Management's Discussion and Analysis of

Results of Operations and Financial Condition

For the three and six months ended

June 30, 2025

 

 

 

August 12, 2025



TABLE OF CONTENTS Page

 
Introduction 1
Hudbay's Business 1
Hudbay's Purpose 2
Summary 3
Key Financial Results 8
Key Production Results 9
Key Costs Results 9
Recent Developments 10
Peru Operations Review 14
Manitoba Operations Review 19
British Columbia Operations Review 25
Financial Review 30
Liquidity and Capital Resources 39
Financial Risk Management 43
Trend Analysis and Quarterly Review 44
Non-GAAP Financial Performance Measures 46
Accounting Changes and Critical Estimates 69
Changes in Internal Control over Financial Reporting 70
Notes to Reader 70
Summary of Historical Results 73


INTRODUCTION

This Management's Discussion and Analysis ("MD&A") dated August 12, 2025 is intended to supplement Hudbay Minerals Inc.'s unaudited condensed consolidated interim financial statements and related notes for the three and six months ended June 30, 2025 and 2024 (the "consolidated interim financial statements"). The consolidated interim financial statements have been prepared in accordance with IFRS® Accounting Standards ("IFRS" or "GAAP") as issued by the International Accounting Standards Board ("IASB").

References to "Hudbay" or the "Company" refer to Hudbay Minerals Inc. and its direct and indirect subsidiaries as at June 30, 2025.

Readers should be aware that:

- This MD&A contains certain "forward-looking statements" and "forward-looking information" (collectively, "forward-looking information") that are subject to risk factors set out in a cautionary note contained in Hudbay's MD&A.

- This MD&A has been prepared in accordance with the requirements of the securities laws in effect in Canada, which may differ materially from the requirements of United States securities laws applicable to US issuers.

- Hudbay uses a number of non-GAAP financial performance measures in Hudbay's MD&A, which do not have standardized meaning under IFRS. For further information and detailed reconciliations of such measures, please see the discussion under the "Non-GAAP Financial Performance Measures" section herein.

- The technical and scientific information in this MD&A has been approved by qualified persons based on a variety of assumptions and estimates. Please see the discussion under the "Qualified Persons and NI 43-101" section herein.

Readers are also urged to review the "Notes to Reader" section beginning on page 70 of this MD&A.

Additional information regarding Hudbay, including the risks related to its business and those that are reasonably likely to affect its consolidated interim financial statements in the future, is contained in Hudbay's continuous disclosure materials, including its most recent Annual Information Form, consolidated interim financial statements and Management Information Circular available on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov.

All amounts are in US dollars unless otherwise noted.

HUDBAY'S BUSINESS

Hudbay is a copper-focused critical minerals company with three long-life operations and a world-class pipeline of copper growth projects in tier-one mining jurisdictions of Canada, Peru and the United States. Hudbay's operating portfolio includes the Constancia mine in Cusco (Peru), the Snow Lake operations in Manitoba (Canada) and the Copper Mountain mine in British Columbia (Canada). Copper is the primary metal produced by the company, which is complemented by meaningful gold production and by-product zinc, silver and molybdenum. The Company's growth pipeline includes the Copper World project in Arizona (United States), the Mason project in Nevada (United States), the Llaguen project in La Libertad (Peru) and several expansion and exploration opportunities near its existing operations. Hudbay is governed by the Canada Business Corporations Act and its shares are listed under the symbol "HBM" on the Toronto Stock Exchange, New York Stock Exchange and Bolsa de Valores de Lima.


HUDBAY'S PURPOSE

The value Hudbay creates and the impact it has is embodied in its purpose statement: "We care about our people, our communities and our planet. Hudbay provides the metals the world needs. We work sustainably, transform lives and create better futures for communities."

Hudbay transforms lives: Hudbay invests in its employees, their families and local communities through long-term employment, local procurement and economic development to improve their quality of life and ensure the communities benefit from the Company's presence.

Hudbay operates responsibly: From exploration to closure, Hudbay operates safely and responsibly, welcomes innovation and strives to minimize its environmental footprint while following leading operating practices in all facets of mining.

Hudbay provides critical metals: Hudbay produces copper and other metals needed for everyday products and essential for applications to support the energy transition toward a more sustainable future.


SUMMARY

Delivered Strong Second Quarter Financial Results; Production Reaffirmed and Cost Guidance Improved

 Achieved revenue of $536.4 million and adjusted EBITDA1 of $245.2 million in the second quarter of 2025.

 Strong financial results were driven by attractive operating cost margins and significant exposure to copper and gold across Hudbay's diversified operating portfolio.

 Steady production continued into the second quarter with consolidated copper production of 29,956 tonnes and consolidated gold production of 56,271 ounces.

 Industry-leading cost performance continued in the second quarter with consolidated cash cost1 and sustaining cash cost1 per pound of copper produced, net of by-product credits, of $(0.02) and $1.65, respectively.

 Reaffirmed full year 2025 consolidated production guidance of 117,000 to 149,000 tonnes of copper and 247,500 to 308,000 ounces of gold.

 Improved full year 2025 consolidated cash cost1 guidance to $0.65 to $0.85 per pound from $0.80 to $1.00 per pound, as year-to-date results are trending well below the low end of the cost ranges due to increased exposure to gold by-product credits and continued strong cost control across all operations.

 Peru operations produced 21,710 tonnes of copper and 7,366 ounces of gold in the second quarter, in line with quarterly cadence expectations, despite lower average mill throughput of approximately 83,100 tonnes per day due to a planned semi-annual mill maintenance shutdown in the second quarter. Peru cash cost1 per pound of copper produced, net of by-product credits, was $1.45 in the second quarter, in line with the annual guidance range.

 Manitoba operations produced 43,235 ounces of gold in the second quarter, slightly lower than quarterly cadence expectations as a result of a temporary shutdown of operations due to wildfire evacuation orders, partially offset by continued strong gold grades at Lalor and mill throughput outperformance at New Britannia. Manitoba cash cost1 per ounce of gold produced, net of by-product credits, was $710 in the second quarter, in line with the annual guidance range.

 British Columbia operations produced 6,634 tonnes of copper at a cash cost1 per pound of copper produced, net of by-product credits, of $2.39 in the second quarter, reflecting efficiency benefits from Hudbay's optimization initiatives.

 Second quarter net earnings attributable to owners and earnings per share attributable to owners were $117.7 million and $0.30, respectively, a 17% and 20% increase, respectively, compared to the first quarter of 2025 and a significant increase compared to the second quarter of 2024, driven by higher gross margins and strong cost control. After adjusting for various non-cash items, second quarter adjusted earnings1 per share attributable to owners was $0.19.

 Cash and cash equivalents increased by $62.9 million to $625.5 million during the second quarter and total liquidity2 was $1,050.2 million as at June 30, 2025.

Continued Free Cash Flow Generation Driving Further Debt Reduction and Balance Sheet Resilience

 Hudbay's unique copper and gold diversification across its operations provides exposure to higher copper and gold prices, which together with a focus on cost control across the business, continues to expand margins and generate attractive free cash flow1.

 While the majority of revenues continue to be derived from copper production, gold represented more than 36% of total revenues in the second quarter of 2025.

 Delivered the eighth consecutive quarter of meaningful free cash flow1 generation with $87.8 million achieved during the second quarter of 2025, resulting in more than $400 million in annual free cash flow1 over the last twelve months.

 Achieved adjusted EBITDA1 of $245.2 million in the second quarter of 2025, resulting in record annual trailing twelve-month adjusted EBITDA1 of $995.9 million.

 Repurchased and retired an additional $50 million of senior unsecured notes through open market purchases at a discount to par during the second quarter, reducing total principal debt to $1.07 billion as of June 30, 2025.

 Approximately $295 million in total debt repayments and gold prepayment liability reductions have been achieved since the beginning of 2024.

 Net debt1 significantly reduced to $434.1 million as at June 30, 2025 compared to $525.7 million at December 31, 2024, a decrease of $91.6 million in the first half of 2025.

 Net debt to adjusted EBITDA ratio1 was 0.4x at the end of the second quarter of 2025, an improvement from 0.6x at the end of the first quarter of 2025 and 0.8x at the end of the second quarter of 2024. This is the lowest net leverage level achieved since Hudbay developed Constancia over a decade ago.

 Current balance sheet expected to be further enhanced with proceeds from the $600 million Copper World joint venture transaction, as mentioned below. On a pro-forma basis, as at June 30, 2025, this would increase cash and cash equivalents to more than $1.0 billion and total liquidity to more than $1.5 billion, while reducing net debt1 to zero.


Prudently Advancing Copper World with Accretive Minority Joint Venture Transaction, Enhanced Stream Transaction and Successful Achievement of "3-P" Plan

 Announced $600 million Copper World joint venture transaction with Mitsubishi Corporation ("Mitsubishi") for a 30% minority interest ("JV Transaction").

 Implies a significant premium to consensus net asset value for Copper World3.

 Mitsubishi's $600 million initial investment will consist of $420 million at closing and $180 million within 18 months of closing.

 Mitsubishi will also fund its pro-rata 30% share of future equity capital contributions.

 Increases levered project IRR to Hudbay to approximately 90% based on pre-feasibility study ("PFS") estimates4.

 Secures a premier long-term strategic partner in Mitsubishi, one of the largest Japanese trading houses with a global mining presence and a significant U.S. based business.

 Mitsubishi is the strategic partner of choice with investments in a world-class portfolio of large and high-quality copper assets, including five of the top twenty copper mines globally by 2024 production.

 Mitsubishi's wholly owned U.S. subsidiary, Mitsubishi Corporation (Americas), has over 50 subsidiaries and affiliates across various business sectors, including mineral resources, oil & gas, real estate, mobility, food, power, etc., and manages the company's strategic investments with approximately $9 billion in total assets and trading businesses in North America, which encompass trading activity with a substantial volume of copper, precious metals, and aluminum in the U.S. market.

 Strategic partnership validates the attractive long-term value of Copper World as a world-class copper asset and endorses the strong technical capabilities of Hudbay.

 Agreed on terms with Wheaton Precious Metals Corp. ("Wheaton") to amend the existing precious metals streaming agreement.

 In addition to the initial $230 million stream deposit, provides an additional contingent payment of up to $70 million on a future potential mill expansion recognizing the long-term potential at Copper World.

 Ongoing payments for gold and silver amended from fixed pricing to 15% of spot prices to provide upside exposure to higher precious metals prices.

 Updated structure aligns with the current development plan for Copper World and the joint venture agreement.

 Successfully completes key elements of Hudbay's prudent financial strategy as part of the three prerequisites ("3-P") plan for Copper World with the announcements of the JV Transaction and the enhanced Wheaton stream, together with the achievements of stated balance sheet targets.

 Before accounting for proceeds from this Transaction, Hudbay had achieved more than $600 million of cash and cash equivalents and a 0.4x net debt to adjusted EBITDA ratio1, as of June 30, 2025, far exceeding the stated balance sheet targets.

 The Mitsubishi initial investment and its pro-rata equity capital contributions, together with the amended Wheaton stream, provide significant financial flexibility by reducing Hudbay's estimated share of the remaining capital contributions to approximately $200 million based on PFS estimates4, and defers Hudbay's first capital contribution until 2028 at the earliest.

 Well positioned to advance Copper World towards a sanction decision in 2026.

 Feasibility study for Copper World is underway with expected completion of a definitive feasibility study ("DFS") by mid-2026.

 With this successful de-risking milestone at Copper World, Hudbay expects to accelerate detailed engineering, some key long lead items and other de-risking activities by advancing $20 million in growth capital expenditures to 2025 from future years, and is updating total 2025 Arizona growth spending guidance to $110 million from $90 million on a 100% basis.

Reinvesting in High-return Growth Initiatives to Further Enhance Copper and Gold Exposure

 Advancing high-return brownfield mill enhancement initiatives and greenfield copper projects to drive near-term and long-term production growth with $33.1 million in growth capital expenditures during the second quarter of 2025.

 Optimization efforts at Copper Mountain are focused on executing the planned accelerated stripping program and mill throughput improvement projects. The planned conversion of the third ball mill to a second SAG mill remains on budget and on schedule, with completion of the initial phase achieved on July 10 and ramp up of the final phase expected in the fourth quarter of 2025.

 Mining of first zinc ore from the exploration and haulage drifts at 1901 was achieved in the second quarter, and planned activities over the next two years are expected to de-risk the path towards full production in 2027.

 Large exploration program in Snow Lake continues to execute threefold strategy focused on near-mine exploration to increase near-term production and mineral reserves, testing regional satellite deposits for additional ore feed to utilize available capacity at the Stall mill, and exploring the large land package for a potential new anchor deposit to meaningfully extend mine life.


 Drilling commenced at the Talbot copper-zinc-gold deposit near Snow Lake as part of a large summer exploration program.

 Continuing to advance Flin Flon tailings reprocessing opportunities through metallurgical test work and economic evaluation to assess the possibility of producing critical minerals and precious metals in an environmentally friendly manner.

 Completed transaction with Mitsubishi Materials Corporation to consolidate Hudbay's 100% ownership of the Copper Mountain mine in a highly accretive transaction to further increase Hudbay's exposure to a long-life, high-quality copper asset in a tier-1 mining jurisdiction, resulting in an expected 200% increase in attributable copper production from Copper Mountain in 2027 compared to 20245.

 Permitting application for the New Ingerbelle growth project at Copper Mountain was accepted for review by the B.C. Major Mines Office in May and is proceeding through the Mine Review Committee review process.

 Continuing to enhance stakeholder engagement and advance additional metallurgical studies at the Mason copper project in Nevada.

Summary of Second Quarter Results

Steady production continued into the second quarter of 2025 with consolidated copper production of 29,956 tonnes and consolidated gold production of 56,271 ounces. Consolidated copper and gold production was lower than the first quarter of 2025 primarily due to the impacts of a temporary suspension of operations in Manitoba as a result of mandatory wildfire evacuation orders. Consolidated silver production of 814,989 ounces and zinc production of 5,130 tonnes in the second quarter of 2025 were also lower than the first quarter of 2025 for the aforementioned reason.

Cash generated from operating activities of $259.9 million increased compared to the same period in 2024 and the first quarter of 2025 as a result of higher gross margins driven by stable copper production, higher realized prices and positive working capital management with reductions in finished goods inventories and receivable balances. Operating cash flow before change in non-cash working capital was $193.9 million during the second quarter of 2025, reflecting an increase of $70.2 million compared to the same period in 2024 and an increase of $30.4 million compared to the first quarter of 2025. The increase compared to the second quarter of 2024 reflects the higher gold realized price during the quarter, strong operating cost performance and higher sales volume partially offset by higher cash taxes paid. The increase compared to the first quarter of 2025 was primarily the result of lower cash taxes paid, offset by lower gold and copper sales volume in Manitoba.

Second quarter adjusted EBITDA1 was $245.2 million, a 15% decrease compared to $287.2 million in the first quarter of 2025 due to lower sales volume, partially offset by higher gold prices. Second quarter adjusted EBITDA1 increased by 69% compared to $145.0 million in the second quarter of 2024 as a result of higher sales volume and higher realized gold prices during the quarter.

Net earnings attributable to owners in the second quarter of 2025 was $117.7 million, or $0.30 per share, compared to $100.4 million, or $0.25 per share, in the first quarter of 2025 and net loss attributable to owners and loss per share attributable to owners of $16.5 million, or $0.04 per share, in the second quarter of 2024. The increase in earnings compared to the first quarter of 2025 is the result of high gross margins from strong revenue growth on the back of stable copper production and higher realized gold prices. In addition, the quarter benefited from various non-cash charges for revaluation gain of closed sites reclamation provisions, and significantly reduced net finance expenses, among other items, more than offsetting the high mining and income tax expense experienced in the current quarter.

Adjusted net earnings attributable to owners1 and adjusted net earnings per share attributable to owners1 in the second quarter of 2025 were $75.5 million and $0.19 per share, respectively, after adjusting for various non-cash items on a pre-tax basis such as a non-cash $18.9 million foreign exchange gain, a non-cash gain of $13.8 million related to quarterly revaluation of Hudbay's closed site environmental reclamation provision, a $6.3 million mark-to-market revaluation gain on various instruments such as investments and share-based compensation, and a $1.2 million gain related to flow-through share expenditures, among other items. This compares to adjusted net earnings attributable to owners1 and net earnings per share attributable to owners1 of $0.2 million and nil per share in the second quarter of 2024 and $93.8 million and $0.24 per share in the first quarter of 2025. The sharp increase in adjusted net earnings attributable to owners1 and adjusted net earnings per share attributable to owners1 compared to second quarter of 2024 is for the same reasons discussed above for net earnings.

In the second quarter of 2025, consolidated cash cost per pound of copper produced, net of by-product credits1, was $(0.02), compared to $(0.45) in the first quarter of 2025 as the Company continued to demonstrate industry-leading cost performance. The change from the first quarter was a result of lower by-product credits and lower production levels in Manitoba during the second quarter. When compared to the second quarter of 2024, consolidated cash cost per pound of copper, net of by-product credits1 decreased by $1.16 as a result of higher by-product credits, higher production and stronger cost performance across all business units.

Consolidated sustaining cash cost per pound of copper produced, net of by-product credits1, was $1.65 in the second quarter of 2025, compared to $0.72 in the first quarter of 2025. The increase was driven by planned higher sustaining capital expenditures and the aforementioned variance in cash cost. Consolidated sustaining cash cost was lower than $2.65 in the second quarter of 2024, primarily due to the same factors impacting consolidated cash cost and partially offset by higher sustaining capital expenditures.


Consolidated all-in sustaining cash cost per pound of copper produced, net of by-product credits1, was $2.03 in the second quarter of 2025, higher than $0.97 in the first quarter of 2025 mainly due to the same reasons outlined above as well as higher corporate G&A from the revaluation of the Company's stock based compensation due to relative higher share prices. Consolidated all-in sustaining cash cost was lower than $3.07 in the same period in 2024 due to the same reasons outlined above as well as lower accretion and amortization of community agreements, partially offset with higher corporate G&A costs.

As at June 30, 2025, total liquidity was $1,050.2 million, including $625.5 million in cash and cash equivalents, and undrawn availability of $424.7 million under Hudbay's revolving credit facilities. Net debt1 at the end of the second quarter was $434.1 million, marking a $92.0 million improvement from the first quarter of 2025 as a result of deleverging activities. Hudbay expects that the current liquidity together with cash flows from operations will be sufficient to meet the Company's liquidity needs for the year.


*Copper equivalent production is calculated using the quarter average LME prices for each metal.

 

1 Adjusted net earnings (loss) - attributable to owners and adjusted net earnings (loss) per share - attributable to owners, adjusted EBITDA, cash cost, sustaining cash cost, all-in sustaining cash cost per pound of copper produced, net of by-product credits, cash cost, sustaining cash cost per ounce of gold produced, net of by-product credits, combined unit cost, net debt, net debt to adjusted EBITDA ratio and free cash flow are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.

2 Liquidity includes $625.5 million in cash and cash equivalents as well as undrawn total availability of $424.7 million under Hudbay's revolving credit facilities.

3 Average analyst consensus net asset value estimate for 100% of Copper World is approximately $1.16 billion as of August 12, 2025.

4 Based on the initial capital investment and the $3.75 per pound copper price used in the PFS published on September 8, 2023 with assumptions of approximately $145 million for pre-sanctioning costs, $230 million from the precious metals stream, $350 million from project-level financing and approximately $700 million from the joint venture partner earn-in, matching contribution and capital contribution.

5 Copper Mountain copper production comparison based on the mid-point of the 2027 guidance range compared to 2024 actuals.


KEY FINANCIAL RESULTS

Financial Condition            
(in $ millions, except net debt to adjusted EBITDA ratio)   Jun. 30, 2025     Dec. 31, 2024  
Cash and cash equivalents and short-term investments $ 625.5   $ 581.8  
Total debt   1,059.6     1,107.5  
Net debt1   434.1     525.7  
Working capital2   26.8     511.3  
Total assets   5,628.6     5,487.6  
Equity attributable to owners of the Company   2,863.3     2,553.2  
Net debt to adjusted EBITDA 1   0.4     0.6  
1 Net debt and net debt to adjusted EBITDA are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.
2 Working capital is determined as total current assets less total current liabilities as defined under IFRS and disclosed on the consolidated interim financial statements. Working capital as of June 30, 2025 was impacted by an increase in the current portion of long-term debt of $523.8 million as the 2026 Notes are now maturing within one year.

Financial Performance   Three months ended     Six months ended  
(in $ millions, except per share amounts or as noted below)   Jun. 30, 2025     Mar. 31, 2025     Jun. 30, 2024     Jun. 30, 2025     Jun. 30, 2024  
Revenue $ 536.4   $ 594.9   $ 425.5   $ 1,131.3   $ 950.5  
Cost of sales   359.9     363.6     347.9     723.5     720.9  
Earnings before tax   153.1     171.3     0.4     324.4     68.2  
Net earnings (loss)   114.7     99.2     (20.3 )   213.9     (1.8 )
Net earnings (loss) attributable to owners   117.7     100.4     (16.5 )   218.1     5.8  
Basic and diluted earnings (loss) per share - attributable   0.30     0.25     (0.04 )   0.55     0.02  
Adjusted earnings per share - attributable1   0.19     0.24     0.00     0.43     0.17  
Operating cash flow before change in non-cash working capital   193.9     163.5     123.7     357.4     271.2  
Adjusted EBITDA1   245.2     287.2     145.0     532.4     360.0  
Free cash flow1   87.8     87.4     32.5     175.2     119.7  
1 Adjusted earnings per share - attributable to owners, adjusted EBITDA and free cash flow are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.


KEY PRODUCTION RESULTS

  Three months ended Six months ended Guidance
Jun. 30,
2025
Mar. 31,
2025
Jun. 30,
2024
Jun. 30,
2025
Jun. 30,
2024
Annual 2025
Contained metal in concentrate and doré produced1            
Copper tonnes 29,956 30,958 28,578 60,914 63,327 117,000 - 149,000
Gold oz 56,271 73,784 58,614 130,055 149,006 247,500 - 308,000
Silver oz 814,989 919,775 738,707 1,734,764 1,686,624 3,520,000 - 4,390,000
Zinc tonnes 5,130 6,265 8,087 11,395 16,885 21,000 - 27,000
Molybdenum tonnes 375 397 369 772 766 1,300 - 1,500
Payable metal sold            
Copper tonnes 30,354 31,768 25,799 62,122 59,407  
Gold2 oz 62,466 75,092 61,295 137,558 169,376  
Silver2 oz 894,160 1,006,968 667,036 1,901,128 1,735,884  
Zinc tonnes 2,871 4,857 5,133 7,728 11,252  
Molybdenum tonnes 427 448 347 875 762  
1 Metal reported in concentrate is prior to deductions associated with smelter contract terms.
2 Includes total payable gold and silver in concentrate and in doré sold.

KEY COST RESULTS

    Three months ended Six months ended Guidance
    Jun. 30,
2025

Mar. 31,
2025

Jun. 30,
2024
Jun. 30,
2025

Jun. 30,
2024
Annual
20252
Peru cash cost per pound of copper produced                  
Cash cost1 $/lb 1.45   1.11   1.78 1.29   1.02 1.35 - 1.65
Sustaining cash cost1 $/lb 2.63   1.92   2.60 2.29   1.71  
Manitoba cash cost per ounce of gold produced                  
Cash cost1 $/oz 710   376   771 515   751 650 - 850
Sustaining cash cost1 $/oz 1,025   626   1,163 793   1,042  
British Columbia cash cost per pound of copper produced                  
Cash cost1 $/lb 2.39   2.44   2.67 2.41   3.09 2.45 - 3.45
Sustaining cash cost1 $/lb 5.18   4.24   5.56 4.69   5.20  
Consolidated cash cost per pound of copper produced                  
Cash cost1 $/lb (0.02 ) (0.45 ) 1.14 (0.24 ) 0.60 0.65 - 0.85
Sustaining cash cost1 $/lb 1.65   0.72   2.65 1.18   1.74 2.25 - 2.65
All-in sustaining cash cost1 $/lb 2.03   0.97   3.07 1.49   2.09  
1 Cash cost, sustaining cash cost, all-in sustaining cash cost per pound of copper produced, net of by-product credits, gold cash cost, sustaining cash cost per ounce of gold produced, and net of by-product credits are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.
2 Improved full year 2025 consolidated copper cash cost guidance range to $0.65 to $0.85 per pound from the original guidance range of $0.80 to $1.00 per pound.


RECENT DEVELOPMENTS

Continued Free Cash Flow Generation from Strong Copper and Gold Exposure

Hudbay has delivered eight consecutive quarters of meaningful free cash flow1 generation as a result of steady operating performance, expanding margins from strong copper and gold exposure and a focus on cost control across the business:

 Achieved record trailing twelve-month adjusted EBITDA1 of $995.9 million.

 Delivered more than $400 million in annual free cash flow1 generation over the last twelve months.

 Increased cash and cash equivalents balance to $625.5 million, the highest level achieved in more than a decade.

 Gold continues to represent more than 36% of total revenues, which together with Hudbay's primary copper revenue business provides unique copper and gold commodity diversification.

Significant Debt Reduction

As a result of the continued free cash flow1 generation and prudent balance sheet management, Hudbay was able to repurchase and retire $50.0 million of senior unsecured notes at a discount to par, during the second quarter of 2025. This has contributed to approximately $295 million in total debt repayments and gold prepayment liability reductions since the beginning of 2024:

 Repurchased and retired a total of $132.6 million of senior unsecured notes in 2024 and year-to-date 2025.

 Repaid $100 million of prior drawdowns under the revolving credit facilities in 2024.

 Fully repaid the gold prepay facility with $62.3 million in gold deliveries in 2024 and the final payment completed in August 2024.

These deleveraging achievements have reduced total principal debt to $1.07 billion as of June 30, 2025, which together with Hudbay's increased cash balance, has substantially reduced net debt1 to $434.1 million, compared to $631.8 million as of June 30, 2024. Incorporating higher levels of adjusted EBITDA1 over the last twelve months, Hudbay's net debt to adjusted EBITDA ratio1 has significantly improved to 0.4x.

Secured Premier Long-term Strategic Partner in Copper World JV Transaction

The joint venture will be structured as a new limited liability corporation, Copper World LLC. Under the JV Transaction, the initial contribution of $600 million for a 30% equity interest in Copper World LLC, will consist of $420 million upon closing and a $180 million matching contribution payable no later than 18 months following closing. Hudbay will retain 100% of its existing U.S. federal net operating losses of approximately $275 million and Arizona state losses of $210 million.

Hudbay welcomes a premier, long-term, strategic partner with deep technical expertise and a proven trading platform which Mitsubishi has established throughout its demonstrated history of industry partnerships. Mitsubishi's impressive track record in co-developing and operating some of the world's largest and highest quality copper projects will complement Hudbay's proven track record as a successful mine builder and operator.

Mitsubishi will be contributing 30% of the ongoing costs beginning August 31, 2025 and will participate in the funding of the DFS as well as the final project design, project financing, and project construction for Copper World.

The JV Transaction is expected to close in late 2025 or early 2026 and is conditioned upon receipt of certain regulatory approvals and the satisfaction of other customary closing conditions.

Enhanced Wheaton Precious Metals Stream

Hudbay is also pleased to announce that it has concurrently executed a non-binding term sheet to amend its existing Wheaton stream agreement for 100% of the gold and silver produced at Copper World (the "Wheaton Stream"), which will increase the value of the project and provide upside exposure to higher precious metal prices.

Key terms of this enhanced Wheaton Stream to include (subject to execution of definitive documentation):

 Up to $70 million contingent payment upon achieving potential mill expansion milestones in the future recognizing the long-term potential at Copper World.

 Amended ongoing payments for gold and silver from a fixed price to 15% of spot gold and silver prices providing upside exposure to higher precious metals prices.

 Initial $230 million stream deposit during project construction remains unchanged.

 Hudbay agreed to maintain existing fixed recoveries in the existing Constancia precious metals stream while Pampacancha is in production as well as provided a corporate guarantee for the existing Constancia stream in connection with the Wheaton Stream enhancement.


"Successfully Completed "3-P" Plan for Advancing Copper World Towards a Sanction Decision in 2026

As part of Hudbay's disciplined financial planning approach to developing Copper World, the Company implemented its 3-P plan in late 2022, including specific leverage targets that it would need to achieve prior to making an investment decision in the project:

1. Permits - Completed - Hudbay received all required state level permits.

2. Plan - Well Underway - Hudbay commenced activities related to the feasibility study for Copper World in late 2024 and expects to continue to advance definitive feasibility study activities throughout 2025 with completion by mid-2026.

3. Prudent Financing Strategy - Completed - Hudbay achieved all key elements of its multi-faceted financing strategy, including:

 Minimum cash balance of $600 million - As of June 30, 2025, Hudbay has over $625 million in cash and cash equivalents;

 Net debt to EBITDA ratio of less than 1.2x - As of June 30, 2025, Hudbay's net debt to adjusted EBITDA ratio1 is 0.4x, meaningfully below the targeted ratio to ensure financial flexibility during the sanctioning and construction of Copper World;

 Renegotiated precious metals stream agreement - Announced an enhanced Wheaton Stream that aligns with the current development plan for Copper World, reflects amended ongoing payments for gold and silver deliveries from a fixed pricing to 15% of spot prices to provide upside exposure to higher precious metals prices, while also providing additional contingent payments of up to $70 million related to potential future mill expansion milestones; and,

 Minority joint venture partner - Announced a $600 million transaction with Mitsubishi for a 30% minority joint venture interest in a highly accretive transaction, which creates a long-term partnership with a premier strategic partner that has a global mining presence and an established U.S. based metals trading business.

As a result of the completion of the prudent financing strategy, Hudbay's estimated share of the remaining capital contributions for the construction of Copper World is approximately $200 million2, and Hudbay's first capital contribution is deferred until 2028 at the earliest based on PFS estimates. Based on Hudbay's pro-forma cash and cash equivalents of more than $1.0 billion and total liquidity of more than $1.5 billion, using figures as at June 30, 2025, the Company has significant financial flexibility to fund its share of the remaining equity contributions at Copper World while continuing to maintain a strong balance sheet throughout the project construction period.

Manitoba Temporary Wildfire Evacuation Orders

Since the end of May, seasonal wildfires in northern Manitoba have resulted in evacuation orders in the regions where Hudbay operates. Emergency preparedness protocols were immediately activated and Hudbay has continued to work closely with local and provincial authorities to ensure the safety and well-being of its employees and nearby communities. The first mandatory wildfire evacuation orders resulted in Hudbay temporarily suspending operations in June for 13 days and operating with a reduced workforce since the end of May, before and after the operation suspension. The Company committed over C$2 million in funding support in June, including C$1.6 million in direct financial support for evacuated Hudbay employees and a C$500,000 donation to the Canadian Red Cross to support wildfire emergency relief and rebuilding efforts in northern Manitoba. The Company's Canadian Red Cross donation was part of a collective C$1.25 million donation that was made by the three leading mining companies that operate in Manitoba, including Hudbay, Vale Base Metals and Alamos Gold Inc. In addition, Hudbay established a Community Relief Donations Fund whereby Hudbay doubled the amounts donated by its employees to the Canadian Red Cross, further multiplying the support for emergency response efforts in the region.

Hudbay's Manitoba team continues to show remarkable resilience as demonstrated by the tremendous effort and unwavering commitment during this unprecedented wildfire season. They have tirelessly safeguarded the Company's assets and collaborated closely with local communities and provincial authorities, providing essential support to emergency response efforts.

On July 10, 2025, a second mandatory wildfire evacuation order was issued for the town of Snow Lake and a controlled, safe and orderly temporary suspension of the Snow Lake operations was implemented. As of August 12, 2025, the wildfire situation near Snow Lake has improved and Hudbay anticipates returning to normal operations later in August. The Company continues to expect to achieve its 2025 annual guidance metrics for all metals in Manitoba, despite the temporary wildfire impacts.


British Columbia Mill Optimization Project Achieves Key Milestone

In July, shortly following the end of the second quarter, Hudbay reached a significant milestone on the Copper Mountain mill optimization project to convert the third ball mill to a second SAG mill. The mill project is intended to increase nominal processing capacity to its permitted capacity of 50,000 tonnes per day starting in 2026.

The initial phase of the project achieved first ore production on July 10, a key milestone to ramp up mill capacity. The first phase was completed on time with more than 41,000 hours worked and zero lost-time incidents, which is a testament to the dedication and safety culture of Hudbay's team. The project remains on budget as it moves into the final phase of the project, which includes converting an interim feed arrangement to a permanent configuration and remains on track for completion in the second half of 2025.

New Ingerbelle Permit Application Achieves Key Milestone

On May 12, 2025, Hudbay's permitting application for the New Ingerbelle growth project at Copper Mountain was successfully accepted into review by the B.C. Major Mines Office and is now proceeding through a Mine Review Committee process. The Copper Mountain team continues ongoing engagement with First Nations and other local stakeholder groups as part of the Company's commitment to cultivating transparency and mutually beneficial relationships.

Exploration Update

Large Snow Lake Exploration Program Continues to Execute Threefold Strategy

Hudbay continues to execute the largest exploration program in Snow Lake in the Company's history through extensive geophysical surveying and multi-phased drilling campaigns as part of Hudbay's threefold exploration strategy:

 Near-mine exploration at Lalor and 1901 further increase near-term production and extend mine life - Following the positive initial step-out drilling from the exploration drift at the 1901 deposit earlier this year, Hudbay completed the development of the drift in the second quarter of 2025, and in June, the first zinc-rich ore from the 1901 mining area was delivered for processing at Stall. Activities at 1901 over the next two years will prioritize exploration, definition drilling, orebody access, and establishing critical infrastructure for full production in 2027. The additional exploration at 1901 planned for later in 2025 will target additional step-out drill holes to potentially extend the ore body and infill drilling to convert inferred mineral resources in the gold lenses to mineral reserves. The Company also expects to continue drilling down plunge of lenses 27 and 17 at Lalor once wildfire conditions improve.

 Testing regional satellite deposits to utilize available processing capacity and increase production - Hudbay increased its regional land package by more than 250% in 2023 through the acquisition of Rockcliff Metals Corp., which included the addition of several known deposits located within trucking distance of the Snow Lake processing infrastructure. The deposits acquired as part of the Rockcliff Metals Corp. acquisition, together with several deposits already owned by Hudbay in Snow Lake, have created an attractive portfolio of regional deposits in Snow Lake, including the Talbot, Rail, Pen II, Watts, 3 Zone and WIM deposits. The continued strong performance from the New Britannia mill has freed up processing capacity at the Stall mill, where there is approximately 1,500 tonnes per day of available capacity which could be utilized by the regional satellite deposits to increase production and extend the life of the Snow Lake operations beyond 2037. Hudbay commenced an extensive summer drill program at the Talbot deposit in July focused on expanding the known mineralization and testing geophysical targets.

 Exploring large land package for new anchor deposit to significantly extend mine life - A majority of the land claims acquired as part of the Rockcliff Metals Corp. acquisition have been untested by modern deep geophysics, which was the discovery method for the Lalor deposit. A large geophysics program is currently underway consisting of surface electromagnetic surveys using cutting edge techniques that enable the team to detect targets at depths of almost 1,000 metres below surface. The planned geophysics program in 2025 is the largest geophysics program in Hudbay's history and includes 800 kilometres of ground electromagnetic surveys and an extensive airborne geophysics survey. The summer geophysics program is currently paused due to the regional wildfires and is expected to resume once the conditions improve and the evacuation orders are lifted.

Maria Reyna and Caballito Drill Permits Update

Hudbay controls a large, contiguous block of mineral rights with the potential to host satellite mineral deposits in close proximity to the Constancia processing facility, including the past producing Caballito property and the highly prospective Maria Reyna property. The Company commenced the drill permitting process at Maria Reyna and Caballito after completing a surface rights exploration agreement with the community of Uchucarcco in August 2022. As part of the drill permitting process, environmental impact assessment (EIA) applications were approved by the government in June 2024 for Maria Reyna and September 2024 for Caballito. The remaining steps in the drill permitting process include the completion by the government of the Consulta Previa consultation process with the local community.


Senior Management Team Appointments

In May 2025, Hudbay promoted Robert Carter to Senior Vice President, Canada and John O'Shaughnessy to Vice President, Manitoba Business Unit.

In his new role, Mr. Carter is responsible for the strategic oversight of Hudbay's business activities in Manitoba and British Columbia. Mr. Carter previously held the role of Vice President, Manitoba Business Unit since April 2022 and prior to that was the General Manager of Hudbay's Manitoba mines since 2018. He has over 25 years of mining industry experience in technical, operational and senior leadership roles, with a majority of those years at Hudbay.

As the new leader of the Manitoba Business Unit, Mr. O'Shaughnessy is responsible for the strategic and operational performance of Hudbay's activities in Manitoba. He previously held the role of Vice President, Business Development at Hudbay where he provided expert oversight and strategic leadership of the global mine planning process. He has over 25 years of mining industry experience, including numerous progressive engineering, operational and leadership roles at Vale's mining operations in Ontario and Newfoundland and Labrador.

Dividend Declared

A semi-annual dividend of C$0.01 per share was declared on August 12, 2025. The dividend will be paid out on September 19, 2025 to shareholders of record as of close of business on September 2, 2025.

 

1 Adjusted EBITDA, net debt, net debt to adjusted EBITDA ratio and free cash flow are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.

2 Based on the initial capital investment and the $3.75 per pound copper price used in the PFS published on September 8, 2023 with assumptions of approximately $145 million for pre-sanctioning costs, $230 million from the precious metals stream, $350 million from project-level financing and approximately $700 million from the joint venture partner earn-in, matching contribution and capital contribution.


PERU OPERATIONS REVIEW

  Three months ended Six months ended
Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024 Jun. 30, 2025 Jun. 30, 2024
Constancia ore mined1 tonnes 6,735,316 8,628,279 5,277,654 15,363,595 7,837,201
Copper % 0.34 0.28 0.29 0.31 0.30
Gold g/tonne 0.03 0.03 0.03 0.03 0.03
Silver g/tonne 3.26 3.14 2.50 3.19 2.60
Molybdenum % 0.02 0.02 0.01 0.02 0.01
Pampacancha ore mined1 tonnes 762,172 389,189 1,288,789 1,151,361 3,503,143
Copper % 0.26 0.44 0.41 0.32 0.51
Gold g/tonne 0.24 0.26 0.20 0.25 0.28
Silver g/tonne 4.59 3.68 3.83 4.28 4.34
Molybdenum % 0.01 0.01 0.02 0.01 0.02
Total ore mined tonnes 7,497,488 9,017,468 6,566,443 16,514,956 11,340,344
Strip ratio2   1.47 1.02 1.74 1.22 1.83
Ore milled tonnes 7,559,047 8,114,024 7,718,962 15,673,071 15,796,923
Copper % 0.34 0.30 0.30 0.32 0.33
Gold g/tonne 0.05 0.05 0.07 0.05 0.11
Silver g/tonne 3.58 3.22 2.85 3.39 3.17
Molybdenum % 0.01 0.01 0.01 0.01 0.01
Copper concentrate tonnes 94,813 92,171 89,629 186,984 203,728
Concentrate grade % Cu 22.90 22.02 21.44 22.46 21.50
Copper recovery % 84.5 84.6 83.1 84.6 84.1
Gold recovery % 56.0 56.5 61.4 56.2 69.7
Silver recovery % 63.5 66.0 63.9 64.7 67.7
Molybdenum recovery % 38.7 35.7 46.3 37.1 44.6
Combined unit operating costs3,4 $/tonne 13.59 11.09 12.68 12.29 11.78
1 Reported tonnes and grade for ore mined are estimates based on mine plan assumptions and may not reconcile fully to ore milled.
2 Strip ratio is calculated as waste mined divided by ore mined.
3 Reflects combined mine, mill and general and administrative ("G&A") costs per tonne of ore milled. Reflects the deduction of expected capitalized stripping costs.
4 Combined unit costs is a non-GAAP financial performance measure with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.



    Three months ended Six months ended
    Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024 Jun. 30, 2025 Jun. 30, 2024
Contained metal in concentrate produced            
Copper tonnes 21,710 20,293 19,217 42,003 43,793
Gold oz 7,366 7,869 10,672 15,235 39,816
Silver oz 551,979 554,692 450,833 1,106,671 1,090,551
Molybdenum tonnes 375 397 369 772 766
Payable metal sold            
Copper tonnes 21,418 22,890 16,806 44,308 40,560
Gold oz 9,721 14,362 13,433 24,083 56,110
Silver oz 616,578 714,654 400,302 1,331,233 1,154,009
Molybdenum tonnes 427 448 347 875 762
Cost per pound of copper produced            
Cash cost1 $/lb 1.45 1.11 1.78 1.29 1.02
Sustaining cash cost1 $/lb 2.63 1.92 2.60 2.29 1.71
1 Cash cost and sustaining cash costs per pound of copper produced, net of by-product credits, are not recognized under IFRS. For more detail on these non-GAAP financial performance measures, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.

Overview

The Peru operations continued to demonstrate steady operating performance with production and costs in line with expectations. Copper production increased in the second quarter of 2025 compared to the same period in 2024 due to higher copper grade in ore mined from Constancia and higher copper recoveries. Copper production was also higher than the first quarter of 2025 as milled copper grades exceeded first quarter levels, partially offset by planned lower mill throughput due to a scheduled mill maintenance shutdown in the second quarter.

The last major stripping program at Pampacancha was completed in the second quarter of 2025, which included higher amounts of waste stripping than planned. As a result, the Company replaced higher grade Pampacancha ore with higher grade Constancia ore in the second quarter and the Pampacancha deposit is now expected to be depleted in the first quarter of 2026 rather than in late 2025. Protests that started early in the third quarter temporarily impacted the transportation of supplies and concentrate to and from the Constancia site and has affected mine sequencing. The Constancia mill has continued to operate during this period, and the road blockades along the concentrate transportation route have since reopened, allowing Hudbay to reduce site concentrate inventory levels and replenish supplies. Despite short-term mine plan changes the Company remains on track to achieve its 2025 production guidance for all metals in Peru.

Mining Activities

Total ore mined in Peru in the second quarter of 2025 increased by 14% compared to the same period in 2024, in line with mine plan expectations.

Year-to-date ore mined in Peru was 46% higher than the same period in 2024 but in line with mine plan expectations.


Milling Activities

Mill throughput levels averaged approximately 83,100 tonnes per day in the second quarter of 2025, lower than the first quarter of 2025 due to the planned semi-annual mill maintenance shutdown during the current quarter, but fairly in line with the same period in 2024. Milled copper grades increased by 13% compared to the comparative periods, primarily due to higher grades in the Constancia pit. Milled gold grades in the second quarter of 2025 were lower than the same period in 2024 due to lower ore feed from Pampacancha, but remained consistent with gold grades in the first quarter of 2025 as Pampacancha stripping activities were underway in both quarters. The mill achieved higher copper recoveries of 85% in the second quarter of 2025 compared to the same period in 2024 and remained consistent with the first quarter of 2025. Recoveries of gold and silver during the second quarter of 2025 were in line with Hudbay's metallurgical models for the ore that was being processed.

Ore milled during the first half of 2025 was relatively unchanged from the comparative 2024 period. Milled copper grades in the first half of 2025 were consistent with the same period in 2024, while milled gold grades decreased by 55% as a result of less ore feed from Pampacancha. Recoveries of copper during the first half of 2025 were 85%, representing an increase of 1%, compared with the 2024 period, despite being impacted by supplemental ore feed from stockpiles during pit stripping activities early in the year. Gold and silver recoveries during the first half of 2025 were 56% and 65%, respectively, representing a decrease of 19% and 4%, respectively, but were in line with Hudbay's metallurgical models.

Production and Sales Performance

The Peru operations produced 21,710 tonnes of copper, 7,366 ounces of gold, 551,979 ounces of silver and 375 tonnes of molybdenum during the second quarter of 2025, in line with mine plan quarterly cadence expectations. Production of copper was higher than the comparative periods primarily due to higher grades from the Constancia pit. Production of all other metals were relatively in line with the first quarter of 2025 and higher than the same period in 2024, with the exception of gold production which was lower than the same period in 2024 due to a lower portion of Pampacancha ore feed.

Year-to-date production of copper and gold in 2025 was 42,003 tonnes and 15,235 ounces, respectively, representing a decrease of 4% and 62%, respectively, from the comparative 2024 period primarily due to lower grades since more material was mined from Constancia and reclaimed from the stockpile during 2025 compared with the prior year.

Quantities of metal sold during the three and six months ended 2025 were in line with the variances in production previously outlined.

       

*Copper equivalent production is calculated using the quarter average LME prices for each metal excluding molybdenum.


         

     

Cost Performance

Combined mine, mill and G&A unit operating cost in the second quarter of 2025 was $13.59 per tonne, 7% higher than the same period in 2024 primarily due to higher plant maintenance costs associated with the planned semi-annual mill maintenance shutdown, partially offset by the impacts of higher stripping. Combined unit operating cost was 23% higher than the first quarter of 2025, as expected, due to higher plant maintenance costs and lower tonnes processed associated with the planned semi-annual mill maintenance shutdown. Combined mine, mill and G&A unit operating costs for the six months ended June 30, 2025 was $12.29 per tonne, a 4% increase compared to the same period in 2024 due to higher plant maintenance costs as mentioned above.

Cash cost per pound of copper produced, net of by-product credits, in the second quarter of 2025 was $1.45, a 19% decrease compared to the same period in 2024 as a result of lower treatment and refining charges and higher copper production. Cash cost per pound of copper produced, net of by-product credits, increased by 31% compared to the first quarter of 2025 due to planned higher maintenance costs and lower by-product credits, partially offset by lower treatment and refining charges and higher copper production. 

Year-to-date 2025 cash cost per pound of copper produced, net of by-product credits2 was $1.29, an increase from $1.02 in the same period of 2024 due to lower gold by-product credits, partially offset by lower treatment and refining charges.

Sustaining cash cost per pound of copper produced, net of by-product credits2, was $2.63 in the second quarter of 2025, an increase of 1% compared to the same period in 2024 due to higher plant and mine maintenance costs, higher community payments and finance leases, partially offset by the factors described above for the cash cost variance. Sustaining cash cost per pound of copper produced, net of by-product credits, increased by 37% compared to the first quarter of 2025 due to planned higher sustaining capital typically associated with the period after the rainy season is complete, as well as the same factors affecting cash costs. On a year-to-date basis, sustaining cash cost per pound of copper produced, net of by-products credits2, was $2.29, higher than the $1.71 for the comparable period in 2024 due to higher plant and mine maintenance costs, finance lease payments and community payments.


Peru Guidance Outlook

    Three months ended Six months ended Guidance
    Jun. 30, 2025 Jun. 30, 2024 Jun. 30, 2025 Jun. 30, 2024 Annual 2025
Contained metal in concentrate produced          
Copper tonnes 21,710 19,217 42,003 43,793 80,000 - 97,000
Gold oz 7,366 10,672 15,235 39,816 49,000 - 60,000
Silver oz 551,979 450,833 1,106,671 1,090,551 2,475,000 - 3,025,000
Molybdenum tonnes 375 369 772 766 1,300 - 1,500
Cost per pound of copper produced            
Cash cost1 $/lb 1.45 1.78 1.29 1.02 1.35 - 1.65
1 Cash cost per pound of copper produced, net of by-product credits, are not recognized under IFRS. For more detail on these non-GAAP financial performance measures, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.

Despite short-term mine plan changes Hudbay is on track to achieve its 2025 production guidance for all metals in Peru. With cash costs in the first half of the year outperforming the low end of the cash cost guidance range. Hudbay is reaffirming its full year 2025 cash cost guidance range in Peru.


MANITOBA OPERATIONS REVIEW

  Three months ended Six months ended
Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024 Jun. 30, 2025 Jun. 30, 2024
Lalor ore mined tonnes 303,062 384,234 385,478 687,296 793,186
Gold g/tonne 4.97 5.46 3.75 5.25 4.31
Copper % 0.61 0.95 0.69 0.80 0.77
Zinc % 2.46 2.42 2.76 2.44 2.84
Silver g/tonne 29.94 31.23 22.29 30.67 22.88
New Britannia ore milled tonnes 162,934 189,124 167,899 352,058 338,308
Gold g/tonne 6.48 7.37 5.31 6.96 6.18
Copper % 0.65 1.18 0.94 0.94 1.04
Zinc % 1.01 1.00 0.92 1.01 0.87
Silver g/tonne 30.29 33.35 24.42 31.93 23.00
Copper concentrate tonnes 6,278 14,396 9,350 20,674 20,997
Concentrate grade % Cu 14.73 14.02 15.96 14.24 15.97
Gold recovery1 % 89.4 90.3 90.0 89.9 89.2
Copper recovery % 87.4 90.3 94.4 89.3 95.4
Silver recovery1 % 78.0 81.6 83.1 80.0 82.6
Contained metal in concentrate produced          
Gold oz 17,801 26,486 18,050 44,287 43,645
Copper tonnes 926 2,019 1,492 2,945 3,353
Silver oz 80,516 120,237 85,759 200,753 162,975
Metal in doré produced2            
Gold oz 15,379 15,111 10,843 30,490 27,338
Silver oz 46,311 45,312 37,675 91,623 76,733
Stall ore milled tonnes 144,204 215,286 229,527 359,490 448,885
Gold g/tonne 3.19 3.86 3.02 3.60 3.05
Copper % 0.56 0.76 0.59 0.68 0.61
Zinc % 4.20 3.44 4.05 3.74 4.29
Silver g/tonne 29.55 29.53 21.74 29.54 23.07
Copper concentrate tonnes 3,854 6,708 6,202 10,562 13,369
Concentrate grade % Cu 17.79 21.62 18.54 20.22 18.23
Zinc concentrate tonnes 9,739 12,584 15,280 22,323 33,118
Concentrate grade % Zn 52.68 49.78 52.92 51.05 50.98
Gold recovery % 67.9 70.1 65.5 69.3 66.7
Copper recovery % 84.7 88.3 85.4 87.1 88.6
Zinc recovery % 84.8 84.7 87.1 84.7 87.7
Silver recovery % 51.9 58.7 54.2 56.0 57.1
Contained metal in concentrate produced          
Gold oz 10,055 18,758 14,595 28,812 29,336
Copper tonnes 686 1,450 1,150 2,136 2,438
Zinc tonnes 5,130 6,265 8,087 11,395 16,885
Silver oz 71,143 120,054 87,213 191,197 190,762
1 Gold and silver recovery includes total recovery from concentrate and doré.
2 Doré includes sludge, slag and carbon fines.



  Three months ended Six months ended
Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024 Jun. 30, 2025 Jun. 30, 2024
Total contained metal in concentrate and doré produced1          
Gold oz 43,235 60,354 43,488 103,589 100,319
Copper tonnes 1,612 3,469 2,642 5,081 5,791
Zinc tonnes 5,130 6,265 8,087 11,395 16,885
Silver oz 197,970 285,603 210,647 483,573 430,470
Payable metal sold in concentrate and doré          
Gold oz 46,932 55,765 42,763 102,697 104,766
Copper tonnes 2,133 2,725 2,429 4,858 5,350
Zinc tonnes 2,871 4,857 5,133 7,728 11,252
Silver oz 209,594 232,255 197,486 441,848 429,327
Unit Operating Costs2            
Lalor C$/tonne 153.08 143.19 150.06 147.55 148.36
New Britannia C$/tonne 67.98 68.12 71.49 68.05 74.78
Stall C$/tonne 51.53 35.97 38.45 42.21 39.54
Combined unit operating costs3,4,5 C$/tonne 241 214 225 225 230
Cost per ounce of gold produced            
Cash cost5,6 $/oz 710 376 771 515 751
Sustaining cash cost5 $/oz 1,025 626 1,163 793 1,042
1 Metal reported in concentrate is prior to deductions associated with smelter terms.
2 Reflects costs per tonne of ore mined/milled.
3 Reflects combined mine, mill and G&A costs per tonne of milled ore.
4 Excludes $3.2 million or C$14 per tonne of overhead costs incurred during temporary suspension during the three months ended June 30, 2025 and $3.2 million or C$6 per tonne during the six month ended June 30, 2025.
5 Combined unit costs, cash cost and sustaining cash cost per ounce of gold produced, net of by-product credits, are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.
6 Excludes $3.2 million or $74 per ounce of overhead costs incurred during temporary suspension during the three months ended June 30, 2025 and $3.2 million or $31 per ounce during the six month ended June 30, 2025.

Overview

Despite significant disruptions from the mandatory wildfire evacuation orders in May and June of this year, the Manitoba operations showed remarkable resilience and achieved several key milestones in the second quarter of 2025. Notably, the New Britannia mill achieved record monthly production in April, the 1901 mining area delivered its first ore for processing in June, and Hudbay signed an exploration agreement with Mosakahiken Cree Nation to explore the Talbot deposit.

Hudbay's dedicated operations team demonstrated tremendous effort and unwavering commitment during the unprecedented wildfire situation near the Company's Flin Flon and Snow Lake operations during the second quarter. The team tirelessly safeguarded Hudbay's assets and collaborated closely with local communities and provincial authorities, providing essential support to emergency response efforts. These efforts resulted in no damage to Hudbay's infrastructure and facilities.

The Lalor mine managed through a period of reduced workforce prior to and after the 13-day temporary suspension of operations in June due to regional mandatory wildfire evacuation orders. Despite these challenges, the mine averaged 3,300 tonnes per day in the second quarter, strategically prioritizing mining from gold zones to ensure a consistent feed for the New Britannia mill.

Continuous improvement efforts at Lalor focused on ore quality and advancing stope modifications to enhance mucking productivity. Capital development continued, aiming to secure high-grade copper-gold mineralization from Zone 27 and prepare Zone 17 for the next copper-gold mining front.


The New Britannia mill achieved record monthly production levels in April, exceeding 2,300 tonnes per day. This significant milestone is a testament to ongoing low-capital projects and recent piping improvements that boosted throughput and maintained gold recoveries.

Exploration and haulage drifts advanced towards the 1901 deposit, where initial zinc-rich massive sulphides were mined and processed in June. The next two years at 1901 will prioritize exploration, definition drilling, orebody access, and establishing critical infrastructure for full production in 2027.

Mining Activities

Total ore mined in Manitoba in the second quarter of 2025 was lower than the comparable periods, reflecting the impacts from the wildfires. Gold grades were better than expected in the second quarter of 2025, resulting in a 33% increase from the second quarter of 2024, despite being lower than the exceptional gold grade mined in the first quarter of 2025. Copper, zinc and silver grades were in line with mine plan expectations. The second quarter of 2025 saw significant improvements in ore quality, aligned with improvements in mining techniques, most notably in longhole muck fragmentation, and anticipated higher grade precious metal sequences. 

Total ore mined at Hudbay's Manitoba operations during the first half of 2025 was 13% lower than the same period in 2024, as a result of the same quarterly factors noted above. Gold, copper, and silver grades mined at Lalor during the first half of 2025 were 22%, 4%, and 34% higher, respectively, compared with the same period in 2024. Zinc grades mined during the first half of 2025 were 14% lower than the same period in 2024.

Milling Activities

Consistent with Hudbay's strategy of allocating more Lalor ore feed to New Britannia to maximize gold recoveries, the New Britannia mill throughput averaged approximately 1,800 tonnes per day in the second quarter of 2025, reflecting record levels of more than 2,300 tonnes per day achieved in April, offset by lower throughput levels in June associated with the wildfire evacuation shutdown. Gold recovery in the second quarter of 2025 was 89% remaining relatively consistent with the same period in 2024 and the first quarter of 2025.

In the second quarter, the Stall mill continued to process less ore compared to prior periods, which is aligned with Hudbay's strategy of allocating more Lalor ore feed to New Britannia, as noted above. The Stall mill achieved gold recoveries of 68% in the second quarter of 2025, reflecting benefits from recent recovery improvement programs.

Production and Sales Performance

The Manitoba operations delivered strong results in the second quarter of 2025, producing 43,235 ounces of gold, 1,612 tonnes of copper, 5,130 tonnes of zinc and 197,970 ounces of silver. Compared to the second quarter of 2024, production of gold was relatively unchanged despite lower production in June associated with the wildfire evacuation shutdown as higher grades offset lower throughput. Production of copper, silver, and zinc decreased by 39%, 6% and 37%, respectively, compared to the second quarter of 2024, primarily due to prioritizing the mining of gold grade areas during the wildfire evacuation shutdown in June to maximize gold ore feed to the New Britannia mill. Compared to the first quarter of 2025, production of gold, copper, silver and zinc in the second quarter of 2025 decreased by 28%, 54%, 31% and 18%, respectively, for the same reason mentioned above, in addition to the first quarter of 2025 having significantly better than expected gold grades.

Year-to-date production of gold and silver in 2025 was higher by 3% and 12%, respectively, than the comparative 2024 period as a result of higher grades and higher New Britannia mill throughput despite throughput limitations in June. Copper and zinc production in the first half of 2025 decreased by 12% and 33%, respectively, aligned with forecasted production and the strategy to mine more gold ore at Lalor, resulting in less mill throughput at Stall as mentioned above.

Quantities of copper, gold and silver sold during the second quarter of 2025 were higher than production levels as unsold copper inventory at the end of March was sold during the second quarter. Zinc metal sold during the second quarter of 2025 was impacted by higher zinc concentrate inventory at the end of June which is expected to be sold during the third quarter of 2025. During the six months ended June 30, 2025, quantities sold for all metals were relatively in line with variances in production, with the exception of zinc sales which were impacted by higher zinc concentrate inventory levels at the end of June 2025.


   

Cost Performance

The Manitoba operations continued to drive operating efficiencies despite temporary disruptions from wildfire evacuations orders in June.

Combined mine, mill and G&A unit operating costs in the second quarter were C$241 per tonne, higher than the comparative periods primarily due to lower total throughput in June, partially offset by continued strong cost performance at New Britannia. Mining costs per tonne of ore milled during the second quarter of 2025 were relatively unchanged from the same period in 2024, as lower costs from efficiency improvement initiatives at Lalor over the past year have offset lower tonnes mined in June, while mining costs per tonne of ore milled were higher than in the first quarter of 2025 as a result of the wildfires in June. Milling costs per tonne of ore milled were higher than the comparative periods as a result of higher unit costs at Stall associated with lower throughput as mentioned above, offset by strong unit cost performance at New Britannia as a result of higher daily throughput levels.

Cash cost per ounce of gold produced, net of by-product credits, in the second quarter of 2025 was $710, an 8% decrease compared to the same period in 2024. This improvement in performance is mostly the result of lower mining and milling costs from robust cost improvement measures undertaken and significantly lower treatment and refining charges. Compared to the first quarter of 2025, cash costs increased primarily due to lower gold production and lower by-product credits as per the production variances discussed above.

Sustaining cash cost per ounce of gold produced, net of by-product credits, in the second quarter of 2025 was $1,025, a 12% decrease compared to the same period in 2024 and a 64% increase compared to the first quarter of 2025, primarily due to the same factors affecting cash cost, partially offset by lower sustaining capital costs during the quarter.

Cash cost per ounce of gold produced, net of by-product credits, during the six months ended June 30, 2025 was $515. These costs were 31% lower compared to the same period in 2024 primarily due to higher gold production and lower mining and milling costs, together with lower treatment and refining charges, partially offset by higher G&A costs resulting from higher employee profit sharing costs. Sustaining cash cost per ounce of gold produced, net of by-product credits, for the six months ended June 30, 2025 was $793 per ounce, a decrease of 24% from the same period in 2024 primarily due to the same factors affecting cash cost noted above, together with slightly lower sustaining capital expenditures compared to the prior year.



Manitoba Guidance Outlook

  Three months ended Six months ended Guidance
Jun. 30,
2025
Jun. 30,
2024
Jun. 30,
2025
Jun. 30,
2024
Annual 2025
Total contained metal in concentrate and doré produced1            
Gold2 oz 43,235 43,488 103,589 100,319 180,000 - 220,000
Copper tonnes 1,612 2,642 5,081 5,791 9,000 - 11,000
Zinc tonnes 5,130 8,087 11,395 16,885 21,000 - 27,000
Silver3 oz 197,970 210,647 483,573 430,470 800,000 - 1,000,000
Cost per ounce of gold produced            
Cash cost4,5 $/oz 710 771 515 751 650 - 850
1 Metal reported in concentrate is prior to deductions associated with smelter terms.
2 Gold production guidance includes gold contained in concentrate produced and gold in doré.
3 Silver production guidance includes silver contained in concentrate produced and silver in doré.
4 Combined unit costs, cash cost per ounce of gold produced, net of by-product credits, are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.
5 Excludes $3.2 million or $74 per ounce of overhead costs incurred during temporary suspension during the three months ended June 30, 2025 and $3.2 million or $31 per ounce during the six month ended June 30, 2025.

On July 10, 2025, a second mandatory wildfire evacuation order was issued for the town of Snow Lake and a controlled, safe and orderly temporary suspension of the Snow Lake operations was implemented. Essential personnel, authorized by emergency services, have remained onsite when safe to do so in order to continue supporting fire mitigation activities and safeguarding Hudbay's assets. To-date, there has been no structural damage to Hudbay's onsite surface infrastructure and facilities. As of August 12, 2025, the wildfire situation near Snow Lake has improved and Hudbay anticipates returning to normal operations later in August. The Company continues to expect to achieve its 2025 annual guidance metrics for all metals in Manitoba, despite the impact from the wildfires. Similarly, with cash costs in the first half of the year outperforming the low end of the cash cost guidance range, Hudbay is well positioned to achieve the 2025 cash cost guidance range in Manitoba.


BRITISH COLUMBIA OPERATIONS REVIEW

    Three months ended5 Six months ended5
    Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024 Jun. 30, 2025 Jun. 30, 2024
Ore mined1 tonnes 2,509,969 2,648,094 2,164,722 5,158,063 5,887,218
Strip ratio2   7.50 6.73 7.61 7.11 5.39
Ore milled tonnes 2,900,008 2,760,986 3,232,427 5,660,994 6,412,576
Copper % 0.28 0.33 0.25 0.31 0.26
Gold g/tonne 0.09 0.10 0.07 0.09 0.07
Silver g/tonne 0.97 1.28 1.01 1.12 1.10
Copper concentrate tonnes 28,198 31,234 29,275 59,432 59,925
Concentrate grade % Cu 23.5 23.0 23.0 23.3 22.9
Copper recovery % 81.0 78.3 82.3 79.5 82.8
Gold recovery % 68.2 63.4 57.2 65.7 59.0
Silver recovery % 71.8 69.8 73.9 70.7 73.1
Combined unit operating costs3,4 C$/tonne 24.51 25.98 19.65 25.12 21.65
1 Reported tonnes and grade for ore mined are estimates based on mine plan assumptions and may not reconcile fully to ore milled.
2 Strip ratio is calculated as waste mined divided by ore mined.
3 Reflects combined mine, mill and general and administrative ("G&A") costs per tonne of ore milled. Reflects the deduction of expected capitalized stripping costs.
4 Combined unit costs is a non-GAAP financial performance measure with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.
5 Copper Mountain mine results are stated at 100%. On April 30, 2025 Hudbay completed the acquisition of the remaining 25% interest in the Copper Mountain mine and now owns 100%.

    Three months ended2 Six months ended2
    Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024 Jun. 30, 2025 Jun. 30, 2024
Contained metal in concentrate produced          
Copper tonnes 6,634 7,196 6,719 13,830 13,743
Gold oz 5,670 5,561 4,454 11,231 8,871
Silver oz 65,040 79,480 77,227 144,520 165,603
Payable metal sold            
Copper tonnes 6,803 6,153 6,564 12,956 13,497
Gold oz 5,813 4,965 5,099 10,778 8,500
Silver oz 67,988 60,059 69,248 128,047 152,548
Cost per pound of copper produced          
Cash cost1 $/lb 2.39 2.44 2.67 2.41 3.09
Sustaining cash cost1 $/lb 5.18 4.24 5.56 4.69 5.20
1 Cash cost and sustaining cash cost, net of by-product credits, are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.
2 Copper Mountain mine results are stated at 100%. On April 30, 2025 Hudbay completed the acquisition of the remaining 25% interest in the Copper Mountain mine and now owns 100%.


Overview

Hudbay continues its focus on advancing optimization plans at the Copper Mountain mine, including ramping up mining activities to optimize the mine ore feed to the plant and implementing site improvement initiatives that mirror Hudbay's successful processes at Constancia. These optimization initiatives have successfully increased the total tonnes moved and improved mill reliability.

Mining activities are focused on continuing to execute the three-year accelerated stripping program intended to bring higher grade ore into the mine plan. During the first half of 2025, Hudbay made significant progress on the key mill improvement project to ultimately increase the nominal plant capacity to its permitted level of 50,000 tonnes per day. The project entails the conversion of the third ball mill to a second SAG mill, and the initial phase of this project was successfully completed shortly following the end of the second quarter on time and on budget with the achievement of first ore production on July 10. The final phase of the project involves converting an interim feed arrangement to a permanent configuration and remains on target for completion in the second half of 2025.

Mining Activities

Total ore mined at Copper Mountain in the second quarter of 2025 was 2.5 million tonnes, an increase of 16% compared to the second quarter of 2024, as the mine continues to execute operational improvement initiatives. Planned ore stockpiles were utilized as ore feed to the mill while the mine operation team continued to increase waste stripping activities to expose additional ore mining fronts. Total ore mined decreased by 5% compared to the first quarter of 2025 due to unplanned production loading fleet activities, despite an increase in total material moved in the quarter as a result of effective usage of the mining fleet to execute the accelerated stripping program to access higher grade phases in the pit. The continued focus in the second quarter of 2025 was on mining efficiencies, including a significant improvement with blasted muck inventories and operator recruitment to effectively utilize the available haul truck fleet. As a result, total material moved is expected to increase quarter-over-quarter in 2025 as per the mine plan. 

Total ore mined at Copper Mountain during the six months ended June 30, 2025 was 12% lower than the same period in 2024, for the same reason mentioned above. 

Milling Activities

The mill processed 2.9 million tonnes of ore during the second quarter of 2025, lower than the second quarter of 2024 but higher than the first quarter of 2025. Mill throughput in the second quarter of 2025 was limited by both planned and unplanned maintenance, elevated clay material which impacted the secondary crushing circuit, and the planned lowering of the main crushed live ore pile feeding the mill due to area constraints related to the completion of the ball mill to SAG conversion project. Several mill initiatives were implemented in 2025, including recovery improvements, crushing circuit chute modifications, installation of advanced semi-autogenous grinding control instrumentation, and redesigned SAG liner package. Progressive mill improvements and updated operational procedures are expected to continue through 2025.

Milled copper grades during the second quarter of 2025 were 12% higher than the second quarter of 2024 as the accelerated stripping efforts continue to unlock higher grades. Milled copper grades in the second quarter were lower than the first quarter due to higher amounts of ore processed from stockpile in the second quarter, as mentioned above, as well as the mining of a high-grade mining sequence during the first quarter of 2025. Copper recoveries were 81% in the second quarter of 2025, an increase from 78% in the first quarter of 2025 despite lower copper head grades. Milled gold grades were higher in the second quarter of 2025 compared to the same period in 2024, resulting in higher gold recoveries of 68% in the second quarter of 2025. Gold recoveries were also higher than the first quarter of 2025, despite slightly lower gold head grades.

Milled copper grades during the first half of 2025 were higher than the same period in 2024 as accelerated stripping efforts unlocked a high-grade mining sequence. Year-to-date 2025 copper recoveries of 80% were lower than 2024 as a result of the composition of ore feed to the mill and the impacts of mill maintenance shutdowns. Operational strategy improvements, including reagent selection and dose modifications are in progress. Milled gold grades during the first half of 2025 were higher than the same period in 2024, resulting in higher gold recoveries of 66% in the first half of 2025.

Production and Sales Performance

The British Columbia operations produced 6,634 tonnes of copper, 5,670 ounces of gold and 65,040 ounces of silver during the second quarter of 2025. Production of copper and silver decreased, compared to prior periods primarily as a result of lower head grades from the use of stockpiled ore. Production of gold significantly increased compared to the second quarter of 2024 due to higher grades and recoveries. Production of gold was also higher than the first quarter of 2025, largely due to higher recoveries.

During the first half of 2025, production of copper, gold and silver was 13,830 tonnes, 11,231 ounces and 144,520 ounces, respectively. Year-to-date copper and gold production was higher than the same period in 2024 and silver production was lower as a result of the same quarterly variances mentioned above.


Quantities of copper, gold and silver sold during the second quarter of 2025 were higher than the first quarter of 2025 as the Company reduced copper concentrate inventory levels that were elevated at the end of March 2025. Year-to-date sales quantity changes compared to the same period in 2024 reflect the changes in production during the periods.

       

*Copper equivalent production is calculated using the quarter average LME prices for each metal. Copper Mountain mine production are stated at 100%. On April 30, 2025 Hudbay completed the acquisition of the remaining 25% interest in the Copper Mountain mine and now owns 100%.


Cost Performance

Combined mine, mill and G&A unit operating costs in the second quarter of 2025 were C$24.51 per tonne milled, higher than the second quarter of 2024, but lower than the first quarter of 2025. The increase compared to the second quarter of 2024 was primarily due to lower ore milled. The decrease compared to the first quarter of 2025 was due to lower milling and G&A costs and higher ore milled, partially offset by higher mining costs.

Combined mine, mill and G&A unit operating costs during the six months ended June 30, 2025 were C$25.12 per tonne milled versus C$21.65 per tonne milled in the first half of 2024 primarily due to lower tonnes milled.

Cash cost and sustaining cash cost per pound of copper produced, net of by-product credits, in the second quarter of 2025 were $2.39 and $5.18, respectively. Cash costs were 11% and 2% lower than in the second quarter of 2024 and first quarter of 2025, respectively, largely due to higher by-product credits. Sustaining cash costs were 7% lower than the second quarter of 2024 mainly as a result of improvements to cash costs, partially offset by higher capital including planned higher capitalized stripping costs in accordance with Hudbay's accelerated stripping program to access higher grade ore. Sustaining cash costs were 22% higher than the first quarter of 2025 due to higher sustaining capital including higher capitalized stripping costs.

Cash cost and sustaining cash cost per pound of copper produced, net of by-product credits, during the six months ended June 30, 2025 were $2.41 and $4.69, respectively. Variances with the same period last year were for largely the same factors affecting the quarterly variances.


British Columbia Guidance Outlook

    Three months ended2 Six months ended2 Guidance
    Jun. 30, 2025 Jun. 30, 2024 Jun. 30, 2025 Jun. 30, 2024 Annual 2025
Contained metal in concentrate produced          
Copper tonnes 6,634 6,719 13,830 13,743 28,000 - 41,000
Gold oz 5,670 4,454 11,231 8,871 18,500 - 28,000
Silver oz 65,040 77,227 144,520 165,603 245,000 - 365,000
Cost per pound of copper produced          
Cash cost1 $/lb 2.39 2.67 2.41 3.09 2.45 - 3.45
1 Cash cost, net of by-product credits, are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.
2 Copper Mountain mine results are stated at 100%. On April 30, 2025 Hudbay completed the acquisition of the remaining 25% interest in the Copper Mountain mine and now owns 100%.

Hudbay remains on track to achieve its 2025 production guidance for all metals in British Columbia and continues to expect higher production in the second half of the year as the mill improvement projects take effect. With cash costs in the first half of the year at the low-end of the 2025 guidance range, Hudbay is well positioned to achieve the full year 2025 cash cost guidance range in British Columbia.


FINANCIAL REVIEW

Financial Results

In the second quarter of 2025, Hudbay recorded net earnings attributable to owners of $117.7 million compared to a net loss on the same basis of $16.5 million in the second quarter of 2024, representing an increase in net earnings attributable to owners of $134.2 million. Year-to-date in 2025, Hudbay recorded net earnings attributable to owners of $218.1 million compared to net earnings on the same basis of $5.8 million for the same period in 2024, representing an increase in earnings attributable to owners of $212.3 million.

The following table provides further details on the makeup of this variance:

(in $ millions) Three months ended
June 30, 2025
Six months ended
June 30, 2025
Increase (decrease) in components of earnings:    
Revenues 110.9 180.8
Cost of sales    
Mine operating costs (13.2) (5.0)
Depreciation and amortization 1.2 2.4
Selling and administrative expenses (2.3) 0.6
Exploration expenses (3.4) (4.7)
Re-evaluation adjustment - environmental obligation 11.1 (7.0)
Other expenses 4.1 15.2
Net finance expense 44.3 73.9
Tax expense (17.7) (40.5)
Increase in net earnings for the period 135.0 215.7
Change in non-controlling interest (0.8) (3.4)
Increase in net earnings attributable to owners for the period 134.2 212.3

Revenue

Revenue for the second quarter of 2025 was $536.4 million, $110.9 million higher than the same period in 2024, primarily due to higher sales volume of copper, gold and silver, and strong copper and gold realized price in the second quarter of 2025.

Revenue during the six months ended June 30, 2025 was $1,131.3 million, $180.8 million higher than in 2024, primarily as a result of higher metal prices and higher copper and silver sales volumes.

While a majority of revenues continue to be from copper, gold represented a significant portion of total revenues at 36% for the three months ended June 30, 2025. This is as a result of exposure to higher gold prices compared to the second quarter of 2024, increasing commodity diversification and improving overall revenues.


The following table provides further details on these variances:

(in $ millions)   Three months ended
June 30, 2025
    Six months ended
June 30, 2025
 
             
Metals prices1            
(Lower) higher copper prices   (12.7 )   32.4  
Higher gold prices   57.0     140.1  
(Lower) higher zinc prices   (1.1 )   0.8  
(Lower) higher silver prices   (0.9 )   4.5  
Sales volumes            
Higher copper sales volumes   45.8     25.1  
Higher (lower) gold sales volumes   2.6     (65.0 )
Lower zinc sales volumes   (6.6 )   (9.2 )
Higher silver sales volumes   6.2     3.9  
Other            
Molybdenum and other volume and pricing differences   1.4     1.6  
Variable consideration adjustments   -     13.7  
Effect of lower treatment and refining charges   19.2     32.9  
Increase in revenue in 2025 compared to 2024   110.9     180.8  
1 See discussion below for further information regarding metals prices.
2 Copper Mountain mine results are stated at 100%.

Hudbay's revenue by significant product type is summarized below:

    Three months ended     Six months ended  
(in $ millions)   Jun. 30, 2025     Mar. 31, 2025     Jun. 30, 2024     Jun. 30, 2025     Jun. 30, 2024  
Copper   297.1     302.3     259.3     599.4     544.5  
Gold   189.2     194.2     119.5     383.4     297.7  
Zinc   7.1     14.3     15.5     21.4     30.4  
Silver   13.9     14.3     10.9     28.2     23.1  
Molybdenum   19.1     20.9     16.0     40.0     34.2  
Other metals   -     (0.2 )   0.5     (0.2 )   0.5  
Revenue from contracts   526.4     545.8     421.7     1,072.2     930.4  
Amortization of deferred revenue - gold   5.9     8.4     5.5     14.3     21.9  
Amortization of deferred revenue - silver   9.5     11.0     6.1     20.5     16.7  
Amortization of deferred revenue - variable consideration adjustments - prior periods   -     9.9     -     9.9     (3.8 )
Pricing and volume adjustments1   (2.1 )   33.8     14.7     31.7     35.6  
Treatment and refining charges   (3.3 )   (14.0 )   (22.5 )   (17.3 )   (50.3 )
Revenue   536.4     594.9     425.5     1,131.3     950.5  
1 Pricing and volume adjustments represents mark-to-market adjustments on provisionally prices sales, realized and unrealized changes to fair value for non-hedge derivative contracts (QP hedges) and adjustments to originally invoiced weights and assays.

For further detail on variable consideration adjustments, refer to note 16 of Hudbay's consolidated interim financial statements.


Realized sales prices

This measure is intended to enable management and investors to understand the average realized price of metals sold to third parties in each reporting period. The average realized price per unit sold does not have any standardized meaning prescribed by IFRS, is unlikely to be comparable to similar measures presented by other issuers and should not be considered in isolation or a substitute for measures of performance prepared in accordance with IFRS.

For sales of copper, zinc, gold and silver Hudbay may enter into non-hedge derivatives ("QP hedges") which are intended to manage the provisional pricing risk arising from quotational period terms in concentrate sales agreements. The gains and losses on QP hedges are included in the calculation of realized prices. Hudbay expects that gains and losses on QP hedges will offset provisional pricing adjustments on concentrate sales contracts.

Hudbay's realized prices for the three months and three and six months ended June 30, 2025 and 2024, respectively, are summarized below:

  Realized prices1 for the   Realized prices1 for the
Three months ended   Six months ended
Prices LME QTD
2025
2
Jun. 30,
2025
Mar. 31,
2025
Jun. 30,
2024
LME YTD
20252
Jun. 30,
2025
Jun. 30,
2024
Copper $/lb 4.32 4.36 4.49 4.56 4.28 4.41 4.19
Gold3 $/oz 3,289 3,135 3,002 2,222 3,075 3,062 2,043
Zinc $/lb   1.15 1.29 1.33   1.24 1.19
Silver3 $/oz   26.17 25.91 27.13   26.04 23.68
1 Realized prices exclude refining and treatment charges and are on the sale of finished metal or metal in concentrate. Realized prices include the effect of provisional pricing adjustments on prior period sales.
2 London Metal Exchange average for Cash copper and zinc prices.
3 Sales of gold and silver from Constancia mine are subject to Hudbay's precious metals stream agreement with Wheaton, pursuant to which Hudbay recognizes deferred revenue for precious metals deliveries and also receive cash payments. Stream sales are included within realized prices and their respective deferred revenue and cash payment rates can be found on page 35 of this MD&A.

In addition to QP hedges, the Company may periodically undertake metal price hedging in accordance with Board approved policies to achieve strategic objectives, including locking in favourable metal prices to ensure minimum cash flows during or after the construction of a mine or during a period of reduced liquidity, to manage cash flows at shorter life or higher cost operations or as part of a financing arrangement. The realized prices, denoted in the table above, excludes the impact of derivative mark-to-market gains and losses on these non-QP hedges, which are included in change in fair value of financial instruments in Hudbay's condensed consolidated interim statements of income.

As of June 30, 2025, Hudbay had no non-QP hedges outstanding.


The following tables provide a reconciliation of average realized price per unit sold, by metal, to revenues as shown in the consolidated interim financial statements.

Three months ended June 30, 2025  
(in $ millions except for realized price and payable metal sold) 1   Copper     Gold     Zinc     Silver     Molybdenum     Other     Total  
Revenue from contracts   297.1     189.2     7.1     13.9     19.1     -     526.4  
Amortization of deferred revenue   -     5.9     -     9.5     -     -     15.4  
Pricing and volume adjustments 3   (4.7 )   0.7     0.2     -     1.7     -     (2.1 )
Revenue, including mark-to-market on QP hedges 4   292.4     195.8     7.3     23.4     20.8     -     539.7  
Realized non-QP derivative mark-to-market   (0.4 )   -     -     -     -     -     (0.4 )
By-product credits 5   292.0     195.8     7.3     23.4     20.8     -     539.3  
Payable metal in concentrate and doré sold 6   30,354     62,466     2,871     894,160     -     -     -  
Realized price 7   4.36     3,135     1.15     26.17     -     -     -  
Three months ended March 31, 2025  
Revenue from contracts   302.3     194.2     14.3     14.3     20.9     (0.2 )   545.8  
Amortization of deferred revenue   -     8.4     -     11.0     -     -     19.4  
Pricing and volume adjustments 3   12.0     22.8     (0.5 )   0.8     (1.3 )   -     33.8  
Revenue, including mark-to-market on QP hedges 4   314.3     225.4     13.8     26.1     19.6     (0.2 )   599.0  
Realized non-QP derivative mark-to-market   (1.9 )   -     -     -     -     -     (1.9 )
By-product credits 5   312.4     225.4     13.8     26.1     19.6     (0.2 )   597.1  
Payable metal in concentrate and doré sold 6   31,768     75,092     4,857     1,006,968     -     -     -  
Realized price 7   4.49     3,002     1.29     25.91     -     -     -  
Three months ended June 30, 2024  
Revenue from contracts 2   259.3     119.5     15.5     10.9     16.0     0.5     421.7  
Amortization of deferred revenue   -     5.5     -     6.1     -     -     11.6  
Pricing and volume adjustments 3   -     11.2     (0.5 )   1.1     2.9     -     14.7  
Revenue, including mark-to-market on QP hedges 4   259.3     136.2     15.0     18.1     18.9     0.5     448.0  
Realized non-QP derivative mark-to-market 5   (2.6 )   -     -     -     -     -     (2.6 )
By-product credits 4   256.7     136.2     15.0     18.1     18.9     0.5     445.4  
Payable metal in concentrate and doré sold 6   25,799     61,295     5,133     667,036     -     -     -  
Realized price 7   4.56     2,222     1.33     27.13     -     -     -  
1 Average realized price per unit sold may not calculate based on amounts presented in this table due to rounding.
2 As per consolidated interim financial statements.
3 Pricing and volume adjustments represents mark-to-market adjustments on provisionally priced sales, realized and unrealized changes to fair value for QP hedge derivative contracts and adjustments to originally invoiced weights and assays.
4 Revenue, including mark-to-market on QP hedges is used in the calculation of realized price.
5 By-product credits subtotal is used in the calculated of cash cost per pound of copper and ounce of gold produced, net of by-product credits. Cash cost per pound of copper and per ounce of gold produced, net of by-product credits, are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.
6 Copper and zinc shown in metric tonnes and gold and silver shown in ounces.
7 Realized price for copper and zinc in $/lb and realized price for gold and silver in $/oz.



Six months ended June 30, 2025  
(in $ millions except for realized price and payable metal sold) 1   Copper     Gold     Zinc     Silver     Molybdenum     Other     Total  
Revenue from contracts   599.4     383.4     21.4     28.2     40.0     (0.2 )   1,072.2  
Amortization of deferred revenue   -     14.3     -     20.5     -     -     34.8  
Pricing and volume adjustments 3   7.3     23.5     (0.3 )   0.8     0.4     -     31.7  
Revenue, including mark-to-market on QP hedges 4   606.7     421.2     21.1     49.5     40.4     (0.2 )   1,138.7  
Realized non-QP derivative mark-to-market   (2.3 )   -     -     -     -     -     (2.3 )
By-product credits 5   604.4     421.2     21.1     49.5     40.4     (0.2 )   1,136.4  
Payable metal in concentrate and doré sold 6   62,122     137,558     7,728     1,901,128     -     -     -  
Realized price 7   4.41     3,062     1.24     26.04     -     -     -  
Six months ended June 30, 2024  
(in $ millions except for realized price and payable metal sold) 1   Copper     Gold     Zinc     Silver     Molybdenum     Other     Total  
Revenue from contracts 2   544.5     297.7     30.4     23.1     34.2     0.5     930.4  
Amortization of deferred revenue   -     21.9     -     16.7     -     -     38.6  
Pricing and volume adjustments 3   4.7     26.5     (0.9 )   1.3     4.0     -     35.6  
Revenue, including mark-to-market on QP hedges 4   549.2     346.1     29.5     41.1     38.2     0.5     1,004.6  
Realized non-QP derivative mark-to-market   (2.6 )   -     -     -     -     -     (2.6 )
By-product credits 5   546.6     346.1     29.5     41.1     38.2     0.5     1,002.0  
Payable metal in concentrate and doré sold 6   59,407     169,376     11,252     1,735,884     -     -     -  
Realized price 7   4.19     2,043     1.19     23.68     -     -     -  
1 Average realized price per unit sold may not calculate based on amounts presented in this table due to rounding.
2 As per financial statements.
3 Pricing and volume adjustments represents mark-to-market adjustments on provisionally priced sales, realized and unrealized changes to fair value for QP hedge derivative contracts and adjustments to originally invoiced weights and assays.
4 Revenue, including mark-to-market on QP hedges is used in the calculation of realized price.
5 By-product credits subtotal is used in the calculated of cash cost per pound of copper and ounce of gold produced, net of by-product credits. Cash cost per pound of copper and per ounce of gold produced, net of by-product credits, are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A.
6 Copper and zinc shown in metric tonnes and gold and silver shown in ounces.
7 Realized price for copper and zinc in $/lb and realized price for gold and silver in $/oz.

The price, quantity and mix of metals sold affect Hudbay's revenue, operating cash flow and gross profit. Revenue from metals sales can vary from quarter to quarter due to production levels, shipping volumes and transfer of risk and title to customers.


Precious metals - stream sales and realized price breakdown

The following table shows a breakdown of realized prices for precious metals inclusive of stream and offtaker revenue. It further identifies the components of the realized price for stream revenues between the amortized drawdown rate and cash payment rate.

(in $ millions except for realized price and payable metal sold)   Gold Silver
  Three months ended Six months ended Three months ended Six months ended
Revenue   Jun. 30,
2025
Jun. 30,
2024
Jun. 30,
2025
Jun. 30,
2024
Jun. 30,
2025
Jun. 30,
2024
Jun. 30,
2025
Jun. 30,
2024
Stream   8.8 8.2 21.4 33.1 13.3 8.8 28.9 23.8
Offtaker   187.0 128.0 399.8 313.0 10.1 9.3 20.6 17.3
Revenue, including mark-to-market on QP hedges 3   195.8 136.2 421.2 346.1 23.4 18.1 49.5 41.1
                   
Payable metal sold                  
Stream oz 6,827 6,640 16,615 26,763 624,787 421,623 1,354,674 1,147,738
Offtaker oz 55,639 54,655 120,943 142,613 269,373 245,413 546,454 588,146
Total payable metal sold oz 62,466 61,295 137,558 169,376 894,160 667,036 1,901,128 1,735,884
                   
Deferred revenue drawdown rate1 $/oz 860 817 860 817 15.06 14.56 15.06 14.56
Cash rate2 $/oz 425 420 425 420 6.26 6.20 6.26 6.20
Stream realized price $/oz 1,285 1,237 1,285 1,237 21.32 20.76 21.32 20.76
Offtaker realized price $/oz 3,361 2,342 3,306 2,195 37.49 37.90 37.70 29.41
Realized price $/oz 3,135 2,222 3,062 2,043 26.17 27.13 26.04 23.68
1 Deferred revenue drawdown rates for gold and silver do not include variable consideration adjustments.
2 The gold and silver cash rate for Peru increased by 1% from $400/oz and $5.90/oz effective August 4, 2019. Subsequently every year, on August 4, the cash rate will increase by 1% compounded.
3 Revenue, including mark-to-market on QP hedges is used in the calculation of realized price.

Subsequent to the variable consideration adjustment recorded on January 1, 2025, the deferred revenue amortization is recorded in Peru at $860 per ounce gold and $15.06 per ounce silver (June 30, 2024 - $817 per ounce gold and $14.56 per ounce silver).


Cost of Sales

Hudbay's detailed cost of sales is summarized as follows:

(in $ millions)   Three months ended     Six months ended  
  Jun. 30, 2025     Mar. 31, 2025     Jun. 30, 2024     Jun. 30, 2025     Jun. 30, 2024  
Peru                              
Mining   28.1     31.0     31.3     59.1     60.5  
Milling   57.8     44.4     51.3     102.2     95.0  
Changes in product inventory   4.0     13.8     1.1     17.8     15.2  
Depreciation and amortization   56.0     68.2     58.9     124.2     129.9  
G&A   23.4     22.6     19.6     46.0     42.7  
Inventory adjustments   1.1     0.4     -     1.5     -  
Freight, royalties and other charges   13.4     16.3     13.5     29.7     32.2  
Total Peru cost of sales   183.8     196.7     175.7     380.5     375.5  
Manitoba                              
Mining   33.5     38.3     42.3     71.8     86.6  
Milling   13.4     14.4     15.2     27.8     31.7  
Changes in product inventory   3.8     (1.0 )   (2.4 )   2.8     (2.9 )
Depreciation and amortization   23.6     23.9     24.7     47.5     51.3  
Overhead costs incurred during temporary suspension (cash)   3.2     -     -     3.2     -  
Inventory adjustments   1.0     -     -     1.0     -  
G&A   14.3     15.1     10.9     29.4     22.5  
Freight, royalties and other charges   5.1     5.7     5.7     10.8     11.8  
Total Manitoba cost of sales   97.9     96.4     96.4     194.3     201.0  
British Columbia1                              
Mining`   24.2     21.9     19.5     46.1     48.0  
Milling   21.4     21.8     21.5     43.2     44.9  
Changes in product inventory   3.6     (0.8 )   11.3     2.8     7.3  
Depreciation and amortization   16.8     16.0     14.0     32.8     25.7  
G&A   6.3     6.6     5.4     12.9     9.3  
Inventory adjustments   1.4     0.8     -     2.2     -  
Freight, royalties and other charges   4.5     4.2     4.1     8.7     9.2  
Total British Columbia cost of sales   78.2     70.5     75.8     148.7     144.4  
Cost of sales   359.9     363.6     347.9     723.5     720.9  

1 Copper Mountain mine results are stated at 100%.

Total cost of sales for the second quarter of 2025 was $359.9 million, reflecting an increase of $12.0 million compared to the second quarter of 2024. Peru cost of sales increased by $8.1 million in the second quarter of 2025, compared to the same period of 2024 mainly due to higher milling costs in line with higher production, G&A and change in product inventory. Manitoba cost of sales increased by $1.5 million in the second quarter of 2025 when compared to the same period of 2024, primarily due to change in product inventory, higher G&A and direct charges to cost of sales related to overhead costs during the temporary suspension of operations in Manitoba in June related to the wildfire evacuation orders. These increases have been offset with a decrease in mining and milling costs due to decreased production during the shutdown. British Columbia cost of sales increased by $2.4 million primarily driven by higher mining, depreciation and inventory adjustments, partially offset by changes in product inventory.


Total cost of sales for the six months ended June 30, 2025 was $723.5 million, reflecting an increase of $2.6 million from the same period in 2024 in part due to $4.3 million of incremental operating costs from British Columbia. In addition, Peru cost of sales increased by $5.0 million as a result of an increase in milling and G&A costs offset by decrease in depreciation and amortization. Manitoba cost of sales decreased by $6.7 million as a result of a decrease in mining and milling costs due to decreased production, offset by changes in product inventory and higher G&A costs.

For details on unit operating costs, refer to the respective tables in the "Operations Review" section of this MD&A.

For the second quarter of 2025, other significant variances in expenses, compared to the same period in 2024, include the following:

- Net finance expenses decreased by $44.3 million, primarily due to a decrease in foreign exchange loss of $20.9 million, decrease in losses of $11.8 million from non-QP hedges, a decrease in mark-to-market loss of $3.6 million from investments, a decrease of $2.9 million from interest expense on long-term debt benefiting from the retirement of some senior notes, an increase of $2.0 million from interest income and a $1.9 million decrease in the relative revaluation loss of the gold prepayment liability.

- Other expenses decreased by $4.1 million, primarily due to a decrease of $2.0 million in the amortization of community costs, decrease of $1.7 million in the write-off of previously capitalized PP&E costs, an increase of $1.0 million from Marubeni option agreement proceeds, an increase of $0.9 million in the amortization of obligation related to flow through share deferred liability and a decrease of $0.8 million in care and maintenance related to the Flin Flon assets. These were partially offset by $2.1 million in costs related to the Manitoba wildfire emergency response efforts during the second quarter.

- Re-evaluation adjustment - environmental gain increased by $11.1 million compared to the same period of 2024 due to the relative revaluation of the environmental reclamation provision on Hudbay's Manitoba non-producing sites from changes in long term risk-free discount rates and inflation rates.

Given the long term nature of the reclamation cash flows, the related environmental reclamation provision is highly sensitive to changes in inflation rates and long-term risk-free discount rates and, as such, Hudbay may continue to experience significant quarterly environmental reclamation provision revaluations. 

For the year-to-date 2025, other significant variances in expenses, compared to the same period in 2024, included the following:

- Net finance expenses decreased by $73.9 million due to a $28.8 million decrease in net foreign exchange loss, decrease in losses of $12.1 million from non-QP hedges, a decrease in mark-to-market loss of $12.0 million from investments, a $6.2 million decrease in interest expense on long-term debt, a decrease in the relative revaluation loss of the gold prepayment liability of $5.4 million, and an increase of $5.1 million in interest income.

- Other expenses decreased by $15.2 million, primarily due to a decrease of $10.2 million in write-off of previously capitalized PP&E costs, a decrease of $3.2 million in the amortization of community costs, an increase of $2.1 million from Marubeni option agreement proceeds, an increase of $2.1 million in the amortization of obligation related to flow through share deferred liability, a decrease of $1.1 million in restructuring and a decrease of $0.5 million in care and maintenance. These were partially offset by $2.1 million in costs related to the Manitoba wildfire emergency response efforts during the second quarter of 2025 and an increase of $0.8 million in evaluation costs.

- Exploration expenses increased by $4.7 million, primarily due to Hudbay's planned Snow Lake exploration program consisting of modern geophysical programs and multi-phased drilling campaigns, much of which was funded by flow-through financing.

- Re-evaluation adjustment - environmental provision gain decreased by $7.0 million due to the same reasons as outlined above in the quarterly variance analysis.


Tax Expense

For the three and six months ended June 30, 2025, tax expense increased by $17.7 million and $40.5 million, respectively, compared to the same period in 2024. The following table provides further details:

(in $ millions)   Three months ended     Six months ended  
  Jun. 30, 2025     Jun. 30, 2024     Jun. 30, 2025     Jun. 30, 2024  
Current tax expense - income tax   30.3     20.5     65.5     55.8  
Deferred tax (recovery) expense - income tax1   (10.5 )   (8.7 )   10.2     (5.2 )
Total income tax expense   19.8     11.8     75.7     50.6  
Current tax expense - mining tax   17.6     10.8     36.2     23.5  
Deferred tax expense (recovery) - mining tax1   1.0     (1.9 )   (1.4 )   (4.1 )
Total mining tax expense   18.6     8.9     34.8     19.4  
Tax expense   38.4     20.7     110.5     70.0  
1 Deferred tax expense (recovery) represents Hudbay's draw down/increase of non-cash deferred income and mining tax assets/liabilities.

Income Tax Expense/Recovery

Applying the estimated Canadian statutory income tax rate of 26.7% to Hudbay's net earnings before taxes of $324.4 million for the year-to-date of 2025 would have resulted in a tax expense of approximately $86.6 million; however, Hudbay recorded an income tax expense of $75.7 million. The primary items causing Hudbay's effective income tax rate to be different than the 26.7% estimated Canadian statutory income tax rate are the following:

- Foreign exchange on the translation of deferred tax balances to group currency, resulting in a deferred tax recovery of $17.9 million

- The tax expense with respect to Hudbay's foreign operations is recorded using an income tax rate other than the Canadian statutory income tax rate of 26.7%, resulting in a tax expense of $20.6 million.

- Current mining tax deductions resulted in a tax recovery of $11.1 million.

Mining Tax Expense

For the year-to-date of 2025, Hudbay recorded a mining tax expense of $34.8 million. Effective mining tax rates can vary significantly based on the composition of Hudbay's earnings and the expected amount of mining taxable profits. Corporate costs and other costs not related to mining operations are not deductible in computing mining profits. A brief description of how mining taxes are calculated in Hudbay's various business units is discussed below.

Manitoba

The Province of Manitoba imposes mining tax on earnings related to the sale of mineral products mined in the Province of Manitoba (mining taxable profit) at the following rates:

- 10% of total mining taxable earnings if mining profit is C$50 million or less;

- Between mining earnings of C$50 and $C55 million, mining tax is equal to a minimum of C$5 million plus mining earnings less C$50 million multiplied by 65%;

- 15% of total mining taxable earnings if mining profits are between C$55 million and C$100 million;

- Between mining earnings of C$100 million and C$105 million, mining tax is equal to a minimum of C$15 million plus mining earnings less C$100 million multiplied by 57%; and

- 17% of total mining taxable earnings if mining profits exceed C$105 million.

Hudbay estimates that the deferred tax rate that will be applicable when temporary differences reverse will be approximately 10.0%.

Peru

The Peruvian government imposes two parallel mining tax regimes, the Special Mining Tax and the Modified Royalty, on companies' operating mining income on a sliding scale, with progressive rates ranging from 2.0% to 8.4% and 1.0% to 12.0%, respectively. Based on financial forecasts, Hudbay has recorded a deferred tax liability as at June 30, 2025, at the tax rate expected to apply when temporary differences reverse.


British Columbia

The Province of British Columbia imposes a 13% net revenue tax on the sale of mineral products mined in the province of British Columbia after the mine owner has recovered the capital invested in the mine and its "Cumulative Expenditure Account" ("CEA") no longer has a balance. The tax is paid on the profit in excess of the capital that has been invested in the mine. British Columbia mineral tax is deductible for federal and provincial income tax purposes.

While there is a balance in the CEA account, the mine owner must pay a "Net Current Proceeds" ("NCP") tax of 2%. Any amounts paid as NCP can then be claimed in the future against net revenue taxes payable.

Hudbay estimates that the effective tax rate that will be applicable when temporary differences reverse will be approximately 9.49%.

LIQUIDITY AND CAPITAL RESOURCES

As at June 30, 2025, Hudbay's total liquidity of $1,050.2 million includes $625.5 million in cash as well as undrawn total availability of $424.7 million under Hudbay's revolving credit facilities.

Senior Unsecured Notes

As at June 30, 2025, Hudbay had $525.0 million aggregate principal amount of 2026 Notes and $542.4 million aggregate principal amount of 2029 Notes.

During the second quarter of 2025, the Company made open market purchases of $50 million of Hudbay's 4.5% senior notes due April 2026 ("2026 Notes"), at a discount to par. As at June 30, 2025, Hudbay has presented all of the 2026 Notes as a current liability amounting to $523.8 million, which affected working capital in the quarter.

Senior Secured Revolving Credit Facilities

Hudbay has two senior secured revolving credit facilities with total commitments of $450 million ("the Credit Facilities") for its Canadian and Peruvian businesses on substantially similar terms and conditions. These facilities include an accordion feature that allows Hudbay the option to increase the facility by an additional $150 million at Hudbay's discretion over the four-year term.

As at June 30, 2025, there were no cash drawings under the Credit Facilities and $25.3 million in letters of credit secured under the Canadian Facility.

As at June 30, 2025, Hudbay was in compliance with its covenants under the Credit Facilities.

C$130 Million Bilateral Letter of Credit Facility

Hudbay has a C$130.0 million bilateral letter of credit facility ("LC Facility") with a major Canadian financial institution. The LC Facility has no financial covenants and enables Hudbay to issue up to C$130.0 million of letters of credit to beneficiaries on an unsecured basis at attractive rates, including C$30.0 million sub-limit for financial letters of credit. As at June 30, 2025, the Manitoba business unit had drawn $56.7 million in letters of credit under the LC Facility.

Surety Bonds and Letters of Credit

As at June 30, 2025, the Arizona business unit had $18.4 million in surety bonds issued to support future reclamation and closure obligations and the Peru business unit had $135.0 million in letters of credit and surety bonds issued with various Peruvian financial institutions to support future reclamation and other operating matters. In addition, the British Columbia business unit had $48.1 million in surety bonds issued to support future reclamation and $1.0 million in surety bonds issued to support the hydro used at Copper Mountain mine, and to Fisheries and Oceans Canada for fish monitoring. No cash collateral is required to be posted under these surety bonds.

Working Capital

Working capital decreased by $484.5 million to $26.8 million from December 31, 2024 to June 30, 2025, primarily due to an increase in current portion of long-term debt of $523.8 million as the 2026 Notes are now maturing within one year, a decrease in short-term investment of $40.0 million from the release of guaranteed investment certificates, a decrease in inventories of $33.2 million primarily from decreasing finished goods inventory levels, an increase in other liabilities of $10.1 million, a decrease in prepaid and other current assets of $6.7 million and an increase in lease liabilities of $5.1 million. Partially offsetting these items was an increase in cash and cash equivalents of $83.7 million, a decrease in taxes payable of $63.0 million, a decrease in trade and other payables of $10.3 million and, a decrease in deferred revenue of $5.1 million.


Cash Flows

The following table summarizes Hudbay's cash flows for the three months ended June 30, 2025, March 31, 2025 and June 30, 2024:

(in $ millions)   Three months ended     Six months ended  
  Jun. 30, 2025     Mar. 31, 2025     Jun. 30, 2024     Jun. 30, 2025     Jun. 30, 2024  
Operating cash flow before change in non-cash working capital   193.9     163.5     123.7     357.4     271.2  
Change in non-cash working capital   66.0     (38.7 )   16.5     27.3     8.6  
Cash generated from operating activities   259.9     124.8     140.2     384.7     279.8  
Cash used in investing activities   (100.6 )   (84.3 )   (129.2 )   (184.9 )   (188.1 )
Cash (used in) generated from financing activities   (98.9 )   (20.8 )   189.8     (119.7 )   142.2  
Effect of movement in exchange rates on cash   2.5     1.1     (1.4 )   3.6     0.1  
Net increase in cash   62.9     20.8     199.4     83.7     234.0  

Cash Flow from Operating Activities

Operating cash flow before change in non-cash working capital was $193.9 million during the second quarter of 2025, reflecting an increase of $70.2 million compared to the second quarter of 2024. Cash generated from operating activities was $259.9 million during the second quarter of 2025, an increase of $119.7 million compared to the same period in 2024. The increase in operating cash flows before change in working capital compared with the second quarter of 2024 was primarily the result of higher sales volume for majority of the metals, and stronger realized gold prices partially offset by higher cash taxes paid which are a function of higher profits in earlier quarters in Peru and Manitoba that were subsequently payable.

Year-to-date cash generated from operating activities was $384.7 million in 2025, an increase of $104.9 million compared to the same period in 2024. Operating cash flow before changes in non-cash working capital for the first half of 2025 was $357.4 million, an increase of $86.2 million compared to the same period in 2024. The increase in operating cash flow before changes in working capital was primarily the result of higher metal prices for all metals and higher copper sales volumes. This was partially offset by lower gold sales volumes and by a significant increase in cash taxes paid of $76.0 million mainly at Hudbay's Manitoba and Peru operations, compared to the same period in 2024.

Cash Flow from Investing and Financing Activities

During the second quarter of 2025, Hudbay spent $199.5 million in investing and financing activities, primarily driven by $121.7 million in capital expenditures, $50.0 million toward the repurchase of senior unsecured notes, $29.9 million in interest paid on Hudbay's long-term debt, $13.9 million in capitalized lease and equipment financing payments, $6.0 million in the Copper Mountain non-controlling interest acquisition payment including associated transaction costs and $5.2 million in community agreement payments. These cash outflows were partially offset by cash inflows of $20.0 million from the release of the guaranteed investment certificates, $6.5 million of investment income received and $4.2 million of proceeds from equity issuance, net of share issuance costs.

Year-to-date, Hudbay spent $304.6 million in investing and financing activities, primarily driven by $213.1 million in capital expenditures, $50.0 million of Hudbay's senior unsecured notes repurchased, $29.9 million in interest paid on Hudbay's long-term debt, $27.3 million in capitalized lease and equipment financing payments, $13.8 million in purchase of investments, $9.0 million in community agreement payments, $6.1 million in financing costs paid and $6.0 million in the Copper Mountain non-controlling interest acquisition payment and related transaction costs. This was offset by cash inflows of $40.0 million from the release of the guaranteed investment certificates, $12.5 million of investment income received and $4.2 million of proceeds from equity issuance, net of share issuance costs.


Capital Expenditures

The following summarizes accrued and cash additions to capital assets for the periods indicated:

    Three months ended     Six months ended     Guidance  
    Jun. 30,
2025
    Mar. 31,
2025
    Jun. 30,
2024
    Jun. 30,
2025
    Jun. 30,
2024
    Annual  
(in $ millions)   20252  
Peru sustaining capital expenditures1   44.4     28.5     29.5     72.9     54.7     170.0  
Manitoba sustaining capital expenditures   11.3     12.5     14.6     23.8     24.3     60.0  
British Columbia sustaining capital expenditures1,3   32.9     21.5     36.9     54.4     53.2     135.0  
Total sustaining capital expenditures   88.6     62.5     81.0     151.1     132.2     365.0  
Arizona capitalized costs4   13.7     11.4     5.4     25.1     9.8     110.0  
Peru growth capitalized expenditures   1.3     0.9     0.1     2.2     0.2     25.0  
Manitoba growth capitalized expenditures   1.6     2.2     1.6     3.9     2.9     15.0  
British Columbia growth capitalized expenditures   16.5     11.0     0.7     27.5     1.0     75.0  
Capitalized exploration   3.5     1.1     2.0     4.5     4.5     10.0  
Right-of-use asset and equipment financing additions   13.9     15.0     22.5     28.9     37.7        
Community agreement additions   0.6     -     -     0.6     1.8        
Non-cash capitalized stripping   8.5     6.4     5.3     14.9     9.1        
Grants   (0.6 )   (0.9 )   -     (1.5 )   (2.4 )      
Other capitalized costs   (0.2 )   (0.1 )   -     (0.3 )   -        
Total other capitalized expenditures   58.8     47.0     37.6     105.8     64.6        
Total accrued capital additions   147.4     109.5     118.6     256.9     196.8        
                                     
Reconciliation to cash capital additions:                                    
Other capitalized costs2   (23.0 )   (21.4 )   (27.8 )   (44.4 )   (48.6 )      
Change in capital accruals and other   (2.7 )   3.3     (1.3 )   0.6     3.6        
Acquisition of property, plant & equipment - cash   121.7     91.4     89.5     213.1     151.8        
1 Peru and British Columbia sustaining capital expenditures include capitalized stripping costs.
2 Other capitalized costs primarily include right-of-use lease and equipment financing additions, which are excluded from guidance in 2025, community agreement additions and non-cash capitalized stripping
3 Includes 100% of Copper Mountain mine production. On April 30, 2025 Hudbay completed the acquisition of the remaining 25% interest in the Copper Mountain mine and now owns 100%.
4 With the announcement of the JV Transaction Hudbay expects to accelerate detailed engineering, long lead items and other de-risking activities by advancing $20 million in growth capital expenditures to 2025 from future years, updating total 2025 Arizona growth spending guidance to $110 million compared to the original 2025 guidance of $90 million.

For the three and six months ended June 30, 2025, total capital additions increased by $28.8 million and $60.1 million, respectively, compared to the same period in 2024, primarily due to an increase in Peru sustaining capital expenditures, British Columbia growth capitalized expenditures, Arizona capitalized costs and non-cash capitalized stripping. These capital increases were planned as sustaining capital typically increases in the second quarter in Peru after the rainy season is complete, and growth capital was expected to increase as Hudbay continues to execute its growth plans in British Columbia and Arizona. This was partially offset by reduced sustaining capital expenditures in Manitoba and British Columbia and a decrease in lease and equipment financing additions.

Sustaining capital expenditures in Peru for the three and six months ended June 30, 2025 were $44.4 million and $72.9 million, respectively, representing an increase of $14.9 million and $18.2 million, respectively, compared to the same periods in 2024 as a result of the timing of various stripping campaigns and civil work projects. Sustaining capital expenditures in Manitoba for the three and six months ended June 30, 2025 were $11.3 million and $23.8 million, respectively, representing a decrease of $3.3 million and $0.5 million, respectively, compared to the same periods in 2024 mostly due to lower capital development at Lalor.  Sustaining capital expenditures in British Columbia for the three and six months ended June 30, 2025 were $32.9 million and $54.4 million, respectively, which included $24.3 million and $38.9 million, respectively, of capitalized stripping related to Hudbay's planned three-year accelerated stripping campaign to access higher grade ore.


Growth capital expenditures in Peru for the three and six months ended June 30, 2025 were $1.3 million and $2.2 million, respectively, representing an increase of $1.2 million and $2.0 million, respectively. The increase mainly relates to the implementation of the pebble crusher in Peru. Growth capital spending in Manitoba for the three and six months ended June 30, 2025 was $1.6 million and $3.9 million, respectively, primarily related to the exploration and haulage drifts advancement towards the 1901 deposit. Arizona's capital expenditures for the three and six months ended June 30, 2025 were $13.7 million and $25.1 million, respectively, mainly related to feasibility study activities and ongoing carrying costs for Copper World. Growth capital expenditures in British Columbia for the three and six months ended June 30, 2025 were $16.5 million and $27.5 million, respectively, representing an increase of $15.8 million and an increase of $26.5 million, respectively compared to the same periods in 2024. The increase mainly relates to the Copper Mountain mill optimization project to convert Ball Mill 3 to a second SAG Mill, which is intended to increase nominal capacity at Copper Mountain.

Capitalized exploration for the three months and six months ended June 30, 2025 was $3.5 million and $4.5 million, respectively.

Capital Commitments

As at June 30, 2025, Hudbay had outstanding capital commitments in Canada of approximately $28.9 million, of which $10.4 million can be terminated, approximately $33.7 million in Peru primarily related to sustaining capital commitments and exploration option agreements, all of which can be terminated, and approximately $74.3 million in Arizona, primarily related to Hudbay's Copper World project, of which $72.1 million can be terminated.


Contractual Obligations

The following table summarizes Hudbay's significant contractual obligations as at June 30, 2025:

  Total Less than
12 months
13 - 36
months
37 - 60
months
More than
60 months
Payment Schedule (in $ millions)
Long-term debt obligations1 1,232.1 584.3 71.4 576.4 -
Equipment financing and lease obligations 206.5 78.2 81.5 33.3 13.5
Purchase obligation - capital commitments 136.9 86.0 19.5 20.6 10.8
Purchase obligation - other commitments2 1,318.3 498.3 348.0 123.1 348.9
Deferred payment and contingent obligations 39.8 3.0 6.0 13.5 17.3
Pension and other employee future benefits obligations3 94.2 6.3 12.9 8.1 66.9
Community agreement obligations4, 5 108.7 26.6 25.7 8.7 47.7
Decommissioning and restoration obligations5 497.5 8.6 15.9 9.2 463.8
Total 3,634.0 1,291.3 580.9 792.9 968.9
1 Long-term debt obligations include scheduled interest payments, as well as principal repayments
2 Primarily made up of trades payables, accrued liabilities, long-term agreements with operational suppliers, obligations for power purchases, concentrate handling and fleet and port services.
3 Discounted.
4 Represents community agreement obligations and various finalized land user agreements, including Pampacancha.
5 Undiscounted before inflation.

In addition to the contractual obligations included in the above payment schedule, Hudbay also has the following commitments which impact Hudbay's financial position:

- A profit-sharing plan with most Manitoba employees;

- A profit-sharing plan with all Peru employees;

- Share-based compensation;

- Wheaton precious metals stream agreement for the Constancia mine;

- Government royalty payments related to the Constancia mines;

- Participation agreements related to the Copper Mountain mine, and

- Contracts related to future production and sales, such as royalties.

Outstanding Share Data

As of August 11, 2025, the final trading day prior to the date of this MD&A, there were 395,679,988 common shares of Hudbay issued and outstanding. In addition, there were 2,948,231 stock options and 50,820 common share purchase warrants outstanding.

FINANCIAL RISK MANAGEMENT

The Financial Risk Management risks in this MD&A are not exhaustive. Please also refer to the heading "Risk Factors" in Hudbay's most recent Annual Information Form, for a discussion of the additional risk factors that may affect Hudbay's business, operations and financial condition, a copy of which is available on the Company's SEDAR+ and EDGAR profiles.


TREND ANALYSIS AND QUARTERLY REVIEW

A detailed quarterly and annual summary of financial and operating performance can be found in the "Summary of Results" section at the end of this MD&A. The following table sets forth selected consolidated financial information for each of Hudbay's eight most recently completed quarters:

(in $ millions, except per share amounts, production on a copper equivalent basis and average realized copper price)   2025     2024     2023  
  Q2     Q1     Q42     Q3     Q2     Q1     Q42     Q3  
Production on a copper equivalent basis (tonnes)   53,693     58,611     77,769     60,895     47,164     62,120     77,951     71,335  
Average realized copper price ($/lb)   4.36     4.49     4.09     4.24     4.56     3.91     3.77     3.77  
Average realized gold price ($/oz)   3,135     3,002     2,327     2,582     2,222     1,941     2,062     1,738  
Revenue   536.4     594.9     584.9     485.8     425.5     525.0     602.2     480.5  
Gross profit   176.5     231.3     184.4     139.8     77.6     152.0     196.8     106.4  
Income before tax   153.1     171.3     103.7     79.7     0.4     67.8     81.0     84.1  
Net income (loss)   114.7     99.2     19.3     50.4     (20.3 )   18.5     33.5     45.5  
Net income (loss) - attributable   117.7     100.4     21.2     49.8     (16.5 )   22.4     30.7     45.1  
Adjusted net earnings1 - attributable   75.5     93.8     70.3     50.3     0.2     59.4     68.6     24.3  
Earnings (loss) per share attributable:                                                
Basic and diluted   0.30     0.25     0.05     0.13     (0.04 )   0.06     0.09     0.13  
Adjusted net earnings1 per share - attributable   0.19     0.24     0.18     0.13     0.00     0.17     0.20     0.07  
Operating cash flow before change in non-cash working capital   193.9     163.5     231.5     186.3     123.7     147.5     246.5     182.0  
Adjusted EBITDA1   245.2     287.2     257.3     206.2     145.0     215.0     274.4     190.7  
Adjusted EBITDA LTM1   995.9     895.7     823.3     840.6     825.1     761.3     647.8     498.5  
1 Adjusted net earnings (loss) - attributable to owners, adjusted net earnings (loss) per share - attributable to owners, adjusted EBITDA, and adjusted EBITDA last twelve months ("LTM") are non-GAAP financial performance measure with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A
2 Annual consolidated results may not calculate based on amounts presented in this table due to rounding.

On a quarterly basis, the Company's revenue is primarily impacted by metal prices, production mix and sales volumes of the key metals Hudbay produces. In addition to these factors, gross profit, net earnings (loss) attributable, earnings (loss) per share attributable, operating cash flow before change in non-cash working capital and adjusted EBITDA are also impacted by input costs. Net earnings (loss) and earnings (loss) per share are further impacted by net finance expense and re-evaluation adjustments of Hudbay's closed site environmental provision.

During the second quarter of 2025, copper equivalent production decreased to 53,693 tonnes because of reduced copper, gold and silver output. This was primarily due to the temporary suspension of operations in Manitoba in June related to the wildfire evacuation order. This was partially offset by record average gold prices and high copper prices which positively impacted gross profits and contributing to increased net income and higher earnings per share in the second quarter of 2025. While higher profitability led to significant cash taxes paid of $43.9 million, the business's strong operating performance caused the overall impact to operating cash flow before changes in non-cash working capital to remain positive. Higher foreign exchange gains due to the strengthening of the Canadian dollar along with declining net interest cost as a result of Hudbay's deleveraging efforts led to reduced net finance expenses in the second quarter. Adjusted EBITDA over the last twelve months hit a record high of $995.9 million as a result of strong operating performances at the Manitoba and Peru operations resulting in higher sales volumes, benefiting from high copper and gold prices. Net debt to EBITDA is now at its lowest level since the development of the Peru operation more than a decade ago given the business's strong operating performance in conjunction with the same aforementioned deleveraging efforts. The lower net debt and stronger cash position is despite larger reinvestment in the business through growing capital expenditures in recent years.

During the first quarter of 2025, copper equivalent production decreased to 58,611 tonnes as expected, reflecting lower production of copper, gold and silver primarily related to lower planned grades in Peru as the final stripping phase at the Pampacancha deposit was underway. This was partially offset by higher gold production in Manitoba and record average gold prices and high copper prices which positively impacted gross profits.


The Manitoba operations delivered strong quarterly throughput as expected and unlocked better-than-expected grades, resulting in higher production that exceeded Hudbay's quarterly cadence expectations. Strong cost control, a weakening Canadian dollar and meaningful exposure to gold by-product credits resulted in consolidated cash cost1 and sustaining cash cost1 per pound of copper produced, net of by-product credits, in the first quarter of 2025 of $(0.45) and $0.72, respectively, contributing to the increased gross margin and very strong growth in adjusted EBITDA. Higher profits since 2023 in Peru and Canada have resulted in significant cash taxes paid of $117.5 million in the first quarter of 2025, which is reflected in operating cash flow before changes in non-cash working capital. In addition, deleveraging efforts including the repurchases of the Company's senior secured notes over the course of 2024 led to declining net interest cost to service Hudbay's long term debt. 

During the fourth quarter of 2024, copper equivalent production increased to 77,769 tonnes. Hudbay's Manitoba and Peru operations delivered strong quarterly production as expected and unlocked higher grade helping the Company exceed 2024 annual gold guidance. Strong cost control and meaningful exposure to gold by-product credits resulted in consolidated cash cost1 and sustaining cash cost1 per pound of copper produced, net of by-product credits1, in the fourth quarter of 2024 of $0.45 and $1.37, respectively, contributing to Hudbay's outperformance of its improved full year 2024 cost guidance. Furthermore, the settlement of the gold prepayment liability in the third quarter of 2024, allowed Hudbay to capitalize on surging gold prices. Since acquiring Copper Mountain in June 2023, Hudbay has moved to optimization efforts which have been focused on ramping up the mining fleet to execute a planned accelerated stripping campaign to gain access to higher grades, as well as plant improvement initiatives to improve mill reliability and recoveries.

During the third quarter of 2024, profitability and cash flows grew compared to the second quarter of 2024. This strength was attributable in part to higher gold, copper and zinc production compared to the second quarter of 2024, along with returning strength in commodity prices including record gold prices. These impacts offset planned lower mined grades observed in Peru in the third quarter of 2024 and the higher cash mining taxes paid in Peru resulting from higher profitability over the past several quarters. Strong operating cost control continued into the third quarter of 2024 resulting from a number of operational initiatives and high levels of mill throughput being experienced throughout the business.

During the second quarter of 2024, realized copper and gold prices continued to climb which overcame the decline in sales volumes of concentrate compared to the first quarter of 2024. Expected lower mined grades observed for the same metals in Peru and Manitoba were the primary factor for the decline in production since the first quarter of the year. Cost control remained favourable as Hudbay continued to track within cost guidance given the expected cadence in the year's production profile. Higher mining taxes continued as Hudbay experienced higher profitability over the past several quarters. Lastly, volatile inter-period copper and gold prices led to relatively high mark-to-market adjustments for Hudbay's strategic non-QP hedging program and high share prices for Hudbay's common shares led to higher share-based compensation expenses. This led to a total of $19.5 million in mark-to-market adjustments to be added back in Hudbay's adjusted net earnings - attributable to owners measure.

The first quarter of 2024 and the fourth quarter of 2023 reflected the continuation of strong copper, gold and silver production that commenced in the third quarter of 2023. The increase in copper, gold and silver prices in the first quarter of 2024 also contributed to strong revenue and profitability in the quarter.

Third quarter of 2023 results reflected significantly higher copper and gold production and sales volumes from the high grade zones of the Pampacancha deposit and higher gold and copper grade zones at Lalor resulting in a significant increase in Hudbay's revenues, gross profits and earnings.


NON-GAAP FINANCIAL PERFORMANCE MEASURES

Adjusted net earnings (loss) attributable to owners, adjusted net earnings (loss) per share attributable to owners, adjusted EBITDA, realized prices, net debt, net debt to adjusted EBITDA, free cash flow, cash cost, sustaining and all-in sustaining cash cost per pound of copper produced, cash cost and sustaining cash cost per ounce of gold produced, combined unit cost and ratios based on these measures are non-GAAP performance measures. These measures do not have a meaning prescribed by IFRS and are therefore unlikely to be comparable to similar measures presented by other issuers. These measures should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS and are not necessarily indicative of gross profit or cash flow from operations as determined under IFRS. Other companies may calculate these measures differently.

Management believes adjusted net earnings (loss) attributable to owners and adjusted net earnings (loss) per share attributable to owners provides an alternate measure of the Company's performance for the current period and gives insight into its expected performance in future periods. These measures are used internally by the Company to evaluate the performance of its underlying operations and to assist with its planning and forecasting of future operating results. As such, the Company believes these measures are useful to investors in assessing the Company's underlying performance. Hudbay provides adjusted EBITDA to help users analyze Hudbay's results and to provide additional information about its ongoing cash generating potential in order to assess its capacity to service and repay debt, carry out investments and cover working capital needs. Net debt is shown because it is a performance measure used by the Company to assess its financial position. Net debt to adjusted EBITDA is shown because it is a performance measure used by the Company to assess its financial leverage and debt capacity. Realized price is shown to understand the average realized price of metals sold to third parties in each reporting period. Free cash flow is shown as it provides investors and management additional information in assessing the Company's ability to generate cash flow from current operations after investing in capital to sustain the operations. Cash cost, sustaining and all-in sustaining cash cost per pound of copper produced are shown because Hudbay believes they help investors and management assess the performance of its operations, including the margin generated by the operations and the Company. Cash cost and sustaining cash cost per ounce of gold produced are shown because Hudbay believes they help investors and management assess the performance of its Manitoba operations. Combined unit cost is shown because Hudbay believes it helps investors and management assess the cost structure and margins that are not impacted by variability in by-product commodity prices.


Adjusted Net Earnings - Attributable to owners

Adjusted net earnings attributable to owners represents net earnings (loss) excluding certain impacts such as mark-to-market adjustments, foreign exchange (gains) loss, revaluation adjustment - environmental provisions for closed sites, variable consideration adjustment related to stream agreements, impairment charges and reversal of impairment charges on assets, (gain) loss on disposal of assets, other items that are not indicative of the underlying operating performance of Hudbay's core business; and tax effect and non-controlling interest of the previously discussed items. These measures are not necessarily indicative of net earnings (loss) as determined under IFRS. The following table provides a reconciliation of net earnings and non-controlling interest per the condensed consolidated interim statements of income, to adjusted net earnings attributable to owners of the Company for the three months ended June 30 and March 31, 2025 and June 30, 2024 and six months ended June 30, 2025 and 2024.

    Three months ended     Six months ended  
(in $ millions)   Jun. 30,
2025
    Mar. 31,
2025
    Jun. 30,
2024
    Jun. 30,
2025
    Jun. 30,
2024
 
Earnings (loss) for the period   114.7     99.2     (20.3)     213.9     (1.8)  
Tax expense   38.4     72.1     20.7     110.5     70.0  
Earnings before tax   153.1     171.3     0.4     324.4     68.2  
Adjusting items:                              
Mark-to-market adjustments1   6.3     (3.1)     19.5     3.2     32.2  
Foreign exchange (gain) loss   (18.9 )   (3.1 )   2.1     (22.0 )   6.9  
Re-evaluation adjustment - environmental provision   (13.8 )   12.8     (2.7 )   (1.0 )   (8.0 )
Manitoba cost of sales and other expense from temporary shutdown   5.3     -     -     5.3     -  
Variable consideration adjustment - stream revenue and accretion   -     (10.5 )   -     (10.5 )   4.0  
Inventory adjustments   3.5     1.2     -     4.7     -  
Restructuring charges   -     0.1     0.3     0.1     1.2  
Reduction of obligation to renounce flow-through share expenditures, net of provisions   (1.2 )   (1.9 )   (0.3 )   (3.1 )   (1.0 )
Write-down/loss on disposal of PP&E   0.3     0.6     2.1     0.9     11.1  
Changes in other provisions (non-capital)   -     0.7     -     0.7     -  
Adjusted earnings before income taxes   134.6     168.1     21.4     302.7     114.6  
Tax expense   (38.4 )   (72.1 )   (20.7 )   (110.5 )   (70.0 )
Tax impact of adjusting items   (23.0 )   (2.8 )   (2.4 )   (25.8 )   11.2  
Adjusted net earnings (loss)   73.2     93.2     (1.7 )   166.4     55.8  
Adjusted net earnings attributable to non-controlling interest:                              
Net loss for the period   3.0     1.2     3.8     4.2     7.6  
Adjusting items, including tax impact   (0.7 )   (0.6 )   (1.9 )   (1.1 )   (3.9 )
Adjusted net earnings - attributable to owners   75.5     93.8     0.2     169.5     59.5  
Adjusted net earnings ($/share) - attributable to owners   0.19     0.24     0.00     0.43     0.17  
Basic weighted average number of common shares outstanding (millions)   395.1     395.0     368.3     395.0     359.6  
1 Includes changes in fair value of the gold prepayment liability, Canadian junior mining investments, other financial assets and liabilities at fair value through net earnings and share-based compensation expenses (recoveries). Also includes gains and losses on disposition of investments.

After adjusting reported net earnings for those items not considered representative of the Company's core business or indicative of future operations, the Company had adjusted net earnings - attributable in the second quarter of 2025 of $75.5 million or $0.19 earnings per share.


Adjusted EBITDA

Adjusted EBITDA is net earnings before net finance expense/income, tax expense/recoveries, depreciation and amortization of property, plant and equipment and deferred revenue, as well as certain other adjustments. Hudbay calculates adjusted EBITDA by excluding certain adjustments included within Hudbay's adjusted net earnings attributable measure which reflects the underlying performance of Hudbay's core operating activities. The measure also removes the impact of non-cash items and financing costs that are not associated with measuring the underlying performance of Hudbay's operations. However, Hudbay's adjusted EBITDA is not the measure defined as EBITDA under Hudbay's senior notes or revolving credit facilities and may not be comparable with performance measures with the same name reported by other companies. Adjusted EBITDA should not be considered as a substitute for earnings, which is calculated in accordance with IFRS. Hudbay provides adjusted EBITDA to help users analyze their results and to provide additional information about Hudbay's ongoing cash generating potential in order to assess its capacity to service and repay debt, carry out investments and cover working capital needs.

The following table presents the reconciliation of earnings per the condensed consolidated interim statements of income, to adjusted EBITDA for the three months ended June 30 and March 31, 2025 and June 30, 2024 and six months ended June 30, 2025 and 2024:

    Three months ended     Six months ended  
(in $ millions)   Jun. 30,
2025
    Mar. 31,
2025
    Jun. 30,
2024
    Jun. 30,
2025
    Jun. 30,
2024
 
Earnings (loss) for the period   114.7     99.2     (20.3)     213.9     (1.8)  
Add back:                              
Tax expense   38.4     72.1     20.7     110.5     70.0  
Net finance expense   -     14.4     44.3     14.4     88.3  
Other expense   7.1     5.2     11.2     12.3     27.5  
Depreciation and amortization   96.4     108.1     97.6     204.5     206.9  
Amortization of deferred revenue and variable consideration adjustment   (15.4 )   (29.3 )   (11.5 )   (44.7 )   (34.7 )
Adjusting items (pre-tax):                              
Re-evaluation adjustment - environmental provision   (13.8 )   12.8     (2.7 )   (1.0 )   (8.0 )
Inventory adjustments   3.5     1.2     -     4.7     -  
Manitoba cost of sales charge from temporary shutdown.   3.2     -     -     3.2     -  
Option agreement proceeds (Marubeni)   1.0     1.5     -     2.5     0.4  
Realized loss on non-QP hedges   (0.4 )   (1.9 )   (2.6 )   (2.3 )   (2.6 )
Share-based compensation expense 1   10.5     3.9     8.3     14.4     14.0  
Adjusted EBITDA   245.2     287.2     145.0     532.4     360.0  
1 Share-based compensation expense reflected in cost of sales and selling and administrative expenses.

Net Debt

The following table presents Hudbay's calculation of net debt as at June 30, 2025 and December 31, 2024:

(in $ millions)   Jun. 30,
2025
    Dec. 31,
2024
 
Total debt   1,059.6     1,107.5  
Cash and cash equivalents   (625.5 )   (541.8 )
Short-term investments   -     (40.0 )
Net debt   434.1     525.7  


Net Debt to Adjusted EBITDA Ratio

The following table presents Hudbay's calculation of net debt to adjusted EBITDA, both metrics have been reconciled above to the most comparable IFRS measure, as at June 30, 2025 and December 31, 2024:

(in $ millions, except net debt to adjusted EBITDA ratio) Jun. 30,
2025
Dec. 31,
2024
Net debt 434.1 525.7
Adjusted EBITDA for the last twelve months 995.9 823.3
Net debt to adjusted EBITDA 0.4 0.6

The following table presents the reconciliation of earnings per the condensed consolidated interim statements of income, to adjusted EBITDA for the twelve months ended June 30, 2025 and December 31, 2024:

    Twelve months ended  
(in $ millions)   Jun. 30,
2025
    Dec. 31,
2024
 
Earnings for the period   283.6     67.8  
Add back:            
Tax expense   224.2     183.8  
Net finance expense   74.8     148.7  
Other expense   42.3     57.4  
Depreciation and amortization   424.2     426.6  
Amortization of deferred revenue and variable consideration adjustment   (80.4 )   (70.5 )
Adjusting items (pre-tax):            
Re-evaluation adjustment - environmental provision   3.5     (3.5 )
Inventory adjustments   7.6     2.9  
Manitoba cost of sales charge from temporary shutdown.   3.2     -  
Option agreement proceeds (Marubeni)   2.5     0.4  
Realized loss on non-QP hedges   (8.6 )   (8.9 )
Share-based compensation expense 1   19.0     18.6  
Adjusted EBITDA for the last twelve months   995.9     823.3  
1 Share-based compensation expense reflected in cost of sales and selling and administrative expenses.


The following table presents the calculation of the last twelve months adjusted EBITDA:

    Three months ended     LTM1  
Trailing Adjusted EBITDA
(in $ millions)
  Jun. 30, 2025     Mar. 31, 2025     Dec. 31, 2024     Sept. 30, 2024  
Earnings for the period   114.7     99.2     19.3     50.4     283.6  
Add back:                              
Tax expense   38.4     72.1     84.4     29.3     224.2  
Net finance expense   -     14.4     34.4     26.0     74.8  
Other expenses   7.1     5.2     22.1     7.9     42.3  
Depreciation and amortization   96.4     108.1     122.2     97.5     424.2  
Amortization of deferred revenue and variable consideration adjustment   (15.4 )   (29.3 )   (26.2 )   (9.5 )   (80.4 )
Adjusting items (pre-tax):                              
Re-evaluation adjustment - environmental provision   (13.8 )   12.8     2.5     2.0     3.5  
Inventory adjustments   3.5     1.2     1.3     1.6     7.6  
Cash portion of Manitoba cost of sales direct charge from temporary shutdown   3.2     -     -     -     3.2  
Realized loss on non-QP hedges   (0.4 )   (1.9 )   (4.2 )   (2.1 )   (8.6 )
Option agreement proceeds (Marubeni)   1.0     1.5     -     -     2.5  
Share-based compensation expenses2   10.5     3.9     1.5     3.1     19.0  
Adjusted EBITDA   245.2     287.2     257.3     206.2     995.9  
1 LTM (last twelve months) as of June 30, 2025.
2 Share-based compensation expense reflected in cost of sales and administrative expenses.

Free Cash Flow

Hudbay defines free cash flow as cash generated from operations adjusted for changes in non-cash working capital, sustaining capital expenditures and cash payments from operating sites related to leases, equipment financings and community agreements. Free cash flow is intended to provide additional information only and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS Accounting Standards. This measure is not necessarily indicative of cash flow from operations as determined under IFRS Accounting Standards. The following table presents Hudbay's calculation of free cash flow and reconciles to the most directly comparable IFRS measure:

  Three months ended Six months ended
(in $ millions) Jun. 30,
2025
Jun. 30,
2024
Jun. 30,
2025
Jun. 30,
2024
Cash generated from operations 259.9 140.2 384.7 279.8
Add back:        
Change in non-cash working capital 66.0 16.5 27.3 8.6
Cash sustaining capital expenditures1 106.1 91.2 182.2 151.5
Free cash flow 87.8 32.5 175.2 119.7
         
Cash sustaining capital expenditures1        
Total sustaining capital costs2 88.6 80.9 151.1 132.2
Capitalized lease and equipment financing cash payments -  operating sites 13.4 9.6 26.2 17.8
Community agreement cash payments 4.1 0.7 4.9 1.5
Cash sustaining capital expenditures1 106.1 91.2 182.2 151.5
1 Excludes amortization of decommissioning and restoration PP&E assets and accretion of decommissioning and restoration liabilities related to producing sites.
2 See reconciliation to property, plant & equipment additions on page 61 of this MD&A.


The following table presents the calculation of the last twelve months free cash flow:

    Three months ended     LTM1  
(in $ millions)   Jun. 30, 2025     Mar. 31, 2025     Dec. 31, 2024     Sept. 30, 2024  
Cash generated from operations   259.9     124.8     238.1     148.2     771.0  
Add back:                              
Change in non-cash working capital   66.0     (38.7 )   6.6     (40.1 )   (6.2 )
Cash sustaining capital expenditures2   106.1     76.1     82.6     99.9     364.7  
Free cash flow   87.8     87.4     148.9     88.4     412.5  
                               
Cash sustaining capital expenditures2                              
Total sustaining capital costs3   88.6     62.5     71.6     89.4     312.1  
Capitalized lease and equipment financing cash payments - operating sites   13.4     12.8     10.3     10.2     46.7  
Community agreement cash payments   4.1     0.8     0.7     0.3     5.9  
Cash sustaining capital expenditures2   106.1     76.1     82.6     99.9     364.7  
1 LTM (last twelve months) as at June 30, 2025
2 Excludes amortization of decommissioning and restoration PP&E assets and accretion of decommissioning and restoration liabilities related to producing sites.
3 See reconciliation to property, plant & equipment additions on page 61 of this MD&A.


Cash Cost, Sustaining and All-in Sustaining Cash Cost (Copper Basis)

Cash cost per pound of copper produced ("cash cost") is a non-GAAP measure that management uses as a key performance indicator to assess the performance of its operations. Hudbay's calculation designates copper as the primary metal of production as it has been the largest component of revenues. The calculation is presented in four manners:

- Cash cost, before by-product credits - This measure is gross of by-product revenues and is a function of the efforts and costs incurred to mine and process all ore mined. However, the measure divides this aggregate cost over only pounds of copper produced, Hudbay's primary metal of production. This measure is generally less volatile from period to period, as it is not affected by changes in the price received for by-product metals. It is, however, affected by the relative mix of copper concentrate and zinc concentrate production, where an increase in production of zinc concentrate will tend to result in an increase in cash cost under this measure.

- Cash cost, net of by-product credits - In order to calculate the net cost to produce and sell copper, the net of by-product credits measure subtracts the revenues realized from the sale of the metals other than copper. The by-product revenues from zinc, gold, and silver are significant and are integral to the economics of Hudbay's operations. The economics that support Hudbay's decision to produce and sell copper would be different if Hudbay did not receive revenues from the other significant metals being extracted and processed. This measure provides management and investors with an indication of the minimum copper price consistent with positive operating margins, assuming realized by-product metal prices are consistent with those prevailing during the reporting period. It also serves as an important operating statistic that management and investors utilize to measure its operating performance versus that of its competitors. However, it is important to understand that if by-product metal prices decline alongside copper prices, the cash cost net of by-product credits would increase, requiring a higher copper price than that reported to maintain positive cash flows and operating margins.

- Sustaining cash cost, net of by-product credits - This measure is an extension of cash cost that includes cash sustaining capital expenditures, including payments on capitalized leases, capitalized sustaining exploration, net smelter returns royalties, payments on certain long-term community agreements, as well as accretion and amortization for expected decommissioning activities for producing assets. It does not include corporate selling and administrative expenses. It provides a more fulsome measurement of the cost of sustaining production than cash cost, which is focused on operating costs only.

- All-in sustaining cash cost, net of by-product credits - This measure is an extension of sustaining cash cost that includes corporate G&A, regional costs, accretion and amortization for community agreements relating to current operations, and accretion for expected decommissioning activities for non-producing sites. Due to the inclusion of corporate selling and administrative expenses, all-in sustaining cash cost is presented on a consolidated basis only.

The tables below present a detailed build-up of cash cost and sustaining cash cost, net of by-product credits, by business unit in addition to consolidated all-in sustaining cash cost, net of by-product credits, and reconciliations between cash cost, net of by-product credits, to the most comparable IFRS measures of cost of sales for the three months ended June 30, and March 31, 2025 and June 30, 2024 and six months ended June 30, 2025 and June 30, 2024. Cash cost, net of by-product credits may not calculate exactly based on amounts presented in the tables below due to rounding.

Consolidated Three months ended Six months ended
(in thousands) Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024 Jun. 30, 2025 Jun. 30, 2024
Peru 47,863 44,738 42,366 92,601 96,547
Manitoba 3,554 7,648 5,825 11,202 12,767
British Columbia 14,626 15,864 14,813 30,490 30,298
Net pounds of copper produced1 66,043 68,250 63,004 134,293 139,612
1 Contained copper in concentrate.

Consolidated   Three months ended  
    Jun. 30, 2025     Mar. 31, 2025     Jun. 30, 2024  
Cash cost per pound of copper produced   $ millions     $/lb     $ millions     $/lb     $ millions     $/lb  
Cash cost, before by-product credits   245.6     3.72     253.7     3.72     260.7     4.13  
By-product credits   (247.3 )   (3.74 )   (284.7 )   (4.17 )   (188.7 )   (2.99 )
Cash cost, net of by-product credits   (1.7 )   (0.02 )   (31.0 )   (0.45 )   72.0     1.14  



Consolidated   Six months ended  
    Jun. 30, 2025     Jun. 30, 2024  
Cash cost per pound of copper produced   $ millions     $/lb     $ millions     $/lb  
Cash cost, before by-product credits   499.3     3.72     539.3     3.86  
By-product credits   (532.0 )   (3.96 )   (455.4 )   (3.26 )
Cash cost, net of by-product credits   (32.7 )   (0.24 )   83.9     0.60  

Consolidated Three months ended
  Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024
Cash cost per pound of copper produced $ millions $/lb $ millions $/lb $ millions $/lb
Mining 85.8 1.30 91.2 1.34 93.1 1.47
Milling 92.6 1.40 80.6 1.18 88.0 1.40
G&A 43.1 0.66 43.6 0.64 35.3 0.56
Onsite costs 221.5 3.36 215.4 3.16 216.4 3.43
Treatment & refining 3.3 0.05 14.0 0.21 22.5 0.36
Freight & other 20.8 0.31 24.3 0.35 21.8 0.34
Cash cost, before by-product credits 245.6 3.72 253.7 3.72 260.7 4.13

Consolidated Six months ended
  Jun. 30, 2025 Jun. 30, 2024
Cash cost per pound of copper produced $ millions $/lb $ millions $/lb
Mining 177.0 1.32 195.1 1.40
Milling 173.2 1.29 171.6 1.23
G&A 86.7 0.64 73.5 0.52
Onsite costs 436.9 3.25 440.2 3.15
Treatment & refining 17.3 0.13 50.3 0.36
Freight & other 45.1 0.34 48.8 0.35
Cash cost, before by-product credits 499.3 3.72 539.3 3.86



Consolidated   Three months ended  
    Jun. 30, 2025     Mar. 31, 2025     Jun. 30, 2024  
Supplementary cash cost information   $ millions     $/lb 1     $ millions     $/lb 1     $ millions     $/lb 1  
By-product credits2:                                    
Zinc   7.3     0.11     13.8     0.20     14.9     0.23  
Gold3   195.8     2.96     225.4     3.30     136.2     2.16  
Silver3   23.4     0.35     26.1     0.38     18.1     0.29  
Molybdenum & other   20.8     0.32     19.4     0.29     19.5     0.31  
Total by-product credits   247.3     3.74     284.7     4.17     188.7     2.99  
Reconciliation to IFRS:                                    
Cash cost, net of by-product credits   (1.7 )         (31.0 )         72.0        
By-product credits   247.3           284.7           188.7        
Treatment and refining charges   (3.3 )         (14.0 )         (22.5 )      
Inventory adjustments   3.5           1.2           -        
Share-based compensation expense   0.9           0.7           0.6        
Change in product inventory   11.4           12.0           10.0        
Royalties   2.2           1.9           1.5        
Overhead costs incurred during temporary suspension   3.2           -           -        
Depreciation and amortization4   96.4           108.1           97.6        
Cost of sales5   359.9           363.6           347.9        
1 Per pound of copper produced.
2 By-product credits are computed as revenue per financial statements, including amortization of deferred revenue and pricing and volume adjustments. For more information, please see the realized price reconciliation table on page 33 of this MD&A for these figures.
3 Gold and silver by-product credits do not include variable consideration adjustments with respect to stream arrangements. Variable consideration adjustments are cumulative adjustments to gold and silver stream deferred revenue primarily associated with the net change in mineral reserves and resources or amendments to the mine plan that would change the total expected deliverable ounces under the precious metal streaming arrangement. For the three months ended June 30, 2025 the variable consideration adjustments amounted to $nil (three months ended June 30, 2024 - $nil and March 31, 2025 - gain of $9.9 million).
4 Depreciation is based on concentrate sold.
5 As per consolidated interim financial statements.



Consolidated   Six months ended  
    Jun. 30, 2025     Jun. 30, 2024  
Supplementary cash cost information   $ millions     $/lb1     $ millions     $/lb1  
By-product credits2:                        
Zinc   21.1     0.16     29.5     0.21  
Gold3   421.2     3.13     346.0     2.48  
Silver3   49.5     0.37     41.2     0.29  
Molybdenum & other   40.2     0.30     38.7     0.28  
Total by-product credits   532.0     3.96     455.4     3.26  
Reconciliation to IFRS:                        
Cash cost, net of by-product credits   (32.7 )         83.9        
By-product credits   532.0           455.4        
Treatment and refining charges   (17.3 )         (50.3 )      
Inventory adjustments   4.7           -        
Share-based compensation expense   1.6           1.0        
Change in product inventory   23.4           19.6        
Royalties   4.1           4.4        
Overhead costs incurred during temporary suspension   3.2           -        
Depreciation and amortization4   204.5           206.9        
Cost of sales5   723.5           720.9        
1 Per pound of copper produced.
2 By-product credits are computed as revenue per financial statements, including amortization of deferred revenue and pricing and volume adjustments. For more information, please see the realized price reconciliation table on page 33 of this MD&A for these figures.
3 Gold and silver by-product credits do not include variable consideration adjustments with respect to stream arrangements. Variable consideration adjustments are cumulative adjustments to gold and silver stream deferred revenue primarily associated with the net change in mineral reserves and resources or amendments to the mine plan that would change the total expected deliverable ounces under the precious metal streaming arrangement. For the six months ended June 30, 2025 the variable consideration adjustments amounted to a gain of $9.9 million (six months ended June 30, 2024 - loss of $3.8 million).
4 Depreciation is based on concentrate sold.
5 As per consolidated interim financial statements.



Peru Three months ended Six months ended
(in thousands) Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024 Jun. 30, 2025 Jun. 30, 2024
Net pounds of copper produced1 47,863 44,738 42,366 92,601 96,547
1 Contained copper in concentrate.

Peru   Three months ended  
    Jun. 30, 2025     Mar. 31, 2025     Jun. 30, 2024  
Cash cost per pound of copper produced   $ millions     $/lb     $ millions     $/lb     $ millions     $/lb  
Mining   28.1     0.59     31.0     0.69     31.3     0.74  
Milling   57.8     1.21     44.4     0.99     51.3     1.21  
G&A   23.2     0.48     22.5     0.51     19.4     0.46  
Onsite costs   109.1     2.28     97.9     2.19     102.0     2.41  
Treatment & refining   (0.1 )   0.00     6.7     0.15     11.1     0.26  
Freight & other   12.4     0.25     15.2     0.34     12.6     0.30  
Cash cost, before by-product credits   121.4     2.53     119.8     2.68     125.7     2.97  
By-product credits   (51.8 )   (1.08 )   (70.2 )   (1.57 )   (50.3 )   (1.19 )
Cash cost, net of by-product credits   69.6     1.45     49.6     1.11     75.4     1.78  

Peru   Six months ended  
    Jun. 30, 2025     Jun. 30, 2024  
Cash cost per pound of copper produced   $ millions     $/lb     $ millions     $/lb  
Mining   59.1     0.64     60.5     0.63  
Milling   102.2     1.10     95.0     0.98  
G&A   45.7     0.50     42.4     0.44  
Onsite costs   207.0     2.24     197.9     2.05  
Treatment & refining   6.6     0.07     26.1     0.27  
Freight & other   27.6     0.30     29.2     0.30  
Cash cost, before by-product credits   241.2     2.61     253.2     2.62  
By-product credits   (122.0 )   (1.32 )   (154.6 )   (1.60 )
Cash cost, net of by-product credits   119.2     1.29     98.6     1.02  



Peru   Three months ended  
    Jun. 30, 2025     Mar. 31, 2025     Jun. 30, 2024  
Supplementary cash cost information   $ millions     $/lb 1     $ millions     $/lb 1     $ millions     $/lb 1  
By-product credits2:                                    
Gold3   17.3     0.36     35.0     0.78     21.6     0.51  
Silver3   13.7     0.29     15.6     0.35     9.7     0.23  
Molybdenum   20.8     0.43     19.6     0.44     19.0     0.45  
Total by-product credits   51.8     1.08     70.2     1.57     50.3     1.19  
Reconciliation to IFRS:                                    
Cash cost, net of by-product credits   69.6           49.6           75.4        
By-product credits   51.8           70.2           50.3        
Treatment and refining charges   0.1           (6.7 )         (11.1 )      
Inventory adjustments   1.1           0.4           -        
Share-based compensation expenses   0.2           0.1           0.2        
Change in product inventory   4.0           13.8           1.1        
Royalties   1.0           1.1           0.9        
Depreciation and amortization4   56.0           68.2           58.9        
Cost of sales5   183.8           196.7           175.7        
1 Per pound of copper produced.
2 By-product credits are computed as revenue per financial statements, including amortization of deferred revenue and pricing and volume adjustments. For more information, please see the realized price reconciliation table on page 33 of this MD&A.
3 Gold and silver by-product credits do not include variable consideration adjustments with respect to stream arrangements.
4 Depreciation is based on concentrate sold.
5 As per the consolidated interim financial statements.



Peru   Six months ended  
    Jun. 30, 2025     Jun. 30, 2024  
Supplementary cash cost information   $ millions     $/lb 1     $ millions     $/lb 1  
By-product credits2:                        
Gold3   52.3     0.56     91.1     0.94  
Silver3   29.3     0.32     25.3     0.26  
Molybdenum   40.4     0.44     38.2     0.40  
Total by-product credits   122.0     1.32     154.6     1.60  
Reconciliation to IFRS:                        
Cash cost, net of by-product credits   119.2           98.6        
By-product credits   122.0           154.6        
Treatment and refining charges   (6.6 )         (26.1 )      
Inventory adjustments   1.5           -        
Share-based compensation expenses   0.3           0.3        
Change in product inventory   17.8           15.2        
Royalties   2.1           3.0        
Depreciation and amortization4   124.2           129.9        
Cost of sales5   380.5           375.5        
1 Per pound of copper produced.
2 By-product credits are computed as revenue per financial statements, including amortization of deferred revenue and pricing and volume adjustments. For more information, please see the realized price reconciliation table on page 33 of this MD&A.
3 Gold and silver by-product credits do not include variable consideration adjustments with respect to stream arrangements.
4 Depreciation is based on concentrate sold.
5 As per the consolidated interim financial statements.



British Columbia Three months ended Six months ended
(in thousands) Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024 Jun. 30, 2025 Jun. 30, 2024
Net pounds of copper produced1 14,626 15,864 14,813 30,490 30,298
1 Contained copper in concentrate.

British Columbia   Three months ended  
    Jun. 30, 2025     Mar. 31, 2025     Jun. 30, 2024  
Cash cost per pound of copper produced   $ millions     $/lb     $ millions     $/lb     $ millions     $/lb  
Mining   24.2     1.65     21.9     1.38     19.5     1.31  
Milling   21.4     1.46     21.8     1.37     21.5     1.45  
G&A   6.1     0.42     6.3     0.40     5.4     0.37  
Onsite costs   51.7     3.53     50.0     3.15     46.4     3.13  
Treatment & refining   2.1     0.14     3.6     0.23     4.2     0.29  
Freight & other   3.3     0.24     3.4     0.21     3.5     0.23  
Cash cost, before by-product credits   57.1     3.91     57.0     3.59     54.1     3.65  
By-product credits   (22.2 )   (1.52 )   (18.3 )   (1.15 )   (14.5 )   (0.98 )
Cash cost, net of by-product credits   34.9     2.39     38.7     2.44     39.6     2.67  

British Columbia   Six months ended  
    Jun. 30, 2025     Jun. 30, 2024  
Cash cost per pound of copper produced   $ millions     $/lb     $ millions     $/lb  
Mining   46.1     1.51     48.0     1.58  
Milling   43.2     1.42     44.9     1.48  
G&A   12.4     0.41     9.3     0.31  
Onsite costs   101.7     3.34     102.2     3.37  
Treatment & refining   5.7     0.19     7.7     0.25  
Freight & other   6.7     0.21     7.8     0.26  
Cash cost, before by-product credits   114.1     3.74     117.7     3.88  
By-product credits   (40.5 )   (1.33 )   (24.1 )   (0.79 )
Cash cost, net of by-product credits   73.6     2.41     93.6     3.09  



British Columbia   Three months ended  
    Jun. 30, 2025     Mar. 31, 2025     Jun. 30, 2024  
Supplementary cash cost information   $ millions     $/lb 1     $ millions     $/lb 1     $ millions     $/lb 1  
By-product credits2:                                    
Gold   19.8     1.35     16.1     1.01     12.2     0.82  
Silver   2.4     0.17     2.2     0.14     2.3     0.16  
Total by-product credits   22.2     1.52     18.3     1.15     14.5     0.98  
Reconciliation to IFRS:                                    
Cash cost, net of by-product credits   34.9           38.7           39.6        
By-product credits   22.2           18.3           14.5        
Treatment and refining charges   (2.1 )         (3.6 )         (4.2 )      
Inventory adjustments   1.4           0.8           -        
Change in product inventory   3.6           (0.8 )         11.3        
Share based payment   0.2           0.3           -        
Royalties   1.2           0.8           0.6        
Depreciation and amortization3   16.8           16.0           14.0        
Cost of sales4   78.2           70.5           75.8        
1 Per pound of copper produced.
2 By-product credits are computed as revenue per financial statements, including amortization of deferred revenue and pricing and volume adjustments. For more information, please see the realized price reconciliation table on page 33 of this MD&A.
3 Depreciation is based on concentrate sold.
4 As per consolidated interim financial statements.

British Columbia   Six months ended  
    Jun. 30, 2025     Jun. 30, 2024  
Supplementary cash cost information   $ millions     $/lb 1     $ millions     $/lb 1  
By-product credits2:                        
Gold   35.9     1.18     19.8     0.65  
Silver   4.6     0.15     4.3     0.14  
Total by-product credits   40.5     1.33     24.1     0.79  
Reconciliation to IFRS:                        
Cash cost, net of by-product credits   73.6           93.6        
By-product credits   40.5           24.1        
Treatment and refining charges   (5.7 )         (7.7 )      
Inventory adjustments   2.2           -        
Change in product inventory   2.8           7.3        
Share based payment   0.5           -        
Royalties   2.0           1.4        
Depreciation and amortization3   32.8           25.7        
Cost of sales4   148.7           144.4        
1 Per pound of copper produced.
2 By-product credits are computed as revenue per financial statements, including amortization of deferred revenue and pricing and volume adjustments. For more information, please see the realized price reconciliation table on page 33 of this MD&A.
3 Depreciation is based on concentrate sold.
4 As per consolidated interim financial statements.



Consolidated   Three months ended  
    Jun. 30, 2025     Mar. 31, 2025     Jun. 30, 2024  
All-in sustaining cash cost per pound of copper produced   $ millions     $/lb     $ millions     $/lb     $ millions     $/lb  
Cash cost, net of by-product credits   (1.7 )   (0.02 )   (31.0 )   (0.45 )   72.0     1.14  
Cash sustaining capital expenditures   108.3     1.64     78.2     1.14     93.0     1.48  
Royalties   2.2     0.03     1.9     0.03     1.5     0.03  
Sustaining cash cost, net of by-product credits   108.8     1.65     49.1     0.72     166.5     2.65  
Corporate selling and administrative expenses & regional costs   22.1     0.33     15.3     0.22     19.8     0.32  
Accretion and amortization of decommissioning and community agreements1   3.2     0.05     2.0     0.03     6.6     0.10  
All-in sustaining cash cost, net of by-product credits   134.1     2.03     66.4     0.97     192.9     3.07  
Reconciliation to property, plant and equipment additions:                                    
Property, plant and equipment additions   93.6           68.2           75.2        
Capitalized stripping net additions   53.8           41.3           43.4        
Total accrued capital additions   147.4           109.5           118.6        
Less other non-sustaining capital costs2   58.8           47.0           37.7        
Total sustaining capital costs   88.6           62.5           80.9        
Capitalized lease & equipment financing cash payments - operating sites   13.4           12.8           9.6        
Community agreement cash payments   4.1           0.8           0.7        
Accretion and amortization of decommissioning and restoration obligations 3   2.2           2.1           1.8        
Cash sustaining capital expenditures   108.3           78.2           93.0        
1 Includes accretion of decommissioning liability relating to non-producing sites, and accretion and amortization of community agreements capitalized to Other assets.
2 Other non-sustaining capital costs include Arizona capitalized costs, capitalized interest, capitalized exploration, right-of-use lease asset additions, equipment financing asset additions, growth capital expenditures and reclassification related to capital spares.
3 Includes amortization of decommissioning and restoration PP&E assets and accretion of decommissioning and restoration liabilities related to producing sites.



Consolidated   Six months ended  
    Jun. 30, 2025     Jun. 30, 2024  
All-in sustaining cash cost per pound of copper produced   $ millions     $/lb     $ millions     $/lb  
Cash cost, net of by-product credits   (32.7 )   (0.24 )   83.9     0.60  
Cash sustaining capital expenditures   186.5     1.39     155.3     1.11  
Royalties   4.1     0.03     4.4     0.03  
Sustaining cash cost, net of by-product credits   157.9     1.18     243.6     1.74  
Corporate selling and administrative expenses & regional costs   37.4     0.27     37.8     0.27  
Accretion and amortization of decommissioning and community agreements1   5.2     0.04     10.6     0.08  
All-in sustaining cash cost, net of by-product credits   200.5     1.49     292.0     2.09  
Reconciliation to property, plant and equipment additions:                        
Property, plant and equipment additions   161.8           121.4        
Capitalized stripping net additions   95.1           75.4        
Total accrued capital additions   256.9           196.8        
Less other non-sustaining capital costs2   105.8           64.6        
Total sustaining capital costs   151.1           132.2        
Capitalized lease & equipment financing cash payments - operating sites   26.2           17.8        
Community agreement cash payments   4.9           1.5        
Accretion and amortization of decommissioning and restoration obligations 3   4.3           3.8        
Cash sustaining capital expenditures   186.5           155.3        
1 Includes accretion of decommissioning liability relating to non-producing sites, and accretion and amortization of community agreements capitalized to Other assets.
2 Other non-sustaining capital costs include Arizona capitalized costs, capitalized interest, capitalized exploration, right-of-use lease asset additions, equipment financing asset additions, growth capital expenditures and reclassification related to capital spares.
3 Includes amortization of decommissioning and restoration PP&E assets and accretion of decommissioning and restoration liabilities related to producing sites.



Peru Three months ended
  Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024
Sustaining cash cost per pound of copper produced $ millions $/lb $ millions $/lb $ millions $/lb
Cash cost, net of by-product credits 69.6 1.45 49.6 1.11 75.4 1.78
Cash sustaining capital expenditures 55.1 1.15 35.3 0.79 33.8 0.80
Royalties 1.0 0.03 1.1 0.02 0.9 0.02
Sustaining cash cost per pound of copper produced 125.7 2.63 86.0 1.92 110.1 2.60

Peru Six months ended
  Jun. 30, 2025 Jun. 30, 2024
Sustaining cash cost per pound of copper produced $ millions $/lb $ millions $/lb
Cash cost, net of by-product credits 119.2 1.29 98.6 1.02
Cash sustaining capital expenditures 90.4 0.98 63.6 0.66
Royalties 2.1 0.02 3.0 0.03
Sustaining cash cost per pound of copper produced 211.7 2.29 165.2 1.71

British Columbia Three months ended
  Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024
Sustaining cash cost per pound of copper produced $ millions $/lb $ millions $/lb $ millions $/lb
Cash cost, net of by-product credits 34.9 2.39 38.7 2.44 39.6 2.67
Cash sustaining capital expenditures 39.6 2.71 27.8 1.75 42.1 2.84
Royalties 1.2 0.08 0.8 0.05 0.6 0.05
Sustaining cash cost per pound of copper produced 75.7 5.18 67.3 4.24 82.3 5.56

British Columbia Six months ended
  Jun. 30, 2025 Jun. 30, 2024
Sustaining cash cost per pound of copper produced $ millions $/lb $ millions $/lb
Cash cost, net of by-product credits 73.6 2.41 93.6 3.09
Cash sustaining capital expenditures 67.4 2.21 62.5 2.06
Royalties 2.0 0.07 1.4 0.05
Sustaining cash cost per pound of copper produced 143.0 4.69 157.5 5.20


Gold Cash Cost and Gold Sustaining Cash Cost

Cash cost per ounce of gold produced ("gold cash cost") is a non-GAAP measure that management uses as a key performance indicator to assess the performance of Hudbay's Manitoba operations. This alternative cash cost calculation designates gold as the primary metal of production as it represents a substantial component of revenues for Hudbay's Manitoba business unit and should therefore be less volatile over time than Manitoba cash cost per pound of copper. The calculation is presented in three manners:

- Gold cash cost, before by-product credits - This measure is gross of by-product revenues and is a function of the efforts and costs incurred to mine and process all ore mined. However, the measure divides this aggregate cost over only ounces of gold produced, the assumed primary metal of production. This measure is generally less volatile from period to period, as it is not affected by changes in the price received for by-product metals.

- Gold cash cost, net of by-product credits - In order to calculate the net cost to produce and sell gold, the net of by-product credits measure subtracts the revenues realized from the sale of the metals other than gold. The by-product revenues from copper, zinc, and silver are significant and are integral to the economics of Hudbay's Manitoba operation. The economics that support its decision to produce and sell gold would be different if Hudbay did not receive revenues from the other significant metals being extracted and processed. This measure provides management and investors with an indication of the minimum gold price consistent with positive operating margins, assuming realized by-product metal prices are consistent with those prevailing during the reporting period. It also serves as an important operating statistic that management and investors utilize to measure Hudbay's operating performance at its Manitoba operation versus that of its competitors. However, it is important to understand that if by-product metal prices decline alongside gold prices, the gold cash cost net of by-product credits would increase, requiring a higher gold price than that reported to maintain positive cash flows and operating margins.

- Gold sustaining cash cost, net of by-product credits - This measure is an extension of gold cash cost that includes cash sustaining capital expenditures, capitalized exploration, net smelter returns royalties, as well as accretion and amortization for expected decommissioning activities for producing assets. It does not include corporate selling and administrative expenses. It provides a more fulsome measurement of the cost of sustaining production than gold cash cost, which is focused on operating costs only.

The tables below present a detailed build-up of gold cash cost and gold sustaining cash cost, net of by-product credits, for the Manitoba business unit, and reconciliations between gold cash cost, net of by-product credits, to the most comparable IFRS measures of cost of sales for the three months ended June 30, and March 31, 2025 and June 30, 2024 and six months ended June 30, 2025 and 2024. Gold cash cost, net of by-product credits, may not calculate exactly based on amounts presented in the tables below due to rounding.

Manitoba Three months ended Six months ended
(in thousands) Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024 Jun. 30, 2025 Jun. 30, 2024
Net ounces of gold produced1 43,235 60,354 43,488 103,589 100,319
1 Contained gold in concentrate and doré.

Manitoba   Three months ended  
    Jun. 30, 2025     Mar. 31, 2025     Jun. 30, 2024  
Cash cost per ounce of gold produced   $ millions     $/oz1     $ millions     $/oz1     $ millions     $/oz1  
Mining   33.5     775     38.3     634     42.3     973  
Milling   13.4     310     14.4     239     15.2     350  
G&A   13.8     319     14.8     245     10.5     240  
Onsite costs   60.7     1,404     67.5     1,118     68.0     1,563  
Treatment & refining   1.3     30     3.7     61     7.2     167  
Freight & other   5.1     118     5.7     95     5.7     130  
Cash cost, before by-product credits   67.1     1,552     76.9     1,274     80.9     1,860  
By-product credits   (36.4 )   (842 )   (54.2 )   (898 )   (47.4 )   (1,090 )
Gold cash cost, net of by-product credits   30.7     710     22.7     376     33.5     771  



Manitoba     Six months ended  
      Jun. 30, 2025     Jun. 30, 2024  
Cash cost per ounce of gold produced     $ millions     $/oz1     $ millions     $/oz1  
Mining     71.8     693     86.6     864  
Milling     27.8     268     31.7     316  
G&A     28.6     277     21.8     217  
Onsite costs     128.2     1,238     140.1     1,397  
Treatment & refining     5.0     48     16.5     164  
Freight & other     10.8     104     11.8     118  
Cash cost, before by-product credits     144.0     1,390     168.4     1,679  
By-product credits     (90.6 )   (875 )   (93.1 )   (928 )
Gold cash cost, net of by-product credits     53.4     515     75.3     751  

Manitoba   Three months ended  
Supplementary cash cost information   Jun. 30, 2025     Mar. 31, 2025     Jun. 30, 2024  
  $ millions     $/oz 1     $ millions     $/oz1     $ millions     $/oz 1  
By-product credits2:                                    
Copper   21.8     504     32.3     535     25.9     596  
Zinc   7.3     169     13.8     228     14.9     343  
Silver   7.3     169     8.3     138     6.1     140  
Other   -     -     (0.2 )   (3 )   0.5     11  
Total by-product credits   36.4     842     54.2     898     47.4     1,090  
Reconciliation to IFRS:                                    
Cash cost, net of by-product credits   30.7           22.7           33.5        
By-product credits   36.4           54.2           47.4        
Treatment and refining charges   (1.3 )         (3.7 )         (7.2 )      
Share-based compensation expenses   0.5           0.3           0.4        
Inventory adjustments   1.0           -           -        
Change in product inventory   3.8           (1.0 )         (2.4 )      
Overhead costs incurred during temporary suspension   3.2           -           -        
Depreciation and amortization3   23.6           23.9           24.7        
Cost of sales4   97.9           96.4           96.4        
1 Per ounce of gold produced.
2 By-product credits are computed as revenue per financial statements, amortization of deferred revenue and pricing and volume adjustments. For more information, please see the realized price reconciliation table on page 33 of this MD&A.
3 Depreciation is based on concentrate sold.
4 As per consolidated interim financial statements.



Manitoba   Six months ended  
Supplementary cash cost information   Jun. 30, 2025     Jun. 30, 2024  
  $ millions     $/oz 1     $ millions     $/oz 1  
By-product credits2:                        
Copper   54.1     522     51.5     514  
Zinc   21.1     204     29.5     294  
Silver   15.6     151     11.6     115  
Other   (0.2 )   (2 )   0.5     5  
Total by-product credits   90.6     875     93.1     928  
Reconciliation to IFRS:                        
Cash cost, net of by-product credits   53.4           75.3        
By-product credits   90.6           93.1        
Treatment and refining charges   (5.0 )         (16.5 )      
Share-based compensation expenses   0.8           0.7        
Inventory adjustments   1.0           -        
Change in product inventory   2.8           (2.9 )      
Overhead costs related to suspension of activities (cash)   3.2           -        
Depreciation and amortization3   47.5           51.3        
Cost of sales4   194.3           201.0        
1 Per ounce of gold produced.
2 By-product credits are computed as revenue per financial statements, amortization of deferred revenue and pricing and volume adjustments. For more information, please see the realized price reconciliation table on page 33 of this MD&A.
3 Depreciation is based on concentrate sold.
4 As per consolidated interim financial statements.

Manitoba Three months ended
  Jun. 30, 2025 Mar. 31, 2025 Jun. 30, 2024
Sustaining cash cost per ounce of gold produced $ millions $/oz $ millions $/oz $ millions $/oz
Gold cash cost, net of by-product credits 30.7 710 22.7 376 33.5 771
Cash sustaining capital expenditures 13.6 315 15.1 250 17.1 392
Sustaining cash cost per ounce of gold produced 44.3 1,025 37.8 626 50.6 1,163

Manitoba Six months ended
  Jun. 30, 2025 Jun. 30, 2024
Sustaining cash cost per ounce of gold produced $ millions $/oz $ millions $/oz
Gold cash cost, net of by-product credits 53.4 515 75.3 751
Cash sustaining capital expenditures 28.7 278 29.2 291
Sustaining cash cost per ounce of gold produced 82.1 793 104.5 1,042


Combined Unit Cost

Combined unit cost ("unit cost") and zinc plant unit cost is a non-GAAP measure that management uses as a key performance indicator to assess the performance of Hudbay's mining and milling operations. Combined unit cost is calculated by dividing the cost of sales by mill throughput. This measure is utilized by management and investors to assess Hudbay's cost structure and margins and compare it to similar information provided by other companies in the industry. Unlike cash cost, this measure is not impacted by variability in by-product commodity prices since there are no by-product deductions; costs associated with profit-sharing and similar costs are excluded because of their correlation to external metal prices. In addition, the unit costs are reported in the functional currency of the operation which minimizes the impact of foreign currency fluctuations. In all, the unit cost measures provide an alternative perspective on operating cost performance with minimal impact from external market prices.

The tables below present a detailed combined unit cost for the Peru and Manitoba business units, and reconciliations between these measures to the most comparable IFRS measures of cost of sales for the three months ended June 30, 2025 and 2024 and March 31, 2025 and six months ended June 30, 2025 and 2024.

Peru   Three months ended     Six months ended  
(in millions except ore tonnes milled and unit cost per tonne)   Jun. 30, 2025     Mar. 31,
2025
    Jun. 30, 2024     Jun. 30, 2025     Jun. 30, 2024  
Combined unit cost per tonne processed
Mining   28.1     31.0     31.3     59.1     60.5  
Milling   57.8     44.4     51.3     102.2     95.0  
G&A1   23.2     22.5     19.4     45.7     42.4  
Less: Other G&A2   (6.4 )   (7.9 )   (4.1 )   (14.3 )   (11.8 )
Unit cost   102.7     90.0     97.9     192.7     186.1  
Tonnes ore milled   7,559     8,114     7,719     15,673     15,797  
Combined unit cost per tonne   13.59     11.09     12.68     12.29     11.78  
Reconciliation to IFRS:                              
Unit cost   102.7     90.0     97.9     192.7     186.1  
Freight & other   12.4     15.2     12.6     27.6     29.2  
Other G&A   6.4     7.9     4.1     14.3     11.8  
Share-based compensation expenses   0.2     0.1     0.2     0.3     0.3  
Inventory adjustments   1.1     0.4     -     1.5     -  
Change in product inventory   4.0     13.8     1.1     17.8     15.2  
Royalties   1.0     1.1     0.9     2.1     3.0  
Depreciation and amortization   56.0     68.2     58.9     124.2     129.9  
Cost of sales3   183.8     196.7     175.7     380.5     375.5  
1 G&A as per cash cost reconciliation above.
2 Other G&A primarily includes profit sharing costs.
3 As per consolidated interim financial statements.



Manitoba   Three months ended     Six months ended  
(in millions except tonnes ore milled and unit cost per tonne)   Jun. 30,
2025
    Mar. 31,
2025
    Jun. 30,
2024
    Jun. 30,
2025
    Jun. 30,
2024
 
Combined unit cost per tonne processed
Mining   33.5     38.3     42.3     71.8     86.6  
Milling   13.4     14.4     15.2     27.8     31.7  
G&A1   13.8     14.8     10.5     28.6     21.8  
Less: Other G&A related to profit sharing costs   (7.2 )   (7.2 )   (3.4 )   (14.4 )   (7.6 )
Unit cost   53.5     60.3     64.6     113.8     132.5  
USD/CAD implicit exchange rate   1.38     1.43     1.38     1.41     1.37  
Unit cost - C$   73.9     86.5     89.3     160.4     181.1  
Tonnes ore milled   307,138     404,410     397,426     711,548     787,193  
Combined unit cost per tonne - C$2   241     214     225     225     230  
Reconciliation to IFRS:                              
Unit cost   53.5     60.3     64.6     113.8     132.5  
Freight & other   5.1     5.7     5.7     10.8     11.8  
Other G&A related to profit sharing   7.2     7.2     3.4     14.4     7.6  
Share-based compensation expenses   0.5     0.3     0.4     0.8     0.7  
Inventory adjustments   1.0     -     -     1.0     -  
Change in product inventory   3.8     (1.0 )   (2.4 )   2.8     (2.9 )
Overhead costs related to suspension of activities (cash)   3.2     -     -     3.2     -  
Depreciation and amortization   23.6     23.9     24.7     47.5     51.3  
Cost of sales3   97.9     96.4     96.4     194.3     201.0  
1 G&A as per cash cost reconciliation above.
2 Excludes $3.2 million or C$14 per tonne of overhead costs incurred during temporary suspension during the three months ended June 30, 2025 and $3.2 million or C$6 per tonne during the six month ended June 30, 2025.
3 As per consolidated interim financial statements.



British Columbia   Three months ended     Six months ended  
(in millions except tonnes ore milled and unit cost per tonne)   Jun. 30,
2025
    Mar. 31,
2025
    Jun. 30,
2024
    Jun. 30,
2025
    Jun. 30,
2024
 
Combined unit cost per tonne processed
Mining   24.2     21.9     19.5     46.1     48.0  
Milling   21.4     21.8     21.5     43.2     44.9  
G&A1   6.1     6.3     5.4     12.4     9.3  
Unit cost   51.7     50.0     46.4     101.7     102.2  
USD/CAD implicit exchange rate   1.38     1.43     1.36     1.40     1.35  
Unit cost - C$   71.1     71.7     63.5     142.2     138.8  
Tonnes ore milled   2,900     2,761     3,232     5,661     6,413  
Combined unit cost per tonne - C$   24.51     25.98     19.65     25.12     21.65  
Reconciliation to IFRS:                              
Unit cost   51.7     50.0     46.4     101.7     102.2  
Freight & other   3.3     3.4     3.5     6.7     7.8  
Change in product inventory   3.6     (0.8 )   11.3     2.8     7.3  
Shared based compensation   0.2     0.3     -     0.5     -  
Inventory adjustments   1.4     0.8     -     2.2     -  
Royalties   1.2     0.8     0.6     2.0     1.4  
Depreciation and amortization   16.8     16.0     14.0     32.8     25.7  
Cost of sales2   78.2     70.5     75.8     148.7     144.4  
1 G&A as per cash cost reconciliation above.
2 As per consolidated interim financial statements.

ACCOUNTING CHANGES AND CRITICAL ESTIMATES

New standards issued but not yet effective

For information on new standards issued but not yet effective, refer to note 3 of Hudbay's June 30, 2025 consolidated interim financial statements.

Estimates and judgements

The preparation of the consolidated interim financial statements in accordance with IFRS requires Hudbay to make judgements, estimates and assumptions that affect the application of accounting policies, reported amounts of assets and liabilities, disclosure of contingent assets and liabilities at the date of the consolidated interim financial statements, and reported amounts of revenue and expenses during the reporting period. Actual results may differ from these estimates.

Hudbay reviews these estimates and underlying assumptions on an ongoing basis based on its experience and other factors, including expectations of future events that Hudbay believes to be reasonable under the circumstances. Revisions to accounting estimates are recognized in the period in which the estimates are revised and in any future periods affected. Certain accounting estimates and judgements have been identified as being "critical" to the presentation of Hudbay's financial condition and results of operations because they require Hudbay to make subjective and/or complex judgments about matters that are inherently uncertain; or there is a reasonable likelihood that materially different amounts could be reported under different conditions or using different assumptions and estimates.

For more information on judgements and estimates, refer to note 2 of Hudbay's June 30, 2025 consolidated interim financial statements.


CHANGES IN INTERNAL CONTROL OVER FINANCIAL REPORTING

Management is responsible for establishing and maintaining adequate internal control over financial reporting ("ICFR"). ICFR is designed to provide reasonable assurance regarding the reliability of financial reporting and the preparation of consolidated interim financial statements for external purposes in accordance with IFRS. 

Hudbay did not make any changes to ICFR during the three months ended June 30, 2025 that materially affected or are reasonably likely to materially affect Hudbay's ICFR. 

NOTES TO READER

Forward-Looking Information

This MD&A contains forward-looking information within the meaning of applicable Canadian and United States securities legislation. All information contained in this MD&A, other than statements of current and historical fact, is forward-looking information. Often, but not always, forward-looking information can be identified by the use of words such as "plans", "expects", "budget", "guidance", "scheduled", "estimates", "forecasts", "strategy", "target", "intends", "objective", "goal", "understands", "anticipates" and "believes" (and variations of these or similar words) and statements that certain actions, events or results "may", "could", "would", "should", "might" "occur" or "be achieved" or "will be taken" (and variations of these or similar expressions). All of the forward-looking information in this MD&A is qualified by this cautionary note.

Forward-looking information includes, but is not limited to, statements with respect to Hudbay's production, cost and capital and exploration expenditure guidance and the potential impact thereon from wildfires and any related evacuation or government orders in Manitoba and British Columbia or social unrest in Peru, the Snow Lake operations' ability to ramp up to full production in a timely manner after its suspension of operations, expectations regarding reductions in discretionary spending and capital expenditures, Hudbay's ability to advance and complete the optimization of the Copper Mountain mine operation including with respect to the ongoing SAG mill conversion and configuration project, the implementation of stripping strategies and the expected benefits therefrom, the estimated timelines and pre-requisites for sanctioning the Copper World project, the consummation and timing of the JV Transaction, the satisfaction of the conditions precedent to the JV Transaction, including but not limited to receipt of regulatory approvals, expectations regarding the anticipated benefits of the JV Transaction to Hudbay, and the United States, the consummation and timing of the DFS, expectations regarding the results of any challenges to the permits for the Copper World project and the potential impact of recent policy decisions from the United States government, the expected benefits of the sanctioning of Copper World project, and the benefits, timing and consummation of the amended Wheaton Stream, the expected benefits of Manitoba growth initiatives, including the use of the exploration drift at the 1901 deposit, and the potential utilization of excess capacity at the Stall mill, Hudbay's future deleveraging strategies and Hudbay's ability to deleverage and repay debt as needed, expectations regarding Hudbay's cash balance and liquidity, expectations regarding tax synergies, expectations regarding the ability to conduct exploration work and execute on exploration programs on its properties and to advance related drill plans, including the advancement of the exploration program at Maria Reyna and Caballito and the status and anticipated timing of the related drill permit application process, expectations regarding the prospective nature of the Maria Reyna and Caballito properties, the ability to continue mining higher-grade ore in the Pampacancha pit and Hudbay's expectations resulting therefrom, Hudbay's evaluation and assessment of opportunities to reprocess tailings using various metallurgical technologies, the anticipated impact of brownfield and greenfield growth projects on Hudbay's performance, anticipated expansion opportunities and extension of mine life in Snow Lake and Hudbay's ability to find a new anchor deposit near Hudbay's Snow Lake operations, anticipated future drill programs and exploration activities and any results expected therefrom, anticipated mine plans, anticipated metals prices and the anticipated sensitivity of Hudbay's financial performance to metals prices, events that may affect Hudbay's operations and development projects, anticipated cash flows from operations and related liquidity requirements, the anticipated effect of external factors on revenue, such as commodity prices, estimation of mineral reserves and resources, mine life projections, reclamation costs, economic outlook, government regulation of mining operations, and business and acquisition strategies. Forward-looking information is not, and cannot be, a guarantee of future results or events. Forward-looking information is based on, among other things, opinions, assumptions, estimates and analyses that, while considered reasonable by Hudbay at the date the forward-looking information is provided, inherently are subject to significant risks, uncertainties, contingencies and other factors that may cause actual results and events to be materially different from those expressed or implied by the forward-looking information.

The material factors or assumptions that Hudbay has identified and were applied in drawing conclusions or making forecasts or projections set out in the forward-looking information include, but are not limited to:

- the ability to achieve production, cost and capital and exploration expenditure guidance;

- no significant interruptions to Hudbay's operations due to social or political unrest in the regions Hudbay operates, including the navigation of the complex political and social environment in Peru and the resolution of grievances raised by local communities and their residents;

- the ability to ramp up to full production in a timely manner following the suspension of operations in Manitoba;

- the closing of the JV Transaction;


- no interruptions to Hudbay's plans for advancing the Copper World project, including with respect to any successful challenges to the Copper World permits;

- Hudbay's ability to successfully advance and complete the optimization of the Copper Mountain operations, obtain required permits and develop and maintain good relations with key stakeholders;

- the ability to execute on its exploration plans and to advance related drill plans;

- the ability to advance the exploration program at the Maria Reyna and Caballito properties;

- the success of mining, processing, exploration and development activities;

- the scheduled maintenance and availability of Hudbay's processing facilities;

- the accuracy of geological, mining and metallurgical estimates;

- anticipated metals prices and the costs of production;

- the supply and demand for metals Hudbay produces;

- the supply and availability of all forms of energy and fuels at reasonable prices;

- no significant unanticipated operational or technical difficulties;

- no significant interruptions to operations due to adverse effects from extreme weather events, including forest fires that have affected and may continue to affect the regions in which Hudbay operates;

- the execution of Hudbay's business and growth strategies, including the success of its strategic investments and initiatives;

- the availability of additional financing, if needed;

- the ability to deleverage and repay debt, as needed;

- the ability to complete project targets on time and on budget and other events that may affect Hudbay's ability to develop Hudbay's projects;

- the timing and receipt of various regulatory and governmental approvals;

- the availability of personnel for Hudbay's exploration, development and operational projects and ongoing employee relations;

- maintaining good relations with the employees at Hudbay's operations;

- maintaining good relations with the labour unions that represent certain of Hudbay employees in Manitoba and Peru;

- maintaining good relations with the communities in which Hudbay operates, including the neighbouring Indigenous communities and local governments;

- no significant unanticipated challenges with stakeholders at Hudbay's various projects;

- no significant unanticipated events or changes relating to regulatory, environmental, health and safety matters;

- no contests over title to Hudbay's properties, including as a result of rights or claimed rights of Indigenous peoples or challenges to the validity of Hudbay's unpatented mining claims;

- the timing and possible outcome of pending litigation and no significant unanticipated litigation;

- certain tax matters, including, but not limited to current tax laws and regulations, changes in taxation policies and the refund of certain value added taxes from the Canadian and Peruvian governments; and

- no significant and continuing adverse changes in general economic conditions or conditions in the financial markets (including commodity prices and foreign exchange rates).

The risks, uncertainties, contingencies and other factors that may cause actual results to differ materially from those expressed or implied by the forward-looking information may include, but are not limited to, risks associated with satisfying the conditions to the closing of the JV Transaction, including the timing, receipt and any conditions associated with regulatory approvals, risks associated with reaching a definitive agreement with Wheaton in respect of the enhanced precious metals stream, risks related to the failure to effectively advance and complete the optimization of the Copper Mountain mine operations including with respect to the ongoing SAG mill conversion and configuration project, political and social risks in the regions Hudbay operates, including the complex political and social environment in Peru and potential disruptions to operations arising from community protests and grievances, risks generally associated with the mining industry and the current geopolitical environment, including future commodity prices, the potential implementation or expansion of tariffs, currency and interest rate fluctuations, energy and consumable prices, supply chain constraints and general cost escalation in the current inflationary environment, uncertainties related to the development and operation of Hudbay's projects, the risk of an indicator of impairment or impairment reversal relating to a material mineral property, risks related to the Copper World project, including in relation to project delivery and financing risks, risks related to the Lalor mine plan, including the ability to convert inferred mineral resource estimates to higher confidence categories, dependence on key personnel and employee and union relations, risks related to political or social instability, unrest or change, risks in respect of Indigenous and community relations, rights and title claims, operational risks and hazards, including the cost of maintaining and upgrading Hudbay's tailings management facilities and any unanticipated environmental, industrial and geological events and developments and the inability to insure against all risks (including any unanticipated significant interruptions to operations due to adverse effects from extreme weather events), failure of plant, equipment, processes, transportation and other infrastructure to operate as anticipated, compliance with government and environmental regulations, including permitting requirements and anti-bribery legislation, depletion of Hudbay's reserves, volatile financial markets and interest rates that may affect Hudbay's ability to obtain additional financing on acceptable terms, the failure to obtain required approvals or clearances from government authorities on a timely basis, uncertainties related to the geology, continuity, grade and estimates of mineral reserves and resources, and the potential for variations in grade and recovery rates, uncertain costs of reclamation activities, Hudbay's ability to comply with Hudbay's pension and other post-retirement obligations, Hudbay's ability to abide by the covenants in Hudbay's debt instruments and other material contracts, tax refunds, hedging transactions, as well as the risks discussed under the heading "Risk Factors" in Hudbay's most recent Annual Information Form which is available on the Company's SEDAR+ profile at www.sedarplus.ca and the Company's EDGAR profile at www.sec.gov.


Should one or more risk, uncertainty, contingency or other factor materialize or should any factor or assumption prove incorrect, actual results could vary materially from those expressed or implied in the forward-looking information. Accordingly, you should not place undue reliance on forward-looking information. Hudbay does not assume any obligation to update or revise any forward-looking information after the date of this MD&A or to explain any material difference between subsequent actual events and any forward-looking information, except as required by applicable law.

Note to United States Investors

This MD&A has been prepared in accordance with the requirements of the securities laws in effect in Canada, which may differ materially from the requirements of United States securities laws applicable to U.S. issuers.

Qualified Persons and NI 43-101

The technical and scientific information in this MD&A related to Hudbay's material mineral projects other than the Copper Mountain mine has been approved by Olivier Tavchandjian, P. Geo, Senior Vice President, Exploration and Technical Services. Mr. Tavchandjian is a qualified person pursuant to National Instrument 43-101 - Standards of Disclosure for Mineral Projects ("NI 43-101").

The technical and scientific information in this MD&A related to the Copper Mountain mine has been approved by Marc-Andre Brulotte, P. Geo, Director, Global Exploration and Resource Evaluation. Mr. Brulotte is a qualified person pursuant to NI 43-101.

For a description of the key assumptions, parameters and methods used to estimate mineral reserves and resources at Hudbay's material mineral properties, as well as data verification procedures and a general discussion of the extent to which the estimates of scientific and technical information may be affected by any known environmental, permitting, legal title, taxation, sociopolitical, marketing or other relevant factors, please see the technical reports for Hudbay's material properties as filed by the Company on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov.


SUMMARY OF HISTORICAL RESULTS

The following unaudited tables set out a summary of quarterly and annual results for the Company.

      Q2 2025     Q1 2025     2024 4     Q4 2024     Q3 2024     Q2 2024     Q1 2024     2023 4     Q4 2023     Q3 2023     Q2 2023  
Consolidated Financial Condition ($ millions)  
Cash and cash equivalents and short-term investments   $ 625.5   $ 582.6   $ 581.8   $ 581.8   $ 483.3   $ 523.8   $ 284.4   $ 249.8   $ 249.8   $ 245.2   $ 179.7  
Total long-term debt     1,059.6     1,108.7     1,107.5     1,107.5     1,108.9     1,155.6     1,278.6     1,287.5     1,287.5     1,377.4     1,370.7  
Net debt1     434.1     526.1     525.7     525.7     625.6     631.8     994.2     1,037.7     1,037.7     1,132.2     1,190.9  
Free cash flow     87.8     87.4     357.1     148.9     88.4     32.5     87.2     320.2     160.5     111.6     9.0  
Consolidated Financial Performance ($ millions except per share amounts)  
Revenue   $ 536.4   $ 594.9   $ 2,021.2   $ 584.9   $ 485.8   $ 425.5   $ 525.0   $ 1,690.0   $ 602.2   $ 480.5   $ 312.2  
Cost of sales     359.9     363.6     1,467.4     400.5     346.0     347.9     373.0     1,297.5     405.4     374.1     289.3  
Earnings (loss) before tax     153.1     171.3     251.6     103.7     79.7     0.4     67.8     151.8     81.0     84.1     (30.7 )
Net income (loss) earnings     114.7     99.2     67.8     19.3     50.4     (20.3 )   18.5     69.5     33.5     45.5     (14.9 )
Net earnings (loss) attributable to owners1   117.7     100.4     76.7     21.2     49.8     (16.5 )   22.3     66.4     30.7     45.1     (14.9 )
Basic and diluted earnings (loss) per share attributable to owners $ 0.30   $ 0.25   $ 0.20   $ 0.05   $ 0.13   $ (0.04 ) $ 0.06   $ 0.22   $ 0.09   $ 0.13   $ (0.05 )
Adjusted earnings (loss) per share attributable to owners 1 $ 0.19   $ 0.24   $ 0.48   $ 0.18   $ 0.13   $ 0.00   $ 0.17   $ 0.23   $ 0.20   $ 0.07   $ (0.07 )
Operating cash flow before change in non-cash working capital   193.9     163.5     691.1     231.5     188.3     123.7     147.5     570.0     246.5     182.0     55.9  
Adjusted EBITDA 1   245.2     287.2     823.3     257.3     206.2     145.0     215.0     647.8     274.4     190.7     81.2  
Consolidated Operational Performance  
Contained metal in concentrate and doré produced 2                                      
Copper tonnes   29,956     30,958     137,943     43,262     31,354     28,578     34,749     131,691     45,450     41,964     21,715  
Gold ounces   56,271     73,784     332,240     94,161     89,073     58,614     90,392     310,429     112,776     101,417     48,996  
Silver ounces   814,989     919,775     3,983,851     1,311,658     985,569     738,707     947,917     3,575,234     1,197,082     1,063,032     612,310  
Zinc tonnes   5,130     6,265     33,339     8,385     8,069     8,087     8,798     34,642     5,747     10,291     8,758  
Molybdenum tonnes   375     397     1,323     195     362     369     397     1,566     397     466     414  
Payable metal in concentrate and doré sold                                                                    
Copper tonnes   30,354     31,768     125,094     37,927     27,760     25,799     33,608     124,996     44,006     39,371     23,078  
Gold ounces   62,466     75,092     335,342     92,734     73,232     61,295     108,081     276,893     104,840     74,799     47,533  
Silver ounces   894,160     1,006,968     3,549,816     1,150,518     663,413     667,036     1,068,848     3,145,166     1,048,877     748,955     805,448  
Zinc 3 tonnes   2,871     4,857     25,120     5,261     8,607     5,133     6,119     28,779     7,385     7,125     8,641  
Molybdenum tonnes   427     448     1,287     182     343     347     415     1,462     468     426     314  
Cash cost 1 $/lb $ (0.02 ) $ (0.45 ) $ 0.46   $ 0.45   $ 0.18   $ 1.14   $ 0.16   $ 0.80   $ 0.16   $ 1.10   $ 1.60  
Sustaining cash cost 1 $/lb $ 1.65   $ 0.72   $ 1.62   $ 1.37   $ 1.71   $ 2.65   $ 1.00   $ 1.72   $ 1.09   $ 1.89   $ 2.73  
All-in sustaining cash cost 1 $/lb $ 2.03   $ 0.97   $ 1.88   $ 1.53   $ 1.95   $ 3.07   $ 1.29   $ 1.92   $ 1.31   $ 2.04   $ 2.98  

1Net debt, adjusted earnings (loss) per share attributable to owners, adjusted EBITDA, cash cost, sustaining cash cost and all-in sustaining cash cost per pound of copper produced, net of by-product credits, are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A. The above table sets forth selected non-GAAP financial performance measures for each of the Company's nine most recently completed quarters and three most recently completed years; detailed reconciliations for non-comparable prior periods can be found in Hudbay's MD&A for these prior periods in the "Non-GAAP Financial Performance Measures" section of these documents. 

2 Metal reported in concentrate is prior to deductions associated with smelter contract terms.

3 Includes refined zinc metal sold.


4 Annual consolidated results may not calculate based on amounts presented in this table due to rounding.

      Q2 2025     Q1 2025     2024 4     Q4 2024     Q3 2024     Q2 2024     Q1 2024     2023 4     Q4 2023     Q3 2023     Q2 2023  
Peru Operations                                                      
Constancia ore mined1 tonnes   6,735,316     8,628,279     15,046,190     4,186,058     3,022,931     5,277,654     2,559,547     9,265,954     973,176     1,242,198     3,647,399  
Copper %   0.34     0.28     0.34     0.40     0.36     0.29     0.31     0.32     0.30     0.30     0.31  
Gold g/tonne   0.03     0.03     0.04     0.04     0.04     0.03     0.04     0.04     0.04     0.04     0.04  
Silver g/tonne   3.26     3.14     3.08     3.88     3.20     2.50     2.79     2.53     2.26     2.91     2.49  
Molybdenum %   0.02     0.02     0.01     0.02     0.02     0.01     0.01     0.01     0.01     0.01     0.01  
Pampacancha ore mined1 tonnes   762,172     389,189     9,317,499     4,037,264     1,777,092     1,288,789     2,214,354     14,756,416     5,556,613     5,894,013     2,408,495  
Copper %   0.26     0.44     0.55     0.63     0.48     0.41     0.56     0.51     0.56     0.53     0.36  
Gold g/tonne   0.24     0.26     0.32     0.38     0.27     0.20     0.32     0.33     0.32     0.30     0.34  
Silver g/tonne   4.59     3.68     5.61     6.43     6.23     3.83     4.64     4.28     4.84     4.22     2.81  
Molybdenum %   0.01     0.01     0.01     0.00     0.01     0.02     0.02     0.01     0.01     0.02     0.02  
Strip Ratio     1.47     1.02     1.78     1.22     2.62     1.74     1.95     1.51     1.26     1.36     1.74  
Ore milled tonnes   7,559,047     8,114,024     31,933,624     7,999,453     8,137,248     7,718,962     8,077,962     30,720,929     7,939,044     7,895,109     7,223,048  
Copper %   0.34     0.30     0.36     0.48     0.32     0.30     0.36     0.39     0.48     0.43     0.31  
Gold g/tonne   0.05     0.05     0.14     0.20     0.11     0.07     0.15     0.16     0.25     0.21     0.09  
Silver g/tonne   3.58     3.22     3.84     5.28     3.70     2.85     3.48     3.62     4.20     3.75     2.78  
Molybdenum %   0.01     0.01     0.01     0.01     0.01     0.01     0.01     0.01     0.01     0.02     0.01  
Copper recovery %   84.5     84.6     85.0     87.8     82.6     83.1     84.9     84.2     87.4     85.2     80.0  
Gold recovery %   56.0     56.5     70.7     73.3     68.1     61.4     73.4     71.8     77.6     74.8     61.1  
Silver recovery %   63.5     66.0     68.8     71.4     67.0     63.9     70.7     70.0     78.0     73.2     65.1  
Molybdenum recovery %   38.7     35.7     41.7     37.1     39.0     46.3     43.2     35.8     33.6     37.2     40.5  
Contained metal in concentrate                                                                  
Copper tonnes   21,710     20,293     99,001     33,988     21,220     19,217     24,576     100,487     33,207     29,081     17,682  
Gold ounces   7,366     7,869     98,226     38,079     20,331     10,672     29,144     114,218     49,418     40,596     12,998  
Silver ounces   551,979     554,692     2,708,262     969,502     648,209     450,833     639,718     2,505,229     836,208     697,211     419,642  
Molybdenum tonnes   375     397     1,323     195     362     369     397     1,566     397     466     414  
Payable metal sold                                                                    
Copper tonnes   21,418     22,890     88,138     28,775     18,803     16,806     23,754     96,213     31,200     27,490     21,207  
Gold ounces   9,721     14,362     103,364     37,459     9,795     13,433     42,677     97,176     38,114     32,757     14,524  
Silver ounces   616,578     714,654     2,343,820     824,613     365,198     400,302     753,707     2,227,419     703,679     460,001     671,532  
Molybdenum tonnes   427     448     1,287     182     343     347     415     1,462     468     426     314  
Unit cost 2,3 $/tonne $ 13.59   $ 11.09   $ 12.91   $ 15.25   $ 12.78   $ 12.68   $ 10.92   $ 12.47   $ 12.24   $ 12.20   $ 14.07  
Peru cash cost3 $/lb $ 1.45   $ 1.11   $ 1.18   $ 1.00   $ 1.80   $ 1.78   $ 0.43   $ 1.07   $ 0.54   $ 0.83   $ 2.14  
Peru sustaining cash cost3 $/lb $ 2.63   $ 1.92   $ 1.86   $ 1.48   $ 2.78   $ 2.60   $ 1.02   $ 1.81   $ 1.21   $ 1.51   $ 3.06  
1 Reported tonnes and grade for ore mined are estimates based on mine plan assumptions and may not fully reconcile to ore milled.
2 Reflects combined mine, mill and general and administrative ("G&A") costs per tonne of ore milled. Reflects the deduction of expected capitalized stripping costs.
3 Combined unit costs, cash cost, and sustaining cash cost per pound of copper produced, net of by-product credits, are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A. The above table sets forth selected non-GAAP financial performance measures for each of the Company's nine most recently completed quarters and three most recently completed years; detailed reconciliations for non-comparable prior periods can be found in Hudbay's MD&A for these prior periods in the "Non-GAAP Financial Performance Measures" section of these documents. 
4 Annual consolidated results may not calculate based on amounts presented in this table due to rounding.



    Q2 2025 Q1 2025 2024 1 Q4 2024 Q3 2024 Q2 2024 Q1 2024 2023 1 Q4 2023 Q3 2023 Q2 2023
Manitoba Operations                        
Lalor ore mined tonnes 303,062 384,234 1,626,935 422,454 411,295 385,478 407,708 1,526,729 372,384 367,491 413,255
Gold g/tonne 4.97 5.46 4.68 4.61 5.45 3.75 4.84 4.74 5.92 5.08 4.07
Copper % 0.61 0.95 0.85 0.95 0.91 0.69 0.84 0.86 1.04 1.02 0.81
Zinc % 2.46 2.42 2.84 2.95 2.73 2.76 2.92 3.00 2.20 3.31 3.14
Silver g/tonne 29.94 31.23 27.14 31.91 30.45 22.29 23.44 24.51 28.92 27.80 23.27
Stall Concentrator:                        
Ore milled tonnes 144,204 215,286 893,510 222,004 222,621 229,527 219,358 965,567 228,799 255,516 238,633
Gold g/tonne 3.19 3.86 3.42 3.36 4.23 3.02 3.07 3.45 4.22 3.70 3.12
Copper % 0.56 0.76 0.71 0.73 0.89 0.59 0.64 0.74 0.73 0.77 0.85
Zinc % 4.20 3.44 4.33 4.62 4.12 4.05 4.54 4.36 3.20 4.88 4.47
Silver g/tonne 29.55 29.53 26.54 29.90 30.20 21.74 24.46 24.19 28.63 28.82 22.15
Gold recovery % 67.9 70.1 68.6 69.6 70.5 65.5 68.0 64.8 67.5 67.8 59.9
Copper recovery % 84.7 88.3 87.4 84.4 88.3 85.4 91.7 90.4 92.0 93.9 88.5
Zinc recovery % 84.8 84.7 86.2 81.7 88.1 87.1 88.4 82.2 78.5 82.6 82.2
Silver recovery % 51.9 58.7 56.8 55.1 57.8 54.2 59.8 61.4 61.8 64.9 60.3
New Britannia Concentrator:                      
Ore milled tonnes 162,934 189,124 715,198 185,592 191,298 167,899 170,409 596,912 165,038 146,927 141,905
Gold g/tonne 6.48 7.37 6.29 5.99 6.77 5.31 7.03 6.76 8.03 6.93 5.82
Copper % 0.65 1.18 1.04 1.17 0.93 0.94 1.13 1.03 1.46 1.22 0.77
Zinc % 1.01 1.00 0.99 1.08 1.12 0.92 0.82 0.84 0.85 0.90 0.85
Silver g/tonne 30.29 33.35 27.78 33.97 30.24 24.42 21.60 25.11 27.97 23.88 25.79
Gold recovery - concentrate and doré % 89.4 90.3 89.7 90.2 90.0 90.0 88.6 88.6 89.0 88.8 88.6
Copper recovery % 87.4 90.3 93.6 91.3 92.8 94.4 96.2 93.3 91.6 97.4 91.2
Silver recovery - concentrate and doré % 78.0 81.6 80.9 79.6 79.9 83.1 82.0 81.5 83.2 82.0 79.6
1 Annual consolidated results may not calculate based on amounts presented in this table due to rounding.



      Q2 2025     Q1 2025     2024 4     Q4 2024     Q3 2024     Q2 2024     Q1 2024     2023 4     Q4 2023     Q3 2023     Q2 2023  
Manitoba Operations (continued)                                                                  
Total Manitoba contained metal in concentrate and doré produced5  
Gold ounces   43,235     60,354     214,225     51,438     62,468     43,488     56,831     187,363     59,863     56,213     35,253  
Copper tonnes   1,612     3,469     12,536     3,347     3,398     2,642     3,149     12,154     3,735     3,580     2,794  
Zinc tonnes   5,130     6,265     33,339     8,385     8,069     8,087     8,798     34,642     5,747     10,291     8,758  
Silver ounces   197,970     285,603     995,090     283,223     281,397     210,647     219,823     851,723     255,579     264,752     180,750  
Total Manitoba payable metal sold in concentrate and doré        
Gold ounces   46,932     55,765     212,243     50,239     57,238     42,763     62,003     171,297     63,635     36,713     33,009  
Copper tonnes   2,133     2,725     11,602     3,321     2,931     2,429     2,921     10,708     3,687     2,925     1,871  
Zinc1 tonnes   2,871     4,857     25,120     5,261     8,607     5,133     6,119     28,779     7,385     7,125     8,641  
Silver ounces   209,594     232,255     956,460     282,158     244,974     197,486     231,841     728,304     246,757     197,952     133,916  
Combined unit cost 2,3 C$/tonne $ 241   $ 214   $ 226   $ 233   $ 211   $ 225   $ 235   $ 217   $ 216   $ 217   $ 220  
Gold cash cost 3 $/oz $ 710   $ 376   $ 606   $ 607   $ 372   $ 771   $ 736   $ 727   $ 434   $ 670   $ 1,097  
Sustaining gold cash cost 3 $/oz $ 1,025   $ 626   $ 868   $ 908   $ 553   $ 1,163   $ 950   $ 1,077   $ 788   $ 939   $ 1,521  
1 Includes refined zinc metal sold.
2 Reflects combined mine, mill and G&A costs per tonne of milled ore.
3 Combined unit costs, cash cost, and sustaining cash cost per pound of copper produced, cash cost, and sustaining cash cost per ounce of gold produced, net of by-product credits, are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A. The above table sets forth selected non-GAAP financial performance measures for each of the Company's nine most recently completed quarters and three most recently completed years; detailed reconciliations for non-comparable prior periods can be found in Hudbay's MD&A for these prior periods in the "Non-GAAP Financial Performance Measures" section of these documents. 
4 Annual consolidated results may not calculate based on amounts presented in this table due to rounding.
5 Metal reported in concentrate is prior to deductions associated with smelter terms



      Q2 2025     Q1 2025     2024 6     Q4 2024     Q3 2024     Q2 2024     Q1 2024     2023 6     Q4 2023     Q3 2023     Q2 2023 5  
British Columbia Operations 4              
Ore mined1 tonnes   2,509,969     2,648,094     11,360,125     2,374,044     3,098,863     2,164,722     3,722,496     6,975,389     2,627,398     3,792,568     555,423  
Strip Ratio     7.50     6.73     5.98     7.36     6.05     7.61     4.10     3.82     5.34     2.96     -  
Ore milled tonnes   2,900,008     2,760,986     12,656,679     2,880,927     3,363,176     3,232,427     3,180,149     6,862,152     3,261,891     3,158,006     442,255  
Copper %   0.28     0.33     0.25     0.26     0.24     0.25     0.27     0.35     0.33     0.36     -  
Gold g/tonne   0.09     0.10     0.08     0.09     0.09     0.07     0.07     0.07     0.06     0.08     -  
Silver g/tonne   0.97     1.28     0.96     0.92     0.73     1.01     1.19     1.36     1.36     1.40     1  
Copper recovery %   81.0     78.3     82.4     79.5     84.1     82.3     83.4     79.7     78.8     80.90     78  
Gold recovery %   68.2     63.4     60.5     55.8     67.3     57.2     61.8     55.9     54.1     56.10     68  
Silver recovery %   71.8     69.8     71.8     69.0     71.2     73.9     72.4     73.0     73.8     71.30     79  
Contained metal in concentrate produced        
Copper tonnes   6,634     7,196     26,406     5,927     6,736     6,719     7,024     19,050     8,508     9,303     1,239  
Gold ounces   5,670     5,561     19,789     4,644     6,274     4,454     4,417     8,848     3,495     4,608     745  
Silver ounces   65,040     79,480     280,499     58,933     55,963     77,227     88,376     218,282     105,295     101,069     11,918  
Payable metal sold                                                                    
Copper tonnes   6,803     6,153     25,354     5,831     6,026     6,564     6,933     18,075     9,119     8,956     -  
Gold ounces   5,813     4,965     19,735     5,036     6,199     5,099     3,401     8,420     3,091     5,329     -  
Silver ounces   67,988     60,059     249,536     43,747     53,241     69,248     83,300     189,443     98,441     91,002     -  
Combined unit cost 2,3 C$/tonne $ 24.51   $ 25.98   $ 20.39   $ 23.22   $ 15.58   $ 19.65   $ 23.67   $ 21.38   $ 20.90   $ 24.88     -  
Cash cost3 $/lb $ 2.39   $ 2.44   $ 2.74   $ 3.00   $ 1.81   $ 2.67   $ 3.49   $ 2.49   $ 2.67   $ 2.67     -  
Sustaining cash cost 3 $/lb $ 5.18   $ 4.24   $ 5.29   $ 5.76   $ 5.06   $ 5.56   $ 4.85   $ 3.41   $ 3.93   $ 3.39     -  
1 Reported tonnes and grade for ore mined are estimates based on mine plan assumptions and may not fully reconcile to ore milled.
2 Reflects combined mine, mill and general and administrative ("G&A") costs per tonne of ore milled. Reflects the deduction of expected capitalized stripping costs.
3 Combined unit costs, cash cost, and sustaining cash cost per pound of copper produced, net of by-product credits, are non-GAAP financial performance measures with no standardized definition under IFRS. For further information and a detailed reconciliation, please see the discussion under the "Non-GAAP Financial Performance Measures" section of this MD&A. The above table sets forth selected non-GAAP financial performance measures for each of the Company's nine most recently completed quarters and three most recently completed years; detailed reconciliations for non-comparable prior periods can be found in Hudbay's MD&A for these prior periods in the "Non-GAAP Financial Performance Measures" section of these documents. 
4 Includes 100% of Copper Mountain mine production. As at March 31, 2025, Hudbay owned 75% of the Copper Mountain mine. Subsequent to quarter end, Hudbay completed an acquisition of the remaining 25% interest and as at June 30, 2025 Hudbay owns 100% of the Copper Mountain mine.
5 Production results from Copper Mountain operations represents the period from the June 20, 2023 acquisition date through to the end of the second quarter of 2023.
6 Annual consolidated results may not calculate based on amounts presented in this table due to rounding.