARB FRESH-3 75 97.5 97.5 97.5
KARC FRESH-2 180 95.7 96.3 96.6
KARC FRESH-2 150 97.1 97.1 97.7
KARC FRESH-2 106 97.3 97.3 97.8
KARC FRESH-2 75 98.3 98.3 98.3

 

Figure 13.6 shows that the highest gold recoveries at 24 hours were experienced at a P80 of 75 µm. There is generally an inverse relationship between grind size and gold leach recovery; this is to be expected, as finer grind size increases the surface area of the sample, and thus the leaching kinetics and total available gold. This is consistent across all samples with some degree of measurement variability. A preliminary economic evaluation was conducted to determine the preferred grind size. A finer grind size shows a higher gold recovery at the cost of additional grinding power. The evaluation based on estimated grinding power indicated an optimal grind size of 106 µm for the fresh and oxide samples. Optimum gold recovery is achieved at 24 hours for fresh samples at 106 µm and at 12 hours for oxide samples, also at 106 µm.

 

October 15, 2025Page 117 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 13.6 Grind Size Optimization of Area A, Area D and Karakara Deposits

 

 

 

Figure prepared by MIQM, 2024

 

The DC Fresh-1 sample, from Area D, showed a significant lower gold recovery compared to other samples with only 74% gold recovery (106 µm) at 24 and 48 hours. This indicates additional residence time would not increase recovery of DC Fresh-1. Diagnostic leaching of DC Fresh-1 residue showed 96% of the gold in the leach tails can be recovered by aqua regia digest. This indicates the remaining gold was predominately associated with gold locked in non-silicate, quartz, and sulfide minerals. Thus, DC Fresh-1 can be classified as semi-refractory, and ultrafine grinding would be needed to extract the remaining gold after initial cyanidation.

 

13.4.3Effect of Lead Nitrate on Cyanidation

 

The DC Fresh-1 was the only sample that would have potential benefits from addition of lead nitrate. Figure 13.7 compares the kinetics of the gold extraction from mineralization when 200 g/t of lead nitrate is added against no lead nitrate.

 

October 15, 2025Page 118 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 13.7 Lead Nitrate vs Au Recovery of DC Fresh-1

 

 

 

Figure prepared by MIQM, 2024

 

The leach kinetics show minimal impact of lead nitrate with recovery converging at 24 hours. Lead nitrate is therefore not recommended for further testwork. Fresh mineralization in Area D accounts for 16% of the total estimated Mineral Resource.

 

13.4.4Effect of Air on Cyanidation

 

Figure 13.8 shows the average kinetics of the extraction of gold from mineralization across eight samples with oxygen and with air sparging. The gold recovery (%) represented in this figure is presented as total gold recovery and therefore includes gravity gold recovery.

 

Figure 13.8 Oxygen vs Air Sparging

 

 

 

Figure prepared by MIQM 2024. Note: *Average is across 8 samples (Optimization samples exclude anomalous DC Fresh-1 result).

 

The overall recovery of gold is not significantly impacted by the use of oxygen instead of air for leaching after 24 hours as the total recovery of gold (including gravity) was around

 

October 15, 2025Page 119 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

95–98% in all cases (excluding DC Fresh-1) and averaged 97.2%. The results also demonstrate that gold leaching kinetics during the initial stages of leaching increased marginally when using oxygen compared to air. This is expected as the additional oxygen sparging provides excess oxygen reagent for gold liberation but does not increase final recovery. While the mineralized material does not appear to be a large oxygen consumer, it was decided that oxygen should be recommended for further testwork and bulk tests for optimal results.

 

13.4.5Carbon in Leach

 

The effect on total gold recovery when carbon was added during leaching was also investigated. This will inform the decision as to whether to proceed with a carbon in leach (CIL) or carbon in pulp (CIP) circuit or a hybrid for the potential flowsheet. Table 13.8 shows the gold extraction with leach only (no carbon) and with 20 g/L of carbon (CIL column) after 48 hours. Leach conditions were held at 40% w/w, 106 µm, oxygen sparge, 1000 ppm CN initial and 500 ppm CN maintained. CIL recovery includes carbon assay and solution assay as almost all extracted gold in solution will be adsorbed to carbon during staged CIL. Gold leaching circuits for free-milling mineralized material of this type typically have 24 hours or less residence time. CIL testwork recovery shows virtually identical leach recoveries with or without carbon. This supports the use of activated carbon for the adsorption of gold in solution and a CIL circuit.

 

Table 13.8 CIL vs Leach Only Cyanidation

 

Sample ID

Au Recovery: Direct Leach
(no Carbon)

48 hours

Au Recovery: CIL
(Carbon in Leach)
48 hours

DA OXIDE-1 97.1 98.9
DB OXIDE-1 98.3 98.0
DC FRESH-1 74.2 65.4
AA FRESH-1 97.7 97.9
AB FRESH-1 96.0 94.7
AC FRESH-1 98.2 97.6
KARA FRESH-1 98.1 97.8
KARB FRESH-3 96.5 96.9
KARC FRESH-2 97.8 97.6
DA OXIDE-1 97.1 98.9
Average* 97.5 97.4

 

Note* Average is across 8 samples (excluding anomalous DC-Fresh-1 result).

 

13.4.6Effect of Cyanide Concentration on Cyanidation

 

The average cyanide consumption at 1,000 ppm initial and 500 ppm maintained was roughly 0.37 kg/t across the eight samples (excluding DC Fresh-1 at a gold grade of 0.29 g/t), this is within the expected range, and average for this type of plant. Figure 13.9 shows the effect of different cyanide concentrations at 250 ppm, 500 ppm and 1,000 ppm initially and maintained at 100 ppm, 250 ppm and 500 ppm, respectively.

 

October 15, 2025Page 120 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 13.9 Effect of NaCN Concentration on Cyanidation

 

 

 

Figure prepared by MIQM, 2024.

 

The results generally show that increasing cyanide concentration marginally increases leaching kinetics during the first eight hours of leaching. Total recoveries from all composites mostly converge after 24 hours of leaching with highest recovery at 1,000 ppm CN. Increasing cyanide concentration also increases overall consumption.

 

Table 13.9 shows how average cyanide consumption changes with cyanide concentration across the eight samples (excluding DC Fresh-1).

 

Table 13.9 Effect of Cyanide Concentration on Gold Recovery and Reagent Consumption after 24 hours

 

Initial Cyanide
Concentration  
(ppm)
Gold Recovery at
24 Hours
(%)
Cyanide
Consumption
(24h)
(kg/t)
Lime Consumption
(24h)
(kg/t)
1,000 96.6 0.37 1.3
500 96.3 0.21 1.1
250 95.7 0.11 0.8

 

Overall cyanide consumption is as expected for free-milling mineralized material. Broadly, cyanide consumption reduces significantly when reducing concentrations from 1,000 ppm to 500 ppm, then slightly more when decreasing from 500 ppm to 250 ppm. As summarized in Table 13.10, oxide mineralization consumes more cyanide than fresh mineralization. Lime is generally used to maintain pH above 9.8. Fresh mineralization lime consumption is between 0.2–0.4 kg/t, as expected. Oxide mineralization lime consumption has a wider variation, between 1.5–4.8 kg/t, as expected.

 

October 15, 2025Page 121 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 13.10 Average Reagent Consumption after 24 hours at 1,000 ppm Cyanide Between Fresh and Oxide Mineralization

 

Lithology Cyanide Consumption
(24h)
(kg/t)
Lime Consumption
(24h)
(kg/t)
Fresh (45% w/w) 0.31 0.34
Oxide (35% w/w) 0.45 4.2

 

In summary, reducing cyanide concentration did have a marginal effect on total gold recovery at 24 hours. Using the cost for supplied cyanide applicable as of the effective date of this Report, a comparison between cost of additional consumed cyanide was compared to the average increase in recovery and it was determined that an initial 1,000 ppm CN concentration was the optimum leach condition for bulk leaching tests. Leaching kinetics also improves slightly with increased concentration. Therefore, in the event of reduced residence time, higher cyanidation would be beneficial.

 

13.4.7Effect of Solid Concentration on Cyanidation

 

The recovery of gold from the mineralized material was tested at solids mass fractions varying from 25–40% at 5% intervals for oxide mineralization and 35–45% at 5% intervals for fresh mineralization. Oxide composites were very viscous due to some clay pockets at concentrations above 40%. Figure 13.10 and Figure 13.11 show the average impact of solids mass fraction on the oxide and fresh samples (excluding DC Fresh-1) gold recoveries, respectively.

 

Figure 13.10 Effect of Solid Mass Fraction (%) – Oxides

 

 

 

Figure prepared by MIQM, 2024.

 

October 15, 2025Page 122 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 13.11 Effect of Solid Mass Fraction (%) – Fresh

 

 

 

Figure prepared by MIQM, 2024. Note: *Average is across 8 samples (excluding anomalous DC Fresh-1 result).

 

The results of the tests show that there is no major impact on total gold recovery when increasing solids mass fraction. Figure 13.10 broadly shows faster kinetics in the lower concentration samples initially, with all samples having nearly the same gold recovery by 24 hours. Maximum recovery is placed between 25–35%, with 35% selected for the remaining bulk leach testwork. Figure 13.11 shows very similar recovery by 24 hours across all samples (excluding DC-Fresh-1). Again, a very high recovery is achieved at 24 hours (~97%). The results don’t clearly indicate any benefit in gold recovery at the various solids concentrations at 24 hours.

 

The solids mass concentration for the bulk leach tests to be conducted was thus chosen on the basis of a possible process flowsheet. While higher solids mass fraction is attractive for minimizing the water requirement for the plant and reducing the total tank volume required, it is difficult to achieve high solids concentrations from oxide mineralization based on previous testwork. A pre-leach thickener is recommended and included in the process design to achieve 45% solids for fresh mineralization.

 

13.4.8Bulk Leach Testwork

 

After the optimum leaching conditions were determined, the next stage of testing applied these optimal conditions to 12 samples of which five from Area D were not used during the optimization tests. Additionally, the equilibrium carbon loading was tested, and sequential CIP/CIL tests were conducted. Intensive leaching tests of the gravity concentrate were also conducted.

 

October 15, 2025Page 123 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The original 12 selected samples and 19 variability samples were ground to 106 µm, then separated by gravity concentration into a concentrate and tails. The tails were subjected to cyanidation at 1,000 ppm NaCN initially and maintained at 500 ppm NaCN, with oxygen sparging, no lead nitrate addition and a solids concentration of 35% for oxide and 45% for fresh samples. Lime was used to maintain the pH above 9.8. Table 13.11 shows the leach recovery (of gravity tails) and total recovery (gravity and leach) at 24 hours.

 

Table 13.11 Bulk Leach Testwork Summary

 

Sample ID %
Solids
(w/w)
Calculated
Assay
Head (g/t)
Leach Recovery
after 24h
(% of gravity
tails)
Total Au
Recovery
(% of head feed)
NaCN
Cons’n
(kg/t)
Lime
Cons’n
(kg/t)
DA OXIDE-1 35 2.87 94.7 96.2 1.05 1.61
DB OXIDE-1 35 5.82 93.1 96.1 1.02 2.38
DA FRESH-1 45 0.83 60.0 73.6 0.61 0.93
DA FRESH-2 45 1.94 76.5 89.2 0.75 1.14
DA FRESH-3 45 2.49 82.3 92.4 0.49 0.45
DB FRESH-1 45 1.17 71.2 85.1 0.55 0.32
DB FRESH-2 45 1.71 66.4 87.7 0.30 0.32
DC FRESH-1 45 1.18 55.7 69.9 0.39 0.39
AA FRESH-1 45 3.27 93.9 98.2 0.36 0.37
KARA FRESH-1 45 3.71 90.0 98.1 0.33 0.66
KARB FRESH-3 45 3.30 89.9 96.7 0.39 0.82
KARC FRESH-2 45 4.05 91.7 97.3 0.24 0.72

 

The bulk leach test results correlate well with the optimization results. The overall recovery ranged between 70–98% with an average of 92% (excluding DC Fresh-1), and had an average residue grade of 0.15 g/t Au. The consumption of cyanide varied from 0.44 kg/t for fresh mineralization and 1.04 kg/t for oxide mineralization. Lime consumption varied from 0.61 kg/t for fresh and 2.0 kg/t for oxide samples.

 

The bulk leach variability test results are presented in Table 13.12.

 

Table 13.12 Bulk Leach Testwork Summary - Variability Tests

 

Sample ID %
Solids
(w/w)
Calculated
Assay
Head (g/t)
Gravity
Recovery
(%)
Leach Recovery
after 24h
(% of gravity
tails)
Total Au
Recovery
(% of head
feed)
NaCN
Cons’n
(kg/t)
Lime
Cons’n
(kg/t)
DA OXIDE VAR 1 35 1.20 20.6 78.1 85.0 1.06 2.54
DB OXIDE VAR 1 35 2.21 25.7 86.5 89.6 0.69 1.70
DC OXIDE VAR 1 45 0.60 18.5 83.1 88.2 0.69 1.51
DC OXIDE VAR 2 35 3.45 19.6 89.1 97.1 1.11 0.75
DC OXIDE VAR 3 35 7.68 37.6 96.0 99.0 0.50 1.24
DC OXIDE VAR 4 45 1.17 27.5 85.4 94.0 0.51 0.46
DA FRESH VAR 1 45 5.39 53.1 78.2 90.9 0.43 0.57
DB FRESH VAR 1 45 1.27 35.3 81.9 89.8 0.49 0.45
DC FRESH VAR 1 45 0.67 58.3 87.1 95.5 0.45 0.19

 

October 15, 2025Page 124 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Sample ID %
Solids
(w/w)
Calculated
Assay
Head (g/t)
Gravity
Recovery
(%)
Leach Recovery
after 24h
(% of gravity
tails)
Total Au
Recovery
(% of head
feed)
NaCN
Cons’n
(kg/t)
Lime
Cons’n
(kg/t)
AA FRESH VAR 1 45 2.40 64.9 89.3 97.5 0.33 0.25
AA FRESH VAR 2 45 0.37 52.7 83.0 92.0 0.33 0.45
AB FRESH VAR 1 45 2.27 59.5 91.5 97.4 0.37 0.22
AB FRESH VAR 2 45 0.59 55.8 86.2 94.9 0.39 0.17
AC FRESH VAR 1 45 1.43 66.3 80.0 93.7 0.37 0.16
AC FRESH VAR 2 45 0.51 27.6 75.5 83.5 0.43 0.14
KARA FRESH VAR 1 45 3.68 68.3 93.1 98.6 0.45 0.20
KARB FRESH VAR 1 45 7.83 74.1 82.0 95.7 0.39 0.20
KARB FRESH VAR 2 45 3.70 71.3 86.3 97.7 0.43 0.20
KARC FRESH VAR 1 45 1.03 71.6 83.5 97.1 0.61 0.21

 

The variability bulk leach tests correlate relatively well with the previous bulk leach results. The overall recovery ranged from 84–99% with an average of 93.5% and an average residue grade of 0.12 g/t Au. The cyanide consumption varied between 0.33–0.61 kg/t for fresh and 0.5–1.1 kg/t for oxide. Lime consumption varied between 0.14–0.57 kg/t for fresh and 0.46–2.54 kg/t for oxide.

 

13.4.9Carbon Testwork

 

Carbon equilibrium and triple contact tests were undertaken on the leach slurry produced as part of the bulk tests to determine what carbon loading (grams of gold per tonne of carbon) can be expected in the plant. In the equilibrium tests, five different masses of carbon were added to samples of the slurry to determine the equilibrium carbon loading at various masses. This test was conducted on two oxide and five fresh samples. Test data were fitted to the Freundlich’s isotherm equation to provide a straight-line plot of log (gold on carbon) against log (gold in solution). From this loading curve, equilibrium gold loading on carbon can be estimated based on nominated gold loading in solution. These results are used to inform the number of CIL/CIP stages that will be required for the plant and are shown on Table 13.13.

 

Table 13.13 Carbon Concentrations and Loading

 

Sample ID Feed Solution Equilibrium Loading (g/t) at Solution
Concentration
[Au, mg/L] 1.0 (mg/L) 0.50 (mg/L) 0.10 (mg/L)
DA OXIDE-1 1.06 3,884 3,011 1,667
DB OXIDE-1 1.63 3,567 2,738 1,482
DA FRESH-1 0.27 1,779 1,420 841
DA FRESH-2 0.56 6,780 5,005 2,473
DA FRESH-3 0.75 9,280 7,269 4,122
AA FRESH-1 0.75 3,345 2,510 1,288
KARA FRESH-1 0.52 2,542 2,030 1,205
KARB FRESH-3 0.80 6,153 4,538 2,237
KARC FRESH-2 1.00 5,293 3,938 1,982
DA OXIDE VAR-1 0.42 1,662 1,250 645

 

October 15, 2025Page 125 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Sample ID Feed Solution Equilibrium Loading (g/t) at Solution
Concentration
[Au, mg/L] 1.0 (mg/L) 0.50 (mg/L) 0.10 (mg/L)
DA FRESH VAR-1 1.67 5,079 3,936 2,177
DB OXIDE VAR-1 0.76 1,623 1,268 714
DB FRESH VAR-1 0.57 2,714 2,196 1,343
DC FRESH VAR-1 0.21 1,143 959 639
DC OXIDE VAR-1 0.34 1,507 1,125 572
DC OXIDE VAR-2 1.44 7,375 5,587 2,933
DC OXIDE VAR-3 2.54 9,210 6,805 3,370
DC OXIDE VAR-4 0.64 2,570 2,036 1,186
AA FRESH VAR-1 0.64 4,658 3,524 1,843
AB FRESH VAR-1 0.71 4,845 3,772 2,109

  

Carbon triple contact tests were also undertaken on the leach slurries. The carbon was contacted with a sample of slurry for two hours, then extracted and transferred to a fresh batch of slurry for two hours, then transferred to a final batch for an additional 20 hours for a total of 24 hours. The cumulative gold loading on the carbon is calculated and provided in Table 13.14.

 

Table 13.14 Carbon Triple Contact Test Results

 

Sample Feed Au
Concentration
(mg/L)
Calculated
Carbon Loading
(g/t)
Fleming Constants
k (hr-1) n
DA OXIDE-1 1.08 1,903 122.1 1.04
DB OXIDE-1 1.68 1,414 98.9 0.60
DA FRESH-1 0.28 814 79.0 0.97
DA FRESH-2 0.57 1,188 208.3 0.65
DA FRESH-3 0.75 2,116 287.0 0.72
AA FRESH-1 0.76 1,509 162.9 0.70
KARA FRESH-1 0.56 1,098 96.3 0.96
KARB FRESH-3 0.84 1,595 107.7 0.97
KARC FRESH-2 1.04 1,652 137.4 0.86
DA OXIDE VAR-1 0.41 693 132.4 0.66
DA FRESH VAR-1 1.70 2,529 179.8 0.70
DB OXIDE VAR-1 0.75 831 72.9 0.67
DB FRESH VAR-1 0.57 1,039 120.6 0.45
DC FRESH VAR-1 0.21 434 87.8 0.62
DC OXIDE VAR-1 0.35 443 44.6 0.84
DC OXIDE VAR-2 1.36 1,857 177.0 0.64
DC OXIDE VAR-3 2.55 2,211 122.5 0.68
DC OXIDE VAR-4 0.64 923 42.7 1.12
AA FRESH VAR-1 0.63 1,381 144.3 0.86
AB FRESH VAR-1 0.70 1,542 176.2 0.80

 

October 15, 2025Page 126 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The main measures for the CIP tests are the Fleming ‘k’ and ‘n’ constants. The ‘k’ constant indicates the empirical rate constant for carbon adsorption—when applied to virgin carbon in a laboratory situation, it can be used as a measure of whether the mineralized material is fouling the carbon. Values of >240 hr-1 are considered excellent. The results broadly show that there is no significant fouling of the carbon by the slurry. The ‘n’ constant indicates the carbon loading capacity, with values between 0.5-1.0 considered reasonable.

  

The expected carbon loading at a gold solution concentration of 1.0 mg/L, based on the equilibrium test, showed successful gold loading above 2,500 g/t Au for all samples except DA FRESH-1. The low loading for DA FRESH-1 is attributed to the low gold grade of 0.28 mg/L. This is also shown in the triple contact gold testwork where the lower tenor in DA FRESH-1 produces the lowest calculated carbon loading as expected. Fleming constants from CIP testwork range from acceptable to excellent across all samples. These results indicate that gold recovery by carbon loading from solution is suitable for the style of mineralization, based on selected samples.

 

13.5Rheology

 

Rheology testwork conducted in 2021 indicated slurry handling issues could be expected due to the large clay content of Area D oxide samples. Vane instrument and Bohlin viscometry rheology tests were conducted to investigate the flow properties of the Area D oxide samples. Spatially representative samples were tested to determine vane stress at 35% w/w solids and 40% w/w solids at 106 µm. The vane test was also repeated at an adjusted slurry pH of 10.5 using lime. Results are summarized in Table 13.15. Bohlin Visco 88 instrument tests were also conducted on these samples at 30%, 40%, and 50% w/w solids. Viscosity, shear rate and shear stress were investigated with results summarized in Table 13.16.

 

Table 13.15 Summary of Vane Yield Stress Test Results

 

Sample ID %Solids
(% w/w)
pH Vane Yield Stress
(Pa)
DA OXIDE-1 35 7.5 2.2
DA OXIDE-1 40 7.5 2.6
DB OXIDE-1 35 7.5 0.8
DB OXIDE-1 40 7.5 1.7
DC OXIDE-1 35 7.5 0.6
DC OXIDE-1 40 7.5 1.1
DA OXIDE-1 35 10.5 2.2
DA OXIDE-1 40 10.5 2.6
DB OXIDE-1 35 10.5 0.8
DB OXIDE-1 40 10.5 1.7
DC OXIDE-1 35 10.5 0.6
DC OXIDE-1 40 10.5 1.1

 

October 15, 2025Page 127 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 13.16 Summary of Bohlin Viscometry Testwork

 

Sample ID %Solids
(% w/w)
Viscosity at Shear Rate Shear Stress at Shear Rate

4.2

(cps)

119.2
(cps)
4.2
(Pa)
119.2
(Pa)
DA OXIDE-1 50 17,217 852 72 102
40 3,481 195 15 23
30 936 86 4 10
DB OXIDE-1 50 6,213 363 26 43
40 1,048 94 4 11
30 299 51 1 6
DC OXIDE-1 50 2,321 156 10 19
40 861 78 4 9
30 487 51 2 6
DA OXIDE VAR-1 45 9,170 443 39 53
40 3,443 179 14 21
35 1,385 116 6 14
DB OXIDE VAR-1 50 7,897 413 33 49
45 3,705 210 16 25
35 898 98 4 12
DA FRESH VAR-1 55 0 65 0 8
45 0 49 0 6
35 0 34 0 4

 

The results indicate that the oxide material may experience pumping difficulties at higher solids densities. Blending or other treatment would be required to pump oxides at higher densities. No issues are expected with the fresh material.

 

13.6Diagnostic Leach

 

Two samples from Area D (DA FRESH-1 and DC FRESH-2) that exhibited particularly low overall recoveries were investigated further with a sequential series of diagnostic leach tests to identify where gold is not recoverable by gravity or cyanidation may be deported. The process consists of the following stages:

 

·Gravity concentration and amalgamation.

 

·Standard direct cyanidation.

 

·Dilute hydrochloric acid digest.

 

·Dilute nitric acid digest.

 

·Aqua regia digest.

 

·Fire assay smelt.

 

The results of the diagnostic leach tests are shown in Table 13.17.

 

Table 13.17 Diagnostic Leach Results

 

Sample Gold Distribution (%)
Stage 1 Stage 2 Stage 3 Stage 4 Stage 5 Stage 6
DA FRESH-1 22.8 46.1 0.0 26.9 4.1 0.0
DC FRESH-1 25.5 42.8 6.1 23.5 1.1 1.0

 

October 15, 2025Page 128 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The majority of the gold not recovered by the gravity/cyanidation flowsheet is recovered by dilute nitric acid digest, suggesting the gold is associated with mostly reactive sulfides.

 

13.7Testwork on Prospects

 

High-level metallurgical testwork was conducted on samples from the Kassassoko, Western Splay deposits, as well as the Bougouda prospect. Two samples were selected from shallower and deeper intervals within the prospect. These samples were all from fresh rock domains and no oxide or transitional litho-oxidation domains were identified. A summary of the various testwork results is summarized in the following sub-sections.

 

13.7.1Comminution Testwork

 

The SMC test derived A*b data indicates the mineralization in the prospects can be categorized as hard and fall inside the common A*b ranges for fresh rock types. The A*b data for prospects are not excessively resistant to breakage and fall well within the rock types that are readily amenable to SAG milling. The prospect A*b data are all higher than the proposed circuit design basis, indicating that the presently designed comminution circuit will crush and grind the new prospect fresh mineralization types.

 

Kassassoko and Western Splay BWi test results indicate that these materials are medium energy intensity when grinding and will readily be milled by the circuit proposed for Diamba Sud at throughput rates at or above design. Target grind size of P80 106 µm will be easily achieved should these mineralization types be milled individually or as a blend with the current deposit mineralized material types.

 

Two Ai test results are higher than the circuit design basis and the Kassassoko sample is very high and is indicative of an extremely abrasive material.

 

13.7.2Gold Leaching Testwork

 

Comprehensive head assays show that elements that can be deleterious to alkaline cyanide gold leaching methods are non-existent. Similarly, no organic carbon was detected in any of the composites removing the major risk causing preg-robbing. Sulfide sulfur levels for all but composite Boug-1 from the Bougouda prospect are low, suggesting gold is unlikely to be associated with sulfide minerals and gold will be free milling at a relatively coarse grind size. However, composite Boug-1 has about 4% sulfide sulfur, and there is a likelihood that some of the gold may not be readily extractable due to the presence of very fine gold particles. There may be potential for sulfide mineral dissociation and the consequent problems caused when sulfide minerals dissolve in alkaline cyanide mixtures (elevated cyanide consumptions, low dissolved oxygen and possible sulfide passivation of the gold surface, which can slow the rate of gold dissolution in cyanide solutions).

 

Concentrations of transitional metals such as copper, nickel and zinc are low in all samples and thus these would not elevate cyanide consumption due to their high amounts of metals competing with gold dissolution.

 

13.7.3Gravity Leach Testing

 

All samples except composite Boug-1 demonstrated high gravity gold recoveries indicating there are large components of coarse free gold present in the tested samples. Gravity gold recoveries ranged from 61–80%. Gravity gold recovery for Boug-1 was still significant at 16%. The gravity gold recovery results achieved in testwork will be higher than achieved at plant scale due to testing recovering a gravity gold concentrate about 100 times larger than that at plant scale and using highly efficient amalgamation to separate

 

October 15, 2025Page 129 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

the gold from the gravity concentrate. Gravity gold recovery is likely to be between 30–50% at plant scale when processing mineralized materials similar to those tested.

 

Overall gravity-leach gold extractions were mostly in the high 90th percentiles and the lower test results were only lower because the calculated head grades were low at 0.60 and 0.42 g/t Au. High gold extraction results were achieved for samples with calculated head grades of 0.92–3.89 g/t Au. The exception was Boug-1 where total extraction was 92% from a calculated head grade of 3.31 g/t Au.

 

Testing demonstrated rapid gold extraction with little if any benefit achieved from extending the leach duration beyond 24 hours.

 

Sodium cyanide consumptions are reported at 48 hours leaching and are all low, with only Boug-1 exceeding 0.50 kg/t at 0.55 kg/t. Other sample consumptions were between 0.34–0.45 kg/t. This is likely to be lower when targeting lower residual sodium cyanide concentrations in the leach residues and the low consumptions are indicative of the samples not containing cyanide consumers like reactive iron sulfides.

 

Target leaching pH was between 10 to 10.5 and all samples ground in a stainless-steel mill remained alkaline after grinding in Perth tap water. Lime consumptions were low, which is indicative of very low, or no reactive sulfides are clays being present in the samples.

 

Gravity-leach testing results on all composites were mostly exceptional, and these target samples did not demonstrate any areas of concern should the same flowsheet be used as that for mineralized material sourced from the deposits with Mineral Resources.

 

13.8Metallurgical Variability

 

It is the opinion of Dr. Lorenzen that the Diamba Sud metallurgical samples tested are representative of mineralization defined for each of the deposits (covers the variability), in respect to geographical orientation, depth, mineralization, grade and metallurgical response. Differences between deposits are minimal regarding metallurgical recovery and have been accounted for. Area A, D, Karakara, Western Splay and Kassassoko were all tested thoroughly and samples selected both covered the main testwork program as well as variability testing to confirm the flowsheet.

 

Limited bottle roll leaching testwork was conducted on mineralized samples from the Southern Arc and Moungoundi deposits to establish indicative recoveries for the current study. A total of three samples from Southern Arc and four samples from Moungoundi were selected to represent expected average, high, and low gold grades and assess grade variability. All samples were taken from fresh mineralization and distributed spatially across the deposits to ensure representativeness.

 

The tests were performed under plant-simulated leach conditions to obtain recovery responses suitable for developing recovery formulas as detailed in Section 13.9. The results were used to derive indicative recovery relationships applied for resource reporting and cutoff grade determination. Additional metallurgical testwork is planned during the next phase of testwork to further increase confidence in metallurgical recoveries of these deposits.

 

He considers that the metallurgical information is acceptable to support Mineral Resource estimation and be used for PEA purposes.

 

October 15, 2025Page 130 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

13.9Recovery Estimates

 

Results, as of the effective date of this Report, indicate very high recovery for oxide material and mostly high recovery for fresh mineralization with a simple free milling processing plant design.

 

Applying the optimized leach conditions to bulk composites, it was found that the leach recovery of gold (that is, of leach feed gold) varied significantly from 56–95%. Overall, the composites tested demonstrated high to very high total gold recoveries (including gravity) of 70–98% after 24 hrs. The grade–recovery regression model has been applied as the recovery estimation method, indicating an average gold recovery of approximately 90% across the project under standardized test conditions (P80 = 106 µm grind size, 24-hour leach time).

 

Gold recovery equations were provided for the weathering profiles, and deposits tested and are provided in Table 13.18. For those deposits with limited samples in certain lithologies (or composites) and those that only done rolling bottle testwork was performed on, fixed gold recoveries per deposit was provided.

 

Table 13.18 Gold Recovery Formula

 

Deposit Material Type Grade Range Metallurgical Recovery Formula
Area D Oxide <0.15 g/t 0%
>=0.15 g/t Au Recovery % = (100% – 1%) × (88.38 × AuHead^0.0454 – 100 × 0.015/AuHead)
Fresh <0.25 g/t 0%
>=0.25 g/t Au Recovery % = (100% – 1%) × [7.0997 × LN(AuHead) + 81.782 – 100 × 0.012/AuHead]
Area A Oxide <0.15 g/t 0%
>=0.15 g/t Same as Area D Oxide
Fresh <0.15 g/t 0%
>=0.15 g/t Au Recovery % = (100% – 1%) × [–2.8853 × (AuHead) + 88.752 – 100 × 0.012/AuHead]
KaraKara Oxide <0.15 g/t 0%
>=0.15 g/t Same as Area D Oxide
Fresh <0.15 g/t 0%
>=0.15g/t <=3.5g/t Au Recovery % = (100% – 1%) × (100 × (AuHead – 0.0347) × (–0.2938 × AuHead)) / (AuHead – 100 × 0.012/AuHead)
>3.5g/t 96.3%
Kassassoko Oxide <0.15 g/t 0%
>=0.15 g/t Same as Area D Oxide
Fresh <0.15 g/t 0%
>=0.15g/t <=5.0g/t Au Recovery % = (100% – 1%) × (100 × (AuHead – 0.0759) × (AuHead – 1.0017) / (AuHead – 100 × 0.012/AuHead))
>5.0g/t 91.2%
Western Splay Oxide <0.15 g/t 0%
>=0.15 g/t Same as Area D Oxide
Fresh <0.15 g/t 0%
>=0.15g/t <=2.0g/t Au Recovery % = (100% – 1%) × [4.674 × AuHead^0.291 – 100 × 0.010/AuHead]
>2.0g/t <=15.0g/t Au Recovery % = (100% – 1%) × [0.3082 × AuHead + 93.389 – 100 × 0.012/AuHead]

  

October 15, 2025Page 131 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Deposit Material Type Grade Range Metallurgical Recovery Formula
    >15.0g/t 97.0%
Moungoundi Oxide <0.15 g/t 0%
>0.15 g/t Same as Area D Oxide
Fresh <0.15 g/t 0%
>=0.15 g/t Au Recovery % = (100% – 1%) × (100 × (AuHead – 0.11375 + 0.015) / (AuHead – 100 × 0.012/AuHead))
Southern Arc Oxide <0.15 g/t 0%
>=0.15 g/t Same as Area D Oxide
Fresh <0.15 g/t 0%
>=0.15 g/t Au Recovery % = (100% – 1%) × (100 × (AuHead – 0.11375 + 0.015) / (AuHead – 100 × 0.012/AuHead))

 

Based on the formula’s set out in Table 13.18 the average metallurgical recoveries were estimated for each ore block and aggregated in the mining / stockpiling / plant feed blending process to produce estimated metallurgical recovery by month. The calculated metallurgical recoveries at the incremental mining cutoff grade and the overall process plant recovery are shown in Table 13.19.

 

Table 13.19 Gold Recovery at Cutoff Grade and Overall Plant Performance

 

 Deposit Material
Type
Mining
Incremental
COG (g/t)
Gold
Recovery at
Inc. COG (%)
Average
Plant Feed
Grade (g/t)
Overall Plant
Gold Recovery
(%)

Area A

 

Oxide 0.35 79.2 0.92 86.8
Fresh 0.40 86.0 1.55 93.4

Area D

 

Oxide 0.35 79.2 2.01 90.8
Fresh 0.47 73.1 1.39 85.2

Karakara

 

Oxide 0.35 79.2 2.17 91.6
Fresh 0.39 86.1 1.84 94.9

Kassassoko

 

Oxide 0.35 79.2 0.81 86.2
Fresh 0.39 88.4 0.99 90.3

Moungoundi

 

Oxide 0.35 79.2 0.72 84.0
Fresh 0.44 78.2 1.14 82.7

Southern Arc

 

Oxide 0.35 79.2 1.19 87.8
Fresh 0.42 82.3 1.70 86.4

Western Splay

 

Oxide 0.35 79.2 1.00 86.4
Fresh 0.46 75.5 1.82 88.3
Weighted on Plant feed Metal
Oxide   79.2   90.4
Fresh   82.1   90.0
Total   81.4   90.1

 

October 15, 2025Page 132 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

13.10Deleterious Elements

 

Testwork and mineralogical analysis conducted showed that at this stage of the study, no deleterious elements were present in any significant quantities or showed any deleterious effect on recoveries or possible throughput. Some reactive sulfides in very small quantities were detected, however, none in significant enough quantities to influence any metallurgical testwork results reported at this stage.

 

13.11Comments on Section 13

 

The testwork program has indicated favorable grinding and leaching characteristics for oxide mineralization and most samples of fresh mineralized material, based on the following QP observations.

 

·Various comminution tests, including Ai, CWi, BWi, and SMC tests, were undertaken on the composites. Initial modelling indicates that single-stage SAG and SABC comminution flowsheets are both suitable for this material. Unfortunately, the oxide composites were too friable to be reliably tested with these methods. Initial size screening indicated the unmilled mineralized material is mostly fine and close to the milling feed F80.

 

·Comminution testing results indicated the following:

 

oAi (average ~0.18 for fresh domain) indicates that the mineralized material is not abrasive.

oBWi and SMC results indicate that the mineralization is moderate to hard (10–22 kWh/t), and the oxide composite was not compatible with the test. The friability of the composite shows that the oxide mineralization is very soft as well.

oThe SMC testwork indicates that the mineralized material is amenable both single-stage crushing followed by SAG milling or alternatively SABC (average A*b of 27 to 53 for fresh mineralization) in closed circuit, with or without a pebble crusher.

 

·Gravity testwork has indicated that the mineralization contains a large proportion of free/gravity recoverable gold. The proportion of gravity-recoverable gold varied from 14–40% for oxide and 28–80% for fresh mineralization. Broadly, the higher gold grade fresh mineralization had higher fractions of gravity gold, while the lower grade samples had lower relative gravity recoveries. Intensive leach results indicated gold recoveries from the gravity concentrate that were >99%.

 

·Leaching optimization tests on two oxide and seven fresh samples indicated that the leaching process was relatively simple and robust with the following observations:

 

oOptimal grind size selected at 106 µm.

oDC Fresh-1 was the only sample with recovery below 90%. Addition of 200 g/t lead nitrate did not improve gold recovery. DC Fresh-1 recovery remained ~74% at 24 hours.

oUse of air instead of oxygen for sparging did not impact gold recovery significantly.

oCyanide concentration initially at 1,000 ppm (maintained at 500 ppm) showed marginal improvement over 500 and 250 ppm.

oVarying the oxide solids concentration from 25–40% did not show major impact with increasing mass fraction in this range. Varying the

 

October 15, 2025Page 133 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

  fresh solids concentration from 35–45% likewise showed no major impact.
oLonger leach times in excess of 24 hrs will not be necessary.

oGold leaching kinetics are fast.

oThe samples did not display any preg-robbing characteristics or carbon fouling.

 

·Applying the optimized leach conditions to bulk composites, it was found that the leach recovery of gold (that is, of leach feed gold) varied significantly from 56–95%. Overall, the composites tested demonstrated high to very high total gold recoveries (including gravity) of 70–98% after 24 hrs. Oxide mineralization showed higher overall recovery with an average of 93%. Average fresh mineralization recovery averaged92% at 24 hours. Total gold recovery of DC Fresh-1 and DA Fresh-1 samples appeared limited to 70 –75% due to locked gold in mostly reactive sulfides and silicates.

 

Results, as of the effective date of this Report, indicate very high recovery for oxide mineralization and mostly high recovery for fresh material with a simple free milling processing plant design.

 

Table 13.20 provides a summary of proposed process design criteria values that can be used by design engineers for the process design in Section 17 based on the current testwork results.

 

Table 13.20 Proposed Process Design Values Based on Testwork

 

Proposed PDC inputs Value
P80 106 µm
Leaching Time ~24 hours
Au Recovery by Gravity of Total Gold 15–60%
Au Recovery by Leaching of Total Gold 35–80%
Total Au Recovery 90–92%
CN Consumption, Oxide 0.85 kg/t
Lime Consumption, Oxide 2.0 kg/t
CN Consumption, Fresh 0.42 kg/t
Lime Consumption, Fresh 0.4 kg/t
O2 Consumption Minimal
% Solid w/w 39% Oxide and 45% Fresh

 

Table 13.21 shows a summary of comminution model data inputs.

 

Table 13.21 Proposed Comminution Model Inputs

 

Model Parameter Value
Ai 0.1829
CWi 6.2 kWh/t
BWi 15.8 kWh/t
SG 2.7
A*b ~34
Throughput 2.5 Mt/a Oxide and 2.0 Mtpa Fresh

 

Based on the metallurgical testwork conducted, as of the effective date of this Report, metallurgical grade versus recovery relationship formulas were developed for oxide/transition rock (all deposits) and separate formulas for fresh rock in each of the seven deposits. The overall recovery is estimated to be 90.4% for oxide/transitional rock

 

October 15, 2025Page 134 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

and 93.4% for fresh rock for Area A; 85.2% for fresh rock for Area D; 94.9% for fresh rock for Karakara; 88.3% for fresh rock for Western Splay; 90.3% for fresh rock for Kassassoko; 82.7% for fresh rock for Moungoundi; and 86.4% for fresh rock for Southern Arc.

 

October 15, 2025Page 135 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

14Mineral Resource Estimates

 

14.1Introduction

 

The Mineral Resource estimates were completed by Fortuna or Entech Mining personnel and peer reviewed by Eric Chapman P. Geo, a Fortuna employee.

 

14.2Supplied Data, Data Transformations and Data Preparation

 

Information used in the 2025 estimation is sourced from the Maxwell DataShed industry standard database system.

 

Boya supplied all available data as of July 7, 2025.

 

14.2.1Data Transformations

 

Lower detection limit assay values received from the ALS Global and SGS Mineral Services laboratories were corrected to numeric values, for example “<0.005” was converted to “0.0001”. This ensured that the values were correctly recognized by the software and mitigated interpolation issues later in the estimation process.

 

Downhole surveys were carried out using either Reflex EZ-Shot, Reflex Gyro Sprint IQ, and Axis Champ gyroscopic tools. The magnetic declination was applied to the azimuth readings from the Reflex EZ-Shot using a single correction factor.

 

14.2.2Software

 

Mineral Resource estimates were completed using several software packages for modeling, statistical, geostatistical and grade interpolation activities. Wireframe modeling of the mineralized envelopes was performed in Leapfrog Geo. Data preparation, block modeling and grade interpolations were performed in Datamine Studio RM. Statistical and variographic analysis was performed in Supervisor.

 

14.2.3Data Preparation

 

Collar, survey, lithology, and assay data were imported into Leapfrog Geo and used to build three dimensional representations of the drill holes.

 

Assay values at or below the detection limit were corrected to a numeric value (removal of “<”) lower than the original limit number, half or less.

 

14.3Geological Interpretation and Domaining

 

Wireframes representing the major geological and weathering units were generated based on cross-sectional interpretations for all deposits. In addition, a wireframe defining gold mineralization (>0.1 g/t Au) in each deposit was generated based on structural and geological data. The low-grade domains were used to constrain probabilistic grade shells that were used to define higher-grade mineralized zones.

 

14.3.1Probabilistic Grade Shells

 

Categorical indicator kriging (CIK) was used to estimate the location of moderate and high gold grade regions of the deposits. CIK was designed to define potentially economic envelopes around mineralized zones digitally that are difficult to outline and delineate using more traditional and labor-intensive methods such as wireframing. Probabilistic envelopes were generated using indicators to define the limits of potentially economic mineralization. The envelopes were used in estimation to confine the higher-grade assays from smearing into lower-grade zones and restrict lower-grade assays

 

October 15, 2025Page 136 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

  

from diluting the higher-grade zones.

 

CIK models were constructed internal to the defined low-grade domains as follows:

 

·An indicator threshold was selected for samples with grades above the threshold set to one and below to zero. Thresholds varied between deposits, based on the grade distributions, but were generally around 0.2–0.3 g/t Au.

 

·Variograms were modeled to represent the spatial variability of the indicators.

 

·Indicator values were estimated by ordinary kriging (OK) into a 2.5 x 2.5 x 2.5 m block model using the modeled variograms and associated search neighborhoods.

 

·Upon completion of the estimate, all blocks with a probability value ≥0.5 were assigned a code of one and blocks with a probability <0.5 were assigned a code of zero.

 

·Wireframes were generated identifying the location of the block codes equal to one for the threshold (gold grade domains ≥0.2 to 0.3 g/t Au).

 

An example of a representative cross-section of mineralized wireframes is shown in Figure 14.1.

 

Figure 14.1 Cross-Section Showing Mineralized Wireframes for Area A

 

 

 

14.3.2Statistical Analysis of Composites

 

Compositing of sample lengths was undertaken so that the samples used in statistical analyses and estimations have similar support (i.e. length). Drill hole samples were

 

October 15, 2025Page 137 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

selected at predominantly 1 m intervals (85% of drill hole samples are 1 m in length for RC/core), although varying interval lengths are sometimes selected depending on the length of intersected geological features and visual mineralization indicators. Occasionally barren waste zones had sample lengths >2 m; however, they represented <0.5% of the mineralized samples and are not regarded as material to the estimates. Sample lengths were examined for each deposit, and the dominant sample length of 1 m was selected as the composite length for all deposits.

 

The Datamine COMPDH downhole compositing process was used to composite the samples within the estimation domains (i.e. composites do not cross over the mineralized domain boundaries). The COMPDH parameter MODE was set to a value of one to allow adjusting of the composite length while keeping it as close as possible to the composite interval; this is done to minimize sample loss.

 

14.4Exploratory Data Analysis

 

Exploratory data analysis was performed on both raw selected samples within mineralized wireframes and on composites identified in each geological domain. Statistical and graphical analysis (including histograms, log probability plots, scatter plots) were investigated for each domain to assess if additional sub-domaining was required to achieve stationarity.

 

The composited data statistics for all deposits and mineralized domains are shown in Table 14.1.

 

Table 14.1 Univariate Statistics of Au Composites for Each Deposit

 

Deposit Domain ID Domain
Grade Zone
Count Min.
(g/t)
Max.
(g/t)
Mean
(g/t)
Variance Std.
Dev.
C.V.
Area A 1001 Low 722 0.00 16.35 0.19 0.64 0.80 4.23
1001.1 High 375 0.00 28.60 1.49 7.04 2.65 1.78
1002 Low 121 0.00 5.59 0.30 0.45 0.67 2.22
1002.1 High 55 0.02 5.92 0.95 1.15 1.07 1.13
1003 Low 4,486 0.00 41.70 0.15 0.73 0.85 5.67
1003.1 High 2,022 0.00 54.60 2.44 19.35 4.40 1.80
1004 Low 2,964 0.00 7.97 0.11 0.13 0.36 3.30
1004.1 High 956 0.00 63.10 2.46 21.37 4.62 1.88
1005 Low 95 0.00 4.56 0.22 0.44 0.67 2.98
1005.1 High 74 0.07 9.92 1.20 2.63 1.62 1.35
1006 Low 256 0.00 5.93 0.16 0.19 0.44 2.74
1006.1 High 24 0.00 3.03 0.48 0.39 0.62 1.30
Area D 101 Low 1,124 0.00 19.30 0.19 0.72 0.85 4.41
101.1 High 376 0.01 25.33 1.11 5.01 2.24 2.03
102 Low 4,521 0.00 11.01 0.14 0.27 0.52 3.61
102.1 High 3,931 0.00 149.00 2.44 37.18 6.10 2.50
103 Low 364 0.00 22.60 0.41 3.61 1.90 4.65
103.1 High 371 0.00 70.70 1.61 18.88 4.35 2.71
104 Low 466 0.00 47.50 0.25 4.94 2.22 8.83
104.1 High 295 0.00 23.78 1.44 8.15 2.86 1.98
105 Low 134 0.00 14.55 0.40 1.85 1.36 3.41
106 Low 1,997 0.00 31.22 0.22 1.56 1.25 5.74
106.1 High 422 0.00 64.27 1.97 22.86 4.78 2.42
107 High 91 0.00 33.50 1.06 13.88 3.73 3.50
108 High 75 0.00 398.00 6.60 2082.44 45.63 6.92
109 Low 281 0.00 3.04 0.29 0.17 0.41 1.40
110 Low 185 0.00 5.47 0.29 0.74 0.86 2.94

 

October 15, 2025Page 138 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Deposit Domain ID Domain
Grade Zone
Count Min.
(g/t)
Max.
(g/t)
Mean
(g/t)
Variance Std.
Dev.
C.V.
  110.1 High 62 0.07 6.91 1.40 2.69 1.64 1.17
111 Low 110 0.00 0.94 0.16 0.03 0.18 1.15
112 High 22 0.30 125.50 6.53 674.44 25.97 3.98
Karakara 1001 Low 2,803 0.00 11.80 0.12 0.30 0.54 4.63
1001.1 Medium 431 0.00 34.90 0.77 8.89 2.98 3.87
1001.2 High 1,156 0.00 58.50 2.93 38.67 6.22 2.12
1002 Low 1,074 0.00 43.80 0.22 3.37 1.84 8.40
1002.1 Medium 245 0.01 11.20 0.38 1.09 1.04 2.72
1002.2 High 311 0.01 52.00 1.65 14.65 3.83 2.33
1003 Low 3,544 0.00 18.10 0.12 0.38 0.61 5.21
1003.1 Medium 579 0.00 23.40 0.48 2.03 1.43 2.98
1003.2 High 943 0.01 280.00 2.92 122.02 11.05 3.79
1004 High 27 0.00 10.35 1.24 4.72 2.17 1.76
1005 High 57 0.00 23.90 1.19 10.80 3.29 2.76
Kassassoko 1001 Low 883 0.00 3.97 0.17 0.14 0.37 2.26
1001.2 Medium 331 0.00 23.40 0.63 2.15 1.47 2.32
1001.5 High 186 0.02 7.66 1.58 2.46 1.57 1.00
1002 Low 469 0.00 2.80 0.15 0.08 0.28 1.89
1002.2 Medium 134 0.02 9.72 0.59 1.06 1.03 1.75
1002.5 High 69 0.08 28.70 1.59 12.16 3.49 2.19
1003 Low 1,900 0.00 4.71 0.13 0.10 0.31 2.34
1003.2 Medium 379 0.01 5.86 0.53 0.58 0.76 1.43
1003.5 High 222 0.00 20.80 1.74 5.63 2.37 1.37
1004 Low 404 0.00 10.85 0.21 0.74 0.86 4.05
1004.2 Medium 78 0.02 6.35 0.49 0.54 0.74 1.49
1004.5 High 30 0.05 20.90 1.70 13.28 3.64 2.14
1005 Low 6 0.01 0.28 0.10 0.01 0.10 1.04
1006 Low 136 0.00 1.48 0.11 0.03 0.19 1.64
1006.2 Medium 53 0.02 5.73 0.79 1.10 1.05 1.33
1006.5 High 38 0.07 5.66 1.29 1.62 1.27 0.98
1007 Low 97 0.00 4.63 0.21 0.37 0.61 2.91
1007.2 Medium 47 0.01 6.83 0.86 2.46 1.57 1.83
1007.5 High 20 0.15 3.45 1.33 0.83 0.91 0.69
1009 Low 274 0.00 10.25 0.15 0.49 0.70 4.57
1009.2 Medium 9 0.06 0.82 0.39 0.07 0.26 0.67
Western Splay 1001 Low 108 0.00 1.05 0.08 0.02 0.15 1.97
1001.2 High 30 0.06 7.57 1.76 4.48 2.12 1.21
1002 Low 118 0.00 0.92 0.05 0.02 0.13 2.61
1002.1 High 44 0.03 5.64 0.85 1.55 1.24 1.47
1003 Low 1,886 0.00 13.20 0.10 0.26 0.51 5.32
1003.2 High 384 0.01 71.60 3.33 46.04 6.79 2.04
1004 Low 218 0.00 6.69 0.17 0.32 0.57 3.33
1004.2 High 45 0.01 8.44 1.18 2.65 1.63 1.38
1005 Low 48 0.00 2.26 0.18 0.17 0.41 2.31
1005.2 High 33 0.01 34.70 4.55 48.13 6.94 1.52
1006 Low 2,894 0.00 21.11 0.10 0.30 0.55 5.73
1006.2 High 642 0.00 39.50 1.60 9.69 3.11 1.95
1007 Low 696 0.00 42.50 0.19 2.84 1.69 8.81
1007.2 High 231 0.00 14.90 1.29 4.38 2.09 1.63
1008 Low 1164 0.00 10.89 0.10 0.25 0.50 4.74
1008.2 High 207 0.01 25.60 1.62 6.74 2.60 1.60
1009 Low 120 0.00 19.80 0.22 3.23 1.80 8.01
1009.1 High 34 0.02 19.80 0.86 10.97 3.31 3.85

 

October 15, 2025Page 139 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Deposit Domain ID Domain
Grade Zone
Count Min.
(g/t)
Max.
(g/t)
Mean
(g/t)
Variance Std.
Dev.
C.V.

Moungoundi 1001 Low 1,209 0.00 15.95 0.23 0.88 0.94 4.07
1002 Low 1,807 0.00 11.80 0.13 0.23 0.48 3.69
1003 Low 245 0.00 4.05 0.10 0.11 0.33 3.35
1004 Low 838 0.00 39.60 0.16 2.34 1.53 9.56
1005 Low 63 0.01 1.45 0.18 0.07 0.26 1.42
2001 High 254 0.00 22.70 1.59 10.52 3.24 2.04
2002 High 187 0.01 17.80 1.12 4.76 2.18 1.95
2003 High 73 0.01 11.15 0.99 2.98 1.73 1.74
2004 High 124 0.02 200.00 4.70 624.19 24.98 5.32
Southern Arc 1001 Low 1,229 0.00 9.59 0.13 0.33 0.58 4.52
1002 Low 124 0.00 4.20 0.17 0.20 0.44 2.61
1003 Low 759 0.00 7.01 0.14 0.16 0.40 2.93
1004 Low 1,088 0.00 20.73 0.13 0.53 0.73 5.69
1005 Low 52 0.00 3.98 0.15 0.34 0.58 3.92
1006 Low 1,951 0.00 6.65 0.10 0.15 0.39 3.86
1007 Low 342 0.00 2.13 0.10 0.04 0.20 1.97
1008 Low 103 0.01 49.21 3.24 61.48 7.84 2.42
1009 Low 26 0.00 5.15 0.43 1.01 1.00 2.34
1010 Low 257 0.00 8.04 0.16 0.45 0.67 4.24
2001 High 520 0.01 67.29 2.87 33.95 5.83 2.03
2002 High 44 0.01 8.89 1.60 5.34 2.31 1.44
2003 High 92 0.01 11.00 1.03 3.23 1.80 1.74
2004 High 259 0.01 55.30 1.52 23.24 4.82 3.17
2005 High 18 0.03 1.60 0.45 0.15 0.39 0.85
2006 High 511 0.01 62.71 2.95 29.74 5.45 1.85
2007 High 67 0.01 8.22 1.42 3.94 1.98 1.40
2010 High 141 0.02 26.40 2.57 21.47 4.63 1.80

 

14.4.1Sub-Domaining

 

Diorites were treated as secondary domains during estimation, were considered waste for reporting, and were considered to be depleting or overwriting the intersected mineralized domains.

 

Lithologic wireframes were used to assess potential favorable domains for unique sample populations. Comparisons of raw geological data, wireframes, and sample data showed no clear distinct populations within these domains, as indicated by log probability and frequency distribution histograms.

 

Weathering profiles can influence search ellipses for estimation and were considered during variographic analysis. Area D contained a significant oxide blanket hosting most of the gold mineralization. Detailed review through contact plot analyses revealed distinct sample populations between oxide/transition and fresh material, which required separation for further spatial analysis.

 

14.4.2Grade Capping

 

Gold grades were reviewed to identify extreme values through sample histograms, log histograms, log-probability plots, and spatial analysis. Top cut thresholds were determined based on these statistical plots and their effect on mean, variance, and coefficient of variation (CV). Top cut comparisons for each domain are shown in Table 14.2. If insufficient data were available to determine top cut values for a domain, the values from all domains were reviewed as a single population and applied if appropriate

 

October 15, 2025Page 140 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

for outlier samples. On average the top cutting reduced the CV values by 23% while having a limited impact on reducing overall metal content, with the exception of domains where limited samples were available.

 

Table 14.2 Top Cut Thresholds

 

Deposit Domain Count Top Cut
(g/t Au)
Capped Mean
(g/t Au)
Number of
Samples Cut
Area A 1001 722 6.00 0.61 2
1001.1 375 15.00 1.49 2
1002 121 1.00 0.30 9
1002.1 55 - 0.95 -
1003 4486 9.00 0.15 5
1003.1 2,022 40.00 2.44 5
1004 2,964 3.00 0.11 8
1004.1 956 26.00 2.45 2
1005 95 - 0.23 -
1005.1 74 - 1.22 -
1006 256 2.00 0.16 2
1006.1 24 3.00 0.49 0
Area D 101 1,124 5.00 0.17 3
101.1 376 12.00 1.04 4
102 4,521 6.50 0.14 6
102.1 3,931 70.00 2.40 4
103 364 3.00 0.26 4
103.1 371 13.00 1.40 4
104 466 2.00 0.15 2
104.1 295 13.00 1.34 5
105 134 3.00 0.30 3
106 1,997 11.00 0.20 5
106.1 422 20.00 1.81 5
107 91 7.00 0.76 4
108 75 10.00 1.20 2
109 281 2.00 0.28 4
110 185 3.00 0.23 5
110.1 62 - - -
111 110 - - -
112 22 5.00 1.05 1
Karakara 1001 2,803 - 0.12 -
1001.1 431 12.00 0.62 12
1001.2 1,156 30.00 2.78 16
1002 1,074 - 0.22 -
1002.1 245 2.50 0.30 8
1002.2 311 12.00 1.45 7
1003 3,544 - 0.12 -
1003.1 579 4.00 0.40 9
1003.2 943 35.00 2.53 7
1004 27 - 1.24 -
1005 57 - 1.19 -
Kassassoko 1001 883 3.00 0.14 5
1001.2 331 4.00 0.54 3
1001.5 186 6.00 1.58 3
1002 469 1.30 0.14 7
1002.2 134 1.30 0.59 18
1002.5 69 10.00 1.22 1
1003 1,900 1.75 0.12 22

 

October 15, 2025Page 141 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Deposit Domain Count Top Cut
(g/t Au)
Capped Mean
(g/t Au)
Number of
Samples Cut
  1003.2 379 1.75 0.44 36
1003.5 222 10.00 1.65 3
1004 404 2.00 0.13 6
1004.2 78 5.00 0.48 1
1004.5 30 10.00 1.34 1
1005 6 - 0.10 -
1006 136 1.00 0.11 5
1006.2 53 5.00 0.78 1
1006.5 38 5.00 1.29 2
1007 97 1.00 0.13 3
1007.2 47 1.00 0.86 7
1007.5 20 1.00 1.33 11
1009 274 1.00 0.10 3
1009.2 9 - 0.39 -
Western Splay 1001 108 0.50 0.07 4
1001.2 30 7.00 1.74 1
1002 118 0.50 0.04 3
1002.1 44 - 0.85 -
1003 1,886 1.30 0.07 22
1003.2 384 20.00 2.90 8
1004 218 0.50 0.09 15
1004.2 45 5.00 1.10 1
1005 48 0.50 0.10 4
1005.2 33 20.00 4.09 2
1006 2,894 6.00 0.09 6
1006.2 642 20.00 1.56 4
1007 696 1.00 0.09 18
1007.2 231 10.00 1.24 3
1008 1,164 1.00 0.07 15
1008.2 207 10.00 1.52 2
1009 120 0.90 0.07 1
1009.1 34 10.00 0.57 1
Moungoundi 1001 1,230 4.00 0.19 10
1002 1,851 3.50 0.12 9
1003 256 0.70 0.07 3
1004 863 4.00 0.09 4
1005 55 - 0.18 0
2001 6,674 16.00 1.53 5
2002 233 10.00 1.04 2
2003 143 5.00 0.87 5
2004 62 12.00 1.67 4
Southern Arc 1001 1,229 3.00 0.11 11
1002 124 0.80 0.13 3
1003 759 2.30 0.13 3
1004 1,088 1.80 0.10 5
1005 52 1.60 0.10 1
1006 1,951 3.00 0.09 7
1007 342 1.10 0.10 2
1008 103 20.00 2.60 4
1009 26 1.50 0.29 1
1010 257 1.50 0.11 4
2001 520 20.00 2.61 6
2002 44 4.00 1.23 4

 

October 15, 2025Page 142 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Deposit Domain Count Top Cut
(g/t Au)
Capped Mean
(g/t Au)
Number of
Samples Cut
  2003 92 6.00 0.94 3
2004 259 11.00 1.16 4
2005 18 - 0.45 0
2006 511 20.00 2.75 7
2007 67 - 1.42 0
2010 141 16.00 2.35 7

 

14.5Variogram Analysis

 

14.5.1Continuity Analysis

 

The grade distribution has a log-normal distribution therefore traditional experimental variograms tended to be poor in quality. To counteract this, data was transformed into a normal score distribution for continuity analysis.

 

Horizontal, across strike, and down dip continuity maps were examined (and their underlying variograms) for gold composites to determine the directions of greatest and least continuity. As each mineralized domain has a distinct strike and dip direction analysis was focused on ascertaining if a plunge direction was present.

 

14.5.2Variogram Modeling

 

Variograms were modelled along the major, semi-major, and minor axes of the mineralization continuity.

 

The nugget effect was examined from downhole variograms, calculated with lags equal to the composite length.

 

Directional variograms were modelled in the three principal directions and informed by continuity analysis using variogram fans. It was not always possible to produce variograms for some domains that contained a limited amount of sample data. Variogram models were reported only for domains with sufficient sample pairs to support robust spatial analysis. For domains that did not have sufficient sample numbers to allow the generation of variogram models, a model was selected from a domain of that deposit that had similar mineralization characteristics and the directions modified to match the strike and dip orientation of the domain, if necessary. Modeled variograms were back-transformed from normal scores, as grade estimation was performed without data manipulation. Variogram parameters are detailed in Table 14.3.

 

Table 14.3 Variogram Model Parameters

 

Deposit Domain Major, Semi Major
and Minor Axes
Rotations ZXZ (o)
C0§ C1§

Ranges

(m)

C2§

Ranges

(m)

C3§

Ranges

(m)

Area A 1001 to 1003 &
1005 to 1006
-75, 50, -20 0.24 0.44 15, 10, 5 0.24 35, 20, 15 0.08 100, 50, 30
1004 & 1004.1 0, 170, 180 0.19 0.44 15, 10, 5 0.17 50, 40, 15 0.20 100, 60, 23
Area D 101 & 101.1 -150, 30, 180 0.64 0.16 18, 23, 9 0.20 98, 77, 23 - -
106 & 106.1 -65, 40, 30 0.54 0.34 81, 33, 3 0.13 118, 36, 24 - -
102 to 105 &
107 to 112
-150, 30, 160 0.39 0.31 7, 16, 30 0.21 25, 29, 33 0.09 65, 45, 38
Karakara 1001 -65, 30, 10 0.33 0.54 20, 9, 2 0.07 136, 43, 19 - -
1002 125, 65, 160 0.39 0.39 35, 5, 2 0.16 130, 40, 20 - -

 

October 15, 2025Page 143 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Deposit Domain Major, Semi Major
and Minor Axes
Rotations ZXZ (o)
C0§ C1§

Ranges

(m)

C2§

Ranges

(m)

C3§

Ranges

(m)

  1003 to 1005 120, 55, 155 0.42 0.42 25, 15, 5 0.12 120, 70, 40 - -
Kassassoko 1001 0, 10, 10 0.20 0.30 25, 15, 1 0.23 50, 25, 5 0.267 120, 70, 30
1002 0, 40, 10 0.22 0.32 25, 10, 1 0.23 60, 15, 4 0.229 130, 50, 13
1003 -20, 40, 10 0.23 0.31 20, 15, 1 0.24 20, 15, 1 0.22 150, 100, 18
1004 -40, 40, 10 0.27 0.35 25, 10, 1 0.21 60, 25, 3 0.164 155, 50, 8
1005 0, 10, 10 0.20 0.30 25, 15, 1 0.23 50, 25, 5 0.267 120, 70, 30
1006 -20, 30, 50 0.14 0.25 16, 5, 1 0.25 35, 10, 4 0.367 65, 35, 23
1007 170, 60, 5 0.19 0.42 5, 3, 1 0.14 10, 7, 6 0.253 18, 15, 10
1009 -30, 30, 5 0.36 0.41 25, 15, 1 0.15 80, 45, 2 0.0795 120, 70, 9
Western Splay 1001 -90, 25, -95 0.11 0.59 30, 20, 3 0.15 65, 50, 5 0.153 210, 180, 13
1002 -100, 30, -95 0.19 0.34 30, 10, 5 0.20 75, 30, 25 0.268 150, 85, 40
1003 -110, 25, -95 0.21 0.55 15, 10, 5 0.13 60, 35, 10 0.106 185, 100, 20
1004 -110, 25, -95 0.16 0.44 40, 20, 2 0.30 110, 85, 7 0.0979 175, 120, 15
1005 -110, 25, -95 0.14 0.36 25, 15, 1 0.16 75, 30, 5 0.339 120, 75, 10
1006 -110, 25, -95 0.17 0.78 30, 25, 15 0.03 100, 80, 30 0.0212 180, 130, 50
1007 -110, 25, -95 0.16 0.68 20, 10, 5 0.12 60, 35, 15 0.0526 110, 75, 25
1008 -110, 25, -95 0.16 0.51 30, 10, 2 0.24 75, 45, 25 0.103 180, 120, 40
1009 -110, 25, -95 0.16 0.51 30, 10, 2 0.24 75, 45, 26 0.103 180, 120, 40
Moungoundi 1001 310, 20, 0 0.49 0.36 30, 15, 5 0.16 98, 70, 55 - -
1002 290, 15, 0 0.48 0.42 11.5, 11.5, 5 0.09 50, 50, 25 - -
1003 90, 75, 0 0.35 0.35 22.5, 12, 12 0.31 65, 30, 30 - -
1004 285, 60, 20 0.46 0.47 10, 8, 6 0.07 70, 32, 32 - -
1005 280, 75, 0 0.48 0.28 5, 5, 5 0.24 40, 40, 40 - -
2001 310, 20, 0 0.46 0.41 30, 20, 3 0.13 50, 50, 20 - -
2002 290, 15, 0 0.52 0.40 6, 6, 6 0.08 45, 45, 45 - -
2003 90, 75, 0 0.50 0.21 20, 20, 20 0.29 80, 80, 80 - -
2004 285, 60, 20 0.38 0.40 30, 15, 5 0.22 60, 40, 25 - -
9999 (Waste) 0, 0, 0 0.50 0.36 10, 10, 10 0.12 60, 60, 60 0.027 600, 600, 600
Southern Arc 1001 & 1002 330, 35, 0 0.34 0.56 10, 10, 10 0.11 52, 52, 52 - -
1003 325, 30, 0 0.37 0.54 10, 10, 6 0.10 62, 50, 50 - -
1004 325, 45, 0 0.37 0.54 10, 10, 6 0.10 62, 50, 50 - -
1005 340, 40, 0 0.50 0.36 12, 12, 6 0.14 80, 48, 40 - -
1006 340, 40, 15 0.50 0.36 12, 12, 6 0.14 80, 48, 40 - -
1007 330, 25, 0 0.43 0.38 15, 15, 5 0.19 45, 45, 20 - -
1008 320, 40, 0 0.31 0.44 9, 9, 9 0.25 38, 38, 38 - -
1009 330, 35, 0 0.31 0.44 9, 9, 9 0.25 38, 38, 38 - -
1010 330, 35, 0 0.33 0.35 35, 15, 5 0.32 55, 25, 25 - -
2001 & 2002 330, 35, 0 0.37 0.43 10, 10, 2 0.20 35, 35, 15 - -
2003 325, 30, 0 0.48 0.46 5, 5, 5 0.06 38, 38, 38 - -

 

October 15, 2025Page 144 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Deposit Domain Major, Semi Major
and Minor Axes
Rotations ZXZ (o)
C0§ C1§

Ranges

(m)

C2§

Ranges

(m)

C3§

Ranges

(m)

2004 325, 45, 0 0.48 0.46 5, 5, 5 0.06 38, 38, 38 - -
2005 340, 40, 0 0.44 0.34 10, 10, 6 0.21 45, 25, 25 - -
2006 340, 40, 15 0.44 0.34 10, 10, 6 0.21 45, 25, 25 - -
2007 330, 25, 0 0.38 0.50 5, 5, 5 0.12 52, 52, 52 - -
2010 330, 35, 0 0.49 0.15 25, 25, 20 0.35 90, 90, 40 - -
  9999 (Waste) 0, 0, 175 0.58 0.40 18, 18, 18 0.02 345, 345, 345    

Note: Structures are modelled with a spherical model and all parameters are reported from a back transformed model. † ranges for major, semi-major, and minor axes, respectively. Domains with whole numbers include sub-domains unless otherwise stated.

 

14.6Modeling and Estimation

 

14.6.1Block Size Selection

 

Block size (see Section 14.6.2) was selected principally based on drill hole spacing, number of samples, mineralized domain geometry, and the proposed mining method. Kriging neighborhood analysis (KNA) was also used to assess the optimum block size based on kriging efficiency (KE) and slope of regression (ZZ) in the domains where variogram models had been established.

 

In conjunction with the KNA process, the proposed mining method of open pit, and the geometry of the mineralized wireframes are considered for selection of the optimal parent cell size.

 

14.6.2Block Model Parameters

 

The mineralized domains at Diamba Sud vary in dimensions significantly. Filling wireframes with blocks was completed in the XY plane for all deposits. Block model parameters used for each deposit are detailed in Table 14.4. Each deposit included three sets of wireframes to fill with blocks, including: lithological, weathering and mineralization. The wireframes were sequentially filled with blocks of the parent size with sub-celling down to a minimum of 0.5 m blocks for narrow domains such as diorite intrusions and high-grade mineralized domains. Wireframe volumes were compared to block model volumes for the mineralized domains to validate the block size and fill direction as appropriate. The deposits of Area A and Area D share the same block model parameters as they are adjacent to one another with the deposits combined into a singular model for pit optimization.

 

Table 14.4 Block Model Parameters by Deposit

 

Deposit Direction Minimum Maximum Parent Size
Area A & D X 232200 233580 5
Y 1428840 1429900 5
Z -100 200 5
Karakara X 231250 232150 5
Y 1427920 1428580 5
Z -80 185 5
Western Splay X 230700 231560 5
Y 1425980 1426600 5
Z -140 175 5
Kassassoko X 231315 232075 5
Y 1425595 1426125 5

 

October 15, 2025Page 145 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Deposit Direction Minimum Maximum Parent Size
  Z -50 210 5
Southern Arc X 232000 233200 10
Y 1425850 1426600 10
Z -100 200 5
Moungoundi X 230500 231260 10
Y 1426450 1427150 10
Z -140 175 5

 

14.6.3Sample Search Parameters

 

KNA was undertaken on each deposit to determine the optimal search parameters for the Mineral Resource estimates. The best estimation results in terms of slope of regression, kriging efficiency, and kriging variance. The optimal estimation and search parameters varied between domains but in general were as follows:

 

·A first pass search range of approximately 20–40 m along strike and down dip and 5-10 m across the strike, equivalent to the mineralized domain thickness.

 

·A minimum of 2 to 6 composites per block.

 

·A maximum of 16 to 20 composites per estimate.

 

·A maximum of two or three samples from a single drill hole.

 

The search ellipsoid used to define the extents of the search neighborhood honored the directions of continuity observed in the variograms. If the estimate failed to inform all blocks in the domain, a second pass was performed with an ellipsoid twice the size of the first. In rare circumstances where blocks remained unestimated after the second pass, a third pass was run, being three times the size of the first.

 

14.6.4Grade Interpolation

 

OK was selected as the preferred grade interpolation method with nearest neighbor (NN) and inverse distance weighting cubed (IDW) completed for validation comparison purposes.

 

Estimation parameters were based on the block size selection, search neighborhood optimization, and variogram modeling. Sample data were composited and, where necessary, top cut prior to estimation.

 

Composites and the blocks were categorized into mineralized domains for the estimation. Each block was discretized (an array of points to ensure grade variability is represented within the block) and grade interpolated into parent cells (Datamine ESTIMA parameter PARENT=1).

 

Dynamic anisotropy was used in the estimation of Area A, Area D and Karakara. This method was applied only to domains with geometry that would benefit from varied dynamic search ellipses. All other estimated domains employed a singular ellipse approach due to the significant sub-domaining of high/mid/low-grade hard boundaries generating relatively small volumes.

 

14.7Model Validation

 

The techniques for validation of the estimated tonnes and grades include visual inspection of the model and samples (plan-view, section-view, and in three-dimensions); cross-validation; global estimate validation through the comparison of declustered sample

 

October 15, 2025Page 146 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

statistics (except Area D where the even distribution of composites meant declustering to obtain representative mean grades was not required) with the average estimated grade per domain; and local estimate validation through the generation of slice validation plots.

 

14.7.1Visual Validation

 

Visual validation was performed on all estimated models, comparing estimated grades from all three estimation methods with the input composite data in cross-section through the entire deposit. Generally, the interpolated grades within the models reflect the input data on which they were based. An example is shown in Figure 14.2 from Area D.

 

Figure 14.2 Cross-Section of Estimated Gold Grade Block Model vs Top Cut Drill Hole Composites in Area D

 

 

 

14.7.2Global Estimation Validation

 

The comparison was conducted by deposit and then by domain. Generally, there was no significant variation for the selected interpolation method. In general, the differences observed were<5% in grades for all deposits and domains, with some of the more significant variations related to low-grade domains where absolute differences were minor and a result of restricting the spatial impact of higher grades. These variations were not considered as material.

 

14.7.3Local Estimation Validation

 

Slice validation plots of estimated block grades and input sample grades were generated for each of the mineralized domains by easting, northing, and elevation to validate the

 

October 15, 2025Page 147 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

estimates on a local scale. Validation of the local estimates assessed each model to ensure over-smoothing or conditional bias was not being introduced by the estimation process and an acceptable level of grade variation was present. An example slice (or swath) plot for Area D is displayed in Figure 14.3. Swath plots were generated for global comparisons mixing all mineralized domains and also separately by domain.

 

Figure 14.3 Swath Plot Analysis for Area D and Comparative Log-Probability Plot

 

 

 

Figure prepared by Fortuna, 2025.

 

The slice plots generally display a good correlation. Areas that do not are typically related to where sample numbers are limited, for example at the periphery of the deposit or at depth where the estimates are unclassified or classified as an Inferred Mineral Resource. Based on the swath plot results it was concluded that OK was a suitable interpolation method for all deposits, providing reasonable global and local estimates of gold.

 

14.7.4Mineral Resource Depletion

 

As at the effective date of this Report, Fortuna has not conducted mining activities at the Diamba Sud Project. However, local artisanal mining is common in the area with hand dug open pits and vertical shafts. Area A and Area D have not been impacted by artisanal mining activities as of the effective date of this Report. The Karakara, Western Splay, Kassassoko, Southern Arc and Moungoundi deposits have all been subject to artisanal mining activities. Recent artisanal mining has been restricted to the southern area of Western Splay only, with security services monitoring and requesting cessation when encountered. This artisanal activity at Western Splay was stopped in June 2024, and as at

 

October 15, 2025Page 148 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

the effective date of this Report, there is no active artisanal activity at Diamba Sud for any deposits with Mineral Resource estimates.

 

In order to account for the historical depletion, photogrammetric drone surveys were conducted during the dry season (when pits were not filled with water). In addition, selected areas were surveyed with handheld GPS and the extents noted on maps if any new workings outside of the surveyed areas were detected during the rainy season (when drone surveys do not provide adequate coverage due to ground water incursion). Wireframes were created based on the surveys with an offset at depth introduced to account for unknown depth of vertical shaft mining and deeper workings that may have collapsed prior to surveying.

 

A unique identifier is coded into the models by selecting block centroids above the artisanal pit wireframes, with a “MINED” field assigned where blocks assigned a value of “1”, if material remains in situ, and “0” if extracted. This is accounted for in reporting by excluding these blocks.

 

14.8Mineral Resource Classification

 

14.8.1Geological Continuity

 

There is sufficient geological information to support a reasonable understanding of the geological continuity at the Diamba Sud Project. The geology and structural controls for the deposits are complex and multiple studies involving re-logging of core and re-interpretation of sections and three-dimensional models have been undertaken to support the current weathering, geological and mineralized wireframe interpretations.

 

14.8.2Data Density and Orientation

 

The estimates of Area A, Area D, Karakara, Western Splay and Kassassoko are based on RC and core drill holes drilled on a 25 m grid pattern to ensure consistent sample support, except for at the periphery of the deposits where spacing increases to up to 50 m. Southern Arc and Moungoundi have generally been drilled using a 50 m grid pattern, with some central areas drilled on a tighter 25 m grid.

 

Drilling perpendicular to dip of mineralized structures at Diamba Sud is the primary accepted methodology for orienting planned holes. In areas where the orientation was not initially understood, drilling was conducted in a scissor pattern until geological continuity was established. The majority of the drill holes in the database intersect mineralization at a reasonable angle as close to orthogonal as is practicable with drilling techniques and interpretation.

 

Geological confidence and estimation quality are closely related to data density, and this is reflected in the resource classifications.

 

14.8.3Data Accuracy and Precision

 

Analysis of CRMs and blanks for the results of both ALS and SGS laboratories used by Boya indicate acceptable levels of accuracy for gold grades. Duplicate sample analyses indicate significant heterogeneity due to the nuggety gold effect at Diamba Sud. However, the variable results do not indicate bias and therefore are not regarded to represent a significant risk to the estimates.

 

14.8.4Spatial Grade Continuity

 

For the Diamba Sud deposits, the variogram nugget variance for gold is between 10–60% of the population variance averaging 35%, demonstrating the variable nature of the

 

October 15, 2025Page 149 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

mineralization. Ranges, representing the distance over which assays are related, generally vary from 20–60 m, being typical of this style of mineralization.

 

Confidence in the estimates has been exercised by controlling classification based on search ellipse size, with Mineral Resources only being estimated when the search size used in the block estimates is less than the variogram ranges.

 

14.8.5Classification

 

The Mineral Resource confidence classification of the Diamba Sud block models incorporated confidence in the drill hole data, the geological interpretation, geological continuity, data density and orientation, spatial grade continuity, and estimation quality. The resource models were coded as Inferred and Indicated in accordance with the 2014 CIM Definition Standards. Classification was based on the following steps:

 

·Blocks estimated using the first pass search neighborhoods were considered for the Indicated Resource category.

 

·Blocks estimated using second and third pass search neighborhoods were considered for Inferred or were unclassified respectively.

 

·KE and ZZ values were used where OK was the method of estimation.

 

·Minimum sample distances, of approximately 25 m for Indicated and 50 m for Inferred, for each estimated block were taken into account.

 

·The number of samples that influenced each block during estimation (typically 9 or 10 minimum sourced from multiple drill holes) was also considered when assigning classification.

 

The criteria were collectively considered with numeric parameters such as minimum distance from a sample, search volumes, and the minimum number of samples filtered in the resulting model. They were used as a guide for wireframe generation to ensure a gradational effect in classification. These were coded into the final model. An example is shown in Figure 14.4 for Area D.

 

October 15, 2025Page 150 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 14.4 Cross-Section Showing Mineral Resource Classification for Area D

 

 

 

14.9Mineral Resource Reporting

 

14.9.1Reasonable Prospects for Eventual Economic Extraction

 

Mineral Resources are reported based on an assumption open pit mining and constrained within a conceptual pit shell. Details of the inputs used to generate the pit shells for Mineral Resource reporting are detailed in Section 16.4.

 

Metallurgical parameters are based on metallurgical testwork as detailed in Section 13.9.

 

Pit slope angles of 33º for weathered material and 46º for fresh have been applied, based on geotechnical testwork as detailed in Section 16.3.

 

A long-term gold price of $2,600/oz was used in the constraining pit shells and for reporting the Mineral Resource estimates.

 

14.9.2Mineral Resource Statement

 

Eric Chapman P. Geo. is the QP responsible for the Diamba Sud Project Mineral Resource estimate.

 

Mineral Resources are reported insitu and have an effective date of July 7, 2025.

 

Mineral Resources are summarized in Table 14.5. Mineral Resources are reported within an optimized pit shell using a gold price of US$2,600/oz. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

 

October 15, 2025Page 151 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 14.5 Mineral Resources for the Diamba Sud Project

 
Category Deposit Material Type Cut-off Grade
(g/t Au)
Tonnes
(t x 1,000)
Au
(g/t)
Au
(koz)
Indicated Area A Oxide/Transitional 0.31 340 1.34 15
Fresh 0.35 3,551 1.48 169
Sub-total 3,891 1.47 184
Area D Oxide/Transitional 0.31 3,007 2.00 194
Fresh 0.42 1,870 1.33 80
Sub-total 4,877 1.75 274
Karakara Oxide/Transitional 0.31 40 1.62 2
Fresh 0.35 2,436 1.80 141
Sub-total 2,476 1.79 143
Western Splay Oxide/Transitional 0.31 160 0.95 5
Fresh 0.41 1,455 1.73 81
Sub-total 1,615 1.65 86
Kassassoko Oxide/Transitional 0.31 125 0.68 3
Fresh 0.35 1,169 0.93 35
Sub-total 1,294 0.90 38
Total Oxide/Transitional 3,672 1.85 218
Fresh 10,481 1.50 506
Total 14,153 1.59 724
Inferred Area A Oxide/Transitional 0.31 16 1.08 1
Fresh 0.35 44 1.00 1
Sub-total 61 1.02 2
Area D Oxide/Transitional 0.31 217 0.97 7
Fresh 0.42 384 1.17 14
Sub-total 600 1.10 21
Karakara Oxide/Transitional 0.31 21 2.92 2
Fresh 0.35 490 1.55 24
Sub-total 510 1.61 26
Western Splay Oxide/Transitional 0.31 23 1.08 1
Fresh 0.41 78 2.41 6
Sub-total 101 2.11 7
Kassassoko Oxide/Transitional 0.31 22 1.09 1
Fresh 0.35 101 0.79 3
Sub-total 123 0.85 3
Southern Arc Oxide/Transitional 0.31 315 1.15 12
Fresh 0.37 3,539 1.60 182
Sub-total 3,854 1.57 194
Moungoundi Oxide/Transitional 0.31 131 0.71 3
Fresh 0.39 791 1.12 28
Sub-total 922 1.06 31
Total Oxide/Transitional 745 1.06 25
Fresh 5,427 1.49 260
Total 6,171 1.44 285
               

Notes to accompany Mineral Resource table:

 

·Mr. Eric Chapman, P.Geo., is the Qualified Person responsible for Mineral Resources, and is a full-time employee of Fortuna.
·Mineral Resources are reported using the 2014 CIM Definition Standards.
·Mineral Resources are reported insitu, on a 100% basis as of July 7, 2025. The Government of Senegal will assume a 10% free-carried ownership interest in the Project when an exploitation permit is granted, and may elect to purchase up to an additional 25% interest in Boya SA at a “fair price” as determined through an independent valuation upon the granting of the exploitation permit.

 

October 15, 2025Page 152 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Mineral Resources are reported from a regularized block model derived from the original sub-blocked model to account for artisanal mining dilution.
·Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
·Mineral Resources are reported inside constraining pit shells using selective mining unit block sizes and at an incremental gold cutoff grade for oxide/transitional material of 0.31 g/t Au, with fresh material reported based on a cutoff of 0.35 g/t Au for Area A, 0.42 g/t Au for Area D, 0.35 g/t Au for Karakara, 0.41 g/t Au for Western Splay, 0.35 g/t Au for Kassassoko, 0.37 g/t Au for Southern Arc, and 0.39 g/t Au for Moungoundi in accordance estimated average base mining costs of US$4.57/t for all material mined, average processing and G&A costs of US$21.45/t milled, and sales and transportation costs of US$7.00/oz of gold. Pit slope angles applied are 33° for weathered material and 46° for fresh rock. The long-term gold price was US$2,600/oz. Metallurgical recoveries are estimated using grade versus recovery relationship formulas developed for oxide/transition rock (all deposits) and separate formulas for fresh rock in each of the seven deposits A royalty of 3.5% has been considered in the generation of the pit shell and cut-off grade determination.
·Totals may not add due to rounding.

 

Factors that may affect the estimates include metal price and exchange rate assumptions; changes to the assumptions used to generate the cut-off grades; changes in local interpretations of mineralization geometry and continuity of mineralized zones; changes to geological and mineralization shape and geological and grade continuity assumptions; variations in density and domain assignments; geometallurgical assumptions; changes to geotechnical, mining, dilution, and metallurgical recovery assumptions; change to the input and design parameter assumptions that pertain to the conceptual open pit constraining the estimates; extent of artisanal mining; and assumptions as to the continued ability to access the site, retain mineral and surface rights titles, maintain environment and other regulatory permits, and maintain the social license to operate.

 

There are no other environmental, legal, title, taxation, socioeconomic, marketing, political or other relevant factors known to the QP that would materially affect the estimation of Mineral Resources that are not discussed in this Report.

 

14.9.3Comparison to Previous Estimate

 

The primary reasons for the changes in Mineral Resources compared to the previous estimate are due to:

 

·A significant extension and infill drilling program at Area A, Area D, Karakara, Western Splay and Kassassoko.

 

·Exploration drilling at Southern Arc and Moungoundi.

 

·Geological reinterpretation.

 

·Changes in metal prices and projected operating costs.

 

The most significant change is considered to be related to the impact of the additional drilling conducted at all of the Diamba Sud deposits.

 

14.10Comment on Section 14

 

The QP is of the opinion that the Mineral Resources for the Diamba Sud Project, which have been estimated using RC and core drilling data, have been performed to industry best practices, and are reported using the 2014 CIM Definition Standards.

 

October 15, 2025Page 153 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

15Mineral Reserve Estimates

 

The Diamba Sud Project has no estimated Mineral Reserves

 

October 15, 2025Page 154 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

16Mining Methods

 

16.1Overview

 

The mine plan is partly based on Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the PEA based on these Mineral Resources will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

 

Mining is proposed for Mineral Resources defined inside an ultimate pit shell based on a long term gold metal price of US$2,300/oz, by conventional open pit mining methods and equipment, using the services of a mining contractor.

 

The proposed mining operations will consist of seven open pits (Area A, Area D, Karakara, Western Splay, Southern Arc, Moungoundi and Kassassoko). The Area D, Karakara and Southern Arc pits will be mined in two stages, the other pits will be mined in a single stage.

 

The overall mining and production strategy is to maintain a mill processing throughput of 2.0–2.5 Mt/a. The processing plant conceptual design capacity is 2.0 Mt/a of fresh rock, with capacity to process up to 2.5 Mt/a assuming a blend of 80% fresh rock and 20% oxidized rock. The pits were sequenced to maximize the amount of oxide mined early in the schedule to maximize the processing rate and cashflow early in the schedule. The mine life based on Indicated and Inferred Mineral Resources is 8.1 years.

 

Drilling and blasting are planned for oxide, transitional and fresh mill feed material and waste, followed by conventional excavator and truck operations within the pits for the movement of mill feed material and waste. Free digging will be conducted in the oxide zones if practical, otherwise blasting has been assumed for all the weathering horizons. Bench heights for extraction of mill feed material and waste material is 5 m taken in two digging flitches of 2.5 m. Where possible in high waste stripping pit stages, 10 m bench heights will be used at an appropriate standoff distance from known mineralization.

 

Mining costs and equipment requirements are predominantly based on a request for pricing conducted in 2025. The mining equipment is proposed to be 120 t and 200 t excavators, along with 100 t haul trucks. The annual rate of mining movement peaks at 9 million bank cubic meters. A common pool of equipment will be used and scheduled across all of the active pits so that movement between the pits is minimized.

 

A tender process will be used to select the mining contractor.

 

Run-of-mine (ROM) material will be trucked from the pits to the ROM pad and tipped onto the ROM pad to be reclaimed and loaded to the crusher feed bin using front-end loaders that will be operated by the mining contractor.

 

16.2Hydrogeology

 

A hydrogeology study was performed by Knight Piésold Consulting (2025a) to evaluate and advance the hydrogeological understanding of the Diamba Sud Project area.

 

Five groundwater exploration boreholes were drilled in 2022, of which two were converted into production boreholes and one into a monitoring borehole. An additional 23 groundwater exploration boreholes were drilled in 2024–2025, with two used to supply the camp water. Five of the remaining 21 boreholes were converted into production

 

October 15, 2025Page 155 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

boreholes and 13 were converted into groundwater monitoring boreholes. The remaining three boreholes encountered drilling issues and were not completed.

 

Based on the drilling results, the successful boreholes all intersect deeper faults/fracture zones associated with the interpreted geological structures. Very little to no groundwater was intercepted in the saprolite and shallower weathered formations. The relatively large yields intercepted in the fractured bedrock indicate that some of the geological structures in the vicinity of the deposits are open and saturated at depth and could potentially be a source of significant volumes of groundwater for operational make-up water into the planned pits.

 

A numerical model was designed and built to estimate pit dewatering requirements, potential dewatering impacts and to assess groundwater levels after closure. The model was calibrated in steady-state and transient modes. The maximum predicted dewatering for all simulated pits is 51 L/s (4,370 m2/day), which could be expected in the first quarter of year 5.

 

A summary of maximum predicted dewatering for the Area A, Area D, and Karakara deposits is presented in Table 16.1.

 

Table 16.1 Maximum Predicted Dewatering (average over one quarter)

 

Pit 99th Percentile
m3 / day liter / second
Area A 2,750 32
Area D 1,970 23
Area D South 1,035 12
Karakara 1,650 19
Maximum Predicted 4,370 51

 

Due to the low permeability of the hydrostratigraphic units in the immediate planned mining areas, sump pumping is the preferred dewatering option for the planned pits on these deposits. Additionally, ex-pit bores may be used and pumped to manage pit inflows, assist with pit wall depressurization, and provide supplementary water supply.

 

The Western Splay and Kassassoko deposits were included by Fortuna in the later stages of the study. These were not included in the site investigations or numerical groundwater model; however, analytical modelling was undertaken to provide preliminary pit inflow estimations for both. The assessment indicates potential pit inflow volumes of 14–39 L/s in year 1, 12–32 L/s in year 5 at Western Splay, 7–19 L/s in year 1 and 6–16 L/s in year 5 at Kassassoko for the pit shells provided. No hydrogeological information is available for these two pits. Aquifer parameters obtained from drilling and aquifer testing in similar hydrogeological settings, such as at the nearby Area A and D deposits, were extrapolated and used in the analytical estimations for Western Splay and Kassassoko.

 

Any future pits not tested as of the effective date of this Report, including Moungoundi and Southern Arc, will be characterized by their size and location with testing undertaken in advance of their proposed mining in accordance with the proposed mine plan.

 

Groundwater elevations are generally shallow or a maximum of 20 m below ground surface. All proposed open pits will require a dewatering plan where the pumped water will be sent to a water storage dam for additional plant make-up water. The plan is to operate the process plant and mine as a “closed circuit”.

 

October 15, 2025Page 156 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Following the cessation of mining and dewatering at Diamba Sud, in-pit water levels are predicted to rebound slowly. Modelled results suggest that the open pits will act as groundwater sinks, inducing groundwater flow towards the pits from about a 2 km radius around the pits, as groundwater levels recover towards pre-mining levels.

 

16.3Mine Geotechnical

 

Geotechnical parameters are based on the report from Piteau Associates (2025). The host rock for the open pits consists primarily of sedimentary, granitic and volcaniclastic rocks with a small proportion of diorites. Rock weathering, as interpreted from borehole logs and review of core photographs, varies throughout the Diamba Sud project area. In Area D the depth of weathering varies from 15–85 m, Area A the depth of weathering varies from 5–30 m and the other planned pits the depth of weathering varies from 1–20 m.

 

An aggressive bench design is proposed based on the short LOM, size and depth of the pits, no use of pushbacks, and use of double benches replaced by single benches to help limit risk, reduce operational complexity and costs, making more manageable any possible bench scale instability (when compared against a 20 m bench height). However, the approach simultaneously limits the opportunity to conduct trial implementations.

 

A fixed set of slope design parameters were used for each of the weathered rock (comprising laterite duricrust, saprolite and partially weathered transition) and fresh rock domains for all pits for all wall orientations (Table 16.2). The slope reliability was then estimated for the designed slopes based on the influence of the structures and the kinematically possible failure mechanisms.

 

Table 16.2 Geotechnical Slope Design Parameters for all Diamba Sud Pits

 

Domain

Batter
Angle (0)

Berm
Width (m)

Berm
Interval (m)

Inter Ramp
Angle (0)

Overall Slope
Angle (0)
Weathered 60 3.5 5.0 38.0 33.2
Fresh 70 3.5 10.0 54.5 46.1
An additional 5.0 m berm width to be added at base of weathering and at 50 m depth of weathering (if weathered zone > 50 m depth).

 

The proposed bench design was validated for the proposed Area A, Area D, and Karakara pits by conducting two-dimensional anisotropic limit equilibrium analyses of the most critical slope sections. Previous pit designs were used as a reference to define pit floor elevations, and the slopes were redrawn based on the proposed bench parameters. The results of the inter-ramp and overall stability analyses support implementing the updated design parameters within the current geological model and structural fabric framework, excluding major faults. Stability analyses will need to be updated once data on major faults become available for these pits.

 

Surface water management (diversion ditches) will be key to avoiding water ponding above the duricrust and saprolite slopes during the wet season.

 

The inter-ramp and overall stability analysis considered a phreatic surface located approximately 20 m below ground surface. This will require monitoring. Additional dewatering efforts might be required once mining starts and if failures occur due to the presence of more groundwater than anticipated.

 

October 15, 2025Page 157 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

16.4Pit Optimizations

 

16.4.1Block Model

 

Block models were provided in Datamine format. The block models for Areas A-D, Karakara, Western Splay, and Kassassoko were regularized to 5 x 5 x 5 m dimensions. The block models for Southern Arc and Moungoundi were regularized to 10 x 10 x 5 m. The block model regularization was used to represent mining dilution and mining recovery inherent within the block model tonnes and grade.

 

Prior to conducting pit optimization, the block models had the following modifications:

 

·All operating costs including mining, processing, selling, and general and administrative costs were estimated for each block within the block model.

 

·Potential revenue was estimated for each mineralized block within the block model based on the estimated metallurgical recoveries and the forecast long-term gold price.

 

·Geotechnical domains were applied based on the weathering domain (oxide/transition, fresh) as per the geotechnical recommendations.

 

16.4.2Optimization Parameters

 

Financial Inputs and Selling Costs

 

Table 16.3 shows the financial parameters and selling costs applied in the pit optimization.

 

Table 16.3 Financial Parameters and Selling Costs Applied Inpit Optimization

 

Input Unit Value
Currency $ Currency US dollars
Discount Rate % 5.0
Gold price US$/oz 2,300
Royalty % Revenue 3.5
Refining and selling costs US$/oz 7.0

 

The pit optimization shells used for the mineralized material in the LOM plan and economic analysis were generated using a gold price of $2,300/oz whereas a gold price of $2,600/oz, assuming a 15% upside, was used to estimate Mineral Resources.

 

Mining Costs

 

Table 16.4 summarizes the mining costs and parameters applied within the pit optimizations. Table 16.5 and Table 16.6 show the variable load and haul costs by bench for waste and mineralized material respectively. Mining dilution and recovery is represented in the selective mining unit (SMU) within the block model regularization.

 

Table 16.4 Mining Parameters Costs Applied Inpit Optimization

 

Input Unit Value
Mining dilution % Included in SMU
Mining recovery % Included in SMU
Mill feed material load and haul costs US$/t Variable by pit and bench
Waste load and haul costs US$/t Variable by pit and bench
Drilling cost – waste US$/t 0.38
Drilling cost – mill feed material US$/t 1.12
Blasting cost – Area A mill feed material US$/t 0.54
Blasting cost – Area A waste US$/t 0.45
Blasting cost – Area D mill feed material US$/t 0.46

 

October 15, 2025Page 158 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Input Unit Value
Blasting cost – Area D waste US$/t 0.34
Blasting cost – Karakara mill feed material US$/t 0.55
Blasting cost – Karakara waste US$/t 0.45
Blasting cost – Kassassoko mill feed material US$/t 0.53
Blasting cost – Kassassoko waste US$/t 0.46
Blasting cost – Moungoundi mill feed material US$/t 0.46
Blasting cost – Moungoundi waste US$/t 0.34
Blasting cost – Southern Arc mill feed material US$/t 0.53
Blasting cost – Southern Arc waste US$/t 0.46
Blasting cost – Western Splay mill feed material US$/t 0.46
Blasting cost – Western Splay waste US$/t 0.34
Mining overheads US$/t 0.29
Diesel cost US$/t 1.02
Mobilization, mine development, demobilization US$/t 0.14

 

Table 16.5 Waste Load and Haul Costs in US$/t

 

Elevation Area A Area D Karakara Kassassoko Western
Splay
Moungoundi Southern
Arc
180 1.39 1.83
175 1.41 1.87
170 1.43 1.90
165 1.44 1.94
160 1.46 1.97
155 1.48 2.01 1.40
150 1.50 2.04 1.41 1.87 1.87  
145 1.52 2.08 1.42 1.92 1.92 2.33
140 1.53 2.11 1.43 1.97 2.33 1.97 2.35
135 1.55 2.15 1.44 2.03 2.35 2.03 2.37
130 1.57 2.18 1.45 2.08 2.37 2.08 2.39
125 1.59 2.22 1.46 2.13 2.39 2.13 2.41
120 1.61 2.25 1.47 2.18 2.41 2.18 2.44
115 1.62 2.29 1.48 2.23 2.44 2.23 2.46
110 1.64 2.32 1.49 2.29 2.46 2.29 2.48
105 1.66 2.36 1.50 2.34 2.48 2.34 2.50
100 1.68 2.39 1.51 2.39 2.50 2.39 2.52
95 1.70 2.43 1.52 2.44 2.52 2.44 2.54
90 1.71 2.46 1.53 2.49 2.54 2.49 2.56
85 1.73 2.50 1.54 2.55 2.56 2.55 2.58
80 1.75 2.53 1.55 2.60 2.58 2.60 2.60
75 1.77 2.57 1.56 2.65 2.60 2.65 2.62
70 1.79 2.60 1.57 2.70 2.62 2.70 2.65
65 1.80 2.64 1.58 2.75 2.65 2.75 2.67
60 1.82 2.67 1.59 2.81 2.67 2.81 2.69
55 1.84 2.71 1.60 2.86 2.69 2.86 2.71
50 1.86 2.74 1.61 2.91 2.71 2.91 2.73
45 1.88 2.78 1.62 2.96 2.73 2.96 2.75
40 1.89 2.81 1.63 3.01 2.75 3.01 2.77
35 1.91 2.85 1.64 3.07 2.77 3.07 2.79
30 1.93 2.88 1.65 3.12 2.79 3.12 2.81
25 1.95 2.92 1.66 3.17 2.81 3.17 2.83
20 1.97 2.95 1.67 3.22 2.83 3.22 2.86

 

October 15, 2025Page 159 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 16.6 Mill Feed Material Load and Haul Costs in US$/t

 

Elevation Area A Area D Karakara Western
Splay
Kassassoko Moungoundi Southern
Arc
180 2.67 1.89
175 2.74 1.94
170 2.81 1.98
165 2.88 2.03
160 2.95 2.07
155 3.02 2.12 1.83
150 3.08 2.16 1.85 2.61 2.61
145 3.15 2.21 1.86 2.68 2.68 2.59
140 3.22 2.25 1.88 2.75 2.59 2.75 2.62
135 3.29 2.30 1.90 2.82 2.62 2.82 2.65
130 3.36 2.34 1.92 2.89 2.65 2.89 2.68
125 3.43 2.39 1.93 2.96 2.68 2.96 2.71
120 3.50 2.43 1.95 3.02 2.71 3.02 2.74
115 3.57 2.48 1.97 3.09 2.74 3.09 2.76
110 3.64 2.52 1.98 3.16 2.76 3.16 2.79
105 3.71 2.57 2.00 3.23 2.79 3.23 2.82
100 3.77 2.61 2.02 3.30 2.82 3.30 2.85
95 3.84 2.66 2.03 3.37 2.85 3.37 2.88
90 3.91 2.70 2.05 3.44 2.88 3.44 2.91
85 3.98 2.75 2.07 3.51 2.91 3.51 2.94
80 4.05 2.79 2.09 3.58 2.94 3.58 2.97
75 4.12 2.84 2.10 3.65 2.97 3.65 3.00
70 4.19 2.88 2.12 3.71 3.00 3.71 3.03
65 4.26 2.93 2.14 3.78 3.03 3.78 3.05
60 4.33 2.97 2.15 3.85 3.05 3.85 3.08
55 4.40 3.02 2.17 3.92 3.08 3.92 3.11
50 4.46 3.06 2.19 3.99 3.11 3.99 3.14
45 4.53 3.11 2.20 4.06 3.14 4.06 3.17
40 4.60 3.15 2.22 4.13 3.17 4.13 3.20
35 4.67 3.20 2.24 4.20 3.20 4.20 3.23
30 4.74 3.24 2.26 4.27 3.23 4.27 3.26
25 4.81 3.29 2.27 4.34 3.26 4.34 3.29
20 4.88 3.33 2.29 4.40 3.29 4.40 3.32

 

Processing, General and Administrative Costs

 

Table 16.7 summarizes the run-of mine (ROM) costs applied to the mill feed material including forecast sustaining capital costs and general and administrative costs, as well as grade control and crusher feed costs.

 

Table 16.7 ROM Costs Applied in Pit Optimization

 

Input Unit Value
Mining Owner Costs
   Oxide US$/t mill feed material 1.14
   Fresh US$/t mill feed material 1.41
Grade Control
   Oxide US$/t mill feed material 0.66
   Fresh US$/t mill feed material 0.74
Processing
   Oxide US$/t mill feed material 11.82
   Fresh US$/t mill feed material 14.11

  

October 15, 2025Page 160 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Input Unit Value
Crusher Feed  
   Oxide US$/t mill feed material 0.45
   Fresh US$/t mill feed material 0.56
General & Administration
   Oxide US$/t mill feed material 6.37
   Fresh US$/t mill feed material 7.96

 

Processing Recovery

 

Processing recovery was applied using formulae reflecting grade recovery relationships for fresh rock and oxidized rock for all deposits. A single grade recovery relationship was used for oxide and partially weathered transition rock across all seven deposits. For fresh rock, separate grade recovery relationships were used in each deposit base on testwork related to that deposit. These recovery formulas and values are detailed in Section 13 of this Report.

 

Overall Slope Angles

 

The overall slope angles applied in the pit optimizations were 32 degrees for weathered material and 46 degrees for fresh material, based on the following:

 

·Geotechnical batter and berm parameters for each weathering domain, as outlined in Section 16.3 of this Report.

 

·Vertical depth of geotechnical domain.

 

·Ramp width and number of ramp passes within each geotechnical domain.

 

16.4.3Optimization Outcomes

 

A set of nested pit shells were produced by the Deswik pseudoflow function. The nested shells were used to determine trends in mineralization and higher-grade areas that would offer opportunities to stage pits to increase discounted cashflow.

 

Table 16.8 shows the selected pit shells used to guide the ultimate pit designs for each deposit.

 

Table 16.8 Optimizations Results

 

Deposit Revenue
Factor
Total Mined
(Mt)
Waste Mined
(Mt)
Strip Ratio
(Waste:Mineralized
Material)
ROM
Feed
(Mt)

Grade
(g/t Au)

Metal
Content
(koz)
Area A 1.00 26.33 22.98  6.9 3.35  1.58 170.2
Area D 1.00 17.50 12.61  2.6 4.89  1.80 283.2
Karakara 1.00 19.40 16.70  6.2 2.70  1.87 162.6
Western Splay 1.00 3.06 2.02  2.0 1.03  1.02 33.9
Kassassoko 1.00 11.90 10.39  6.9 1.51  1.77 85.8
Moungoundi 1.00 4.36 3.56  4.5 0.80  1.12 28.9
Southern Arc 1.00 16.11 12.98  4.1 3.13  1.71 171.7

 

Revenue factor 1 pit shells were chosen for the ultimate pit extents due to the relatively short mine life of each individual pit. Each set of nested pit shells informed pit stage designs. Trends in stripping ratio and cash costs were used to prioritize and sequence lowest stripping ratio and lowest cash cost ounces, while maintaining an appropriate level of working benches.

 

October 15, 2025Page 161 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

16.5Mine Design

 

16.5.1Pit Design

 

Detailed pit stage designs were prepared based on the results of the pit optimizations and incorporating appropriate wall angles, geotechnical berms, minimum mining widths, and access ramps with sufficient width for the proposed mining equipment.

 

16.5.2Pit Design Parameters

 

The geotechnical parameters applied to the pit designs include batter face angles, berm widths, and overall slope angles.

 

Pit ramps were designed with the following characteristics:

 

·Dual lane ramps are a total of 24.8 m wide (corresponding to three haul truck widths), including 19.5 m distance for safe passing of two of the selected CAT 777E haul truck, a 4.8 m wide bund, and a 0.5 m drain width.

 

·Single lane ramps are a total of 15.0 m wide, including 9.7 m distance for sufficient room for a single CAT 777E haul truck, a 4.8 m wide bund, and a 0.5 m drain width.

 

·Gradient of 1:10 for all dual lane ramps.

 

·Gradient of 1:9 for single lane ramps for the final 40 vertical meters of each ultimate pit.

 

·Single lane ramps have an overtaking lane every 20 vertical meters.

 

·Ramps exit the pit in the direction of the WRSFs.

 

·All pits include a goodbye cut at a maximum depth of 5 m.

 

Pits were designed to have a minimum mining width of 20 m and a minimum cutback width of 25 m. The location of the proposed pits is displayed in Figure 16.1.

 

October 15, 2025Page 162 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 16.1 Diamba Sud Project Proposed Mining Area Layout

 

 

 

Figure prepared by Knight Piésold, 2025.

 

Area D

 

Area D commences during the pre-strip-mining phase due to mineralization being associated with near-surface oxide material. Area D will be mined in two pit stages, prioritizing the highest grade, lowest waste stripping mineralized material. Stage 1 will be 55 m deep and will have a strip ratio of 1.8 (waste to mill feed material). Stage 2 will be 115 m deep and will have a strip ratio of 3.6. Mining stage 2 is planned to commence in month 7 and completed in month 31.

 

The Area D pit will be located within 1 km of the proposed processing plant and ROM pad. Mill feed material will be hauled to the ROM pad and waste rock will be hauled to the Area D WRSF that will be located to the northwest of the pit. Area D waste rock will be used for future lifts of the TSF, as well as to form a buttress for the tailings at the end of the mine life if required.

 

October 15, 2025Page 163 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Karakara

 

Karakara will be mined in two stages and also will commence during the pre-strip-mining phase to provide an early source of high-grade fresh rock feed to blend with Area D oxide feed. This blending will improve plant performance and maximize gold production in the first four years of the mine life. Stage 1 will be 55 m deep and have a strip ratio of 9.4. Stage 2 will be 140 m deep and have a strip ratio of 6.0 and will be completed in month 29. Mill feed material will be hauled to the ROM pad and waste rock will be hauled to the WRSF adjacent to the pit.

 

Area A

 

Area A will require a large waste strip prior to producing significant quantities of plant feed and is forecast to have a lower profit margin (US$/oz) than Area D and Karakara. The Area A pit will be 170 m deep and have a strip ratio of 8.1. Mining will commence in month 32, when Area D Stage 2 pit is complete. Mining of Area A will be completed in month 71. Mill feed material will be hauled to the ROM pad and waste rock will be hauled to the Area A-D WRSF that will be located to the northwest of the pit.

 

Western Splay

 

The Western Splay pit will be at the southern end of the mining area, will be 130 m deep and will have a haul distance to the ROM pad of about 4.0 km. Mining will commence in month 25 and will be completed in month 45. Mill feed material will be hauled to the ROM pad and waste rock will be hauled to the WRSF adjacent to the pit.

 

Southern Arc

 

Southern Arc will be mined as two separate pits at the southern end of the mining area. The pits will be 115 and 105 m deep respectively and have a haul distance to the ROM pad of approximately 4.0 km. The Mineral Resource estimate for Southern Arc is classified as Inferred and has been delayed in the mine plan for this reason. Mining will commence in month 41 and be completed in month 82. Mill feed material will be hauled to the ROM pad and waste rock will be hauled to the WRSF adjacent to the pit.

 

Kassassoko

 

Kassassoko will be the smallest of the pits (45 m deep), is low grade (~1.0 g/t) and is located at the southern end of the mining area. Mining will commence in month 71 and be completed in month 79. It will provide low-grade mineralized material that will be blended with the higher-grade mineralization from Area A. Mill feed material will be hauled to the ROM pad and waste rock will be hauled to the WRSF adjacent to the pit.

 

Moungoundi

 

Moungoundi will be at the southern end of the mining area, will be low grade (~1.0 g/t), and 80 m deep and will have a haul distance to the ROM pad of approximately 4.0 km. The Mineral Resource estimate for Moungoundi is classified as Inferred and has been delayed in the mine plan for this reason. Mining will commence in month 83 and be completed in month 88. It will provide low-grade mill feed material that can be blended with the higher-grade mineralization from Area A. Mill feed material will be hauled to the ROM pad and waste rock will be hauled to the WRSF adjacent to the pit.

 

16.5.3Waste Rock Storage Facilities

 

WRSFs were designed for each deposit, with the intention of minimizing haulage distance for the movement of waste material from the open pit to the adjacent surface WRSF. Designs included consideration of surface water drainage, and existing and planned infrastructure locations. The facilities were designed using an 18º batter slope, with a 7 m

 

October 15, 2025Page 164 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

berm every 20 vertical meters to achieve a footprint consistent with the requirements of rehabilitated waste dumps at closure. Figure 16.1 shows the location of each of the proposed WRSF designs within the mining area layout.

 

Table 16.9 shows the WRSF capacities in cubic meters for each of the WRSF designs.

 

Table 16.9 WRSF Capacities

 

WRSF Capacity (million m3)
Area A / Area D 31.5
Karakara 12.4
Western Splay / Kassassoko / Southern Arc / Moungoundi 25.9

 

There is sufficient capacity within the WRSF designs to support the PEA. Total waste volume will be 32.2 million bank cubic meters and given a 25% swell factor and 5% compaction factor, the total WRSF capacity required for the LOM is 69.8 Mm3.

 

The mine design and schedule does not include any pit backfilling using waste rock.

 

There is no known potentially acid forming waste rock, as at the effective date of this Report, at the Diamba Sud Project.

 

16.6Mining Operations

 

Conventional drill and blast, load and haul open pit mining is proposed to extract mineralized material from the pits. ROM material will be defined by grade control procedures in the pit and delivered by truck to the ROM pad, which is planned to be located adjacent to the Diamba Sud processing facility. Waste rock will be hauled to the closest WRSF associated with the pit being mined.

 

A mining contractor will be used for the eight years of operations. If additional mineralization is outlined, there is potential that any future mining operations could transition to an Owner-operation model, or the contractor could be retained as the operator.

 

A common pool of equipment will be used and scheduled across all active pits, so that movement of equipment between the pits is minimized, and consumables and spare parts are shared within the fleet.

 

Mining activities are planned to operate 24 hours per day, seven days a week with work occurring over three eight-hour shifts.

 

16.6.1Drill and Blast, Excavate, Load and Haul

 

The Diamba Sud Project will be mined by conventional truck and excavator operation for the mining of mill feed material and waste. Drill and blasting are planned for oxide, transitional and fresh mineralized material and waste material. Some free digging of oxide material is planned for weathered zones when feasible. Table 16.10 summarizes the drill and blast parameters used.

 

Table 16.10 Drill and Blast Assumptions

 

Material Type Bench Height
(m)
Diameter
(mm)
Powder
Factor
Product Burden
(m)
Spacing
(m)
Subdrill
(m)
Oxide -laterite 5–10 127 0.3 ANFO 4.8 4.2 0.5
Transitional 5–10 127 0.5 Emulsion 4.7 4.1 0.5
Fresh 5–10 127 0.7 Emulsion 4.0 3.4 0.5

 

October 15, 2025Page 165 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

To minimize dilution and mill feed material loss, all mineralized material will be drilled and blasted with 5 m bench heights and mined at 2.5 m flitch heights. To minimize costs and increase productivity, in high waste stripping pit stages, waste not directly adjacent to mineralized material will be drilled and blasted with 10 m bench heights where possible. All mining equipment will be supplied by the contractor, and all equipment costs are fully considered in the contractor’s schedule of rates.

 

The mining fleet is proposed to be a combination of 120 t and 200 t excavators, paired with 100 t trucks. The truck fleet will be used to haul waste material to the WRSF adjacent to each pit and mill feed material to the ROM pad. The furthest mill feed material haulage route is from the southern mining area (Western Splay, Southern Arc, Moungoundi and Kassassoko pits), a distance of approximately 4.0 km.

 

16.6.2Ancillary and Support Fleet

 

The ancillary and support mining fleet will include dozers, graders, water trucks and service trucks.

 

The ancillary fleet will be required to construct roads, strip and clear vegetation and topsoil, complete rehabilitation works, maintain WRSFs and stockpiles and carry out general clean-up operations around mining faces and provide support to the primary excavation equipment.

 

Front-end loaders will be used on the ROM pad to feed the crusher with a blend from ROM stockpiles, removal of oversized boulders, road construction and rehabilitation work.

 

16.6.3Other Mining Infrastructure

 

A workshop that maintains the mine fleet will be constructed by the mining contractor, along with the required offices and storage facilities for the contractor to conduct their operations.

 

16.6.4Equipment and Personnel Requirements

 

The estimate of equipment requirements over the mine life is detailed in Table 16.11, which will be shared across the various deposits. The estimated personnel requirements over the mine life are detailed in Table 16.12.

 

Table 16.11 LOM Mining Equipment Requirements

 

Equipment Max LOM Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Mining Fleet Load and Haul
Excavator - 120 - 200t 3 3 3 3 3 3 3 2 2 2
Trucks – 100 t 18 12 15 15 18 18 12 12 12 12
Ancillary
Dozer 3 3 3 3 3 3 3 3 3 3
Grader 1 1 1 1 1 1 1 1 1 1
Watercart 2 2 2 2 2 2 2 2 2 2
ROM Loader 2 2 2 2 2 2 2 2 2 2
Rock Breaker 1 1 1 1 1 1 1 1 1 1
Compactor 1 1 1 1 1 1 1 1 1 1
Service Truck 1 1 1 1 1 1 1 1 1 1
Drill and Blast
Blast hole Drill Rig 6 4 6 6 6 6 6 3 3 3
Grade Control Rig 2 2 2 2 2 2 2 2 2 2
Bulk Explosive Truck 1 1 1 1 1 1 1 1 1 1

 

October 15, 2025Page 166 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 16.12 LOM Personnel Requirements

 

Personnel Max LOM Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Fortuna Mine Department
Mining Manager 1 1 1 1 1 1 1 1 1 1
Mining Superintendent 1 1 1 1 1 1 1 1 1 1
Chief Mining Engineer 1 1 1 1 1 1 1 1 1 1
Mining Engineer 4 4 4 4 4 4 4 4 4 4
Senior Geotechnical Engineer 1 1 1 1 1 1 1 1 1 1
Geotechnical Engineer 2 2 2 2 2 2 2 2 2 2
Production Eng /Pit Supervisor 1 1 1 1 1 1 1 1 1 1
Senior Supervisor 1 1 1 1 1 1 1 1 1 1
Surveyor 4 4 4 4 4 4 4 4 4 4
Data Entry Clerk 2 2 2 2 2 2 2 2 2 2
Secretary 2 2 2 2 2 2 2 2 2 2
Chief Geologist 1 1 1 1 1 1 1 1 1 1
Senior Mine Geologist 1 1 1 1 1 1 1 1 1 1
Mine Geologist 4 4 4 4 4 4 4 4 4 4
Geology / Survey Technician 12 12 12 12 12 12 12 12 12 12
Contractor Management & Support
Production Manager 1 1 1 1 1 1 1 1 1 1
Pit Superintendent (DBLH) 3 3 3 3 3 3 3 3 3 3
Stores Manager 1 1 1 1 1 1 1 1 1 1
Junior Drill & Blast Engineer 1 1 1 1 1 1 1 1 1 1
Human Resources & Training Manager 1 1 1 1 1 1 1 1 1 1
Safety Controller 3 3 3 3 3 3 3 3 3 3
Load & Haul Foreman 3 3 3 3 3 3 3 3 3 3
Drill & Blast Foreman 3 3 3 3 3 3 3 3 3 3
Dewatering Supervisor 1 1 1 1 1 1 1 1 1 1
Instructor (Production & Engineering) 2 2 2 2 2 2 2 2 2 2
Financial Controller 1 1 1 1 1 1 1 1 1 1
Clerks 2 2 2 2 2 2 2 2 2 2
Storeman 4 4 4 4 4 4 4 4 4 4
Buying & Logistics 2 2 2 2 2 2 2 2 2 2
Contractor Mining Personnel
Excavator Operator 12 12 12 12 12 12 12 12 12 12
Dump Truck Operator 54 54 54 54 54 54 54 54 54 54
Dozer Operator 12 12 12 12 12 12 12 12 12 12
ROM Loader Operator 3 3 3 3 3 3 3 3 3 3
All Round Operator 9 9 9 9 9 9 9 9 9 9
Driller 15 15 15 15 15 15 15 15 15 15
Driller assistant 5 5 5 5 5 5 5 5 5 5
Grader Operator 3 3 3 3 3 3 3 3 3 3
Water Bowser Operator 3 3 3 3 3 3 3 3 3 3
Dewatering Assistants 6 6 6 6 6 6 6 6 6 6
Pit Controllers 5 5 5 5 5 5 5 5 5 5
Office & General 3 3 3 3 3 3 3 3 3 3
Diesel Truck Diesel Operator 6 6 6 6 6 6 6 6 6 6
Shift Change Bus Driver 5 5 5 5 5 5 5 5 5 5
Site Superintendent 1 1 1 1 1 1 1 1 1 1
Site Supervisors 2 2 2 2 2 2 2 2 2 2
Site Admin - Safety Officers 2 2 2 2 2 2 2 2 2 2
Blasters 3 3 3 3 3 3 3 3 3 3
Mobile Mixing Unit Operator 3 3 3 3 3 3 3 3 3 3

 

October 15, 2025Page 167 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Personnel Max LOM Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Mobile Mixing Unit Assistant 4 4 4 4 4 4 4 4 4 4
Blasting Assistants 4 4 4 4 4 4 4 4 4 4
Stemming Crew 4 4 4 4 4 4 4 4 4 4
Site Mechanics 2 2 2 2 2 2 2 2 2 2
Plant Foreman 2 2 2 2 2 2 2 2 2 2
Contractor Maintenance Personnel
Earthmoving Plant Manager 1 1 1 1 1 1 1 1 1 1
Boilermaker Foreman 1 1 1 1 1 1 1 1 1 1
Technical Analyst 1 1 1 1 1 1 1 1 1 1
Tyre Foreman 1 1 1 1 1 1 1 1 1 1
Maintenance Planner 1 1 1 1 1 1 1 1 1 1
Shift Foreman 4 4 4 4 4 4 4 4 4 4
Artisan (Mechanic) 13 13 13 13 13 13 13 13 13 13
Electrical 3 3 3 3 3 3 3 3 3 3
Boilermaker 3 3 3 3 3 3 3 3 3 3
Maintenance Assistants 21 21 21 21 21 21 21 21 21 21
Multiskilled Truck Drivers 15 15 15 15 15 15 15 15 15 15
Tyre Handler Operator 3 3 3 3 3 3 3 3 3 3
Tyre Handler - Assistant 3 3 3 3 3 3 3 3 3 3
Mobile Crane 1 1 1 1 1 1 1 1 1 1
Plant Clerk 1 1 1 1 1 1 1 1 1 1
Reporting Clerk 3 3 3 3 3 3 3 3 3 3
General Workers 7 7 7 7 7 7 7 7 7 7
Total Mining Personnel 316 316 316 316 316 316 316 316 316 316

 

16.7Mining and Production Schedule

 

A mining and production schedule was prepared for the eight-year LOM based on the following scheduling parameters:

 

·Monthly scheduling periods.

 

·The overall mining and production strategy is to maintain a mill processing throughput of 2.0–2.5 Mt/a. The processing plant design capacity is 2.0 Mt/a of fresh rock, with capacity to process up to 2.5 Mt/a where a blend of 80% fresh rock and 20% oxidized rock is used. The processing throughput will ramp up over two months at commissioning.

 

·Mined tonnage as required to ensure sufficient mill feed stocks are available at the grades required to meet gold production forecasts.

 

·Pit stage sequencing is determined by several criteria. Whenever feasible, the schedule prioritizes higher-grade and lower strip ratio pit stages early on in the LOM to facilitate higher gold production and delay the costs associated with waste mining.

 

·Slower mining rates in low waste stripping and deeper benches where grade control, drill and blast, pit dewatering, and small work areas will reduce mining productivity.

 

·Higher mining rates in high waste stripping and higher benches where 10 m bench heights are blasted, and there are reduced requirements for dewatering and grade control drilling.

 

October 15, 2025Page 168 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Maximum vertical rate of advance of 120 m/year (highest rate in schedule is 90 m/year).

  

·Inferred Mineral Resources were included.

 

Table 16.13 summarizes the proposed mining and production schedule.

 

Table 16.13 Proposed Mining and Production Schedule

 

Parameter Units Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year7 Year 8 LOM
Plant days   0 365 365 365 365 365 365 365 334  
Mine days   60 365 365 365 365 365 365 365 100  
Mining total movement kt 2,412 19,171 19,173 19,228 19,091 15,723 9,637 9,459 953 114,846
Waste to WRSF kt 2,322 16,326 15,588 16,380 17,166 13,793 7,264 7,597 656 97,092
Strip ratio w/o 25.8 5.7 4.3 5.8 8.9 7.1 3.1 4.1 2.2 5.5
Mill Feed material to ROM / Stockpile kt 90 2,845 3,585 2,847 1,925 1,931 2,373 1,862 296 17,754
Gold grade g/t 1.1 2.3 1.6 1.4 1.8 1.8 1.5 1.1 1.3 1.6
Gold contained koz 3 209 180 131 110 109 112 66 12 932
Stockpile – opening stock kt   0.1 0.6 1.7 2.0 1.7 1.5 1.9 1.5  
Gold grade g/t   1.1 0.8 0.6 0.6 0.7 0.6 0.6 0.6  
Gold contained koz   3 14 31 38 37 29 35 29  
ROM to crusher kt 0 2,354 2,500 2,500 2,225 2,111 2,030 2,213 1,821 17,754
Gold grade kt 0.0 2.6 2.0 1.5 1.5 1.7 1.6 1.0 0.7 1.6
Gold contained koz 0 198 164 123 111 117 106 73 41 932
Process recovery % 0.0 92.5 92.1 86.1 88.2 90.0 91.9 87.9 86.6 90.1
Recovered gold ounces koz 0 184 151 106 98 105 97 64 35 840

 

Figure 16.2 shows the mined mineralized tonnes by deposit.

 

Figure 16.2 Mineralization Mined by Deposit

 

 

 

Figure prepared by Fortuna, 2025.

 

October 15, 2025Page 169 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The mining and production schedule demonstrates a technically achievable operation for the LOM. The key risk to achieving the mine plan is being ahead in mine development, waste stripping and grade control activities to access deposits and increased confidence in the mineralization to be able to mine in sequence. The schedule is generally derisked by the ability to substitute pit stages with similar waste stripping ratios, as well as maintaining sufficient ROM stockpiles.

 

16.8Comments on Section 16

 

The QP is of the opinion that:

 

·The mining methods being used are appropriate for the deposit being mined. The open pit mine design, WRSF, TSF design, and equipment fleet selection are appropriate to reach production targets.

 

·The mine life is estimated as 8.1 years.

 

·The mine plan is based on a historically successful mining philosophy and presents low risk.

 

·Projected mining equipment and personnel requirements are regarded as reasonable in Fortuna’s experience to meet the proposed production rate of 7,000 t/d.

 

·Planned mine infrastructure and supporting facilities are regarded as suitable to meet the needs of the mine plan and production rate.

 

October 15, 2025Page 170 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

17Recovery Methods

 

17.1Processing Plant Design

 

The process plant is designed to process oxide and fresh material from open pit mines. The treatment plant is designed to process 2.0 Mt/a of fresh mill feed material (or 2.5 Mt/a based on a blend of at least 20% oxidized rock) at average head grades of 1.8 g/t Au (oxide) and 1.6 g/t Au (fresh).

 

The metallurgical testwork program has indicated that the mineralization is free-milling with a very low proportion of fine gold locked in sulfides, and is amenable to typical gold cyanidation treatment.

 

The process flow diagrams for the Diamba Sud study were developed from the process design criteria prepared from the metallurgical testwork. The plant design proposed is simple, but robust, and broadly comprises the following:

 

·Primary crushing.

 

·Crushed mill feed stockpile.

 

·Grinding and classification.

 

·Gravity recovery.

 

·Leaching and adsorption.

 

·Elution.

 

·Electrowinning.

 

·Smelting.

 

The comminution circuit modelling was undertaken by Orway Minerals Consultants (Orway) in Perth, Australia in consultation with MIQM. Orway was requested by MIQM to model a single-stage SAG milling circuit (1C SS SAG or SAC) as well as a SABC circuit as the basis for their design. After consultation and LOM mill feed material properties were taken into consideration, a single-stage crush and SAG milling circuit was adopted for the comminution circuit.

 

The flowsheet and plant equipment selections were based on the results of the metallurgical testwork program (refer to Section 13). The proposed flowsheet is provided in Figure 17.1.

 

October 15, 2025Page 171 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 17.1 Schematic of Proposed Processing Flowsheet for the Diamba Sud Project

 

 

 

Figure prepared by Fortuna, 2025.

 

17.2Processing Design Philosophy

 

The plant was designed to achieve the required throughput, as stated in the process design criteria. The crushing circuit will be designed with a throughput of 400 t/h and availability of 70%, on a 24-hour per day operation. Crushed products will report to an open stockpile, which will have a total capacity of 19,000 t and a nominal live capacity with free running material of 3,000 t.

 

A buried apron feeder installed in a reclaim tunnel will reclaim mill feed material and directly feed the milling circuit via the mill feed conveyor. An emergency reclaim feeder will also be installed in the reclaim tunnel to provide feed to the mill when reclaiming dead mill feed from the stockpile with a front-end loader.

 

The milling circuit was designed for a nominal throughput of 250 t/h (fresh) and 313 t/h (≥ 20% oxide blend). It will operate at 91.3% availability and achieve a design grind product size of 80% passing (P80) 106 µm(fresh) and about 75 µm (oxide) due to its natural fineness.

 

October 15, 2025Page 172 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The gravity circuit will take a cut from the cyclone underflow and will consist of two centrifugal concentrators and an intensive leach reactor for treatment of the gravity concentrate. The gravity circuit is expected to treat up to 90% of the cyclone underflow.

 

The CIL circuit will consist of a leach feed thickener followed by seven adsorption tanks, treating the cyclone overflow. The CIL circuit was designed for a design fresh gold leach feed grade of 1.63 g/t Au.

 

The metal recovery and refining will consist of an elution circuit, electrowinning cells and smelting.

 

Water, which will be required for a wide range of services, will be sourced primarily from the water harvesting dam. Water from the water harvesting dam will be pumped and stored in the water storage dam. The water storage dam will be located about 2.5 km north of the plant. The water storage dam will also supply water from its own catchment area and open pit dewatering. As a contingency and if required, the Falémé River, located approximately 7 km east of the plant site, could be used to supply additional make-up water during the rainy season to the water storage dam. However, based on current modeling results, there is more than sufficient water available from the water storage dam and open pit dewatering to provide all operational water requirements (see discussion in Section 18).

 

17.3Process Plant Feed

 

The feed sources will be from fresh and oxide materials. The LOM schedule has greatly influenced the process design, especially the comminution circuit.

 

The mining schedule (Table 17.1) indicates that the design basis will be suitable. Oxides will be the main feed material for the first year, followed by three years of blending (>15% oxides) and then two to three years of only fresh material.

 

Table 17.1 Proposed LOM Feed Composition

 

Parameter Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Tonnes Milled
Oxide (Mt) 1.78 0.93 0.64 0.34 0.13 0.03 0.22  
Fresh (Mt) 0.57 1.57 1.86 1.89 1.98 2.00 1.99 1.82
Total (Mt) 2.35 2.50 2.50 2.22 2.11 2.03 2.21 1.82
Percent Milled
Oxide (%) 76 37 26 15 6 1 10  
Fresh (%) 24 63 74 85 94 99 90 100

 

17.4Comminution Circuit Design Basis

 

17.4.1Design Criteria

 

Based on the analyses of the comminution testwork the following characteristics were selected for the fresh mill feed material design (Table 17.2).

 

Table 17.2 Fresh Mill Feed Material Comminution Characteristics

 

Parameter Design Mill Feed Material Characteristics
Ai (g) 0.197
CWi (kWh/t) 6.9
BWi (kWh/t) 17.2
A*b 30.1
Mineralization SG 2.75

 

October 15, 2025Page 173 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

17.4.2Comminution Circuit Selection

 

Processing in years 1 and 2, which will primarily be of oxide material, the option to operate in either single-stage SAG or SAB configuration were considered. In a single-stage SAG operation, the SAG mill will operate at low speed i.e. 60% of the mill’s critical speed (Nc) with a low ball charge, to minimize build-up of a sand load. In a SAB configuration the SAG mill will operate like a scrubber, at a low speed i.e. 50%Nc and will have no ball charge, and the ball mill would be operated at a low speed i.e. 60%Nc and a low ball charge. The single-stage SAG option was selected after consultation between Fortuna, Otway and MIQM.

 

17.5Process Plant Description

 

The plant layouts were developed, and general arrangement drawings were produced for each area together with the overall plant site layout including positioning of the crushing plant, mill feed stockpile, feed conveyers, SAG mill, leach tanks, gold room, reagents storage and preparation areas, and infrastructure buildings.

 

Equipment selections were completed for all major process plant mechanical equipment based on the project design criteria.

 

17.5.1Primary Crushing

 

Gold-bearing mineralization will be fed to the process plant via the ROM pad. The ROM pad will be located adjacent to the primary crushing building for efficiency of mill feed to the crushing plant. Haul trucks operating directly from the open pit will deliver ROM mill feed material to the ROM pad and material stored on the ROM pad in separate stockpiles of varying mineralization types and grades to facilitate blending of the feed into the crushing plant. The estimated maximum particle size of material on the ROM pad will be 900 mm in any dimension. Any oversized rock will be placed to one side and reduced to minus 900 mm on the ROM pad.

 

The primary crushing plant will provide single stage crushing to feed the SAG mill. The primary crushing plant will include a 162 t capacity ROM bin, an apron feeder, a primary jaw crusher, a stockpile feed conveyor, a rock breaker and associated electrical equipment, steelwork and plate work.

 

The primary crusher will be installed on a concrete foundation with the ROM bin, apron feeder and rock breaker, and will be located adjacent to a concrete retaining wall against the ROM pad. Walkways and stairs will provide full operational and maintenance access throughout the primary crusher building.

 

The ROM bin will be fed blended mill feed material from the ROM stockpiles using a front-end loader (CAT980 or equivalent). The ROM bin will be sized to accommodate direct tipping from 100 t sized haul trucks (CAT 777 or equivalent). However, that is not expected that this will be the usual method of feeding the plant. The ROM bin will be lined with replaceable steel wear resistant liners. Feeding of the ROM bin will be controlled by a ‘dump – no dump’ traffic signal mounted adjacent to the ROM bin. The traffic signal will be controlled by a radar level sensor mounted above the ROM bin.

 

The ROM bin discharge will be controlled by an apron feeder, which will feed directly into the primary jaw crusher. The primary jaw crusher will be a single toggle jaw crusher (C150 equivalent) that accepts nominal minus 900 mm rocks. The rock breaker mounted adjacent to the jaw crusher will break any oversized rocks that lodge in the crusher and would otherwise not be passed.

 

October 15, 2025Page 174 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The crushed product from the primary jaw crusher will discharge onto the 1,500 mm-wide stockpile feed conveyor. A weightometer installed on the stockpile feed conveyor will provide information on the tonnage of crushed mineralization passing through the circuit and onto the stockpile. Dust control will be achieved using the dust suppression system with high pressure water sprays, installed within the ROM bin, to form a mist to contain fugitive dust particles.

 

Primary crushed mill feed material will discharge to a 19,000 t total capacity conical stockpile. The stockpile was sized to provide up to a maximum 12 hour live feed capacity to the grinding circuit at the design throughput of 250 t/h (fresh) and 313 t/h (≥ 20% oxide blend), although with some mineralization blends live storage capacity may not be possible, and with other mineralization blends live capacity may only be 3–4 hours. The total capacity of the stockpile will be equivalent to 76 hours of fresh feed at the design throughput.

 

A 1,200 mm wide x 7,826 mm long reclaim apron feeder installed in a concrete reclaim vault will reclaim crushed mineralization from under the stockpile and feed it onto a 1,200 mm wide x 95 m long mill feed conveyor. The mill feed conveyor will provide a nominal 250 dry t/h instantaneous feed rate to the mill feed chute. A weightometer installed on the mill feed conveyor will monitor and control the reclaim apron feeder variable speed drive, which in turn will control the feed rate to the nominated operator set point.

 

An emergency reclaim apron feeder will be positioned towards the exit of the reclaim tunnel in the same concrete reclaim vault adjacent to reclaim apron feeder, but outside the edge of the stockpile. This will allow the front-end loader that feeds the crusher to also be used to feed the emergency reclaim feeder by loading the feed chute with mill feed material from the dead parts of the stockpile when there is no live mineralization in the stockpile or when reclaim apron feeder is under maintenance. The emergency feeder will also be used for the addition of grinding media to the SAG mill.

 

Lime will be added directly onto mill feed conveyer from the lime handling system which will be positioned after the emergency reclaim apron feeder. The lime system will consist of a 100 t capacity silo and will include a pneumatic bin activator, discharge isolation slide gate, rotary valve feeder, level instrumentation, dust collector, free standing structure and access platforms, and stairs. Bulk bags of powdered lime will be split and emptied into a transfer hopper, from which the lime will be pneumatically conveyed into the storage silo.

 

17.5.2Grinding and Classification Circuit

 

Primary crushed mill feed material will be fed via mill feed conveyor to the SAG mill from the crushed mineralization stockpile. An 8.53 m diameter by 5.77 m long effective grinding length SAG mill is proposed for the primary grinding duty. The SAG mill will operate with a duty ball charge of 10-15% with an expected pinion power draw of 5.7 MW and an installed power of 7.1 MW. A variable speed drive will be installed on the mill to vary the mill speed so that it can be adjusted as needed for changes in mineralized material characteristics.

 

Mill slurry will discharge to the mill discharge vibrating screen installed to separate pebbles from the discharge, control the particle size of the slurry reporting to the classification circuit and to adequately rinse the oversize material, prior to it reporting to the pebble crushing circuit. The undersize slurry from the discharge screen will fall into the mill discharge hopper.

 

October 15, 2025Page 175 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Mill discharge pumps will be installed in a duty/standby arrangement, each having separate suction lines from the mill discharge hopper. Pneumatically actuated suction inlet knife gate valves, pneumatically actuated knife gate dump valves on the pump suction pipework and pneumatically actuated knife gate valves on the discharge pipework will facilitate pump operations and maintenance of the off-duty pump when the system is operating the duty pump.

 

The slurry in the mill discharge hopper will be pumped to a 10-pack classifying cyclone cluster. The cluster will have six operating cyclones and four standby cyclones. The cyclones will classify the slurry feed into an overflow product with a P80 of 106 µm, which will be directed to the leaching circuit and coarse cyclone underflow product. From the cyclone underflow, the slurry will be fed back to the SAG mill.

 

New feed from the mill feed conveyor will be added to the recirculating loads in the mill feed chute. The recirculating load was designed to be a nominal 333% of new mill feed with a 35% solids overflow. Proportional controllers will provide the mill operator with density control in the circuit by varying water addition to either the mill feed chute or discharge hopper in fixed proportion to the SAG mill feed rate.

 

A davit crane in the cyclone tower will be used for cyclone pack maintenance activities. Major maintenance activities around the SAG mill and discharge pumps will be undertaken with a mobile hydraulic crane. Platforms and stairs will provide full operational and maintenance access throughout the grinding and classification building.

 

17.5.3Pebble Crushing

 

The oversized material from the mill discharge screen will be directed either to a scats bunker or to the pebble crusher circuit. The pebble crusher feed conveyor will deliver pebbles to a 220 kW pebble crusher at a design rate of 165 t/h. The crusher will operate at a closed side setting of 12 mm and the product from the pebble crusher will return via the pebble crusher discharge conveyer to the mill feed conveyor.

 

A magnet on the pebble crusher feed conveyor and a metal detector further along the same conveyor will protect the pebble crusher from tramp metal. A shuttle at the end of the pebble crusher feed conveyor will divert any tramp metal detected by the metal detector to bypass the crusher. The crusher station will also have an overflow to allow excess pebbles to recirculate to the SAG mill if the crusher is overloaded.

 

17.5.4Gravity Recovery Circuit and Pre-leach Thickener

 

The primary cyclone underflow will report by gravity flow to the cyclone underflow boil box, then into a gravity feed box directing feed over two scalping screens (2 mm aperture) operating in parallel to enable continuous operation of the batch gravity concentration units. Undersize from the scalping screens will be directed to two 30 inch batch centrifugal gravity concentrations continually operating on a 45 minute cycle. Each unit will be fed a solids throughput of 150 dry t/h and will remove approximately 33 kg of concentrate per cycle. This will be transferred as gravity flow to an intensive leach reactor located in the gold room. Gravity tails will slurry flow to the mill discharge hopper. Oversize from the scalping screens will report by gravity to the SAG mill feed.

 

The classified slurry from the cyclone overflow will be directed to a pair of trash screens from the trash screen distribution box with the ability to operate either one or both screens. Oversize material from the trash screens will discharge to a trash bin at ground level.

 

Trash screen underflow will be fed into a leach feed thickener which will be used to remove excess water. Thickener overflow will be fed into a process water tank for further

 

October 15, 2025Page 176 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

use. The leach feed thickener underflow will be pumped by the leach feed pumps in a duty/standby arrangement into a distribution box that will allow the slurry to be directed to either the first or the second CIL tank. Slurry will only be directed to the second tank in the event that the first tank is offline for maintenance.

 

17.5.5Carbon in Leach Circuit

 

The CIL train will comprise seven tanks of nominal dimensions of 12 m in diameter and 14 m high, providing a slurry residence time in the leach circuit of 24 hours with a slurry density of 45% solids by weight (for fresh mineralization).

 

Each CIL tank will be fitted with pumped inter-stage tank screens. Carbon will be held in all tanks except the first tank where the inter-stage screen will act as a safety screen to prevent oversize material entering downstream tanks in the event of cyclone roping and a trash screen overflow or failure.

 

All tanks will be equipped with hollow shaft agitators to facilitate oxygen injection through the shafts. Only the first three tanks will be sparged with oxygen. The first three tanks will also be fitted with a nozzle to facilitate oxygen injection through the side of the tanks.

 

All CIL tanks will be equipped with recessed impeller type carbon transfer, and these will be used to advance the carbon between tanks and to remove carbon from the circuit.

 

The recessed impeller pump in tank 2 will be used to pump slurry to the carbon recovery screen for the loaded carbon to be removed from the circuit. The recessed impeller pump in tank 3 will normally provide for carbon transfer between tank 3 and tank 2; however, in the event that tank 2 is offline for maintenance, it will be used to recover loaded carbon to the carbon recovery screen. The loaded carbon will undergo an acid wash before proceeding to the elution circuit.

 

A vibrating carbon safety screen will be located adjacent to tank 6. This screen will collect any carbon that escapes from tank 7 (or tank 6 in the event that tank 7 is off-line) in a disposal drum for reintroduction to the circuit manually. The undersize product from the carbon safety screen will be gravity fed to a detoxification tank. The undersize product will then be pumped to the TSF by the tailings discharge pumps in a duty/standby arrangement.

 

A gantry crane will facilitate removal of the inter-stage screens for maintenance and cleaning. The tanks will be constructed on concrete ring beams within a concrete bunded containment structure. The CIL bund will be fitted with a sump pump which will collect any spillage within the bund and direct it back to the trash screen distributor box. The bunded structure around the tanks will not be designed to comply with dangerous goods regulations, because all process fluids are not dangerous goods and it is not normal practice to contain them beyond normal operational spillage. Minor spillages are contained, and in the highly unlikely event that large spills should occur, they will be contained within the confined drainage system of the plant and contaminated water will collect in an environmental pond adjacent to the plant. Solids will be recovered by mechanical means (e.g., front-end loader).

 

17.5.6Elution, Electrowinning and Smelting

 

The acid wash and rinse cycles will be performed in a 15 m3 capacity rubber lined acid wash hopper to be located beneath the loaded carbon recovery screen. Following the rinse cycle the carbon in the acid wash hopper will be discharged into the elution column through an actuated ball valve. The elution column will have a volumetric capacity of 15 m3 (6 t) and be capable of holding 4 t of carbon.

 

October 15, 2025Page 177 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The strip solution will be injected with sodium hydroxide and sodium cyanide and then be preheated by the in-line elution heater to reach a solution temperature of 130 °C. The hot strip solution will then be introduced to the bottom of the elution column.

 

After approximately one bed-volume of caustic cyanide solution has been passed through the elution column to pre-soak the carbon a further five bed volumes of hot rinse water will be passed through the column. A further one bed volume of cold rinse water will be passed through the column after the hot rinse water to cool down the carbon. The first 3.5 bed volumes of pre-soak and hot rinse water will be returned via the duty/standby eluate filters to either one of the two pregnant solution tanks via a recovery heat exchanger to recover heat to the strip solution from the eluate. The last 3.5 bed volumes of hot and cold rinse water will be directed to the intermediate solution tank which will supply the feed water to the first half of the next strip.

 

Elution of the gold from the carbon is expected to take about six hours and pregnant solution will be collected into one of two pregnant solution tanks. The pregnant solution tanks will have a common pregnant solution pump which will feed the electrowinning cells. The barren solution from the electrowinning cycle will be returned to CIL tank 1 using a barren solution pump.

 

At the completion of the elution cycle, barren carbon will be pumped from the elution column to the regeneration kiln carbon feed hopper. The hopper is located on top of the regeneration kiln which in turn sits above CIL tank 6. From this hopper the carbon will be either regenerated in the kiln or discharged directly into CIL tank 6 under gravity depending on the carbon activity level. Prior to regeneration, the barren carbon will be de-watered over a carbon dewatering screen positioned above the storage hopper. The rotary kiln feed chute will drain any residual and interstitial water from the carbon prior to it entering the kiln. Kiln off-gases will be used to dry the carbon before it enters the kiln. At the end of the regeneration process, the regenerated carbon will discharge back into CIL tank 7.

 

The gold sludge from the separate gravity and the elution circuit electrowinning cell cathodes will be washed in the cathode wash box, a manual process. The resultant sludge will then be transferred via the cell sludge trolley, to the calcine oven to remove the steel wool cathodes through oxidation. The product from the calcine oven will then be direct smelted using fluxes in a liquified petroleum gas fired smelting furnace to produce the final gold product doré bars, which after weighing using a Sartorius Balance will be stored in the gold safe. The gold sludge from the gravity circuit will be refined separately from that of the elution circuit to allow for separate accurate metallurgical accounting of the gravity and CIL circuits.

 

17.5.7Tailings Disposal

 

The tailings pipeline to the TSF will be installed above ground, except for locations where road crossings necessitate these sections to be buried. Leaks in the tailings line will be detected by comparison between two flow meters; one located at the plant and the other located at the TSF. The tailings and decant return pipelines will be laid in a fully bunded and lined trench between the process plant and the TSF to help protect the environment if an unplanned minor release happens from the pipelines.

 

October 15, 2025Page 178 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

17.6Reagents

 

17.6.1Lime

 

Quicklime will be delivered in bulk to the mill feed conveyor from a 100 t lime silo. Lime will be used to raise the pH of the process slurry to suit the cyanidation leaching reaction.

 

The lime silo will hold approximately seven days’ supply of quicklime to allow for delivery interruptions. The expected annual consumption of quicklime is 10.5 kt for oxide mineralization and 0.7 kt for fresh mineralization.

 

17.6.2Cyanide

 

Cyanide will be delivered to site in 20 t shipping containers in 1 t bulk bags. Cyanide will be mixed with raw water to create a 30%w/w solution in the cyanide mixing system, which will comprise the following items:

 

·A hoist which will lift the bags directly onto the bag splitter.

 

·A bag splitter.

 

·A mixing tank.

 

·A mixing agitator, which will mix the cyanide and the water to create a homogenous solution.

 

The mixed solution will be transferred by a cyanide transfer pump to a separate cyanide storage tank, where duty/standby cyanide recirculating pumps will circulate the cyanide solution through the plant ring main with a constant pressure bypass return to the tank. In addition, a cyanide dosing pump will deliver cyanide from the ring main to the elution circuit in a controlled manner. The cyanide mixing and storage tank will be contained within a concrete bund with a collection sump to recover spillage. The sump pump will recover any minor spillage and deliver it to the trash screen distributor box.

 

Sodium cyanide and sodium hydroxide will be mixed to provide a solution at a strength suitable for direct dosing to the process facilities.

 

The sodium cyanide mixing facility will include a dedicated mixing and storage tank. Once a mix is undertaken the solution will be pumped to the storage tank which will hold a buffer volume. This arrangement will also allow additional mixes to be undertaken whilst operating without upsetting the dosed reagent concentration.

 

The various mixing/storage/dosing facilities will provide a short-term buffer for operating such that there is at least one day’s storage available under most conditions. This will allow reagent management to be undertaken on day shift only.

 

Additional reagent storage will be achieved by storing 1,000 kg of bags of sodium cyanide in the reagent store.

 

The quantities held in reserve will vary as a function of the most cost-effective shipping volumes/masses as well as consideration as to the time of the year with regard to wet season access and other influences.

 

17.6.3Caustic Soda/Sodium Hydroxide

 

Caustic soda will be delivered in 25 kg bags to site. It will be mixed with raw water in a skid mounted caustic mixing system to create a solution with 25%w/w concentration. The mixing system will consist of the following items:

 

·A bag splitter.

 

·A 1m³ mixing tank.

 

October 15, 2025Page 179 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·An agitator, which will mix the caustic soda and the water to create a homogenous solution.

 

The mixing system will be in the same containment bund as the cyanide mixing and storage tanks. A caustic dosing pump will draw the solution from the mixing tank and deliver it to the elution circuit.

 

The sodium hydroxide facility will be arranged such that the mixing and storage is contained in one tank. As the sodium hydroxide use is intermittent, mixing will be undertaken in those periods where there is no demand, and the mixed reagent allowed to homogenize prior to use. A volume equivalent to 1.7 days use will be mixed and stored per batch.

 

The various mixing/storage/dosing facilities will provide a short-term buffer for operating such that there is at least one day’s storage available under most conditions. This allows reagent management to be undertaken on day shift only.

 

Additional storage of reagent will be achieved by storing 1 t pallet lots of sodium hydroxide as 25 kg bags in the reagent store.

 

The quantities held in reserve will vary as a function of the most cost-effective shipping volumes/masses as well as consideration as to the time of the year with regard to wet season access and other influences.

 

17.6.4Hydrochloric Acid

 

Concentrated liquid hydrochloric acid (32%w/w) will be supplied in 1,185 kg intermediate bulk containers (IBC) and delivered to site in shipping containers of 23.7 t capacity. The acid will be transferred from the IBCs by an acid dosing pump to the acid wash hopper for a carbon acid wash cycle, by injection into a water stream pumped from the water tank to create a diluted 3% w/w hydrochloric acid solution.

 

The concrete containment bund which will surround the acid preparation area will comply with the dangerous goods statutory requirements and be protected with a coating to prevent acid damage to the concrete.

 

Hydrochloric acid will be received in 1 m3 IBC tanks at the appropriate dose strength. The IBC vessels will be connected to a common suction manifold so that the dosing pump always has a reserve of acid to draw from. Each IBC will provide around two days of reagent and so management of the IBC levels is required to ensure there is always one vessel with adequate volume for intermittent dosing to the acid wash facility. A volume equivalent to three days’ use will be available.

 

The various mixing/storage/dosing facilities will provide a short-term buffer for operating such that there is at least one day’s storage available under most conditions. This will allow for reagent management to be undertaken on day shift only.

 

Additional storage of reagents will be achieved by storing additional hydrochloric acid IBC vessels on a pad to control run-off (out-doors).

 

The quantities held in reserve will vary as a function of the most cost-effective shipping volumes/masses as well as consideration as to the time of the year with regard to wet season access and other influences.

 

17.6.5Activated Carbon

 

Activated carbon in 500 kg bulk bags will be transported to the site by road in 22 t sea containers. The carbon will be stored in these containers or under tarpaulins to protect it

 

October 15, 2025Page 180 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

from the weather. When required, carbon will be hoisted up to the top of CIL tank 7 and broken directly into the tank.

 

17.6.6Flocculant

 

Flocculant will be delivered to site in 1 t bulk bags. A forklift/telehandler will lift bulk bags onto the flocculant mixing systems bag splitter filling the flocculant loading hopper. Flocculant will be mixed to a 0.05%w/v concentration and transferred to a storage tank. From the storage tank, flocculant dosing pumps will dose liquid flocculant to the leach feed thickener via a static mixer to further dilute the flocculant concentration to the required dosage strength of 0.025%w/v.

 

17.6.7Balls and Liners

 

Modelling of the comminution circuit by OMC provided the liner and ball consumption rates for the mineralized material tested. These rates and quantities have been included in the operating cost and critical spares list. The balls and liners will be purchased as standard store items to be supplied to the SAG mill. Balls will be fed to the SAG mill continuously during operations and also stored in a storage bin feeding the mill (different balls in different storage bins). Some liners (critical spares) for mills and crushers will also be a store item and all liners for relining will be ordered in time for scheduled shutdowns.

 

17.7Control Systems

 

The plant control systems will be a network of process logic controllers sitting beneath a supervisory control and data acquisition (SCADA) network layer. The process logic controllers will perform the necessary controls and interlocking whilst the SCADA terminals will monitor the process logic controllers and provide an interface for operator interaction.

 

The process logic controllers and SCADA terminals will communicate via a plant wide ethernet network, the backbone of which will be dedicated, single mode, fiber-optic cables. For short distances, Cat 6 ethernet cables will be installed.

 

GE Fanuc RX3i process logic controllers and Citect SCADA are proposed. This combination has worked very well on past projects and has proven to be very reliable. Deviations from this to an alternative process logic controller and SCADA system would need to be investigated during the design stage for reliability and cost.

 

Field instrumentation and drive status signals will interface to the plant control system by means of hard-wired signals. Vendor packages may be connected to the SCADA network via a communications link, where appropriate.

 

The plant control system equipment installed within each area will function autonomously, such that a failure of the plant control system in one plant area will not affect the other areas.

 

The control philosophy of the plant will provide an appropriate level of automatic start up and shut down of various plant areas which will aid the plant operator in performing his tasks. Automatic interlocking, sequence control and analogue control will be implemented by the plant control system equipment, where required. Safety interlocks will be hard-wired.

 

Proportional integral derivative loop controllers will be programmed into the plant control system and be accessible via the SCADA terminals in the control rooms.

 

The PCS will provide detailed information including:

 

October 15, 2025Page 181 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Plant status monitoring.

 

·Fault annunciation and logging.

 

·Drive and systems diagnostics.

 

·Trending for all analogue process parameters.

 

The plant control systems will be powered by uninterrupted power supply equipment, providing fully synchronized power for thirty minutes after total power failure.

 

Process logic controllers will be installed in the main plant motor control center).

 

Vendor panels may contain process logic controllers depending on the complexity of control provided. Where possible, vendors will be asked to comply with the site standard PLCs, to minimize on spare holdings.

 

SCADA terminals will be installed in the following locations:

 

·CIL control room x 2 (above CIL deck).

 

·Crusher control room.

 

·Desorption control panel.

 

·Electrical Supervisor’s office.

 

The SCADA system will be configured so that only wet plant drives can be controlled from the main control room, only crusher drives from the crusher control room and only the desorption sequence from the desorption control panel. In situations where SCADA terminals have failed, it will be possible to bypass this by the user access level.

 

Password protected, user accounts will be set up in the SCADA to limit access to certain control functions. All functions required for day-to-day running of the plant will be made available at the operator level. Changing of set-points and proportional integral derivative parameters will be allowed at the Supervisor level (e.g. Plant Manager/Metallurgist/Plant Shift Supervisor). Complete control and development access will be allowed at the Administrator level (e.g. Electrical Supervisor).

 

Two SCADA terminals will exist in the main control room and provide the redundancy so that should one terminal fail then the wet plant can still be operated from the other terminal.

 

The desorption terminal will be installed in a stand-alone, metal cabinet with a Perspex window for viewing the monitor. The panel will also include a pull-out draw for the keyboard so that it can be drawn out when required. The panel will be located within the desorption area, most likely beside the electrowinning rectifiers. Operators will be able to monitor and control the desorption sequence locally, from this control panel, avoiding constant trips to the main control room.

 

The SCADA terminal in the Electrical Supervisor’s office will contain the necessary licensing for future on-site development of the SCADA application. Application updates of all other SCADA terminals will be possible from the supervisor’s terminal.

 

17.8Electrical Reticulation

 

Power for the process plant is planned to be generated from the Diamba Sud heavy fuel oil (HFO) power plant. Power will be accepted at the terminals of the plant high voltage feeder housed in the plant main substation. This will house the plants’ main 11 kv

 

October 15, 2025Page 182 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

distribution board. Power distribution within the plant area and vicinity will be at 11 kV and 415 v. Power consumption for each general plant area will be metered as indicated on the plant single line diagram. Power metering will generally take place at the 11 kV switchboard and at motor control center incomers.

 

The 11 kV power distribution cables will generally be underground within the plant area, while all other plant cabling will be in above-ground cable ladder attached to buildings and structural steelwork. Overhead power lines will not be installed in the immediate plant area to avoid interference with the movement of mobile equipment (e.g., mobile cranes and haul trucks).

 

Substation buildings will be of the demountable/transportable type and be fully air-conditioned to maintain the internal air temperature at 25°C maximum. Equipment in substations will be designed for continuous operation at rated output in a substation ambient temperature of 40°C maximum, 5°C minimum. Substation buildings will house the motor control centers, distribution boards and variable speed drives for that area and have sufficient space to allow the extension of switchboards as appropriate. Each substation building will incorporate a personnel access door and a two-leaf equipment door. The doors will be fitted with a panic release device. All substation building doors will open outwards.

 

In addition to the electrical and instrumentation equipment, each substation will be equipped with an internal light and small power system, emergency lighting, safety notices, fire detection system and fire extinguishers. Fire detection systems will be limited to smoke detectors and a Vesda system wired to a fire panel within each building. Local annunciators will be installed on the outside of the building. Fire suppression systems have not been allowed for nor has the painting of cables with fire retardant paint.

 

The substation buildings will be designed to be mounted on supports 1.5 m high, to facilitate cable entry into the motor control centers from the bottom. Transformers associated with plant substations will be located in outdoor compounds located adjacent to substation buildings.

 

Substation buildings have been allowed for in the following areas:

 

·Crushing area low voltage substation.

 

·Wet plant area low voltage substation (this may be one large building or split into two smaller buildings depending on final plant layout).

 

·SAG mill high voltage substation.

 

All transformers on the plant site will be pad mounted and installed complete with compound fencing and underground earthing. They will include cables boxes on the high voltage and low voltage terminations. The following transformers have been allowed within the process plant:

 

·Crushing area transformer (pad mount).

 

·Wet plant area transformer x 2 (pad mount).

 

·SAG mill motor transformer (pad mount).

 

·Plant buildings transformer (kiosk).

 

·Mining contractor transformer (kiosk).

 

October 15, 2025Page 183 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

High voltage switchgear will be supplied for the SAG mill so that isolations of the drive can be performed under the control of the site maintenance personnel without relying on the power station operator or requiring access to the power station switchboard.

 

The switchgear will be indoor, metal clad switchgear with a vacuum or SF6 circuit breaker on a withdrawable truck, enclosed to IP41. A Multilin 469 electronic protection relay was allowed for protection of the SAG mill motor r.

 

Motor current indication will be provided where specified, either as a panel mounted ammeter on the motor starter door, or as a current input to the plant control systems. Motors requiring control system current indication will require a current transducer to be incorporated into the motor starter, the current transducer having a 4-20mA direct current output.

 

The following motor control centers will be supplied within the plant site:

 

·Crushing area motor control centers (indoor, c/w PLC).

 

·Wet plant motor control centers x 2 (indoor, c/w PLC).

 

·Electronic variable speed drive panels will be either floor mounted or wall mounted panels, depending on size.

 

·Motors driven by variable speed drives will be provided with thermistor protection.

 

All variable speed drives will be capable of having their speed regulated by the plant control systems. However, when the associated drive control is selected to “local” mode, it will be possible for local speed setting to take place at the variable speed drive. Variable speed drives were allowed as indicated in the maximum demand calculation.

 

17.9Water Supply

 

The majority of the process plant make-up water supply (70–85%) will be made up of recycled water from the supernatant pond from the TSF. Additional process make-up water will be provided by a water storage dam that will be supplied by a water harvesting facility, open pit dewatering and Falémé River abstraction. Potable and gland/instrumentation water supply will be from dedicated fractured bedrock wells (see Section 16.3 for more details on dewatering wells). More details on water management are provided in Section 18.5 with respect to the project water balance and infrastructure.

 

17.10Comments on Section 17

 

The QP observed that the process flowsheet is a typical standard free milling gold process plant flowsheet. No real risks are seen with selecting this flowsheet from the testwork results provided in Section 13. The next study phase should include optimizing the flowsheet using additional testwork results provided during that study phase. There is no water supply risk for the project. The next stage of the project will optimize the water supply requirements for the project and potentially remove the need for Falémé River abstraction.

 

October 15, 2025Page 184 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

18Project Infrastructure

 

18.1Overview

 

The PEA envisages the following key site infrastructure:

 

·Seven open pits.

 

·Site access roads.

 

·Site haul roads.

 

·Site bypass road.

 

·TSF.

 

·Sediment management system.

 

·Surface water management system.

 

·Water storage dam.

 

·Water harvesting dam.

 

·Aerodrome.

 

Mining contractor infrastructure.

 

·Administration and plant buildings.

 

·Process plant, including plant site, warehouses and ROM pad foundation.

 

·Accommodation camp.

 

·Three WRSFs.

 

·Stockpiles.

 

·Power generation.

 

·Fuel supply.

 

·Communications.

 

·Plant security.

 

·Water supply.

 

The proposed site infrastructure is shown in Figure 18.1.

 

October 15, 2025Page 185 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 18.1 Plan View of Mine Infrastructure

 

 

 

Figure prepared by Knight Piésold, 2025

 

October 15, 2025Page 186 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

18.2Roads

 

The proposed roads to support the planned mining operations are shown in Figure 18.1. The main mine access road will tie in with the N24 national road, approximately 1.5 km west of Gamba Gamba. Private mine roads will interconnect the facilities and provide an opportunity for expansion into the DS2 block. The access roads will be unpaved.

 

18.2.1Site Access Roads and Bypass Road

 

The design objectives for the site access roads are as follows:

 

·Provide suitable access to the Project area from the existing paved highway, including allowance for design speeds.

 

·Provide suitable access to connect the accommodation village and process plant.

 

·Optimize access road operability with consideration of reducing the earthworks volumes.

 

The design objectives for the bypass road are as follows:

 

·Provide suitable access around the Project area to the existing paved highway to the communities surrounding the Project area, for those communities that were cut off from the highway.

 

18.2.2Site Haul Roads

 

The design objectives for the site haul roads are as follows:

 

·Provide suitable access between the WRSFs, open pit, ROM pad, TSF embankments and mine services area, including allowance for design speeds.

 

·Optimize haul road operability with consideration of reducing the earthworks volumes and limiting ground disturbance.

 

18.3Tailing Storage Facilities

 

The TSF will be located in the north of the DS1 block, approximately 5 km north of the proposed process plant. The TSF will be a cross-valley deposition facility, using the natural topography on the west to provide storage.

 

The TSF was designed based on the 2025 assumed peak plant treatment capacity of 2.5 Mt/a in the initial three years and 2.0 Mt/a on average for the remaining LOM. The Stage 1 TSF was designed to store 12 months of tailings (2.4 Mt) with a tailings embankment elevation of 195.3 masl. The final design will have an embankment elevation of 215.9 masl and will provide sufficient storage capacity for the remaining LOM (17.8 Mt), based on the production rates assumed in the PEA.

 

The TSF was designed to be a robust downstream constructed facility with a low permeability core (zone A) with downstream filter compatible transition (zone B) and compacted waste rock (zone C1). The dam will be primarily lined with a 1.5 mm high density polyethylene (HDPE) liner and the downstream zones A, B and C1 will provide additional potential seepage protection if there is a leak in the primary liner. The TSF impoundment will be composite lined with a 200 mm compacted soil liner overlain by a 1.5 mm HDPE liner.

 

October 15, 2025Page 187 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The TSF will be equipped with a leakage collection and recovery system below the composite basin liner system. Furthermore, a downstream seepage collection system will be installed within and downstream of the TSF embankment to allow monitoring and collection of seepage (if any) from the TSF.

 

About 80–85% of the supernatant water from the TSF will be recovered and pumped back to the plant as a closed-circuit system.

 

At each design stage, the TSF will be able to safely hold and have sufficient freeboard to contain the 1:100 year, 72 hour storm. Additionally, each stage will be incorporated with an emergency spillway capable of passing the peak flow from the probable maximum precipitation to ensure the TSF integrity remains intact.

 

Finally, as per Global Industry Standard on Tailings Management (GISTM), the TSF will be designed for closure and be designed as if the consequence classification is Extreme; however, the preliminary consequence classification is currently designated between the range of High to Very High.

 

The design parameters adopted for the TSF are summarized in Table 18.1.

 

October 15, 2025Page 188 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 18.1 Tailings Storage Facility Design Parameters

 

 

 

18.4Sediment Management

 

Sediment control structures are sediment dams that will be constructed in the downstream reaches of catchments impacted by site infrastructure. Sediment control structures reduce flow velocities facilitating sediment settling. They will be located downstream of all site infrastructure, and the discharge from the sediment control structures will be to the environment downstream of the project infrastructure sites. For minor events and depending on storage within the structure prior to a rainfall event, they may completely contain runoff.

 

18.5Water Storage Dam and Water Management

 

The design objectives for the water storage dam are as follows:

 

·Secure clean water supply for the process plant, and make-up process water during dry conditions, with a view to optimizing discharge to downstream environments after the storage requirements are met.

 

October 15, 2025Page 189 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Storage of water from the Falémé River.

 

·Storage of water from pit dewatering.

 

·The water storage dam will provide storage for water sourced from the Falémé River. However, preliminary modelling and the project water balance indicate that sufficient water should be available from the water harvesting dam only. This will be further investigated and confirmed in future mining studies, and may ultimately negate the need to abstract water from the Falémé River.

 

·The water storage dam will consist of a multi-zoned earth fill embankment, with central low permeability core. The embankment will contain internal drains and have the upstream batter lined with textured 1.5 mm HDPE geomembrane liner. Additionally, the basin will comprise a composite basin liner comprising a 200 mm compacted soil liner and a smooth HDPE geomembrane liner overlaid.

 

·The water storage dam will be able to safely hold and have sufficient freeboard to contain the 1:100 year, 72 hour storm. Additionally, an emergency spillway capable of passing the peak flow from the probable maximum precipitation to ensure the water storage dam integrity remains intact.

 

·If a water harvesting dam proves to be a feasible water source the water harvesting dam will consist of a multi-zoned earth fill embankment, with upstream low permeability zone and be lined with textured HDPE geomembrane liner. The water harvesting dam will have a capacity of approximately 150,000 m3 and an operation spillway capable of passing a 1:100 year storm event, occurring when the pond is at spillway inlet level.

 

Water storage dam design criteria are shown in Table 18.2.

 

October 15, 2025Page 190 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

  

Table 18.2 Water Storage Dam Design Parameters

 

 

The design objectives for the site surface water management (Figure 18.2) are as follows:

 

·Containment of sediment-laden runoff from site development areas, within sediment basins for controlled discharge from site.

 

·Divert clean runoff water around sediment dams to discharge downstream of site and direct runoff from disturbed catchments into sediment dams prior to discharge, thus reducing the catchment area reporting to sediment dams.

 

·Collect and divert sediment-laden runoff emanating from site infrastructure (earthworks) into sediment dams.

 

·Divert existing natural drainage courses around site infrastructure.

 

·Operate as a “closed-circuit” to maximize recycled water, minimize make-up water requirements and prevent spilling/discharging any supernatant or sediment laden water.

 

October 15, 2025Page 191 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 18.22 Water Balance Modelling Block Model Diagram

 

 

 

Figure prepared by Fortuna, 2025.

 

18.6Aerodrome

 

There is currently no aerodrome incorporated into the Project, as the company intends to use the nearby Kédougou airstrip. However, during the next stages of the Project, the potential location and viability of an on-site aerodrome are expected to be assessed.

 

October 15, 2025Page 192 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

18.7Mining Contractor’s Infrastructure

 

An area adjacent to the processing plant was demarcated as the mining services area for the purposes of the PEA. The mining contractor will provide its own workshop, store facilities, offices, washdown area and waste oil management facility, which will be located within the mining contractor’s area. The washdown slab will incorporate a silt and oil trap, and an oil separator will remove any contaminant oil from the wastewater before it is recycled into the wash bay facility, with excess water used for dust suppression. The mining contractor will manage the safe removal of waste oil by using approved suppliers of waste oils as required by law. The explosive materials will be stored in a magazine located in a remote area and well away from people. The magazine will be secured within a fenced compound and surrounded by embankments. The magazine will be manned with security at all times.

 

18.8Administration and Plant Buildings

 

The following buildings will be located within the perimeter of the project footprint:

 

·Administration building.

 

·Administration mess hall.

 

·Security and first aid building.

 

·High security, laundry and change room building.

 

·Laboratory.

 

The administration building will provide a meeting room, male and female ablutions, kitchen, and offices for management, mine and process plant technical services and administrative personnel. The administration office will be fitted throughout with split-system air-conditioners and reticulated power from an uninterruptible power supply to service computers and peripherals. A parking lot will be located at the front of the administration building.

 

The security and first aid building will be located at the mine entrance. The security office will house a security reception area and the security manager’s office. The first aid area will house the nurse and the doctor within the low security area. A parking lot will also be located at this building for site visitors.

 

The following buildings will be located within the high security area:

 

·Plant workshop.

 

·Warehouse.

 

·Reagents store.

 

·Motor control center building.

 

·Plant control rooms.

 

·Plant office building.

 

·Plant mess hall.

 

·Gold room building.

 

October 15, 2025Page 193 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The high security, laundry and change room building will be located at the entrance to the high security area. This building will have a guard house, in/out one way turnstiles, a laundry room, and male and female change rooms. This building also includes an ablution section that will only be accessible from the high security area.

 

The plant workshop will be a single steel-framed building arranged in three separate areas for mechanical, electrical, and welding workshops. The warehouse and reagent stores will be single steel framed buildings with eaves height will be at least 6 m to allow for good crane and forklift access. The warehouse will have an outdoor fenced enclosure for laydown storage. Delivery vehicles for both the warehouse and reagent stores will report to the security office in the high security area for inspection before and after deliveries have been made.

 

The laboratory and sample preparation buildings will comprise:

 

·Unloading and drying area.

 

·Wet chemical room.

 

·Balance room.

 

·Atomic absorption equipment room.

 

·Fire assay area.

 

·Metallurgical laboratory.

 

·Environmental laboratory.

 

·Grade control preparation area.

 

·Exploration and sample preparation area.

 

·Offices and stores.

 

·Male and female ablutions.

 

Electrical high voltage and low voltage switch rooms will be located near the processing facility.

 

A process control room will be located above the CIL tanks and able to view the mill on one side and the CIL circuits on the other. The control room will include a titration room. The crusher control room will be located next to the primary crusher. The crushing plant will be controlled from this control room.

 

The plant office will include a kitchenette, male and female toilets, a meeting room, and office areas for the maintenance superintendent, plant foreman (electrical, mechanical, and mill), maintenance planner, and plant metallurgists.

 

The gold room will be a steel-clad building. The building will house the leach reactor, calcine oven, electrowinning cells, smelting furnace, safe (enclosed within a concrete vault), and associated equipment.

 

A supervisor workstation will be installed in the gold room; this workstation will be equipped with a telephone and data connection. A secure area with inner and outer doors will ensure that the gold room remains sealed during bullion transfer to the transport vehicle. All operations within the gold room will be subject to full-time closed-circuit television (CCTV) surveillance with security alarms provided to the security coordinator.

 

October 15, 2025Page 194 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Two mess halls will be incorporated in the plant and administration building areas. Both buildings will have verandas attached to them. All meals are expected to be prepared at the village or accommodation camp outside the high security area and transported into the high security mess at mealtimes.

 

18.9Accommodations Camp

 

The accommodation camp will house the senior level construction workforce prior to mobilization of the operations personnel late in the construction period. The remaining personnel will be accommodated in the nearby town of Gamba Gamaba, Karakena, Saraya and Kédougou (house rentals, hotels, etc.). This will minimize the cost of the camp facilities while providing sufficient accommodation required during the overlapping period between construction and operation.

 

The accommodation camp and facilities are designed for 329 staff not residing in the project area. It is expected to be located west of the process plant and will consist of the following major components:

 

·Accommodation facilities suitable for 329 personnel.

 

·Kitchen, dining and wet mess facility.

 

·Water treatment plant.

 

·Sewage treatment plant.

 

·Laundry facilities.

 

·Administration office.

 

·General ablution block.

 

·Recreation facilities.

 

·Security fencing/gates and security office.

 

18.10Waste Rock Storage Facilities

 

Waste rock storage facilities will be located adjacent to each open pit with details described in Section 16.5.3.

 

18.11Stockpiles

 

ROM mineralized material will be stockpiled on the ROM pad by the mining contractor. From where it will be reclaimed and loaded to the crusher feed bin using front-end loaders operated by the mining contractor. Lower grade mineralized material will be stockpiled on the west side of the ROM pad. From where it will be reclaimed and loaded to the crusher feed bin using a front-end loader and trucks operated by the mining contractor.

 

18.12Power Generation

 

The grid connection point is located at Kédougou, Senegal, approximately 110 km from the Diamba Sud site. Thus, it is envisaged that power for the project will be supplied via an on-site HFO power plant rather than through the national grid. As studies progress, the feasibility of supplementing the site supply with a solar photovoltaic or hybrid power solution will also be assessed in conjunction with increasing LOM requirements.

 

October 15, 2025Page 195 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

18.13 Fuel Supply

  

Bulk fuel storage for the operation and mining fleet is assumed to be owned and managed by the fuel supplier.

 

18.14Communications

 

There is limited telecommunication infrastructure in the immediate mine site area at the present time. Mobile coverage and optic fiber internet are available, however it can be intermittent at times. Telecommunications will be expanded and improved to include voice, email and internet traffic for process plant, camp and main office to ensure a reliable connection in the future.

 

18.15Plant Security

 

From a security perspective the project footprint will be configured as small as possible so that security personnel and systems have to cover as minimal an area as possible. The security provision will consist of:

 

·Access control to the mine lease at several locations (including mine, plant and camp).

 

·Read in/read out access control.

 

·Two-stage gates for vehicle access.

 

·Electronic surveillance including CCTV within the plant area and at several key locations around the property.

 

·Physical and visual barriers.

 

·Fencing (double, single and cattle).

 

·Lighting.

 

·Patrols.

 

Double security fencing will enclose the process plant. This is demarcated as a high security area. A single security fence will enclose the mining contractor’s area, main administration building area, laboratory, camp, magazine, and tailings storage facility. The security fence will consist of a 1.8 m high fence with razor wire at the top of the support posts. A cattle fence will also be installed around the water storage and harvesting facilities.

 

Electronic security will be provided by a reputable security system provider and audited by an independent security consultant experienced in security installations in Africa. It will be monitored by the security contractor. The security system is expected to be configured as follows:

 

Installation of and integrated security solution consisting of a combination of various access control points, coupled with intruder detection devices, supported by CCTV cameras located across the site; and Some of the remote cameras and access control locations will be interlinked via the installation of a line-of-sight wireless network connection with a common receiver located appropriately to operate within “line of site” protocols.

 

October 15, 2025Page 196 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

18.16Water Supply

 

Water supply make-up water for the proposed operations will be provided through a combination of harvesting rainfall runoff, and pit dewatering sent to the water storage dam. The Falémé River which runs south to north, approximately 7 km east of the DS1 block boundary is the current base case for water supply make-up sent to the water storage dam. The site water balance (developed by Knight Piésold) indicates that an effective abstraction rate of 170–230 L/s (612–828 m3/hr), and a maximum abstraction limit of 8% of the river instantaneous flow rate would be sufficient to steadily fill the water storage dam to capacity for the dry season. Under average conditions, a constant water supply of 66 L/s will be required for operations.

 

A water harvest dam will be constructed to provide an additional raw water source for the project. The water harvest dam will be located to the southeast of the planned Southern Arc 1 pit within the Gamba Gamba creek. Design work indicates that if a catchment yield of 13% can be achieved between the months of June to October, the water harvest dam will be able to replace the requirement to abstract water from the Falémé River and this will be verified during the next study phase.

 

It is estimated that approximately 75–85% (average of 80%) of the water in the slurry deposited into the TSF can be recovered from the TSF and pumped back to the plant for reuse in the process.

 

Potable water will be supplied through the process plant water treatment system, which will service the process plant and mining services area via a dedicated pipeline from the plant. Outside of these areas, water will be supplied by fractured bedrock wells similar to those used by the village of Gamba Gamba and the current exploration camp. A water treatment plant will be incorporated to improve overall water quality.

 

18.17Comments on Section 18

 

The QP is of the opinion that the Project has sufficient surface area to accommodate all infrastructure requirements to support the LOM, and that sufficient work was completed to ascertain reasonable locations for all major infrastructure to support a PEA.

 

October 15, 2025Page 197 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

19Market Studies and Contracts

 

19.1Market Studies

 

No market studies have been performed as part of this PEA; however Fortuna has sold gold doré from West Africa since 2020 and is familiar with selling this product.

 

Diamba Sud will produce gold doré, which is readily marketable on an ‘ex-works’ or delivered basis to several refineries in Europe and Africa. There are no indications of the presence of penalty elements that may impact on the price or render the product unsalable.

 

19.2Commodity Pricing

 

The Fortuna financial department provided gold prices using a five-year historical average and consensus commodity price projection. Fortuna established the pricing using a consensus approach based on long-term analyst and bank forecasts prepared in May 2025.

 

The long-term gold price used for estimating potential mineralized material in the LOM plan was US$2,300/oz, based on the mean consensus prices from 2026 to 2028 of US$2,726/oz weighted at 40% and a five-year historical average of $2,023/oz weighted at 60%.

 

An elevated gold price of US$2,600/oz, using a 15% upside was used for the Mineral Resource estimate.

 

The economic analysis conducted in October 2025 used a base case gold price of US$2,750/oz.

 

19.3Contracts

 

As part of Fortuna’s socio-economic commitment to the region and other local stakeholders, Fortuna will preferentially award contracts to local businesses to participate in the Diamba Sud Project, thereby establishing a role as an active member of the community and a participant in the region’s sustainable development.

 

No sales or material contracts have been executed in relation to the development, construction, or operation of the Diamba Sud Project, as of the effective date of this Report, including mining, power plant operations and maintenance, smelting, refining, transportation, handling, sales, hedging, or forward sales agreements.

 

It is anticipated that several material contracts will be required in the future as the Project advances in its development. These are expected to include, as a minimum, a mining services contract, a power plant operations and maintenance contract, and transportation and related sales contracts. Additional operational or specialist service contracts may also be required as project scope evolves.

 

19.4Comments on Section 19

 

The QP has reviewed the information provided by Fortuna on metal price projections and exchange rate forecasts and notes that the information provided is consistent with what is publicly available for industry norms.

 

Long-term metal price assumptions used in this Report are based on a consensus of price forecasts for those metals estimated by numerous analysts and major banks as of May 

 

October 15, 2025Page 198 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

2025. Over several years, the actual metal prices can change, either positively or negatively, from what was earlier predicted. If the assumed long-term metal prices are not realized, this could have a negative impact on the operation’s financial outcome. At the same time, higher than predicted metal prices could have a positive impact.

 

The QP has reviewed the marketing assumptions and proposed major contract areas and considers the information acceptable for use in estimating Mineral Resources and in the economic analysis that supports the PEA.

 

October 15, 2025Page 199 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

20Environmental Studies, Permitting and Social or Community Impact

 

20.1Base Line Studies

 

The development of the Diamba Sud Project, including construction and operations, will require an Environmental Permit in accordance with Senegalese legislation in order for Boya to be able to obtain an Exploitation Permit.

 

Earth Systems, an environmental and social science and engineering company from Australia registered in Senegal, was commissioned to prepare an Environmental and Social Impact Assessment (ESIA) in compliance with Senegalese regulatory requirements, and in accordance with international best practices such as the Equator Principles and International Finance Corporation (IFC) Performance standards. As required by Ministerial Order No. 9470 MJEHP-DEEC (2001), Earth Systems holds a current ESIA accreditation from the Government of Senegal. The submission of the ESIA is a prerequisite for obtaining an Environmental Permit.

 

Field studies have been undertaken by the ESIA consultants since 2021, and with the support of Oryx Expertise in 2024, a specialized biodiversity consultancy firm. These studies in the DS1 block (Figure 20.1) included socio-economic conditions, land and water use, surface and groundwater resources, biodiversity, air quality, noise and vibration, climate change, as well as archaeology and cultural heritage.

 

The ESIA was submitted to the Direction de la Réglementation Environnementale et du Contrôle (DiREC), a division of the Ministry of the Environment and Sustainable Development of Senegal on October 6, 2025, for approval, with a decision expected in early 2026.

 

October 15, 2025Page 200 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 20.1 Diamba Sud Project Study Area in DS1 Block

 

 

 

20.1.1Socio-Economic Environment

 

Administration and Governance

 

The Diamba Sud Project is situated in the rural commune of Bembou within the department of Sayara, and region of Kédougou in the South-East of the Republic of Senegal. The Project is located approximately 7 km to the west of the Falémé River which marks the border with Mali, and 665 km southeast of Dakar the capital of Senegal. The

 

October 15, 2025Page 201 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Kédougou-Saraya highway (National Road 7), which leads to the border town of Moussala, cuts across the DS1 block. The Commune of Bembou covers an area of 26,068 km2 and is made up of 30 villages.

 

Population and Demographics

 

According to the fifth General Population and Housing Census conducted in Senegal in 2023 (ANSD, 2023), a total of 4,732 people reside across 959 households within the DS1 study area settlements. In 2023, Gamba Gamba had a total population of 640. Karakaéné is considerably the largest settlement in the study area with a population of 3,253.

 

The number of males in the settlement of the Project area is significantly higher than the number of females. This trend is likely associated with artisanal small-scale mining (ASM) activities in the study area and wider region.

 

Livelihoods and Income

 

The primary livelihood activities of surveyed households are agriculture and artisanal mining. Surveys conducted in 2024 among village authorities revealed artisanal mining as being the main source of income in the settlements of Gamba Gamba and Lingueya, followed by agriculture. The hamlet of Khourdiakhouma is an exception, with agriculture remaining the main livelihood activity and artisanal mining in second place.

 

Artisanal and small-scale mining is a key livelihood activity for household members in the study area. This sector is a significant economic and demographic driver in the study area and the wider Kédougou region. In the study area, the village heads of all four settlements ranked ASM activities and gold panning as the biggest income generator for their village. In Gamba Gamba specifically, 44% of the working age workforce listed ASM as their main occupation during the household census.

 

Most agricultural activities are entirely rain-fed, and as such production yields are seasonal and dependent on climatic conditions: length of season, distribution, and abundance of rainfall. The main commercial crops grown in the vicinity of the Project include cotton, cashew nuts, peanuts, and watermelon. Key subsistence crops include corn, rice, groundnuts, beans, millet and legumes.

 

Livestock is an important subsistence activity, with approximately 21% of households surveyed citing livestock as a key livelihood activity. In Gamba Gamba, approximately 27% of surveyed households reported livestock as a key subsistence activity, compared to approximately 20% in Karakaéné and 13% in Kourdiakhouma.

 

The Kédougou region has experienced significant growth in retail and service activities, largely attributed to the opening of the National Road 7 (RN7) highway and the region’s integration into the global economy. Within the study area, retail activity is concentrated in markets and small trading shops, which serve as the primary source of household food and goods for local communities. The Karakaéné market is the largest commercial hub in the study area, with more than 100 small traders and shops offering a wide variety of goods and services. Surveys conducted with 44 market stall and shop owners at Karakaéné market revealed a strong dependency on trading opportunities created by ASM activities and RN7 traffic. However, many shop owners reported declines in demand and footfall over the last 3–5 years, primarily due to reduced artisanal mining activity. Despite this, the market remains a critical source of income, with most stalls operating seven days a week, experiencing peak sales on Mondays and Fridays when ASM sites close.

 

Collection of non-timber forest products is a traditional activity that involves the collection of various plant products for food or medicinal purposes. The most collected are the Saba senegalensis (Kaba), Vitellaria paradoxa (Shea tree), Borassus aethiopoum (Sibo),

 

October 15, 2025Page 202 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

bamboo cherry, and dougouto. They are mainly for local consumption and not sold. Grass species including Andropogon gayanus and Andropogon pseudapricus are collected for use as fodder or to thatch hut roofs.

 

Community Assets and Infrastructure

 

Table 20.1 summarizes key community infrastructure in the study area.

 

Table 20.1 Key Community Infrastructure

 

Settlement Health Education Water
Gamba Gamba 1 Health hut (currently not operational) 1 primary school

1 Borehole Connected to a water tower which can store 10,000 litres of water.

1 Borehole connected to a pump

20 Traditional Wells

Karakaéné 1 Health Post 1 primary school

3 Boreholes connected to a pump

>100 Traditional Wells

Lingueya None 1 primary school 2 Boreholes with pumps
Kourdiakhouma None None 1 Traditional Well
Dialadakhoto None 1 primary school

1 water house

7 traditional wells

 

Health and Nutrition

 

The main causes of mortality in Senegal include neonatal diseases, lower respiratory infections, heart disease, diarrheal diseases, and stroke.

 

For the Bembou Commune, the proximity of the Falémé River and important water points means there is a high incidence of diseases relating to water and hygiene (diarrhea, malaria, bronchopneumonia and bilharzia).

 

The Gamba Gamba Health Hut Community Health Officer reported in 2023 that several cases of HIV/AIDS have been diagnosed in the village of Karakaéné. No cases of HIV/AIDS were identified in households surveyed in the study area. The lack of knowledge and social stigma of HIV in rural areas are constraints to patients being diagnosed.

 

ASM is often practiced by the youth and is associated with acute and chronic health risks including physical injury from poorly maintained machinery; toxin poisoning such as mercury; and silica dust exposure leading to acute respiratory problems.

 

It was identified that 31% of households reported that they always had enough food and 67% reported that they very occasionally had to skip a meal or reduce portion size (this was highest in Lingueya (78%)). Four households (1.5% of the study area) reported that they did not have enough food and found it a constant struggle to access foodstuffs, two each were located in Gamba Gamba and Karakaéné.

 

Traffic and Transport

 

A main paved road, RN7, crosses the area covered by the DS1 block, with 9.8 km of road running along the block boundary.

 

Other roads and access tracks in the DS1 block area consist of minor unpaved tracks connecting villages, agricultural and grazing areas, and artisanal gold mining sites. Motorcycles are the most common mode of transport and are widely used for public transport and the transport of goods to artisanal gold mining sites.

 

October 15, 2025Page 203 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Most of the tracks in the permit area are 3–4 m wide. The tracks are in poor condition, heavily degraded, and inaccessible during the rainy season. During the rainy season, some crossing points along the Daléma River (a tributary of the Falémé River) become impassable on foot.

 

Archaeology and Cultural Heritage

 

The Project is located near Falémé River, in the Kédougou region, in southeastern Senegal. It lies within an important historical and archaeological corridor that has been inhabited since prehistoric times.

 

The initial survey conducted in 2022 identified 12 unique archaeological sites, while the 2024 survey identified an additional 21 sites, for a total of 33 sites. The 2022 mission report indicates a low to medium density of sites in the Diamba Sud permit, possibly due to the proximity of the Falémé River, where important archaeological sites are concentrated along the left bank, from Doundé to Alinguel. This suggests that settlements were historically favored along major valleys, rather than in secondary valleys such as Diamba Sud, which may explain the abandonment of Neolithic sites and their subsequent reoccupation in historical times. Archaeological surveys conducted in 2022 identified 10 sites located within the boundaries of the proposed fenced Project. These include three settlement sites, two metallurgical sites, and five sites containing only material remains. Surveys in 2024 identified four additional archaeological sites within the proposed fenced Project area. These include a Neolithic site notable for its size, the diversity of its material culture, its milling tools, and its thick pottery; a metallurgical site that is highly conducive to iron reduction; and sites which contain ceramics pieces dating from the Neolithic period.

 

A total of 40 tangible cultural sites were identified during surveys conducted in 2022 and 2024 in the study area but none in the operations footprint as proposed in the PEA. Gamba Gamba is the only settlement located within the DS1 block area, but outside the Project’s planned fenced area.

 

It includes three tangible cultural sites, including a mosque, a cemetery, and a sacred site. Almost all of residents of Gamba Gamba are Muslim and are of Malinké ethnicity. The sacred site of Sého is located on the banks of the village's stream. Sacrifices are made to a tree there, in the form of white chickens, eggs, and rice-based fritters. The sacrifices are led by the village chief but require the contribution of the entire village population.

 

In terms of intangible cultural heritage, many traditions are still practiced. This can be seen in the strict observance of days of rest, traditional music, and rituals of offerings and libations. It is clear that the rise of gold panning and a cash economy is bringing about changes in local communities. Among the popular traditional celebrations, the people of the village of Gamba Gamba use songs and dances to preserve and practice their cultural traditions.

 

20.1.2Physical Environment

 

Climate and Meteorology

 

Please refer to Section 5.2 of this Report.

 

Geomorphology and Topography

 

Please refer to Section 5.3 of this Report.

 

October 15, 2025Page 204 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Hydrogeology and Groundwater

 

The availability of groundwater resources in sub-Saharan Africa depends critically on the geology, the history of weathering, faulting, and recharge to groundwater. The hydrogeology of the Project area is characterized by a crystalline basement environment, comprising crystalline igneous and metamorphic rocks over 550 million years old.

 

Basement aquifers include the geological sequence comprising the weathered residual overburden (the regolith), the transition zone between the bedrock and the regolith and the fractured bedrock. Unweathered and non-fractured basement rocks are generally considered to contain negligible quantities of groundwater. The basal section of regolith and the deeply weathered bedrock are generally considered to be those parts of the sequence with the highest yield. The degree and depth of weathering vary depending on physical characteristics and chemical composition of the rock.

 

Hydrology and Surface Water

 

Hydrology in the Project area is governed by annual rainfall patterns, and the distinct dry and wet seasons that are influenced by the annual movement of the Intertropical Convergence Zone. This rainfall patterns govern surface water flow regimes in the region.

 

Runoff from the Project area ultimately drains into the Falémé River to the east of the Project, which is located approximately 7 km from the Project area at its closest point. The Falémé River originates in Northern Guinea, where it flows towards the Malian border and then crosses into Senegal. It is a tributary of the Senegal River and forms an important watershed for this river system. In recent years, the hydrology and water quality of the Falémé River have been significantly impacted by the intensification of ASM activities along the river, resulting in significant degradation of water quality.

 

The hydrology of the Project Area includes a network of ephemeral watercourses as shown on Figure 20.2.

 

Figure 20.2 Creeks in and Around the Diamba Sud Project

 

 

 

Note: infrastructure shown for the Project is proposed.

 

October 15, 2025Page 205 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Water Quality

 

Physio-chemical analysis of surface water indicates that, in general, it has a pH close to neutral and low to moderate electrical conductivity, indicating relatively stable water quality conditions. Concentrations of dissolved metals such as aluminum and iron are generally low, with occasional peaks above drinking water standards observed during the wet season, particularly in the Gamba Gamba Creek. No cyanide was detected in any samples.

 

Groundwater quality was assessed based on monitoring data collected from sites representing community boreholes, exploration boreholes, and boreholes in the vicinity of the exploration camp. Groundwater quality was generally acceptable, with a pH close to neutral and moderate mineral content. Most chemical parameters, including major ions such as calcium, magnesium, and sodium, were at low levels, consistent with drinking water standards. Metals such as arsenic, selenium, barium, iron, and manganese sometimes exceeded health recommendations, suggesting potential contamination from agricultural runoff, wastewater discharge, or natural geogenic sources amplified by human activities.

 

Soils

 

The main soil types in the study area are:

 

·Regosols: defined by their absent properties rather than their present ones. They are poorly developed mineral soils in unconsolidated materials that are neither superficial, sandy, nor fluvial. Regosols correspond to soil taxa characterized by incipient formation, such as skeletal soils (FAO Global Reference Base for Soil Resources).

 

·Gleysols: form in waterlogged conditions due to rising groundwater. They are characterized by chemical and visual signs of iron reduction. In warm climates, these soils are often found on periodically flooded landforms and are defined by a shallow or non-existent surface horizon and alluvial parent material.

 

Geochemistry

 

Waste rock geochemical studies completed by Knight Piésold in 2022 indicate that the geochemical risk from weathering and sulfide oxidation is low. Of the 57 waste rock samples analyzed, 55% were classified as non-acid forming (NAF) and 45% were classified as acid consuming. No potentially acid forming (PAF) material was observed, with all samples containing very low sulfur contents. Fifty additional tests were completed by Earth System in 2025 which confirm the overall low potential for acid rock drainage, with only 1% of the sampling classified as potentially acidogenic.

 

Air Quality

 

Air quality monitoring was conducted during dry season and wet season around the Diamba Sud Project area to establish baseline conditions for particulate matter (PM10, PM2.5), sulfur dioxide (SO2), ozone (O3), nitrogen dioxide (NO2) and carbon monoxide (CO).

 

Monitoring followed IFC Guidelines (2007) and included multiple sites representing upwind and downwind conditions near sensitive receptors.

 

Key existing air emission sources include:

 

·Seasonal Harmattan dust transport during the dry season.

 

October 15, 2025Page 206 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Vehicular traffic on nearby roads including exhaust emissions and fugitive dust.

 

·Agricultural activities such as slash and burn producing dust and gas emissions.

 

·Local biomass burning for fuel and refuse, releasing particulates and various gases.

 

Baseline particulate concentrations (PM10) frequently exceed the World Health Organization (WHO) (2021) guidelines during the dry season, with lower but still notable exceedances in the wet season. Pollutant gases generally remain below WHO guideline levels, although SO2 and NO2 showed higher levels in the dry season, likely due to lightning and woodsmoke.

 

Noise and Vibration

 

The main sources of existing noise emissions in the vicinity of the Project area include:

 

·Vehicle and motorcycle use.

 

·Generators used for electricity generation.

 

·Water pumps and motorized machines.

 

·Domestic animals, birds, wildlife and insect activity.

 

Baseline noise monitoring recorded average daytime noise levels generally below WHO guidelines. Night-time noise levels were consistently above WHO guidelines. Some sites near villages and ASM activities recorded the highest noise levels. Sources include human activities in villages, vehicles, motorcycles, livestock, road construction, and ASM generators.

 

Baseline vibration monitoring detected standard background levels of surface and near surface seismic waves, including micro-seism’s (low-frequency waves <1 Hz). Sources of these waves include human activity related to transportation or industrial activity, winds, rivers, ocean waves, and other natural atmospheric phenomena.

 

20.1.3Biological Environment

 

Terrestrial Biodiversity

 

There are no intact, pristine habitat types in the study area. During the dry season of 2022, field surveys revealed the presence of traditional artisanal gold mining activities in virtually all habitats in the study area. Cultivated, cleared, and livestock grazing areas, as well as bush fires and heavy pruning of certain species (e.g., Acacia sieberiana) for fodder, have also impacted floristic diversity and regeneration.

 

The area covered by the Diamba Sud exploration permit is mainly composed of the following dominant habitat types: shrub savannah (1,650.1 ha, or 37% of the permit area), shrub savannah and bowal mosaic (1,018.3 ha, or 22.0% of the permit area), and tree savannah (433.0 ha, or 9.4% of the permit area). Some habitat areas have been totally degraded, mainly due to artisanal gold mining, farming settlements, and roads, with higher levels of disturbance from human activities located near Gamba Gamba and riparian areas.

 

Flora surveys conducted during the dry and rainy seasons of 2022 identified the presence of 288 species divided into 198 genera and 61 families in the permit area. Five species were present in almost all sites in the study area, namely: Anogeissus leiocarpa, Terminalia macroptera, Diospyros mespiliformis, Pterocarpus erinaceus, and Sarcocephalus latifolius.

 

October 15, 2025Page 207 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

According to the Senegalese Forest Code, 13 partially or totally protected species are present in the study area, which means that it is prohibited to fell or remove foliage from these species without authorization from the Senegalese water and forestry services. Of these, two are fully protected (Vitellaria paradoxa and Diospyros mespiliformis) and the other 11 are partially protected (Adansonia digitata, Afzelia africana, Borassus aethiopum, Ceiba pentandra, Cordyla pinnata, Grewia bicolor, Khaya senegalensis, Prosopis africana, Pterocarpus erinaceus, Tamarindus indica and Ziziphus mauritiana).

 

Four globally threatened species were recorded in the area. They are classified as “endangered” (Pterocarpus erinaceus) and “vulnerable” (Afzelia africana, Khaya senegalensis, and Vitellaria paradoxa) on the International Union for Conservation of Nature (IUCN) Red List of Threatened Species. All four species were found to be locally common in the study area, in savannah and forest habitats. The endangered species Pterocarpus erinaceus was found to be particularly common. Although classified as threatened, all four species are widespread in West Africa and occur in several countries other than Senegal. None of these species is restricted to the study area, nor does any significant part of their range occur within this area.

 

A total of 40 mammal species were recorded directly or indirectly. One species classified as critically endangered and benefiting from critical habitat, the western chimpanzee, was recorded in the area covered by the DS1 block. In addition, signs of the presence of hippopotamuses, a vulnerable species, have been found along the banks of the Falémé River, and indirect signs (footprints) of leopards, also vulnerable, have been found east of the area covered by the DS1 block. In addition, signs of the presence of the Guinea baboon, colobus monkey, and African buffalo, near-threatened species, were recorded in the Diamba Sud exploration permit area. The other mammal species recorded are classified as “of concern” on the IUCN Red List of Threatened Species.

 

Four species recorded during the baseline survey period are fully protected under the Senegalese Hunting Code, namely the western chimpanzee, hippopotamus, leopard, and aardvark. Twenty-two partially protected species were also recorded in the study area.

 

A total of 169 bird species belonging to 62 families were identified during the 2024 survey period. All species are classified as “least concern” on the IUCN Red List of Threatened Species, with the exception of six: the hooded vulture (Necrosyrtes monachus) (critically endangered; observed near the exploration camp), the bateleur (Terathopius ecaudatus) (endangered, was common and frequently observed flying over the landscape), Beaudouin's snake eagle (Circaetus beaudouini), the European turtle dove (Streptopelia turtur) (a single European turtle dove was also observed near a gallery forest south of the Project area), the northern ground hornbill (Bucorvus abyssinicus) (known to be in decline due to habitat loss and hunting, was captured on camera traps and frequently observed by villagers), and the tawny eagle (Aquila rapax) (vulnerable, observed once). In surveys conducted earlier in 2022, out of a total of 78 species observed, 62 species (76%) were strictly resident, seven species (9%) were both resident and African migratory, four species were intra-African migratory, three species were African migratory and resident, and two species were Palearctic migratory.

 

There are 27 bird species that are fully protected by the Senegalese Hunting Code. In addition, most birds of prey (e.g., vultures, eagles, kites, falcons, and buzzards) as well as owls, hornbills, and terns are fully protected. Thirteen other bird species are partially protected. The study area is likely to provide suitable habitat for a number of fully or partially protected bird species.

 

October 15, 2025Page 208 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

A total of 23 species of terrestrial reptiles were recorded in the study area during baseline biodiversity surveys conducted in 2022 and 2024. All species are classified as “least concern” on the IUCN Red List of Threatened Species, with the exception of one species, Echis jogeri, which is classified as “data deficient”. Echis jogeri is considered endemic, with a range limited to southeastern Senegal and southwestern Mali.

 

One fully protected turtle species was recorded in the study area during the biodiversity surveys: Bell's hinge-back tortoise (Kinixys belliana nogueyi).

 

There are four species of partially protected terrestrial reptiles in Senegal. Two partially protected monitor lizard species classified as “near threatened” on the IUCN Red List were recorded in the study are, being the Nile monitor (Varanus niloticus) and the savannah monitor (Varanus exanthematicus).

 

Aquatic Biodiversity

 

The Project is located in the Senegal and Gambia Freshwater Ecoregion, dominated by tropical and subtropical floodplains and wetland complexes. The Falémé River is adjacent to the Project, and waters from the permit area drain towards the Falémé River. Two main tributaries flow into the Falémé River from the Diamba Sud exploration permit area, with the larger tributary flowing at the southern boundary of the permit area and the other flowing north from the permit area to join the Falémé River further downstream. Streams and drainage lines in the Project area are primarily ephemeral and often bordered by gallery forest.

 

There are no international or national aquatic protected areas in or near the Diamba Sud Project area.

 

Fish species diversity in the study area is low: studies identified 24 species (2022) and 13 species (2024), spanning 19 genera and 10 families. The most frequently caught species were Schilbe intermedius, Alestes dentex, Brycinus nurse, and Petrocephalus bovei. Schilbe intermedius was present at all sites. All inventoried species are classified as “least concern” by the IUCN; none are protected or endemic in Senegal. Lates niloticus is the only species of notable commercial value. No invasive fish species were identified during the survey period.

 

For the herpetofauna, the West African crocodile (Crocodylus suchus) was observed in 2022 and 2024. Indirect evidence of the African dwarf crocodile (Osteolaemus tetraspis, vulnerable) was found in 2024. The African helmeted turtle (Pelomedusa olivacea) was recorded and is fully protected in Senegal. Nineteen semi-aquatic amphibian species were identified, all “least concern.” The Senegal softshell turtle (Cyclanorbis senegalensis, vulnerable) and suitable habitat for the African softshell turtle are present.

 

Macroinvertebrate surveys in 2022 identified 88 macroinvertebrate species (61 in the dry season, 66 in the rainy season); the 2024 surveys recorded 47 genera and 32 families. Arthropoda, especially insects, dominated. Mollusks were found at six sites. In 2024, insects made up 96% of total abundance. No macroinvertebrates are protected, endemic, or invasive.

 

The main threats include artisanal gold mining, agriculture, housing, and pastoralism. Artisanal mining causes pollution, erosion, and biodiversity loss. Water quality has declined, reducing fish stocks and impacting local fishermen. Unsustainable fishing practices further decrease stocks. Invasive alien species are a regional concern, but none were recorded in the study area.

 

October 15, 2025Page 209 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Ecosystem Services

 

The study area features woodlands, savannahs, gallery forests, and grasslands. Timber is abundant, especially near watercourses and mountains, but overexploited near villages and mining sites. Timber is essential for fuel, construction, and furniture. Most households use wood for cooking; charcoal and gas are less common. Key timber species include Pterocarpus erinaceus (Senegalese rosewood), Oxynanthera abyssinica, and Anogeissus leiocarpa, used for construction, furniture, and tools. Timber is also used at mining sites.

 

Local ecosystems provide food, medicine, spices, oils, resins, and materials such as bamboo and rattan. About 42% of households collect non-timber forest products, with variation between villages.

 

Small ruminant farming is common, mainly for self-consumption and occasional sale. Goats and sheep are most common, with some cattle. Water sources include rivers and boreholes, but availability drops at the end of the dry season.

 

Groundwater from boreholes and wells is the main source of drinking water. Quality declines in winter due to artisanal mining runoff. River water is used for laundry and gardening, but not for drinking due to contamination from mining chemicals. Most households rely on boreholes or wells, with irregular availability. Communities worry that the Project may further impact water resources.

 

Traditional huts use clay, straw, wood, and bamboo from the environment. Modern huts with concrete and tin roofs are more common in mining villages. About 90% of households have traditional huts, showing reliance on natural materials.

 

Fishing is a minor but practiced activity. Main species caught include Synodontis sp., Petrocephalus bovei, Citharinus citharus, Hydrocynus brevis, and Sarotherodon galilaeus. Water quality and fish stocks have declined due to mining and unsustainable practices. Most fish are consumed locally; some are sold. Fishing is mainly seasonal, with methods including gillnets, beach seines, lines, and rods.

 

Critical Habit Assessment

 

Using the IFC Performance Standards, a Critical Habitat Assessment was undertaken through consultation and review of existing literature and data, field work, and analysis of critical habitat according to the following five potential critical habitat triggers as defined in IFC Performance 6 (IFCPS6):

 

i.Presence of critically endangered or endangered species, as listed on the IUCN Red List of Threatened Species.

 

ii.Presence of endemic or species with limited distribution.

 

iii.Presence of concentrations of migratory or gregarious species of global importance.

 

iv.Highly threatened and/or unique ecosystems.

 

v.Areas associated with key evolutionary processes.

 

Based on the data collected at this stage, the analysis of critical habitats shows that criterion (i) is applicable according to IFC PS6 for the West African chimpanzee. In the Diamba South Project study area, this therefore applies to:

 

·Gallery forests.

 

October 15, 2025Page 210 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Relief areas of more than 200 m elevation (Kharakhene and Kourdiakhouma hills).

 

·The interface zone between gallery forests and open forests (a buffer of 100 m is considered around gallery forests adjoining open forests).

 

According to IFC PS6, a Biodiversity Action Plan for the Diamba Sud Project will be required as part of further project development. A conceptual Biodiversity Action Plan was developed and would require an estimated budget of US$2.4 million over the LOM.

 

Protected Areas

 

The nearest conservation protected area is the Bafing-Falémé Ramsar Wetland located at 50 km south to the Project, near the confluence of the Bafing and Senegal Rivers in Guinea. It spans 5,173 km2 and includes gallery forests, shrubby and wooded savannahs, and floodplains. It is home to unique hydrophytic grasses, aquatic herbs, and endangered species such as chimpanzees, lions, and vultures.

 

Niokolo-Koba National Park is the closest international protected area to the Project, located approximately 95 km to the west. It covers 9,130 km² and is a World Heritage Site, a UNESCO-MAB Biosphere Reserve, and an Important Bird Area. The park contains diverse habitats, including gallery forests, savannah floodplains, ponds, and dry forests. It is home to key species such as chimpanzees, lions, elephants, Western Derby Eland, and African wild dogs.

 

The Diamba Sud Project falls within the Falémé Hunting Area, a designated hunting zone by decree in 1972 (Decree n° 72-1170) covering approximately 8,400 km². The hunting activity is compatible with mining activities as per Decree n° 78-506.

 

20.2Environmental Issues – Climate Change

 

Climate change is expected to lead to dryer and hotter conditions in Senegal with potentially larger rain events during the wet season. It is not currently anticipated that climate change will have a significant effect on operations during the time frame of the Project. However, factors such as water supply and structure design will need to incorporate climate change considerations into the engineering of the Project to minimize risks and ensure long term resilience of the infrastructures.

 

20.2.1Physical Risks

 

Temperature

 

Climate projections from the World Bank Group's Climate Knowledge Portal indicate that daily means, maximum and minimum temperatures in the Project area (Kédougou region) could increase. The Project area is expected to experience an increase in mean surface air temperature of between 1.16°C (SSP1–2.6) and 2.01°C (SPP5–8.5) by 2060, compared with the reference period 1950–2014, according to the lowest and highest emissions scenarios respectively. The greatest increases in mean, maximum and daily temperatures could occur between November and March, during the dry season. Overall, the temperature rise forecast for the region over the next 50 years is likely to be slightly higher than the global average (Think Hazard, 2020).

 

In addition, the number of hot days with a maximum temperature above 35°C and tropical nights with a minimum temperature above 29°C is set to increase in both the high and low emissions scenarios. In the medium and high emissions scenario, 31 more hot days per year are expected in 2030 than in 2000, 47 more in 2050 and 82 more in 2080 (German Federal Ministry for Economic Cooperation and Development, 2022).

 

October 15, 2025Page 211 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Precipitation

 

The rainy season is governed by the movement of the Intertropical Convergence Zone, resulting in great variability from year to year and decade to decade, which can make it difficult to identify long-term trends. However, the consensus is that precipitation in the Kédougou region is trending downwards, particularly from June to August, and that higher greenhouse gas emissions point to an overall drier future (German Federal Ministry for Economic Cooperation and Development, 2022).

 

Heavy precipitation events are expected to intensify, and the proportion of total annual precipitation falling during severe events tends to increase in the overall projections. Seasonally, this ranges from a downward trend from January to March and April to June, to an upward trend from July to September and October to December (USAID, 2021).

 

A study carried out on the Senegal River Basin, which includes the Falémé basin (sub-basin 4) in the Kédougou region, indicates changes in rainfall intensity in the basin (Diakhate et al., 2022). The results indicate that after 2050, there is a risk of a decrease in rainfall intensity (by around 20%) during the first phase of the monsoon season (May–August) in the RCP8.5 scenario and by less than 10% in the RCP4.5 scenario. The study points out that the peak of the monsoon season is likely to shift from August to September by 2100 (Diakhate et al. 2022).

 

Evapotranspiration

 

The IPCC RE6 report indicates that it is highly likely that evapotranspiration rates will increase under all emission scenarios. In Sahelian climatic zones, evapotranspiration rates could reach 266 mm by 2065 in the RCP4.5 scenario, and up to 277 mm in the RCP8.5 scenario (Ndiaye et al. 2021).

 

Bush Fires

 

Modelled climate projections indicate a likely increase in the frequency of fire-prone weather conditions in this region, including higher temperatures and greater variability in rainfall. In areas already affected by fire risk, the fire season is likely to lengthen, with a greater number of days conducive to fire spread due to longer rain-free periods during fire seasons. Climate projections also indicate an increase in fire severity. Areas at very low or low risk could see their risk level increase, as climate projections indicate an expansion of the forest fire risk zone (Think hazard, 2020).

 

Scenario Analysis

 

While climate parameters are likely to change in the future, according to the climate change scenario analysis based on SSP2–4.5 medium emissions and SSP5–8.5 high emissions executed by S&P Global in 2023, the Project appears to have a low physical risk exposure (below 10% of the asset value) with a relative risk in 2030 estimated at 0.4%.

 

20.3Permitting

 

The development of the Diamba Sud Project requires a number of permits and authorizations in line with Senegalese legislation. A list of permits and authorizations are summarized in Table 20.2. All necessary permits and authorizations must be obtained for the Project to meet Senegalese regulatory requirements and must be integrated into the Project's operations and management systems.

 

October 15, 2025Page 212 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 20.2 Summary of Key Permits and Authorisations Required for the Diamba Sud Project

 

Permit/Authorizations Ministry/Department Relevant
Legislation
Work Activity to
Support Legal
Requirement
Schedule For Legal Authority
Environmental and Social Attestation of Compliance Directorate of Environmental Regulation and Control (Direction de la RéglementationEnvironnementale et du Contrôle following an examination by the Technical Committee) (DIREC) Environment Code, 2023 ESIA Feasibility study (Following validation of ESIA)
Certificate of Environmental and Social Conformity Ministry for the Environment and Ecological Transition (Ministère de l’Environnement et de la Transition écologique) (METE) Environment Code, 2023 ESIA Feasibility study (Following validation of ESIA)
Authorization to pump from Falémé River

Organisation pour la mise en valeur du fleuve Gambie (OMVG) and

Department of Management and Planning of Water Resources (DGPRE)

Water Code ESIA/Application for operational permit Feasibility study (Following validation of ESIA)
Blasting Certificate/Authorization/Permit Autorité Sénégalaise de Radioprotection et de Sûreté Nucléaire (ARSN) Radiation law (2004) ESIA/Application for operational permit Feasibility study (Following validation of ESIA)
Permit for discharge of water Ministry of Sanitation / DGPRE. Environment Code, 2023 ESIA/Application for operational permit Feasibility study (Following validation of ESIA)
Permit for construction works located outside the Mine Concession boundary i.e. site access road Minister of Mines and the Minister of Lands Mining Code, 2016 Application for auxiliary construction works (It may be possible for these to be conditioned as part of the ESIA) Feasibility study (Following validation of ESIA)
Mine Concession Ministry of Mine Mining Code, 2016 Application for Mine Concession Feasibility study (Following receipt of Certificate of Environmental Conformity)
Authorization for an ICPE, including authority for the importation, transport, storage and use of hazardous materials DIREC / Governor Environment Code, 2023 Application for ICPE, including public enquiry, an Internal Operations Plan (POI)) and an emergency plan (Plan Particulier d'Intervention (PPI)) Pre-mobilization (Following receipt of Mine Concession)
Land clearance Ministry of Environment and Sustainable Development (DEFCCS) Forestry Code, 1998 Environment Code, 2023 Forestry inventory (post ESIA) Pre-mobilization (Following receipt of Mine Concession)
Permit for construction of WSD Ministry of Hydraulic

Environment Code, 2023

Water code, 1981

ESIA/Application for operational permit Pre-mobilization (Following receipt of Mine Concession)
Permit for importation, transportation, storage and handling of hazardous materials (cyanide, explosives) Ministries of Mines and Interior (DEEC) and Department of Mines and Geology (DMG) Mining and Environment Code, Ministry of interior Notice ESIA/Application for operational permit Pre-mobilization (Following receipt of Mine Concession)
Permit for exploitation of borrow areas where these may be located outside the Mine Concession boundary Ministries of Mines and Environment Mining Code, 2016 Application for exploitation permit (It may be possible for these to be conditioned as part of the ESIA) Pre-mobilization (Following receipt of Mine Concession

 

October 15, 2025Page 213 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

20.4Tailings Storage Facilities

 

Please refer to Section 18.3 of this Report.

 

20.5Water Management

 

Please refer to Section 18.5 of this Report.

 

20.6Environmental Management and Monitoring

 

The Project will need to comply with discharge and emissions guidelines for potential off-site releases of water, waste and airborne contaminants, as well as ambient guidelines for the protection of environmental values (e.g. protection of aquatic fauna and fisheries, drinking water, etc.). A list of relevant Senegalese standards is presented in Table 20.3 together with the date these requirements were enacted.

 

Table 20.3 Key Air Quality, Noise and Water Standards and Legal Requirements

 

Source Title Year
Water Discharge and Monitoring
Senegal Interministerial Order no 1555 Discharge Water Guidelines 2002
Wastewater Discharge Standard, NS 05-061 2001
Law no. 81-13 of 4 March 1981 on the Water Code (Articles 49 and 56) 1981
Decree no. 98-556 of 25 June 1998 on water policing (Article 13) 1998
Water Treatment Code, Law 2009-24 of 8th July 2009 2009
Decree 2001-245 of 17th February 2011 2011
Air Quality
Senegal Interministerial Order no. 7358 Application of Air Pollution Standard 2003
Atmospheric Pollution Standard, NS 05-062 2018
Environment Code (Title 5 ; Chapter II) 2023
Law no. 83-71 of 5 July 1983 on the Hygiene Code (Article L31) 1983
Noise and vibration
Senegal Environment Code (noise, Title 4, Chapter 8) 2001
Decree No 2001-282 implementing the Environment Code (Article R84) 2001
Law No. 97-17 of 1 December 1997 on the Labour Code 1997
Decree No. 200601252 of 15 November 2006 on environmental factors 2006

 

20.6.1Environmental and Social Management System

 

The preliminary ESIA, submitted on October 6, 2025, and undergoing validation, contains a full Environmental and Social Management and Monitoring Plan (ESMMP), a key part of the Project’s Environmental and Social Management System (ESMS).

 

The ESMMP describes monitoring arrangements for all relevant environmental and social compartments affected by the Project including: meteorology, climate change, surface and groundwater quality and quantity, erosion and sedimentation, air quality, noise and vibration, ecology and biodiversity, road safety, waste management, organizational health and safety, stakeholder engagement, cultural heritage, in-migration, community health, safety, well-being and livelihoods, as well as mine rehabilitation and

 

October 15, 2025Page 214 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

closure. These arrangements are defined for the entire Project lifecycle including construction, operation and closure phases. Key environmental and social issues are already being monitored during the Exploration phase as part of best-practice environmental stewardship as well as baseline studies for the ESIA.

 

The key objectives of the management and monitoring program developed for the Project are as follows:

 

·comply with the environmental, social, and health commitments and measures described in the ESIA;

 

·avoid or mitigate potentially negative environmental or social impacts that could result from the development and operation of the Project;

 

·maximize beneficial impacts and minimize unavoidable residual impacts; and

 

·comply with applicable regulatory requirements, legislation, and international environmental and social standards.

 

The ESMMP describes Boya's legal obligations and other environmental and social management requirements and commitments due to the development of the Project. In particular, the ESMMP describes the set of management measures and monitoring programs that will be implemented during the construction, operation, and closure phases of the Project. The ESMMP also ensures the link between policy and Project implementation as a planning document summarizing legal requirements and obligations, international standards and guidelines, and the environmental and social commitments described in the ESIA and presenting the management measures and monitoring programs to be implemented to achieve them.

 

The ESMMP will be used in conjunction with the following stand-alone management plans, which are considered part of the ESMMP and are also provided in the ESIA:

 

·Stakeholder Engagement Plan (SEP).

 

·Conceptual Rehabilitation and Mine Closure Plan (CRMCP).

 

·Livelihood Restoration Plan (LRP).

 

The Plans will be supported by procedures, forms, registers, and a full ESMS, which will be developed and implemented as needed.

 

A Hazard Study has also been prepared for the Project and presented in the ESIA. The Project's risk assessment will be reviewed annually to identify potential emerging issues. It will serve as the basis for the development of emergency response plans for the Project. These plans will match Senegalese legislative requirements and will be prepared prior to the construction of the Project.

 

Boya will establish inspection, audit, and review processes for the Project. Regular audits of the Project's ESMMP and associated management systems will be conducted internally and externally. The audits will assess:

 

·The adequacy of the ESMMP and related plans in relation to the scale and nature of the anticipated impacts and the current stage of development of the Project.

 

·Staff awareness, competence, and matching with the ESMS and related plans and procedures.

 

October 15, 2025Page 215 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·The performance of managers and operators in implementing, maintaining, and enforcing the ESMS and related plans.

 

·The adequacy of resources, equipment, and budget allocated to the implementation of the ESMS.

 

All recommendations arising from the audits will be discussed, corrective actions will be documented, and progress will be reported. Independent external audits will be conducted as well. Environmental and social monitoring will be coordinated with national regulators in collaboration with relevant national and regional technical services as well as local authorities and local government.

 

20.7Community Relations

 

Fortuna recognizes stakeholder engagement as a prerequisite for acquiring and maintaining the sustainable Social License to Operate and as a core element for good social risk management.

 

A detailed Stakeholder Engagement Plan will be developed as part of the ESIA that will identify among other requirements: stakeholder consultation, participation, and disclosure activities.

 

In addition, a Grievance Management Mechanism was developed at an early stage of the Project to take into account complaints that may relate to unmet expectations, build-up of nuisances, compensation for damages, eligibility criteria for compensation by the Project, perceptions and attitudes of the parties toward the mining sector, or the quality of services and assistance provided to the parties by mining activities.

 

A voluntary social investment or corporate social responsibility program is already in place, aiming to support local socio-economic development.

 

20.7.1Stakeholder Engagement

 

To date, official stakeholder engagement and public participation activities with affected communities include:

 

·Active community engagement with key stakeholders since the start of exploration activities in 2015, including host villages and communities affected by the Project, vulnerable groups, particularly women and youth, health service providers, local administrative authorities, technical agencies, and government regulatory bodies.

 

·Stakeholder participation and consultation as part of the environmental and social studies and preliminary economic assessment, including environmental and social baseline studies, in April-May 2022, March 2023, and April 2024.

 

·Stakeholder consultations and engagement as part of the ESIA in June and July 2025.

 

The main stakeholder groups are comprised of the following: Project affected communities; the Government of Senegal (at all levels) and local traditional authorities (e.g.: village chiefs); public and commercial interests; Project-related committees; non-governmental organizations /civil society organizations; and youth, women, elderly, and other vulnerable groups.

 

The stakeholder consultations completed at the Report effective date highlighted several expected Project benefits and the main community concerns. The expected Project

 

October 15, 2025Page 216 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

benefits identified by the communities consulted include developing the local economy, creating jobs and skills, developing agriculture and livestock farming, and improving community health infrastructure, water infrastructure, and basic services.

 

The villages identified employment opportunities, training programs, local entrepreneurship, and service providers, particularly for young people, as a key expected benefit, which is a municipality expectation of rural communities located in the immediate vicinity of major development projects. The creation of agricultural development opportunities was identified as a potential benefit, particularly by women (e.g. equipment, water infrastructure, market gardening, and other income-generating activities). Women's additional development needs mainly are concerned with the establishment of cooperatives.

 

The communities also highlighted several development needs, such as providing water supply infrastructure, rehabilitating or building educational and health facilities, completing agriculture (tools, seeds, training), and improving electrification and road access during the rainy season. Specific comments at the community level from villages, including Gamba Gamba, highlighted the good collaboration with Fortuna/Boya. However, concerns were also expressed about the Project's impact on ASM and the loss of livelihoods.

 

20.7.2Social Investment

 

Fortuna implemented a social investment program to support socio-economic development initiatives of the communities in the Project area. Following consultation of these communities to identify to their needs, more than 20 local development activities were conducted from 2021–2025.

 

An estimated budget of US$ 2.1 million over the LOM has been allocated to implement socio-economic initiatives near the mine and in the region.

 

20.7.3Land Acquisition

 

The Project will require the acquisition of the land corresponding to the operations footprint and the fenced-in area. To manage this activity, a process based on Senegalese regulation and the IFC principles for involuntary resettlement will be developed and implemented. This process will include a Livelihood Restoration Program to compensate for eligible economic impacts due to land acquisition. It is important to note that no permanent infrastructure has been identified within the Project development area. The Project is, therefore, not expected to have a physical impact on any dwellings, community structures or infrastructure associated with the village of Gamba Gamba, located approximately 0.5 km from the nearest fence line, or any other village within the study area. Based on the current Project design, it is currently estimated that 1,700 ha of land will be required to implement the fenced-in perimeter for the proposed Diamba Sud mine and <50 ha of crops.

 

In Senegal, a land acquisition and compensation process must be undertaken in accordance with national legislation (law no. 64-46 of June 17, 1964 relating to the national domain; law no. 76-67 of July 2, 1976 relating to expropriation of land for public utility and other land operations of public interest; and decree no. 77-563 of July 3, 1977) to ensure that all landowners are identified and compensated for the loss of their land and livelihoods. In terms of best practices, the IFC Performance Standards, particularly Performance Standard 5 (IFP PS5), have become the international benchmark for land acquisition issues on extractive industry projects.

 

October 15, 2025Page 217 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Based on Senegalese regulation and IFC best practices, the Diamba Sud Project land acquisition process will comply with Senegalese regulations and IFC PS5 according to framework. Where national requirements are superseded by IFP PS5, or where IFP PS5 requirements are more favorable to Project-affected people, it will complement its arrangements to comply with IFC PS5.

 

Within the Project area, most land is held under customary forms of land titling. The land use baseline study showed dominant land types in the Project footprint: mainly empty plateau areas, followed by few farmland and grazing areas. Residential areas are outside the Project development area.

 

No physical resettlement is expected for the development of the Diamba Sud Project. Land impacts due to the Project will primarily be associated with acquisition of land for the Project footprint (mine pits, WRSFs, TSF), construction of haul roads, process plant and other infrastructure. Land loss will be minimized through Project design, reducing impacts to the communities in this area.

 

The village of Gamba Gamba is located within the DS1 block area boundary, with a small amount of land belonging to Gamba Gamba residents within the footprint of Project components. Some loss of cultivated land located within the footprint is expected for Gamba Gamba village lands.

 

A full Inventory of Loss will be undertaken to formally identify the owners of land and any structures within the Project development area that will be lost as a direct result of the Project. The Inventory of Loss will guide appropriate compensation for losses associated with construction and operation of the Project.

 

A final Livelihood Restoration Plan will be prepared based on the Inventory of Loss and agreed with local stakeholders and people affected by the Project.

 

20.7.4Artisanal Small-Scale Mining (ASM)

 

ASM is a key livelihood activity for households in the Diamba Sud study area, particularly in the villages of Karakaéné, Gamba Gamba, and Lingueya. In several villages, ASM is ranked as the main subsistence activity, with nearly half of the working population in Gamba Gamba engaged in ASM as their primary occupation. In the Kédougou region, the sector is a significant economic and demographic driver, estimated to produce 4.2 t of gold annually and provide direct employment to over 32,000 people locally. In the Project area, the ASM activities have decreased over the past years due to the current legal exploration activities ongoing, with no ASM activities and settlement in the Project development or fenced in area at the Report effective date.

 

From an environmental perspective, artisanal mining is identified as the main threat to biodiversity in the study area. ASM activities have complex impacts, including the creation of deep excavation pits and the potential release of harmful contaminants such as mercury and cyanide into waterways and surrounding soils. These pollutants contribute to declining water quality, putting downstream areas at risk of biodiversity loss. Local authorities have responded by implementing conservation measures to protect affected ecosystems and species.

 

Aquatic ecosystems are also severely affected by ASM. The Falémé River, in particular, has experienced significant degradation due to intensified ASM activities, which have led to land clearing, bank erosion, and soil loss. The release of mercury and cyanide into the aquatic environment has resulted in water pollution, a decline in fish stocks, and reduced ecosystem functioning, with direct economic impacts on local fishermen. Unsustainable

 

October 15, 2025Page 218 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

fishing practices, combined with ASM, have further contributed to the decline in aquatic biodiversity.

 

Artisanal mining is illegal within the permit area, and access to ASM sites has been restricted as part of exploration activities. While numerous active ASM sites exist nearby, none have currently been reported in areas of the Project where Mineral Resources are located. ASM remains an important livelihood for neighboring communities, especially Gamba Gamba. The Project will restrict access to ASM sites within the permit, but other sites remain accessible in the vicinity. Economic impacts on ASM will be mitigated indirectly by job creation within the proposed operations, including opportunities for service contractors. These jobs will aim to provide alternative sources of income and promote more secure, stable, and sustainable livelihoods. Targeted community development initiatives, such as local employability programs, vocational training, and small business development, are planned to support this transition.

 

Stakeholder consultations have highlighted concerns about the proposed operation’s impact on ASM and the potential loss of livelihoods. Fortuna’s engagement with local communities includes addressing ASM-related concerns and supporting alternative livelihoods.

 

ASM Approach

 

Boya aims to engage with ASM, as needed, within host country regulations and international guidelines but without compromising the sustainability of its activities. Consequently, the main strategy to appropriately manage artisanal miners’ relationships and achieve business and development goals is, where possible, to minimize broad-ranging indirect negative impacts to communities with social development initiatives and to create a secure environment for Company operations within the national framework. Boya is committed to:

 

·Periodically following the evolution of the ASM regulation and activities in the mining area.

 

·Engaging with local ASM, local communities, national and local authorities in a transparent and constructive dialogue.

 

·Ensuring that the large-scale mining activities will not put the ASM miners’ safety at risk and vice versa.

 

·Proactively supporting community investment projects focusing on economic development and other improvements in local communities.

 

·Providing local communities with fair and reasonable opportunities to participate in the company's workforce and the supply of goods and services, including its subcontractors.

 

20.7.5Community Development Fund

 

In accordance with the Senegal’s Mining Code (2016) Article 115, a Community Development Fund (CDF) will be established and contributed to annually during production. The purpose of the fund is to promote the economic and social development of local communities residing around the mining areas. Under the 2016 Mining Code, mining companies must contribute 0.5% of annual after-tax sales revenue to the CDF. The actions to be undertaken must be defined in a Local Development Plan in consultation with local communities and administrative authorities.

 

October 15, 2025Page 219 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

20.8Mine Closure Plan

 

In accordance with Senegalese regulations and industry best practices, a mine closure plan must be developed for the Project. At this PEA stage, the mine closure plan takes the form of a Conceptual Mine Rehabilitation and Closure Plan which presents a general framework and initial implementation plan for the rehabilitation and closure of the proposed Diamba Sud mine.

 

20.8.1National Framework

 

The 2016 Mining Code is the main legislation governing the mining industry in Senegal. The sections of the code relevant to Mine Closure are as follows:

 

·Article 100 - Commencement and termination of work: Any decision to commence or terminate work for the exploration and exploitation of mineral substances must be declared in advance to the Ministry in charge of mines.

 

·Article 103 - Rehabilitation of mining sites: Any holder of a mining title is required to rehabilitate the sites covered by that title.

 

·Article 104 - Mining rehabilitation guarantee: Notwithstanding the obligations arising from article 103 of this Code, any holder of an exploration permit, an authorization to open and operate a permanent quarry, an authorization to operate a small mine, a mining license or a production sharing contract is required to open and maintain a trust account with a specialized public institution designated by the State. This account is intended to constitute a fund to cover the costs of implementing the environmental management plan. The procedures for operating and replenishing this fund shall be laid down by decree.

 

·Article 111: As part of the exercise of control over mining operations, the mining administration has the right to have the accounts, installations, infrastructures, systems and processes of any holder of mining titles audited, including by an independent body. Such audits shall be carried out in accordance with internationally recognized standards and procedures and without hindering the smooth running of mining operations.

 

In accordance with the Mining Code, Decree no. 2009-1335: a Mine Rehabilitation and Closure Fund will be created to provide the mechanisms and operational framework for a mine rehabilitation fund.

 

20.8.2Conceptual Closure Costs

 

The cost estimate for the conceptual closure plan (Table 20.4) is based on benchmarked closure activities costs from equivalent projects in similar legal and natural environments crossed with the mining infrastructure characteristics and current closure assumptions. Costs will be adjusted according to periodic re-evaluation and the real costs recorded during implementation.

 

October 15, 2025Page 220 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 20.4 Summary of Closure Costs

 

Area Estimated Cost (US$)
Pits 200,000
Waste dumps 4,900,000
ROM and stockpiles 100,000
Tailings storage facility 3,400,000
Processing plant 2,000,000
Explosives magazine 200,000
Social closure 500,000
Environmental management 1,000,000
Total 12,300,000

 

Based on the defined Project and these characteristics, the costs of rehabilitation and closure of the proposed Diamba Sud mine as envisaged in the PEA are estimated at US$12.3 million.

 

20.9Comments on Section 20

 

It is the opinion of the QP that appropriate environmental and social studies have been conducted to date for the Diamba Sud Project to assess the risks and opportunities related to the project as presented.

 

With careful implementation of the environmental and social management measures such as the ESMMP, the livelihood restoration program, and the biodiversity action plan, the Project is expected to be developed in a way which provides compliance to local regulation, alignment with international industry standards and a net socio-economic benefit to local communities and to Senegal without compromising the integrity of the broader environment.

 

The design of the Project as envisaged in the PEA will be used for the Project environmental and social permitting including the preparation of the ESIA. The formal ESIA process began with the Senegal Government with the submission and approval of the Term of Reference of the ESIA in the first quarter 2025, followed by the submission of the ESIA for review and approval on October 6, 2025, with the intention of obtaining approval for same in early 2026. The results of this governmental process may have an impact on the proposed requirements and management plans to be implemented under the ESIA that was submitted for approval.

 

October 15, 2025Page 221 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

21Capital and Operating Costs

 

21.1Capital Cost Estimates

 

This section of the Report summarizes the base of the estimates for capital expenditure (±25–30%) for the Diamba Sud Project. The estimated Project capital cost is US$216.9 million excluding mining and contingency.

 

The capital cost estimate is based upon an engineering, procurement and construction management (EPCM) approach where the Owner assumes the builder’s risk. As a result, the cost estimate does not include a builder’s margin.

 

MIQM (Mintrex), with Fortuna input, prepared the capital cost estimate for the process plant, associated infrastructure (except electrical power supply), accommodation camp and some Owner’s costs. Cost estimates for the electrical and instrumentation elements of the process plant and infrastructure were prepared by ECG Engineering. The TSF, water storage dam and site roads cost estimates were prepared by Knight Piésold.

 

A summary of the capital cost estimate for the Diamba Sud Project is presented in Table 21.1.

 

Table 21.1 Summary of Projected Capital Costs

 

Area Capital Cost (US$M)
Process plant and infrastructure 180.4
Mining 19.9
Owner’s costs 31.9
Withholding tax, duties, levies 4.5
Contingency (20%) 46.4
Total 283.2

 

A breakdown of capital costs for the processing plant, infrastructure and Owners’ costs is presented in Table 21.2.

 

Table 21.2 Summary of Projected Major Capital Costs (US$M)

 

Area Installation
Hours ('000)
Material
Costs
Installation
Costs
Freight
Costs
Total
Process Plant Costs
Construction overheads   0.6 2.7 0.0 3.3
Bulk earthworks   1.7 0.0 0.0 1.7
EPCM   21.1 0.0 0.0 21.1
Primary crushing 54 4.8 1.5 0.5 6.9
Milling & classification 255 25.3 5.7 2.3 33.4
Leaching & adsorption 95 9.9 3.1 1.3 14.3
TSF & decant return 12 1.0 0.2 0.1 1.3
Metal recovery & refining 35 3.8 1.2 0.3 5.3
Reagents 18 0.8 0.5 0.1 1.5
Services 40 4.6 1.0 0.3 6.0
Total Process Plant Costs 509 73.7 16.0 5.0 94.6
Infrastructure          
Tailings storage facility 25 28.9 0.9 0.1 30.0
Process plant infrastructure 16 11.6 1.8 0.2 13.6

 

October 15, 2025Page 222 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Area Installation
Hours ('000)
Material
Costs
Installation
Costs
Freight
Costs
Total
Camp 17 5.3 0.0 0.0 5.3
High voltage power supply - 32.5 0.0 0.0 32.5
Plant vehicles & mobile equipment - 4.4 0.0 0.0 4.4
Other Costs -        
Temporary construction facilities - 0.9 0.0 0.0 0.9
Capital spares - 4.4 0.0 0.5 4.9
First fills - 1.2 0.0 0.0 1.2
Owner's costs          
Construction insurance - 0.6 0.0 0.0 0.6
Compensation - 1.2 0.0 0.0 1.2
Pre-production labor - 4.0 0.0 0.0 4.0
Preproduction expenses - 4.2 0.0 0.0 4.2
Mining pre-production - 19.9 0.0 0.0 19.9
Owners’ general - 0.6 0.0 0.0 0.6
Owners project management - 9.6 0.0 0.0 9.6
Business systems - 0.5 0.0 0.0 0.5
Training - 0.3 0.0 0.0 0.3
Rehabilitation - 3.9 0.0 0.0 3.9
Total Indirect Costs 58 134.0 2.8 0.9 137.6
Total Project Costs 567 207.7 18.7 5.8 232.2

 

Equipment and infrastructure costs are attributed to all departments of the Project including mine, plant, tailing facilities, maintenance and energy, safety, information technology, administration and human resources, logistics, camps, geology, planning, laboratory and environmental.

 

21.1.1Estimate Assumption and Clarifications

 

The following assumptions and clarifications apply to the cost estimates:

 

·The capital estimate is based on an EPCM implementation strategy (engineer manages construction contracts on behalf of client who assumes builders’ risk). It is assumed the EPCM engineer will be based in Australia for the engineering and procurement phase.

 

·Limited materials handling testwork was undertaken with preliminary plant design based on best engineering knowledge and previous experience.

 

·Mining will be performed by an experienced and competent mining contractor.

 

·It is assumed that the cost of mining-related bulk earthworks, such as the construction of the ROM mineralization stockpile area, primary crushed mineralization stockpile and the mining haulage roads will be undertaken by the mining contractor and will form part of the mining pre-strip costs.

 

·It is assumed that geotechnical ground conditions are favorable in the proposed SAG mill and CIL tank locations. Geotechnical holes will be drilled and assessed

 

October 15, 2025Page 223 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

  following confirmation of the CIL and mill locations to confirm ground properties.

 

·Power supply and distribution to the main plant incomer switch point is excluded from this estimate.

 

·The estimate is based on wage rates from MIQM’s database for projects in West Africa.

 

·It has been assumed that sufficient manpower resources are available in Senegal and nearby countries to undertake the Project in the timescale envisaged.

 

·It is assumed that all plant vehicles and major items of mobile equipment will be purchased.

 

·It is assumed that the accommodation camp will be constructed ahead of the commencement of process plant construction and will be available to meet the requirements of the construction workforce.

 

21.1.2Estimate Exclusions

 

The following exclusions apply to the capital cost estimate:

 

·Escalation of prices to a future date.

 

·Financing costs or interest.

 

·Import duty for capital items.

 

·Government approvals and special permits.

 

·Currency exchange rate variations.

 

·Goods and services taxes are not expected to apply.

 

·The special provision of process guarantees or performance warranties beyond the normal vendor obligations under the Trade Practice Act and the Sale of Goods Act.

 

·Owner’s sunk costs prior to project implementation approval.

 

·Expatriate construction personnel taxation and employment law compliance costs (no additional costs are expected).

 

·Unseasonal inclement weather delays.

 

21.1.3Capital Estimate

 

The following sub-sections provide a description of the estimate methodology used to develop the capital cost estimate.

 

Escalation

 

Where prices from previous projects have been escalated for used in this Project, the ABS Mining Construction Materials Index (No. A2309126F) was applied.

 

Plant Bulk Earthworks

 

Plant bulk earthworks were estimated by MIQM based on 8.0% of the total mechanical equipment supply cost.

 

October 15, 2025Page 224 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Civil Construction

 

Concrete quantities were established using a combination of the general arrangement drawings and the 3D model prepared for the PEA, MIQM’s historical detailed designs, and MIQM’s database of quantities from previous projects.

 

Concrete rates were based on rates from MIQM’s database for similar projects in West Africa.

 

Structural Steel – Supply

 

Structural steel quantities including light, medium, heavy gauge steel, grating, guarding, handrails and stair treads were established using a combination of general arrangement drawings and the 3D model prepared for the PEA, MIQM’s historical detailed designs and MIQM’s database of quantities from previous projects.

 

Detail, supply and fabrication rates were based on rates from MIQM’s database for similar projects in West Africa, with fabrication taking place in China.

 

Platework – Supply

 

Platework quantities, including shop fabricated tanks, bisalloy liners and rubber liners, were established using a combination of the general arrangement drawings and the 3D model prepared for the study, historically similar MIQM detailed designs and MIQM’s database of quantities from previous projects.

 

Detail, supply and fabrication rates were based on rate from MIQM’s database for similar projects in West Africa, with fabrication taking place in China.

 

Site erected tankage was assumed, bolted tank with supply rates were based on the platework supply and fabrication rate from MIQM’s database for similar projects in West Africa.

 

Mechanical Equipment – Supply

 

The major mechanical equipment items were sized to prepare the mechanical equipment list for the PEA, reflecting the process design criteria and the plant throughput assumptions. Equipment data sheets were prepared for all major equipment, and these were issued to equipment vendors for budget pricing. Multiple pricing was requested for major items of mechanical equipment, whilst minor items pricing is from MIQM’s database.

 

Structural, Mechanical and Piping Installation

 

The structural, mechanical and piping installation and equipment rates were based on rate from MIQM’s database for similar projects in West Africa.

 

Piping – Supply and Install

 

The supply and installation estimate for process plant piping was based on factors from MIQM’s historical project costs. These factors were based on a percentage of the mechanical equipment supply price and calculated for each area of the plant. An overall factor of 37% of mechanical equipment supply was adopted.

 

Major pipeline costs for the tailings discharge, decant return, water supply and sewage transfer duties were estimated separately with the pipe supply rate from MIQM’s database for similar projects in West Africa.

 

October 15, 2025Page 225 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Electrical and Instrumentation

 

Electrical and instrument costs were estimated as a factor of the total process plant cost. The capital cost for the high voltage power supply station was provided by Fortuna.

 

Tailings Storage Facility and Water Abstraction & Storage Facilities

 

Knight Piésold provided a detailed bill of quantities as well as design and supervision estimates for the construction of the TSF and associated decant water system. The capital estimate uses rates provided by Knight Piésold’s database of previous projects.

 

For PEA purposes, the cost of the first lift of the TSF with an initial capacity of 12 months was included in the initial capital cost estimate and the remaining lifts were included as sustaining capital.

 

The primary water supply for the project will be sourced from the water storage dam, which will be supplied via an abstraction pipeline from the Falémé River. Knight Piésold provided a detailed bill of quantities, together with design and supervision estimates for the construction of the water storage dam. Alternate water sources from the water harvesting dam and open pit dewatering should be investigated, as these may ultimately negate the need to abstract from the Falémé River. The capital cost estimate uses rates derived from Knight Piésold’s database of comparable projects.

 

Plant Buildings, Camp and Equipment

 

Plant infrastructure buildings were estimated based on MIQM’s database for similar projects.

 

Project Infrastructure

 

The Project infrastructure cost was estimated based on the following:

 

·Infrastructure buildings cost: based on budget pricing obtained by MIQM for projects in West Africa.

 

·Plant access road cost: based on Knight Piésold rates.

 

·Communication cost: based on MIQM’s database for similar projects in West Africa.

 

·Security cost: based on MIQM’s database for similar projects in West Africa.

 

Plant Mobile Equipment

 

The number and type of vehicles/plant in the mobile equipment fleet were nominated by MIQM. All plant and equipment were assumed to be owned and operated by Fortuna apart from the front-end loader to be used for ROM and stockpile rehandling, which will be owned and operated by the mining contractor. The cost estimated pricing is based on MIQM’s database for similar projects in West Africa.

 

Engineering, Procurement and Construction Management (EPCM)

 

The EPCM estimate was established from first principles based on an assessment of person-hours required per EPCM discipline. The EPCM person-hours associated with process engineering, design engineering, drafting, procurement and expediting were developed using MIQM’s database for similar projects.

 

October 15, 2025Page 226 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The project and construction management were estimated as a time-based EPCM cost and were developed using MIQM’s database for similar projects.

 

Current MIQM and ECG Engineering rates were applied to the estimated EPCM person-hours to develop the overall EPCM cost estimate.

 

Temporary Construction Facilities

 

The construction overheads estimate for the Owner’s components of the Project were derived as follows:

 

·Temporary construction facilities cost: estimated by MIQM based on a 0.5% pre-contingency process plant cost.

 

·Temporary construction equipment cost: estimated by MIQM based on a 0.5% pre-contingency process plant cost.

 

Capital Spares

 

Capital spares were estimated as follows:

 

·Capital spares were estimated by MIQM based on 10% of the total mechanical equipment supply cost.

 

·Consumable spares were estimated by MIQM based on 5% of the total mechanical equipment supply cost.

 

·Commissioning spares were estimated by MIQM based on 2.5% of the total mechanical equipment supply cost.

 

First Fills

 

The first fill cost was estimated by MIQM based on 5% of the total mechanical equipment supply cost.

 

Construction Overheads

 

Construction overheads have been based on quotations from MIQM’s database for similar projects in West Africa.

 

In general, the construction overheads represent cost items including:

 

·Mobilization and demobilization of contractors and sub-contractors.

 

·Site establishment and site facilities.

 

·Travel costs for contractors and sub-contractors.

 

·Tools, plant and construction equipment.

 

·Fuel.

 

Owner’s Costs

 

Owner’s costs were provided by Fortuna.

 

Contingency

 

A flat contingency of 20% was applied to the capital cost estimate and totaled approximately US$46.4 million.

 

October 15, 2025Page 227 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Exchange Rates

 

The capital cost estimate is presented in US$. Where cost estimates were included in foreign currencies the exchange rates used are summarized in Table 21.3.

 

Table 21.3 Exchange Rates Used for Capital Cost Estimates

 

Currency Code US Dollar Source and Reference Date
Australian Dollar AUD 0.655 XE September 2, 2025
Euro EUR 1.171 XE September 2, 2025
Canadian Dollar CAD 0.727 XE September 2, 2025
South African Rand ZAR 0.057 XE September 2, 2025
US Dollar USD 1.000 XE September 2, 2025
British Pound GBP 1.354 XE September 2, 2025
Franc CFA CFA 0.002 XE September 2, 2025

 

21.1.4Mine Development

 

Capital mine development costs were derived from the request for pricing process and are estimated at approximately US$19.9 million. These costs include contractor site establishment, mobilization, and pre-stripping activities required to prepare the initial open pits (Area D and Karakara) pits for production.

 

21.1.5Mine Rehabilitation

 

Mine closure costs were attributed to site rehabilitation required to remediate the area where the mine is located and to meet mine closure requirements.

 

21.2Operating Cost Estimates

 

The mining operating costs were developed based on budgetary quotes from reputable mining contractors, all with experience in West Africa, including current operating experience in Senegal, and based on the PEA mine plan for the Diamba Sud Project. The study assumes the mining activities to be executed with a mining contractor at Diamba Sud. The processing operating costs were developed from testwork, first principles and MACA Interquip Mintrex’s database according to typical industry standards applicable to gold processing plants in West Africa. General and administration costs were factored from historical operating cost data from the development and operation of Fortuna’s previously owned Yaramoko Mine in Burkina Faso, Fortuna’s currently owned Séguéla Mine in Côte d’Ivoire, as well as quoted services in Senegal. Operating costs were estimated with an accuracy range of ±25–30%, and were current at Q3, 2025.

 

Direct operating costs are estimated as $51.16/t of material milled or $1,081/oz of gold produced, as summarized in Table 21.4.

 

Table 21.4 Life-of-Mine Operating Costs

 

Operating Cost $M $/t milled $/payable oz
Mining 542 30.54 646
Processing 247 13.91 294
G&A 119 6.70 142
Total operating costs excluding Royalties and Social Fund 908 51.16 1,081
Refining 3 0.14 3
Royalties* 69 3.90 83
Social Fund* 12 0.65 14
Total Operating costs including Royalties and Social Fund 992 55.85 1,180
*The PEA assumes a 3% royalty payable to the State and 0.5% contribution to a Social Development Fund

 

October 15, 2025Page 228 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The calculated operating cost for the processing plant at a design oxide throughput of 2.5 Mt/a is US$11.82/t processed. Mining operating costs are forecast to be $4.82/t mined.

 

The calculated operating cost for the process plant at a design fresh throughput of 2.0 Mt/a is US$14.11/t processed. The mining operating cost forecast is $4.64/t mined.

 

Projected operating costs for the Project are detailed in Table 21.5 (oxide) and Table 21.6 (fresh).

 

Table 21.5 Oxide Mill Feed Material Operating Cost Estimates

 

Area Cost (US$/t Processed) Annual Cost (US$M)
Labor 1.74 4.36
Mobile equipment 0.60 1.49
Power 2.77 6.92
Consumables 5.50 13.76
Maintenance 0.85 2.13
Laboratory 0.36 0.90
Total 11.82 29.56
G&A 5.93 14.83
Owner’s mining 1.14 2.84

 

Table 21.6 Fresh Mill Feed Material Operating Cost Estimates

 

Area Cost (US$/t Processed) Annual Cost (US$M)
Labor 2.18 4.36
Mobile equipment 0.74 1.49
Power 4.95 9.90
Consumables 4.65 9.30
Maintenance 1.14 2.27
Laboratory 0.45 0.90
Total 14.11 28.22
G&A 7.42 14.83
Owner’s mining 1.41 2.82

 

Consumables

 

Reagent consumptions were based on metallurgical testwork, whilst grinding media consumption was advised by Otway based on modelling and mineralization properties from testwork. Reagent and grinding media costs were based on supplier quotes. Crusher wear parts and mill liner consumption rates were advised by Otway, and costs were obtained from the MIQM database.

 

Maintenance

 

Maintenance costs for the plant were factored from installed plant and infrastructure capital costs using industry standard ratios. Maintenance costs were calculated based on 100% fresh feed, with oxide maintenance costs factored at 75%.

 

Mobile Equipment

 

The mobile equipment and light vehicle fleet for Process, maintenance, mining and administration were estimated by MIQM from previous operational experience. The estimate assumes that all vehicles are owned by Fortuna. The cost of fuel was included in the estimate from the annual usage and fuel rate for each vehicle type. Fuel consumptions

 

October 15, 2025Page 229 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

were estimated by MIQM based on vehicle performance specifications and usage hours were assumed.

 

Power

 

Installed power summaries were developed based on equipment selection and installed powers, as detailed in the mechanical equipment list. Operating and load factors were applied to determine the actual power requirements. The cost of power ($0.156/kWh) was provided by Fortuna, and was derived from the installation of a HFO generator-powered powerhouse.

 

Water Supply

 

The operating costs of the water supply and distribution within the plant were included within the power, maintenance and consumables sections.

 

Labor

 

Labor was considered a fixed yearly cost largely independent of processing plant throughput. Plant staffing numbers were applied by MIQM based on similar sized projects in West Africa and advice from Fortuna. The salaries were based on current market knowledge and experience from similar projects. A factor of 1.2 was applied to expatriate base salaries to include an annual pre-tax bonus.

 

General & Administration (G&A) costs

 

G & A costs cover the fixed operational overhead for the planned operation. This includes:

 

·Personnel outside of processing and maintenance.

 

·Site and country office costs.

 

·Insurance.

 

·Contracts for the camp operation, security and logistics.

 

·Flights.

 

·Environmental and corporate social responsibility costs.

 

Personnel salaries were provided by Fortuna, whilst other allowances were estimated by MIQM.

 

Accommodation costs

 

Accommodation and meal costs were estimated annually for all direct Fortuna employees as well as additional security, laboratory, mining, maintenance and village contractors. Camp man-days and casual meals were estimated by MIQM, whilst camp accommodation and meal costs were provided by Fortuna.

 

Laboratory costs

 

A laboratory services fee was estimated from the MIQM database. A monthly fee was incorporated including laboratory repayments, labor, and sample preparation costs.

 

21.2.1Mine Operating Costs

 

Mining operating costs were derived from bids by five experienced West African contractors. Three closely aligned submissions (within ± 2.5% of the midpoint) were selected, resulting in an overall assumed mining operating cost of US$4.82/t mined. This

 

October 15, 2025Page 230 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

operating mining cost excluded capital items such as mobilization, site establishment, pre-stripping, and other one-time development activities.

 

21.2.2Operating Cost Exclusions

 

The processing cost estimate is exclusive of:

 

·Any impact of foreign exchange rate fluctuations.

 

·Escalation from the date of estimate.

 

·Contingency allowance.

 

21.3Sustaining Capital Costs

 

Projected sustaining capital costs for the proposed LOM are summarized in Table 21.7, and total US$48 million.

 

Table 21.7 Summary of projected major sustaining capital costs for the LOM

 

Capital Cost Item (US$M) * Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Mine development (access and haul roads) - 2.1 0.2 - - 0.1 0.3 -
 
Surface water management - 1.0 0.9 - - - 0.3 -
Tailings storage facility 4.5 - 7.3 - 11.7 - 11.1 -
Equipment and infrastructure 4.5 3.1 8.4 - 11.7 0.1 11.7 -
 
Mine closure & site rehabilitation - - 0.6 0.6 0.6 0.6 0.6 5.3
 
Total capital expenditure 4.5 3.1 9.1 0.6 12.3 0.7 12.4 5.3
*Numbers may not total due to rounding

 

Sustaining capital costs included all investments in mine development, equipment and infrastructure necessary to maintain the mine facilities and sustain the continuity of the operation. Sustaining capital costs were split into two main areas; equipment and infrastructure; and mine closure and site rehabilitation.

 

21.3.1Mine Development

 

Mine development included the main development and infrastructure of the mine through the generation of haul and access roads.

 

21.3.2Equipment and Infrastructure

 

Equipment and infrastructure costs were attributed to departments of the mine including surface water management and the TSF.

 

21.3.3Mine Closure and Rehabilitation

 

Mine closure costs were attributed to site rehabilitation costs required to remediate the area where the mine will be located and to meet mine closure requirements.

 

21.4Comment on Section 21

 

The capital and operating cost provisions for the LOM plan that supports the PEA have been reviewed. The basis for the estimates is appropriate for the known mineralization, proposed mining and production schedules, marketing plans, and equipment replacement and maintenance requirements.

 

October 15, 2025Page 231 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The QP considers the capital and operating costs estimated for the Diamba Sud Project as reasonable based on industry-standard practices and estimated costs in 2025.

 

Opportunity exists for Fortuna to explore multiple powerhouse combinations including renewables. The current light fuel oil calculations show a relatively low capital cost yet high operating cost option. A HFO powerhouse presents higher capital cost and low operating cost fuel consumption, whilst investment in renewables subsidizes both options.

 

Expatriate workers were selected at senior level and above. An opportunity exists to lower expatriate personnel throughout the LOM to reduce operating costs and align with government expectations.

 

October 15, 2025Page 232 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

22Economic Analysis

 

The following sub-sections summarize the economic evaluation methodology and results for the Diamba Sud PEA. The PEA is preliminary in nature, includes Inferred Mineral Resources that are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the PEA will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

 

22.1Methodology Used

 

The Diamba Sud Project was valued using a discounted cash flow (DCF) approach with a 5% discount rate, consistent with gold industry practice and peer-company valuation benchmarks. This required projecting monthly cash inflows, or revenues, and subtracting yearly outflows such as operating costs, capital costs, royalties, federal taxes, etc. The resulting net cash flows were discounted back to the date of valuation (start of construction) to determine net present values (NPVs) at the selected discount rates. The internal rate of return (IRR) was calculated as the discount rate that yields a zero NPV.

 

22.2Assumptions

 

Table 22.1 shows the key assumptions used in the economic analysis.

 

Table 22.1 Key Economic Assumptions

 

Parameter Units Value
Gold Price $/oz 2,750
Mill Recovery % 90
Power Price $/kWh 0.16
Base Case Discount Rate % 5
Exchange Rate    
      West African Franc to US dollar x 0.0017
Royalty    
      Government % 3.0
      Social Fund % 0.5
Investment Tax Credit % 40

 

The State of Senegal is entitled to a 10% free-carried interest in Boya upon the granting of the exploitation permit (with the right for the State to acquire an additional contributory interest of up to 25%); however, all economic analysis is presented on a 100% project basis.

 

The PEA assumes the amount of royalties and taxes payable to the State, including that the royalty payable on production to the State is 3% and that the investment tax credit is 40%, in accordance with the provisions of the Mining Convention between Boya and the State of Senegal dated April 8, 2015, and the Mining Code of 2003. It should be noted, however, that the State retains the sovereign prerogative to review or revisit certain fiscal terms during the exploitation permit approval process, and as such, the current framework may be subject to amendment.

 

October 15, 2025Page 233 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

22.3Summary

  

The results of the economic analysis are shown in Table 22.2. All monetary amounts are presented in US dollars (US$), unless otherwise specified.

 

Table 22.2 Preliminary Economic Assessment Summary

 

Metrics Units Results
Gold Price $/oz 2,750
Life of mine years 8.1
Processing Duration years 7.9
Total mineralized material mined kt 17.8
Contained gold in mineralized material mined koz 932
Strip ratio Waste: Mineralized material 5.5
Throughput initial 3 years (primarily oxide) Mtpa 2.5
Throughput after 3 years (primarily fresh) Mtpa 2.0
LOM grade g/t 1.63
Recoveries % 90
Gold production    
Total production over LOM koz 840
Average annual production over LOM koz 106
Average annual production over first 3 years koz 146
Per Unit Costs LOM    
Mining $/t, mined 4.82
Processing $/t, processed 13.9
G&A $/t, processed 6.7
Cash costs 1    
Average operating cash costs over LOM $/oz 1,081
Average operating cash costs over first 3 years $/oz 759
AISC 1    
Average AISC over LOM $/oz 1,238
Average AISC over first 3 years   $/oz 904
Capital costs    
Initial capital expenditure $M 283
Sustaining capital expenditure + infrastructure (includes closure costs) $M 48
Returns    
NPV5%, pre-tax (100% Project basis) $M 772
Pre-tax IRR % 86
NPV5%, after-tax (100% Project basis) $M 563
After-tax IRR % 72
After Tax Payback Period years 0.8
     
Annual EBITDA 1    
Average EBITDA over LOM $M 167
Average EBITDA over first 3 years   $M 277

 

Note: (1)  This is a non-IFRS financial measure. The definition and purpose of this non-IFRS financial measure is included under the heading “Cautionary Note on Non-IFRS Measures” in this Report. Non-IFRS financial measures have no standardized meaning under IFRS and therefore, may not be comparable to similar measures presented by other issuers.

 

·The pit optimization shells used for the mine plan were generated using a gold price of $2,300 per ounce.
·Average operating cash costs and average AISC represent costs for projected production for the LOM at the time of gold sales.
·The PEA is presented on a 100% project basis. However, upon the granting of the exploitation permit, the State of Senegal is entitled to a 10% free-carried interest Boya, with the right for the State to acquire an additional contributory interest of up to 25%.

 

October 15, 2025Page 234 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·The economic analysis was carried out using a discounted cash flow approach on a pre-tax and after-tax basis, based on the gold price of $2,750/oz.
·The IRR on total investment that is presented in the economic analysis was calculated assuming a 100% ownership in Diamba Sud.
·The NPV was calculated from the after-tax cash flow generated by the Project, based on a discounted rate of 5% and an effective date of October 10, 2025.
·The PEA assumes that the percentage of certain royalties and taxes payable to the State, the percentage of the investment tax credit available to the company and the percentage payable to the social development fund will be in accordance with the provisions of the Mining Convention between Boya S.A. and the State of Senegal dated April 8, 2015. It should be noted, however, that the State retains the sovereign prerogative to review or revisit certain fiscal terms during the exploitation permit approval process, and as such, the current framework may be subject to amendment.
·The PEA is preliminary in nature, and it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and, as such, there is no certainty that the PEA results will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability

 

The pre-tax net present value with a 5% discount rate (NPV5%) is $772 million and the IRR is 86% using a base gold price of $2,750/oz. The economic analysis assumes that Fortuna will provide all development funding via inter-company and shareholder loans to the mine operating entity, which will be repaid with interest from future gold sales.

 

The post-tax Project NPV5% is $563 million, with an IRR of 72% and a payback period of less than one year at a gold price of $2,750/oz. The payback period is defined as the time after process plant start-up that is required to recover the initial expenditures incurred developing the Diamba Sud Project.

 

The cashflow analysis was prepared on a constant 2025 US dollars basis. No inflation or escalation of revenue or costs were incorporated.

 

22.4Forecast Production and Mill Feed

 

The annual mine production and mill feed schedule is shown in Figure 22.1. LOM mill feed totals 17.8 Mt material at an average gold grade of 1.6 g/t Au.

 

Figure 22.1 Diamba Sud PEA Production Profile

 

 

 

Figure prepared by Fortuna, 2025

 

October 15, 2025Page 235 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The Diamba Sud Project will consist of the concurrent exploitation of multiple deposits, including Area D, Area A, Karakara, Western Splay, Kassassoko, Southern Arc and Moungoundi deposits. The overall strategy is to have staged overlapping production from these deposits to achieve a total production rate of 2.5 Mt/a during initial high oxide throughput (three years) and 2.0 Mt/a thereafter. A mineralized material stockpile will be maintained throughout the mine life. The stockpile size averages about seven months of production serving as a buffer between mining and process plant operation and also as storage for lower grade material to be processed later in the mine life. Table 22.3 includes annual estimates of recovered gold, based on the projected overall process recovery estimate of 90% presented in Section 13. Recovered gold is estimated to total 840 koz over the mine life, for an average of 106 koz per year over the 7.9-year processing period (not to be confused with the 8.1 years mining period that takes into account preproduction).

 

Table 22.3 Estimate of Recovered Gold for Diamba Sud Project

 

Parameter Units LOM
Total
Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Tonnes mined kt 17,754 90 2,845 3,585 2,847 1,925 1,931 2,373 1,862 296
Tonnes milled kt 17,754 - 2,354 2,500 2,500 2,225 2,111 2,030 2,213 1,821
Gold mill feed grade g/t 1.6 - 2.62 2.04 1.53 1.55 1.72 1.62 1.03 0.70
Gold recovery % 90 - 93 92 86 88 90 92 88 87
Gold recovered koz 840 - 184 151 106 98 105 97 64 35

 

22.5Cost Estimates

 

22.5.1Capital and Operating Costs

 

Capital and operating cost estimates are presented in Section 21 of this Report. Initial capital is estimated at $283.2 million (including 20% contingency) with an additional $48 million of sustaining capital and closure costs over the 8.1 year LOM.

 

LOM total operating costs average $55.85/t milled.

 

The electricity price is based on a self-owned power plant running on heavy fuel oil diesel and assume power is solely provided from the power plant.

 

22.5.2Closure and Salvage Value

 

Total mine closure cost is estimated at US$12.3 million.

 

No allowances for salvage value of process plant equipment or other equipment and facilities are included in the project economic evaluation.

 

22.5.3Working Capital

 

Working capital requirements are calculated as the difference between the timing of payments on expenses (payables) and receipt of funds from product sales (receivables).

 

Assumptions on all receivables are 100% of funds received on shipment, with shipment assumed to occur in the month of production. All costs are assumed to be paid in the period incurred.

 

22.5.4All-in Sustaining Unit Cost Estimates

 

Estimated unit costs, based on World Gold Council non-generally accepted accounting (GAAP) metrics, are summarized in Table 22.4. The Project is expected to produce gold at an average all-in sustaining cost of $1,238/oz of payable gold.

 

October 15, 2025Page 236 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 22.4 Life of Mine All-in Sustaining Cost and All-in Cost

 

Parameter $M $/t milled $/payable oz
Operating cost      
Mining 542 30.54 646
Processing 247 13.91 294
G&A 119 6.70 142
Subtotal, direct operating costs 908 51.16 1,081
Refining 3 0.14 3
Royalties 69 3.9 83
Social Fund 12 0.65 14
Total operating costs1 992 55.85 1,180
Sustaining capital, and reclamation        
Sustaining capital 40 2.23 47
Closure Fund 8 0.48 10
All-in sustaining cost1 1,040 58.56 1,238

 

Note: (1) Cash costs and AISC per payable ounce of gold sold are non-IFRS financial measures. Please see “Cautionary Note Regarding Non-IFRS Measures”.

 

22.6Taxes and Royalties

 

Several taxes and royalties are included in the economic evaluation.

 

22.6.1Government Royalty

 

The State of Senegal is entitled to assess a gross revenue royalty on production from gold projects. Based on the tax stability provisions in Boya’s current Mining Convention signed with the State in 2015, and the provisions of the 2003 Mining Code, a royalty rate of 3% is payable on gold sales. It should be noted, however, that the State retains the sovereign prerogative to review or revisit certain fiscal terms during the exploitation permit approval process, and as such, the current framework may be subject to amendment.

 

22.6.2Social Fund

 

Under the 2016 Mining Code, the government of Senegal established a community development fund to be financed in part by assessing a gross revenue royalty of 0.5% to holders of an exploitation license.

 

22.6.3Duties and Levies

 

The Government of Senegal assesses customs duties (10%) and other levies (totaling 5%) on imported goods. During the development phase and initial investment period, the holder of an exploitation permit is exempt from customs duties, including value-added tax (VAT), on the importation of machinery, materials, equipment, and spare parts included in the approved program and directly and definitively intended for mining operations. Operating and capital cost estimates include allowances for government duties and levies. Under Boya’s current Mining Convention, the Project is exempt from customs duties for seven years and benefits from a two-year suspension of VAT.

 

22.6.4Value Added Tax

 

Senegal has a VAT rate currently set at 18%. The holder of an exploitation permit is exempted from VAT on its imports and foreign services, the purchase of goods and services in the Senegal and on sales in connection with the mining operations up to the date of the first commercial production. A detailed estimation of VAT for each non-fuel item has not been completed for PEA purposes. For the purposes of the cash flow

 

October 15, 2025Page 237 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

analysis, it was assumed that VAT is applicable on 2% of the sustaining capital and costs and 1% of the G&A costs and assumed to be refunded two months after it is paid.

 

22.6.5Corporate Income Tax

 

A federal tax rate of 30% is applicable on income after deductions for gold mining projects in Senegal. Deductions from income for estimating income subject to income tax include the following items:

 

Depreciation

 

In this assessment, development and facilities are depreciated using a unit of production method. Depreciation commences once the facilities are placed into service and the mine and mill are operating. Using this approach, equipment and facilities are fully depreciated over the mine life.

 

Carry Forward Costs

 

Sunk exploration and other eligible project costs can be carried forward and deducted from income via depreciation.

 

Mine operating losses can also be carried forward and deducted from income in future years

 

Investment Tax Credit

 

An Investment Tax Credit amounting to 40% of upfront capital has also been assumed in line with Boya’s Mining Convention with Senegal. The credit is available for a 5-year period after the start of operations and is subject to an annual cap of 50% of taxable income.

 

Other Deductions

 

Other deductions from income for the purpose of estimating income subject to tax include management fees and interest expenses.

 

22.6.6Withholding Taxes

 

The government of Senegal assesses withholding taxes of 16% on interest income and 10% on dividends.

 

22.7Government-Carried Interest

 

Under the mining code of Senegal, the State is entitled to a 10% free carried interest in the project upon formal award on an exploitation permit, with the right for the State to acquire an additional contributory interest of up to 25%t. The State’s interest has been modelled in accordance with the following:

 

·Fortuna holds 90% and the government of Senegal holds10% of the shares of Fortuna’s in country operating entity, Boya.

 

·Fortuna’s sunk costs and funds provided to develop the mine will be booked as a shareholder loan to the operating company, to be repaid with interest out of available cash flow.

 

·The remaining operating company cash flow after sustaining capital requirements and shareholder loan repayments have been met will be distributed to the two shareholders in the form of dividends, with 10% of the dividends going to the government of Senegal and 90% to Fortuna.

 

October 15, 2025Page 238 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Dividends and interest received by Fortuna will be subject to Senegal withholding taxes.

 

22.8Economic Results

 

The pre-tax net present value with a 5% discount rate (NPV5%) is $772 million and with an IRR of 86% using a base gold price of $2,750/oz.

 

The post-tax Project NPV5% is $563 million, with an IRR of 72% and a payback period of less than one year at a gold price of $2,750/oz.

 

Detailed cash flow estimates by year are presented in Table 22.5.

 

October 15, 2025Page 239 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Table 22.5 PEA Cash Flow Estimate

 

Parameter Units LOM Total Year -1 Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8
Production                        
Tonnes mined kt 17,754   90 2,845 3,585 2,847 1,925 1,931 2,373 1,862 296
Tonnes milled kt 17,754   - 2,354 2,500 2,500 2,225 2,111 2,030 2,213 1,821
Gold mill feed grade g/t 1.6   - 2.62 2.04 1.53 1.55 1.72 1.62 1.03 0.70
Gold recovery % 90%   - 93 92 8% 88 90 92 88 87
Gold recovered koz 840   - 184 151 106 98 105 97 64 35
Gold Revenue                        
Gold price $/oz 2,750   2,750 2,750 2,750 2,750 2,750 2,750 2,750 2,750 2,750
Gold sales koz 840   - 183 151 106 97 106 97 64 36
Gold Sales Revenue $M 2,310   - 503 415 292 267 292 267 176 99
Operating Costs                        
Mining $M (542) - - (81) (88) (93) (91) (76) (55) (51) (6)
Processing $M (247) - - (30) (31) (31) (32) (32) (32) (32) (28)
G&A $M (119) - - (16) (16) (16) (16) (16) (16) (14) (9)
Gold refining $M (3) - - (1) (0) (0) (0) (0) (0) (0) (0)
Total operating costs excluding royalties and social fund $M (911) - - (128) (136) (141) (139) (124) (103) (97) (43)
Royalties $M (69) - - (15) (12) (9) (8) (9) (8) (5) (3)
Social fund $M (12) - - (3) (2) (1) (1) (1) (1) (1) (0)
Total operating costs including royalties and social fund $M (992) - - (145) (150) (151) (149) (134) (113) (103) (46)
Capital and Closure Costs                        
Development capital $M (283) (52) (231) - - - - - - - -
Sustaining capital $M (40) - - (5) (3) (8) - (12) (0) (12) -
Closure Fund $M (8) - - (1) (1) (2) (2) (2) (2) (2) 2
Total Capital and Closure Costs $M (331) (52) (231) (6) (4) (10) (2) (13) (2) (13) 2
Project Valuation                        
Project net cash flow, pre-tax $M 987 (52) (231) 352 261 130 116 144 152 60 55
NPV5% $M 772                    
IRR % 86                    
Payback period years 0.8                    
Project net cash flow, after-tax $M 728 (52) (231) 352 196 59 80 122 120 28 53
NPV5% $M 563                    
IRR % 72                    
Payback period years 0.8                    

 

October 15, 2025Page 240 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

22.9Sensitivity Analysis

 

The Diamba Sud Project contemplated in the PEA demonstrates strong economic performance across a range of variables. Estimated NPV sensitivities for key operating and economic metrics are presented in Table 22.6, Table 22.7, and Table 22.8.

 

Like most gold mining projects, the key economic indicators of NPV5% and IRR are most sensitive to changes in gold price. A $250/oz reduction in the gold price reduces Fortuna’s after-tax NPV5% by $119 million and the IRR by 13%. A $250/oz increase in the gold price increases Fortuna’s NPV5% by $119 million and the IRR by 13%.

 

Table 22.6 After-Tax NPV Sensitivity to Discount Rate and Gold Price ($M)

 

    Gold Price ($/oz)
    2,250 2,500 2,750 3,000 3,250 3,500 3,750
Discount Rate 3% $362 $494 $622 $750 $878 $1,007 $1,134
5% $322 $444 $563 $682 $800 $919 $1,037
7% $287 $400 $511 $621 $731 $841 $951

 

Table 22.7 After-Tax IRR Sensitivity to Gold Price

 

    Gold Price ($/oz)
    2,250 2,500 2,750 3,000 3,250 3,500 3,750
IRR 45% 59% 72% 85% 97% 109% 121%

 

Table 22.8 After-Tax NPV5% Sensitivity to Capital Costs and Operating Costs ($M)

 

    Operating Costs
    -25% -10% 0% 10% 25%
Capital Costs -25% 744 663 608 554 472
-10% 717 636 581 527 443
0% 700 618 563 509 424
-10% 682 600 545 490 405
-25% 655 573 518 462 376

 

The sensitivity of the after-tax NPV5% of the project to changes in the key operating parameters of gold price, capital costs, operating costs, grade and recovery are shown in Figure 22.2. Similarly, the after-tax IRR of the project changes in the key operating parameters are shown in Figure 22.3. The sensitivity results due to a parameter change assume the remaining parameters remain unaffected.

 

October 15, 2025Page 241 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Figure 22.2 After-Tax NPV5% Sensitivities to Key Input Parameters

 

 

 

Figure prepared by Fortuna, 2025

 

Figure 22.3 After-Tax IRR Sensitivity to Key Input Parameters

 

 

 

Figure prepared by Fortuna, 2025

 

October 15, 2025Page 242 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The project IRR is most sensitive to changes in revenue parameters (i.e. gold price and gold grade) and operating costs, while changes to recovery and capital costs are secondary.

 

22.10Comment on Section 22

 

The economic analysis was conducted using a discounted cash flow methodology following standard industry practices and shows that the project is potentially economically viable.

 

October 15, 2025Page 243 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

23Adjacent Properties

 

This section is not relevant to this Report.

 

October 15, 2025Page 244 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

24Other Relevant Data and Information

 

This section is not relevant to this Report.

 

October 15, 2025Page 245 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

25Interpretation and Conclusions

 

25.1Mineral Tenure, Surface Rights, Royalties and Agreements

 

Fortuna was provided with a legal opinion that supports that the mining tenure held by Boya for the Diamba Sud Project is valid and that Fortuna has a legal right to explore the property.

 

The Diamba Sud concession is an Exploration Permit (Permis de Recherche) granted in June 2015 under the 2003 Mining Code and was last renewed on June 9, 2021, for a period of three years, being the third and final renewal which expired on June 9, 2024. However, Boya has obtained a special two-year retention period to complete the works necessary for a preliminary economic assessment of the project and to conduct environmental studies required for the application for a mining license. This retention is valid until June 21, 2026, and requires the submission of a request for a mining license before this date.

 

The permit comprises two blocks, the northern block, DS1 is approximately 46.56 km2 and the southern block, DS2, some 20 km to the south is approximately 6.31 km2, for a total permit area of 53.46 km2.

 

Mineral exploration permits, within their boundaries, entitle the holder exclusive surface rights to explore for the nominated mineral commodities specified (in this case, gold), as well as encumbrance-free disposal of materials extracted during exploration process. Such permits allow for beneficial ownership to be held by a foreign entity.

 

Boya has full and unrestricted surface rights to the land covered by the exploration permit. The perimeter of the exploration permit is free to access and is not subject to any kind of restriction.

 

The Diamba Sud Project is not subject to any back-in rights, liens, payments or encumbrances.

 

There are royalties attached to the mineral concessions, however, the only royalties that affect the Mineral Reserves and have been considered in the economic analysis are:

 

·A 3% royalty to the State of Senegal on the gross revenue from gold production, with deductions allowed for transportation and refining costs.

 

·A local contribution royalty of 0.5% also calculated after deductions allowed for transportation and refining costs.

 

25.2Geology and Mineralization

 

The Diamba Sud Project is located within the Loulo Mining district of the WAC.

 

Exploration has identified several prospects where gold mineralization has been identified at surface and through exploration drilling. This includes Area A, Area D, Karakara, Kassassoko, Western Splay, Moungoundi, and Southern Arc deposits.

 

Mineralization at Diamba Sud is classified as Birimian style mesothermal orogenic gold deposits. Although not formally classified as such, the gold deposits of Diamba Sud show similarities to the post-collisional, atypical orogenic Loulo/Falémé-style deposits. This tentative classification is based on the correlation between the mineral assemblages, geochemistry and the structural and lithological controls on mineralization with that of the nearby deposits classed as the same type which sit in close proximity to the SMSZ.

 

October 15, 2025Page 246 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

25.3Exploration, Drilling and Analytical Data Collection in Support of Mineral Resource Estimation

 

Drill holes drilled under Boya management in the period 2015 to 2025 have data collected using industry-standard practices. Drill orientations are appropriate to the orientation of mineralization and core logging meets industry standards for exploration of mesothermal orogenic gold deposits.

 

Geotechnical logging is sufficient to support Mineral Resource estimation and a PEA study level assessment.

 

Collar and downhole surveys have been conducted using industry-standard instrumentation. Any uncertainties in survey information have been incorporated into subsequent resource confidence category classification.

 

All collection, splitting, and bagging of chip and core samples were carried out by Boya personnel since 2015 representing all of the information collected at the project. No material factors were identified with the drilling programs that could affect Mineral Resource estimation.

 

Sample preparation and assaying for samples that support Mineral Resource estimation have followed approximately similar procedures for most drill programs since 2015. The preparation and assay procedures are adequate for the type of deposit and follow industry standard practices.

 

Sample security procedures met industry standards at the time the samples were collected. Current core and chip sample storage procedures and storage areas are consistent with industry standards.

 

25.4Data Verification

 

Site visits were completed. The QPs individually reviewed the information in their areas of expertise, and concluded that the information supported Mineral Resource estimation, and could be used in mine planning and in the preliminary economic analysis that supports the PEA.

 

25.5Metallurgical Testwork

 

Metallurgical testing was performed at the ALS Metallurgy laboratory in Perth, Western Australia, Australia under the supervision of Fortuna, and Mintrex/MIQM. The testwork program(s) expanded upon earlier work to include additional comminution, cyanidation, rheology and recovery testing on samples from the seven deposits, Area A, Area D, Karakara Western Splay and Kassassoko, Southern Arc and Moungoundi, weighted in accordance with the anticipated portion of mill feed each deposit contributes over the LOM. A testwork program was also conducted to further investigate the effect of oxygen injection on leaching.

 

The testwork showed that leaching is substantially complete within 24 hours and that there is no apparent preg-robbing of dissolved gold from solution. Testing has shown that over 90% of the material fed to the plant is non-refractory. Area D fresh material, which comprises 9% of total mineralized material feed to the plant, has a slightly lower process recovery (averaging 85%). Bulk Mineralogical Analysis (BMA) testwork indicated that gold in this Area D fresh material is ultra-fine and locked within albite and sulfides.

 

October 15, 2025Page 247 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The material tested across all deposits exhibited limited grind sensitivity with an optimal grind size of 106 µbeing confirmed for all extraction testwork. The results of that program were very encouraging, indicating free milling of the material with good leach kinetics and overall recoveries averaging 90%.

 

Comminution testwork including BWI, CWi, Ai, SMC, and UCS tests were conducted and confirmed the PEA findings of all previous testwork.

 

25.6Mineral Resource Estimation

 

The 2025 Mineral Resource estimate used RC and DD drill hole sample information obtained by Boya since 2015. Mineralized domains identifying potentially economically extractable material were modeled for each vein and used to code drill hole intervals for geostatistical analysis, block modeling and grade interpolation by ordinary kriging or inverse distance weighting.

 

Mineral Resources are reported based on open pit mining within SMU block sizes based on estimated operational costs and mining equipment sizes using cut-off grades in the block model calculated based on projected long-term metal prices, metallurgical recoveries, and operational costs. Mineral Resources have been reported above a gold cut-off grade of 0.31 g/t for oxide material and a variable gold cut-off grade ranging 0.35 to 0.42 g/t depending on the deposit.

 

Mineral Resources are categorized as Indicated or Inferred. The criteria used for classification includes the number of samples, spatial distribution, distance to block centroid, KE and ZZ.

 

Mr. Chapman is of the opinion that the Mineral Resources have been estimated using standard industry practices.

 

Furthermore, it is the opinion of Mr. Chapman that by the application of projected long-term gold prices, the average metallurgical recovery, as well as constraining the Mineral Resources to those SMU blocks inside an ultimate pit shell that accounts for projected operating costs, mining dilution and operational dilution, the Mineral Resources have ‘reasonable prospects for eventual economic extraction’.

 

25.7Mine Plan

 

The Diamba Sud Project is planned as the simultaneous development of multiple deposits, including Area A, Area D, Karakara, Western Splay, Kassassoko, Moungoundi, and Southern Arc, with no more than three pits mined at any one time. The production strategy targets an initial throughput of 2.5 Mtpa during the first three years, supported by the high oxide content at Area D, before transitioning to a sustained rate of 2.0 Mtpa from year four onwards as the feed becomes predominantly fresh material. The PEA contemplates a total mine life of 8.1 years. The pit optimization shells used for the mining inventory were generated in Deswik software using a gold price of US$2,300 per ounce and a revenue factor of 1.0. Optimization parameters incorporated are government royalties, refining, mining costs, processing costs, and G&A costs to ensure realistic pit designs and economic assumptions.

 

Mining activities at Diamba Sud will use conventional open-pit mining methods. Drill and blasting are planned for oxide and fresh mineralized material, followed by conventional truck and shovel operations within the pits for the movement of mineralized material and waste.

 

October 15, 2025Page 248 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Three 200 t class excavators, complimented with one 120 t class and one 80 t class excavators in the latter stages of the LOM when smaller pits Kassassoko, Western Splay and Moungoundi are being mined, with an estimated total material productive capacity of approximately 20.0 Mtpa, will have sufficient capacity to allow for maintenance, transport between the pits, and make-up capacity to account for low productivity periods such as high rainfall events. A fleet of up to twenty Caterpillar 777 trucks (payload of 90 t) will be used in conjunction with several smaller articulated trucks (payload of 45 t) for the latter stages of the satellite pits to truck and haul all mineralized and waste material. Fortuna will engage a mining contractor for operations. A common pool of equipment will be used and scheduled across all active pits so that movement between the pits is minimized.

  

25.8Recovery

 

The Diamba Sud process plant design is based on a metallurgical flowsheet envisioned for the production of gold doré at optimum recovery while minimizing initial capital expenditure and operating costs. The flowsheet comprises a conventional crushing, milling, gravity recovery, CIL, carbon elution and gold recovery circuit.

 

The process requirements are well understood.

 

25.9Infrastructure

 

Mine and process infrastructure and supporting facilities are included in the general layout and will meet the needs of the mine plan and production rate envisaged in this Report:

 

·The Diamba Sud Project is located in the Kédougou region at the southeast corner of Senegal approximately 665 km southeast of Dakar, the capital of Senegal.

 

·The mine site area to be enclosed in the site perimeter fence will be 1,720 ha.

 

·The construction of one TSF located in the north of the DS1 tenement, approximately 5 km north of the process plant is designed based on the 2024 plant treatment capacity of 2.5 Mtpa in the initial 3 years and 2.0 Mtpa on average for the remaining life of the mine.

 

·Power demand on the operations is approximately an average of 10.0 MW provided from generators on site.

 

·Water demand at the Diamba Sud Project is estimated at 66 L/s under average conditions. Approximately 80% of the water in the slurry deposited into the TSF can be recovered from the TSF and pumped back to the plant for reuse in the process. Additional make-up water for the plant will be sourced from open pit dewatering and Falémé River abstraction as required. The next phase of the project will investigate the option of a water harvesting dam in the Gamba Gamba creek to remove the requirement of water abstraction from the Falémé River.

 

25.10Markets and Contracts

 

No market studies have been performed as a component of this PEA; however Fortuna has sold gold doré from West Africa since 2020 and is familiar with selling this product.

 

October 15, 2025Page 249 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

There are no sales contracts on the Diamba Sud Project. Diamba Sud will produce gold doré, which is readily marketable on an ‘ex-works’ or delivered basis to several refineries in Europe and Africa. There are no indications of the presence of penalty elements that may impact on the price or render the product unsalable.

 

The QP has reviewed the information provided by Fortuna on metal price projections and exchange rate forecasts and notes that the information provided support the assumptions used in this Report and is consistent with the source documents, and that the information is consistent with what is publicly available within industry norms.

 

25.11Environmental, Permitting and Social Considerations

 

The Diamba Sud Project is currently held under an exploration permit due to expire in June 2026. An exploitation permit application is expected to be submitted before the end of February 2026. The Terms of Reference, which are a prerequisite for submitting the ESIA, were accepted in May 2025, with the ESIA subsequently submitted October 6, 2025. With these milestones achieved, the project remains on track to secure the necessary approvals for exploitation in 2026, aligning with Fortuna’s anticipated construction decision.

 

With careful implementation of the environmental and social management measures such as the social and environment management and monitoring plan, the livelihood restoration program, and the biodiversity action plan, the Project is expected to be developed in a way which provides compliance to local regulation, alignment with international industry standards and a net socio-economic benefit to local communities and to Senegal without compromising the integrity of the broader environment. The ESIA that will be approved by the Government will define the final measures to be implemented to manage the risks associated with the Project.

 

25.12Capital and Operating Costs

 

The capital required to develop Diamba Sud is estimated to be $283.2 million (including $4 million of capitalized closure costs put in escrow and $46.4 million contingency) with sustaining capital representing an additional $40 million directly related to mining operations, processing and infrastructure sustaining capital, and an additional $8 million of closure costs over the eight year mine life. The mining pre-production capital relates to mining activities prior to commissioning of the processing facility, where 90,000 t of potentially mineralized material and 2.3 Mt of waste are mined in order to establish a reasonable stockpile ahead of processing operations commencing. All contractor mobilization and setup costs are included in the pre-production capital allowance.

 

The processing plant capital relates to a facility with a nameplate throughput of 2.0 Mtpa, designed to accommodate up to 2.5 Mtpa during the initial high-oxide years. The capital cost estimate is based on an EPCM implementation approach. The capital cost for the processing plant considered in this study was based on actual pricing from reputable suppliers for major mechanical equipment. In addition, other equipment and materials pricing was based on the consultants’ databases from similar scale projects in the region and considered representative for Diamba Sud.

 

Operating costs, which include mining, processing and general and administrative costs, are estimated to be US$51.16/t milled or US$1,081 per payable ounce of gold sold over the eight-year operating plan in the PEA. AISC, which includes sustaining capital, reclamation, royalties, and refining costs, total US$1,238 per payable ounce of gold sold over the eight-year operating plan in the PEA.

 

October 15, 2025Page 250 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

The mining operating costs were developed based on budgetary quotes from reputable mining contractors, all with experience in West Africa, including current operating experience in Senegal, and based on the PEA mine plan for the Diamba Sud project. The study assumes the mining activities to be executed with a mining contractor at Diamba Sud. The processing operating costs were developed from testwork, first principles and MACA Interquip Mintrex’s database according to typical industry standards applicable to gold processing plants in West Africa. General and administration costs were factored from historical operating cost data from the development and operation of Fortuna’s previously owned Yaramoko Gold Mine in Burkina Faso, Fortuna’s currently owned Séguéla Mine in Côte d’Ivoire, as well as quoted services in Senegal. Operating costs were estimated with an accuracy range of ±25–30%, and were current at Q3, 2025.

 

The capital and operating costs estimated for the Diamba Sud Project are reasonable, and are based on industry-standard practices.

 

25.13Economic Analysis

 

The Diamba Sud Project has been evaluated on a discounted cash flow (“DCF”) basis. The results of the analysis show the project to be economically very robust. The pre-tax net present value with a 5% discount rate (NPV5%) is $772 million and with an IRR of 86% using a base gold price of $2,750/oz. The economic analysis assumes that Fortuna will provide all development funding via inter-company and shareholder loans to the mine operating entity, which will be repaid with interest from future gold sales.

 

Post-tax Project NPV5% is $563 million, with an IRR of 72% and a payback period of less than one year at a gold price of $2,750/oz. Payback period is defined as the time after process plant start-up that is required to recover the initial expenditures incurred developing the Diamba Sud Project.

 

25.14Risks and Opportunities

 

A number of opportunities and risks were identified by the QPs during the evaluation of the Diamba Sud Project.

 

Opportunities include:

 

·Ongoing work aimed at optimizing the process flowsheet to enhance recoveries and operating efficiencies.

 

·Significant exploration upside following the initial resource estimates at Moungoundi and Southern Arc.

 

·Untested prospective targets across the broader Diamba Sud tenement package.

 

·Ongoing geological interpretation and modelling to improve understanding of the Diamba Sud deposits and to identify additional drill targets.

 

·Evaluation of a hybrid solar power system that could reduce operating costs and lower the project’s environmental footprint.

 

·Ongoing optimization of mine design and scheduling to potentially enhance operational efficiency.

 

·Opportunities to further reduce capital and operating costs through detailed engineering and optimization studies.

 

October 15, 2025Page 251 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Opportunity to enhance the socio-economic impacts of the Project by developing partnerships with local institutions, such as for local employment, and by further optimizing the design of the Project to reduce the impacts on the environment, such as greenhouse gas (GHG) emissions and footprint on critical habitats.

 

Risks include:

 

·Local Content Compliance: The evolving implementation of Senegal’s local content regulations may affect contracting and recruitment. Mitigation includes regular engagement with authorities, maintaining strong relationships with relevant government parties, dedicated local content specialists, and early alignment of procurement and staffing strategies to ensure compliance.

 

·Material Cost Increases and Inflation: Global inflation and supply chain pressures could impact capital and operating costs. Mitigation includes proactive cost tracking, early contractor engagement, and appropriate contingencies within cost estimates. Advancing detailed mining studies and investment decision timeline is also expected to help limit exposure to inflationary pressures.

 

·Long Lead Times for Critical Equipment: Extended procurement and delivery times for key mechanical and power generation equipment pose schedule risks. Mitigation measures include early identification, prioritization, and ordering of long-lead items during future more detailed studies.

 

·Taxes and Royalties: Certain taxes and royalties included in the economic analysis have been based upon the provisions included in the Mining Convention between Boya and the State of Senegal dated April 8, 2015, and the Mining Code of 2003. It should be noted, however, that the State retains the sovereign prerogative to review or revisit certain fiscal terms during the exploitation permit approval process, and as such, the current framework may be subject to amendment.

 

·Interest of the State: The State of Senegal is entitled to a 10% free-carried interest in Boya upon the granting of the exploitation permit, with the right for the State to acquire an additional contributory interest of up to 25%. There can be no assurance that the State will not increase its interest above 10%. The economic analysis in this Report is presented on a 100% project basis.

 

October 15, 2025Page 252 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

26Recommendations

 

26.1Overview

 

The following recommendations outline the key activities required to advance the Diamba Sud Project from the PEA to a more advanced study level. The focus is on resource expansion and infill, technical de-risking, design optimization, and confirmation of environmental, permitting, and social frameworks. The next phase of work is broken into activities relating to exploration, growth and infill, and those optimizing and advancing technical studies to support project development. All recommended programs are independent and may be executed concurrently unless otherwise stated.

 

26.2Exploration

 

An exploration and infill drilling program is recommended to expand the existing deposits that have not been fully defined and potentially support upgrading of Inferred Mineral Resources to Indicated Mineral Resources.

 

Key priorities for the exploration program include:

 

·Ongoing step-out and expansion drilling at the Southern Arc and Moungoundi deposits.

 

·Continued infill drilling at the Moungoundi, Southern Arc, Area A, Area D and Karakara deposits to potentially support upgrades in Mineral Resource classification and improve geological confidence.

 

·Continuing regional auger, geochemical, and geophysical surveys across the Diamba Sud permit to generate new drill targets.

 

·Detailed structural mapping and surface sampling of untested high-priority targets to refine the geological model and guide future drill programs.

 

The budget to execute the exploration and infill program is estimated at approximately US$10.1 million based on current contracted drill rates and in-country expenses. The program for 2026 will include, but not be limited to:

 

·11,300 m of infill and resource extension drilling (RC and core) across the Project area, guided by the next iteration of Mineral Resource estimation and provision for advancing emerging prospects.

 

·24,000 m of target generation RC and core drilling at Southern Arc, Gamba Gamba Moungoundi North, and other emerging targets generated from 2025 auger and geophysical campaigns, as well as deep stratigraphic diamond core drilling to validate certain geological concepts and to examine likely geological targets for future underground mining potential.

 

26.3Geotechnical

 

Recommendations to improve geotechnical data confidence and support pit design optimization for the Western Splay, Kassassoko, Southern Arc, and Moungoundi pits as follows:

 

·Undertake a dedicated geotechnical-specific drilling program, including the infill of selected resource drill holes, to obtain representative geotechnical data across key deposit areas.

 

October 15, 2025Page 253 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

·Conduct geotechnical logging at the drill rig to minimize mechanical breakage and preserve core integrity during handling and transport.

 

·Collect geotechnical samples for laboratory testing (direct shear on natural joints, unconfined compressive strength, tensile compressive strength, Brazilian, and undrained triaxial tests) to characterize joint and intact rock strengths, as well as saprolite behavior.

 

·Perform point load index testing in fresh zones to improve understanding of variability in rock strength.

 

·Install piezometers or standpipes to monitor and quantify hydrogeological conditions within pit walls and surrounding areas.

 

·Integrate ATV and optical televiewer (OTV) surveys into the geotechnical program to enhance structural characterization and refine the geotechnical model.

 

An allocation of approximately US$500,000 has been made for the geotechnical investigation program, comprising both technical studies and physical drilling activities.

 

Technical studies and analysis are budgeted at approximately US$250,000, covering project supervision and reporting, televiewing, laboratory rock strength testing, and interpretation of results.

 

Physical drilling is budgeted at approximately US$200,00, consisting of 11 geotechnical drill holes totaling approximately 1,250 m, at an estimated all-in cost of US$160/m.

 

These programs are designed to improve pit design confidence and ensure adequate data coverage across newly-defined Mineral Resource areas. The combined dataset will provide critical input for refining slope design parameters, improving overall pit stability assessments, and reducing geotechnical risk for any future open-pit development.

 

26.4Water Management

 

A minimum catchment yield of 13% is required in the area upstream of the proposed water harvest dam between the months of June and October to eliminate the need for abstraction from the Falémé River to a water storage dam. Ongoing monitoring of flow in the Gamba Gamba Creek (Karakaka watercourse) should continue to further refine the yield of the catchment upstream of the proposed water harvest dam and confirm its suitability as a sustainable raw water source for the project.

 

Additional drilling, pump testing, and technical assessments are required for the pits Western Splay, Kassassoko, Southern Arc, and Moungoundi pits to confirm the availability of supplementary site water supplies and to support accurate estimation of pit dewatering requirements.

 

An allocation of approximately US$270,000 has been made for technical work and analysis, excluding additional funds allocated for the physical drilling of hydrogeological holes associated with these studies.

 

These activities will refine the understanding of groundwater conditions, improve pit dewatering designs, and ensure the adequacy and sustainability of a long-term process water supply.

 

October 15, 2025Page 254 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

26.5Metallurgical

 

Additional metallurgical testwork is recommended for the Southern Arc and Moungoundi deposits under process design conditions to confirm metallurgical recoveries in line with the plant’s design criteria. An allocation of approximately US$270,000 has been made for additional metallurgical testwork, reporting, and analysis.

 

26.6Environmental and Social

 

It is recommended to use the next study stage to optimize the Project by reducing its environmental footprint and potential impacts while enhancing opportunities for local communities where possible. In parallel, it is also recommended to explore renewable energy options, such as solar hybrid power solutions, to improve project sustainability and reduce long-term operating costs. This work is expected to be completed using in-house resources and part of normal operating costs for Fortuna’s West Africa regional office.

 

26.7Engineering Studies

 

In addition to addressing these key gaps, it is further recommended that the following studies be completed to optimize and advance the project:

 

·Mining Study Preparation and Integration. An allowance of approximately US$700,000 has been included for engineering, trade-off studies, discipline inputs, and integration of all technical workstreams to support estimation of Mineral Reserves. This scope will also consolidate the outcomes of ongoing technical and optimization studies.

 

·Integration of Solar PV and Renewable Power Options. This work is estimated at approximately US$150,000 and will be integrated into the mining studies to evaluate hybrid HFO–solar configurations aimed at reducing operating costs and enhancing overall project sustainability.

 

·Mining Cost Optimization Study. This is budgeted at approximately US$240,000, and covers updated pit optimizations, mine design revisions, detailed mine planning and scheduling, Mineral Reserve estimation, and supporting mining studies.

 

·Local Content and Procurement Studies. Completion of these studies is estimated at approximately US$100,000. These studies will ensure full compliance with Senegal’s evolving local content framework and identify in-country participation opportunities across construction and operations.

 

·Tailings and Water Storage Optimization Review. This is estimated at approximately US$150,000. The work will confirm capacity, sequencing, and design integration with early works and mine layouts, and ensure alignment between storage infrastructure, water balance, and process plant requirements.

 

·Operational Readiness and Implementation Planning. Estimated at approximately US$70,000, this study will define resource requirements, schedules, and execution strategies.

 

October 15, 2025Page 255 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

27References

 

Allibone, A., Lawrence, D., Scott, J., Fanning, M., Lambert-Smith, J., Stenhouse, P., Harbidge, R., Vargas, C., Turnbull, R., & Holliday, J. (2020). Chapter 7: Paleoproterozoic Gold Deposits of the Loulo District, Western Mali. In R. H. Sillitoe, R. J. Goldfarb, F. Robert, and S. F. Simmons (Eds.), Geology of the World's Major Gold Deposits and Provinces (pp. 141–162). Society of Economic Geologists.

 

CIM 2019. CIM Estimation of Mineral Resources and Mineral Reserves – Best Practice Guidelines. Prepared by the CIM Mineral Resource and Mineral Reserve Committee. Adopted by the CIM Council, November 29, 2019.

 

CIM, 2014. CIM Definition Standards on Mineral Resources and Mineral Reserves. Prepared by the CIM Standing Committee on Reserve Definitions. Adopted by the CIM Council, May 10, 2014.

 

Diallo, M., Baratoux, L., Dufréchou, G., Jessell, M. W., Vanderhaeghe, O., Ly, S., & Baratoux, D. (2020). Structure of the Paleoproterozoic Kédougou-Kéniéba Inlier (Senegal-Mali) deduced from gravity and aeromagnetic data. Journal of African Earth Sciences162, Article 103732.

 

Dioh, E., Debat, P., Diallo, M., Bossière, G., Ba, D., Diop, H., & Dia, A. (2006). Diversity of the Palaeoproterozoic granitoids of the Kédougou inlier (eastern Senegal): Petrographical and geochemical constraints. Journal of African Earth Sciences44(3), 351–371.

 

Earth Systems, 2025. Diamba Sud Gold Project Environmental, Social Impact Assessment Study - Preliminary Version (Main Report, Hazard Study, Key Management Plans, and Technical Annexes). Oct 6, 2025.

 

Knight Piesold Consulting, 2025a. Diamba Sud Gold Project – Feasibility Study Hydrogeological Assessment – Rev B. July 25, 2025.

 

Knight Piesold Consulting, 2025b. Diamba Sud Gold Project – Prefeasibility Study Water Balance Modelling Summary – rev 1. July 17, 2025

 

Knight Piesold Consulting, 2025c. Diamba Sud Gold Project – Prefeasibility TSF Design Study Summary – Rev 4. Oct 9, 2025.

 

Lambert-Smith, J.S., Lawrence, D.M., Vargas, C.A., Boyce, A.J., Treloar, P.J. & Herbert, S. (2016). The Gounkoto Au deposit, West Africa: Constraints on ore genesis and volatile sources from petrological, fluid inclusion and stable isotope data. Ore Geology Reviews, 78, 606–622.

 

Lambert-Smith, J. S., Allibone, A., Treloar, P. J., Lawrence, D. M., Boyce, A. J. and Fanning, M. (2020) Stable C, O, and S isotope record of magmatic-hydrothermal interactions between the Falémé Fe Skarn and the Loulo Au systems in Western Mali. Economic Geology, 115(7), pp. 1537-1558.

 

Lawrence, D. M., Treloar, P. J., Rankin, A. H., Harbidge, P., & Holliday, J. (2013). The Geology and Mineralogy of the Loulo Mining District, Mali, West Africa: Evidence for Two Distinct Styles of Orogenic Gold Mineralization. Economic Geology, 108(2), 199-227.

 

Masurel, Q., Eglinger, A., Thébaud, N. et al. Paleoproterozoic gold events in the southern West African Craton: review and synopsis. Miner Deposita 57, 513–537 (2022).

 

October 15, 2025Page 256 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Piteau Associates, 2025. Diamba Sud Project – Geotechnical Pit Slope Design Update. July 7, 2025.

 

Pons, J., Oudin, C., & Valéro, J. (1992). Kinematics of Large Syn-Orogenic Intrusions: Example of the Lower Proterozoic Saraya Batholith (Eastern Senegal). Geologische Rundschau82(3), 473–486.

 

October 15, 2025Page 257 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

Certificates

 

CERTIFICATE of QUALIFIED PERSON

 

I, Eric Chapman, Senior Vice President of Technical Services for Fortuna Mining Corp.(“Fortuna”), 820-1111 Melville St, Vancouver, BC V6E 3V6 Canada; do hereby certify that:

 

1. I am the co-author of the technical report prepared for Fortuna titled “Diamba Sud Gold Project, Kédougou Region, Senegal” that has an effective date of October 15, 2025 (the “Technical Report”).

 

2. I graduated with a Bachelor of Science (Honors) Degree in Geology from the University of Southampton (UK) in 1996 and a Master of Science (Distinction) Degree in Mining Geology from the Camborne School of Mines (UK) in 2003. I am a Professional Geologist of the Engineers and Geoscientists of the Province of British Columbia (Registration No. 36328) and a Chartered Geologist of the Geological Society of London (Membership No. 1007330). I have been practicing as a geoscientist and preparing resource estimates for approximately twenty years and have completed more than thirty resource estimates for a variety of deposit types such as epithermal gold/silver veins, porphyry and orogenic gold deposits, and volcanogenic massive sulfide deposits. I have completed at least fifteen Mineral Resource estimates for precious metal projects over the past five years.

 

As a result of my experience and qualifications, I am a Qualified Person as defined in National Instrument 43–101 Standards of Disclosure for Mineral Projects (“NI 43–101”).

 

3. I last visited the Diamba Sud Project on October 19 to 22, 2023, a duration of four days.

 

4.) I am responsible for the preparation of Sections 1.1 to 1.4, 1.7, 1.9, 1.19 and the introduction to Section 1.20; Sections 2.1, 2.2, 2.3.1, and 2.4 to 2.7; Sections 3 to 6; Section 10 (except for Section 10.6.3); Section 11; Sections 12.1 to 12.3, 12.5, 12.6, 12.7.1 and 12.8; Section 14; Sections 25.1, 25.3, 25.4, 25.6 and 25.14; Section 26.1 and Section 27 of the Technical Report.

 

5. I am not independent of Fortuna as independence is described by Section 1.5 of NI 43–101, as I am a Fortuna employee.

 

6. I have been involved with the Diamba Sud Gold Project which is the subject of the Technical Report since September 2023.

 

7. I have read NI 43–101 and Form 43-101F1, and the sections of the Technical Report for which I am responsible have been prepared in compliance with that Instrument and Form.

 

8. As of the effective date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report for which I am responsible contain all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Dated at Vancouver, BC, November 26, 2025.

 

[signed]

 

Eric Chapman, P. Geo.

 

October 15, 2025Page 258 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

CERTIFICATE of QUALIFIED PERSON

 

I, Paul Weedon, Senior Vice President, Exploration of Fortuna Mining Corp. (“Fortuna”), 820-1111 Melville St, Vancouver, BC V6E 3V6 Canada, do hereby certify that:

 

1.) I am the co-author of the technical report prepared for Fortuna titled “Diamba Sud Gold Project, Kédougou Region, Senegal” that has an effective date of October 15, 2025 (the “Technical Report”).

 

2. I graduated from Curtin University, Western Australia in December 1991 with a Bachelor of Science (Geology), and a Post Graduate Diploma of Economic Geology (Distinction) and have practiced my profession continuously since 1991.      I am a professional Geologist and a Member of the Australian Institute of Geoscientists (MAIG #6001). I have worked across all roles of exploration and mining geology, covering open-pit and underground gold mining in production roles up to Technical Services Manager for large scale complex operations. My exploration experience extends from project generation through to project development and corporate roles. These roles have been conducted across Australasia, Africa and Latin America. I have held my current position of Senior Vice President – Exploration for Fortuna Mining Corp. since October 2021.

 

As a result of my experience and qualifications, I am a Qualified Person as defined in National Instrument 43–101 Standards of Disclosure for Mineral Projects (“NI 43–101”).

 

3. I last visited the Diamba Sud Project on April 11 to 15, 2025, a duration of five days.

 

4. I am responsible for the preparation of Sections 1.5, 1.6, 1.19 and 1.20.1; Section 2.3.2; Sections 7 to 9; Sections 12.4, 12.7.2 and 12.8; Sections 25.2 and 25.14; Section 26.2 and Section 27 of the Technical Report.

 

5. I am not independent of Fortuna as independence is described by Section 1.5 of NI 43–101, as I am a Fortuna employee.

 

6. I have been involved with the Diamba Sud Project which is the subject of the Technical Report since September 2023.

 

7. I have read NI 43–101 and Form 43-101F1, and the sections of the Technical Report for which I am responsible have been prepared in compliance with that Instrument and Form.

 

8. As of the effective date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report for which I am responsible contain all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Dated at Perth, Australia, November 26, 2025.

 

[signed]

 

Paul Weedon, MAIG.

 

October 15, 2025Page 259 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

CERTIFICATE of QUALIFIED PERSON

 

I, Raul Espinoza, Technical Services Director for Fortuna Mining Corp. (“Fortuna”), 820-1111 Melville St, Vancouver, BC V6E 3V6 Canada; do hereby certify that:

 

1. I am the co-author of the technical report prepared for Fortuna titled “Diamba Sud Gold Project, Kédougou Region, Senegal” that has an effective date of October 15, 2025 (the “Technical Report”).

 

2. I graduated with a Bachelor of Science Degree in Mining Engineering from Pontificia Universidad Catolica del Peru in 2001 and a Master of Engineering Science in Mining from Curtin University, Australia, in 2015. I am a Fellow of the Australasian Institute of Mining and Metallurgy and registered as a Chartered Professional in Mining - FAusIMM (CP) with Membership No. 309581. I have practiced my profession for 24 years and have been preparing reserve estimates for approximately 12 years. My experience has covered operational, technical, managerial and consultancy functions for open pit and underground mines from early-stage projects through to producing mines in Peru, Australia, Canada and Mexico.

 

As a result of my experience and qualifications, I am a Qualified Person as defined in National Instrument 43–101 Standards of Disclosure for Mineral Projects (“NI 43–101”).

 

3. I have not visited the Diamba Sud Project.

 

4. I am responsible for the preparation of Sections 1.10, 1.11, 1.13 to 1.19, 1.20.5 and 1.20.6; Sections 12.7.3 and 12.8; Section 15; Sections 16.1, 16.4, the introduction to Section 16.5, 16.5.1, 16.5.2, and 16.6 to 16.8; Sections 18.1, 18.2, 18.6 to 18.9, 18.11 to 18.15 and 18.17; Sections 19 to 24; Sections 25.7 and 25.9 to 25.14; Sections 26.6 and 26.7; and Section 27 of the Technical Report.

 

5. I am not independent of Fortuna as independence is described by Section 1.5 of NI 43–101, as I am a Fortuna employee.

 

6. I have been involved with the Diamba Sud Project, which is the subject of the Technical Report since September 2023.

 

7. I have read NI 43–101 and Form 43-101F1, and the sections of the Technical Report for which I am responsible have been prepared in compliance with that Instrument and Form.

 

8. As of the effective date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report for which I am responsible contain all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Dated at Vancouver, Canada, November 26, 2025.

 

[signed]

 

Raul Espinoza, FAusIMM (CP)

 

October 15, 2025Page 260 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

CERTIFICATE of QUALIFIED PERSON

 

I, Mathieu F. Veillette, Director, Geotechnical, Tailings and Water for Fortuna Mining Corp. (“Fortuna”), 820-1111 Melville St, Vancouver, BC V6E 3V6 Canada; do hereby certify that:

 

1. I am the co-author of the technical report prepared for Fortuna titled “Diamba Sud Gold Project, Kédougou Region, Senegal” that has an effective date of October 15, 2025 (the “Technical Report”).

 

2. I graduated with a Bachelor of Science Degree in Civil Engineering in 1997 from Queen’s University and a Graduate Diploma Business Administration from Simon Fraser University in 2018. I am a Professional Engineer of the Association of Professional Engineers and Geoscientists of the Province of British Columbia (Registration No. 28397), also a Professional Engineer from Colorado (Registration No. 36639) and Alaska (Registration No. 10914). I have practiced my profession continuously for 28 years in geotechnical and water management related fields. The majority of my experience has been in the mining industry including international projects on all stages of the mining process from advanced exploration through decommissioning and reclamation. My relevant work experience includes analysis, site investigations, design, construction, dewatering and operation of open pits, waste dumps, heap leach pads, tailings storage facilities, process ponds, water dams, diversion structures and other mining facilities in Canada (BC, QC), USA (CO, UT, NM, AZ, MT, AK, SC), México, Panamá, Venezuela, Guyana, Peru, Chile, Argentina, Bolivia, Cote d’Ivoire, Burkina Faso, Senegal, Australia, New Zealand and New Caledonia.

 

As a result of my experience and qualifications, I am a Qualified Person as defined in National Instrument 43–101 Standards of Disclosure for Mineral Projects (“NI 43–101”).

 

3. I last visited the Diamba Sud Project from October 19 to 22, 2023, a duration of four days.

 

4. I am responsible for the preparation of Sections 1.19, 1.20.2 and 1.20.3; Section 2.3.3; Section 10.6.3; Sections 12.7.4 and 12.8; Sections 16.2, 16.3, and 16.5.3; Section 17.9; Sections 18.3 to 18.5, 18.10 and 18.16; Section 25.14; Sections 26.3 and 26.4; and Section 27 of the Technical Report.

 

5. I am not independent of Fortuna as independence is described by Section 1.5 of NI 43–101, as I am a Fortuna employee.

 

6. I have been involved with the Diamba Sud Project which is the subject of the Technical Report since September 2023.

 

7. I have read NI 43–101 and Form 43-101F1, and the sections of the Technical Report for which I am responsible have been prepared in compliance with that Instrument and Form.

 

8. As of the effective date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report for which I am responsible contain all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Dated at Vancouver, Canada, November 26, 2025.

 

[signed]

 

Mathieu F. Veillette, P.Eng.

 

October 15, 2025Page 261 of 262

 

Diamba Sud Gold Project, Kédougou Region, Senegal

Technical Report

 

CERTIFICATE of QUALIFIED PERSON

 

I, Leendert (Leon) Lorenzen, Senior Principal Consultant (Process) of Lorenzen Consultants Pty Ltd, 3 Deanery Mews, Churchlands, WA 6018, Australia, do hereby certify that:

 

1. I am the co-author of the technical report prepared for Fortuna titled “Diamba Sud Gold Project, Kédougou Region, Senegal” that has an effective date of October 15, 2025 (the “Technical Report”).

 

2. I am a graduate of the University of Stellenbosch, Stellenbosch, South Africa and hold a Bachelor of Engineering (Chemical), Master of Science in Engineering (Metallurgy), cum laude and Doctor of Philosophy (Metallurgical Engineering) from Stellenbosch University, Stellenbosch, South Africa (1993).

 

I am a Fellow of the Australasian Institute of Mining and Metallurgy (FAusIMM #304479), Fellow of the Southern African Institute of Mining and Metallurgy (FSAIMM #20258), Fellow of the Institute for Chemical Engineers (FIChemE #20029470), Fellow of the Institute of Engineers Australia (FIEAust #3671379) as well as a Chartered Professional Engineer (Australia), Chartered Engineer (UK) and Professional Engineer (South Africa). I have practiced my profession continuously for 43 years with extensive management and working experience in metallurgical testing and mineral processing in the mining industry.

 

As a result of my experience and qualifications, I am a Qualified Person as defined in National Instrument 43–101 Standards of Disclosure for Mineral Projects (“NI 43–101”).

 

3. I have not visited the Diamba Sud Project.

 

4. I am responsible for the preparation of Sections 1.8, 1.12 and 1.19; Section 1.20.4; Sections 12.7.5 and 12.8; Section 13; Sections 17.1 to 17.8, and 17.10; Sections 25.5, 25.8 and 25.14; Section 26.5 and Section 27 of the Technical Report.

 

5. I am independent of Fortuna as independence is described by Section 1.5 of NI 43–101.

 

6. I have been involved with the Diamba Sud Project which is the subject of the Technical Report since April 2022.

 

7. I have read NI 43–101 and Form 43-101F1, and the sections of the Technical Report for which I am responsible have been prepared in compliance with that Instrument and Form.

 

8. As of the effective date of the Technical Report, to the best of my knowledge, information and belief, the sections of the Technical Report for which I am responsible contain all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.

 

Dated at Perth, Australia, November 26, 2025.

 

[signed]

 

Dr Leendert (Leon) Lorenzen, CEng, CPEng, PrEng, FAusIMM (CP)

 

October 15, 2025Page 262 of 262