2.01 SDfalse00008445512024-12-31USDNRThe Dividends category required by the Regulations has been excluded from the table as no payments were made against this category for the year ended 31 December 2024.Figures are rounded to the nearest $0.1 million.North West Shelf includes Okha FPSO.Includes 100% of the taxes paid by Burrup Facilities Company Pty Ltd and Burrup Train 1 Pty Ltd. Woodside holds a 90% interest in these entities.Where Taxes paid to governments cannot be attributable to a project, the applicable entity has been referenced. Corporate/Other includes exploration, projects that are no longer producing (Griffin, Minerva and Stybarrow) and payments which cannot be attributed to a specific project. Production entitlement is for payments in kind for 0.7 million barrels of oil equivalent (MMboe) of crude oil and gas valued per the Production Sharing Agreement.Production entitlement is for payments in kind for 5.7 MMboe of crude oil and gas valued per the Production Sharing Agreement.The royalties collected are shared between the WA State and Federal Governments, and approximately 68% of the Federal royalties are paid to the State.Reported community and social contribution payments are those required by law or contract as required under this Form SD. Woodside makes social and community contribution payments above those required by law or contract. 0000844551 2024-01-01 2024-12-31 0000844551 wds:TrinidadAndTobagoProjectMember 2024-01-01 2024-12-31 0000844551 wds:TrinidadAndTobagoProjectMember wds:GreaterAngosturaMember 2024-01-01 2024-12-31 0000844551 wds:SenegalProjectMember 2024-01-01 2024-12-31 0000844551 wds:SenegalProjectMember wds:SangomarMember 2024-01-01 2024-12-31 0000844551 wds:AustraliaProjectsMember 2024-01-01 2024-12-31 0000844551 wds:AustraliaProjectsMember wds:BassStraitMember 2024-01-01 2024-12-31 0000844551 wds:AustraliaProjectsMember wds:CorporateOtherMember 2024-01-01 2024-12-31 0000844551 wds:AustraliaProjectsMember wds:GreaterEnfieldMember 2024-01-01 2024-12-31 0000844551 wds:UnitedStatesOfAmericaProjectMember 2024-01-01 2024-12-31 0000844551 wds:MexicoProjectMember wds:TrionMember 2024-01-01 2024-12-31 0000844551 wds:SenegalProjectMember wds:SangomarOneMember 2024-01-01 2024-12-31 0000844551 wds:SingaporeProjectMember 2024-01-01 2024-12-31 0000844551 wds:SingaporeProjectMember wds:WoodsideEnergyTradingSingaporePteLtdMember 2024-01-01 2024-12-31 0000844551 wds:SingaporeProjectMember wds:WoodsideEnergyAustraliaAsiaHoldingsPteLtdMember 2024-01-01 2024-12-31 0000844551 wds:AustraliaProjectsMember wds:JulimarBrunelloWheatstoneMember 2024-01-01 2024-12-31 0000844551 wds:AustraliaProjectsMember wds:NorthWestShelfMember 2024-01-01 2024-12-31 0000844551 wds:AustraliaProjectsMember wds:PlutoMember 2024-01-01 2024-12-31 0000844551 wds:AustraliaProjectsMember wds:PyreneesFpsoAndMacedonMember 2024-01-01 2024-12-31 0000844551 wds:AustraliaProjectsMember wds:WoodsideEnergyGroupLtdMember 2024-01-01 2024-12-31 0000844551 wds:MexicoProjectMember 2024-01-01 2024-12-31 0000844551 wds:UnitedStatesOfAmericaProjectMember wds:GulfOfAmericaMember 2024-01-01 2024-12-31 0000844551 wds:UnitedStatesOfAmericaProjectMember wds:WoodsideEnergyUSAOperationsIncMember 2024-01-01 2024-12-31 0000844551 wds:UnitedStatesOfAmericaProjectMember wds:WoodsideEnergyDeepwaterIncMember 2024-01-01 2024-12-31 0000844551 wds:UnitedStatesOfAmericaProjectMember wds:WoodsideEnergyUsaServicesIncMember 2024-01-01 2024-12-31 0000844551 wds:AustraliaProjectsMember wds:ScarboroughMember 2024-01-01 2024-12-31 0000844551 wds:AustraliaProjectsMember wds:BrowseMember 2024-01-01 2024-12-31 0000844551 wds:TimorLesteProjectMember 2024-01-01 2024-12-31 0000844551 wds:TimorLesteProjectMember wds:SunriseMember 2024-01-01 2024-12-31 0000844551 wds:TrinidadAndTobagoProjectMember wds:GreaterAngosturaOneMember 2024-01-01 2024-12-31 0000844551 wds:BarbadosProjectMember 2024-01-01 2024-12-31 0000844551 wds:BarbadosProjectMember wds:WoodsideEnergyBimshireLimitedMember 2024-01-01 2024-12-31 0000844551 country:SN 2024-01-01 2024-12-31 0000844551 country:SN wds:MinistereDesEnergiesDuPetroleEtDesMinesMember 2024-01-01 2024-12-31 0000844551 country:TT 2024-01-01 2024-12-31 0000844551 country:TT wds:MinistryOfEnergyAndEnergyIndustriesMember 2024-01-01 2024-12-31 0000844551 country:SG 2024-01-01 2024-12-31 0000844551 country:MX wds:ServicioDeAdministracinTributariaMember 2024-01-01 2024-12-31 0000844551 country:MX 2024-01-01 2024-12-31 0000844551 country:AU 2024-01-01 2024-12-31 0000844551 country:AU wds:AustralianTaxationOfficeMember 2024-01-01 2024-12-31 0000844551 country:US wds:TexasComptrollerOfPublicAccountsMember 2024-01-01 2024-12-31 0000844551 country:SG wds:InternalRevenueAuthorityOfSingaporeMember 2024-01-01 2024-12-31 0000844551 country:US wds:InternalRevenueServiceMember 2024-01-01 2024-12-31 0000844551 country:US wds:LouisianaDepartmentOfRevenueMember 2024-01-01 2024-12-31 0000844551 country:US 2024-01-01 2024-12-31 0000844551 country:SN wds:ReceveurGeneralDuTresorMember 2024-01-01 2024-12-31 0000844551 country:AU wds:DepartmentOfIndustryScienceResourcesMember 2024-01-01 2024-12-31 0000844551 country:US wds:UsDepartmentOfTheInteriorMember 2024-01-01 2024-12-31 0000844551 country:US wds:OfficeOfNaturalResourcesRevenueMember 2024-01-01 2024-12-31 0000844551 country:AU wds:ShireOfExmouthMember 2024-01-01 2024-12-31 0000844551 country:AU wds:ShireOfAshburtonMember 2024-01-01 2024-12-31 0000844551 country:TL wds:AutoridadeNacionalDoPetrleoEMineraisMember 2024-01-01 2024-12-31 0000844551 country:AU wds:DevelopmentWaWesternAustralianLandAuthorityMember 2024-01-01 2024-12-31 0000844551 country:AU wds:DepartmentOfPlanningLandsAndHeritageMember 2024-01-01 2024-12-31 0000844551 country:AU wds:NationalOffshorePetroleumSafetyAndEnvironmentalManagementAuthorityMember 2024-01-01 2024-12-31 0000844551 country:BB 2024-01-01 2024-12-31 0000844551 country:BB wds:MinistryOfEnergyAndWaterMember 2024-01-01 2024-12-31 0000844551 country:TL 2024-01-01 2024-12-31 0000844551 country:AU wds:PilbaraPortsAuthorityMember 2024-01-01 2024-12-31 0000844551 country:TT wds:MinistryofEnergyandEnergyIndustriessOneMember 2024-01-01 2024-12-31 0000844551 country:AU wds:DepartmentOfMinesIndustryRegulationAndSafetyMember 2024-01-01 2024-12-31 0000844551 country:AU wds:DepartmentOfWaterAndEnvironmentalRegulationMember 2024-01-01 2024-12-31 0000844551 country:SN wds:NationalInstituteForPetroleumAndGasMember 2024-01-01 2024-12-31 0000844551 country:AU wds:GovernmentOfWesternAustraliaConstructionTrainingFundMember 2024-01-01 2024-12-31 0000844551 wds:SenegalProjectMember wds:SangomarTwoMember 2024-01-01 2024-12-31 iso4217:USD
Exhibit
2.01
Exhibit 2.01 - Resource Extraction Payment Report
Reporting Entity
Woodside Energy Group Ltd
Reporting Fiscal Year
From 01/01/2024 to
31/12/2024
Reporting currency
All payments are reported in
US dollars
. Payments made in currencies other than US dollars are translated at the exchange rate existing at the time the payment is made.
Activities
This Report includes cash and
in-kind
payments made to Foreign Governments, the U.S. Federal Government or U.S. State Governments with respect to the commercial development of oil and natural gas involving the exploration, prospection, discovery, development and extraction for any such activity. All such activities with the extraction method of “well”, are included in this Report.
Foreign Government
Foreign Government is defined as the national government of a foreign country, as well as any department, agency, or instrumentality of the national government, or a company at least majority owned by the national government of a foreign country. As used in this Item 2.01, foreign government also includes a foreign subnational government, such as the government of a state, province, department, county, district, municipality, or territory under a foreign national government.
Project
Payments are reported at project level except for payments that are not attributable to a specific project, which are reported at the entity level. Project is defined as operational activities which are governed by a single contract, licence, lease, concession or similar legal agreement, and form the basis for payment liabilities with a government. If these agreements are substantially interconnected, then they may be treated as a single project.
Substantially interconnected means forming a set of operationally and geographically integrated contracts, licences, leases or concessions or related agreements with substantially similar terms that are signed with a government, giving rise to payment liabilities.
Materiality
In accordance with the Resource Extraction Payment Rules, payments below $100,000 to a government are excluded from this Report.

Payments by government
 
Total payments to governments
(US$ million)
1
,
2
  
Currencies
used to make
the payment
 
Production
entitlements
   
Taxes
   
Royalties
   
Signature,
discovery and
production
bonuses
   
Payments for
infrastructure
improvements
   
Fees
   
Community
and social
contribution
3
   
Total
(US$ million)
 
Australia
    
 
— 
 
 
 
2,471.4
 
 
 
228.4
 
 
 
— 
 
 
 
0.3
 
 
 
22.1
 
 
 
4.3
 
 
 
2,726.5
 
Australian Taxation Office
   AUD     —        2,471.4       —        —        —        —        —        2,471.4  
Department of Industry, Science and Resources
4
   AUD     —        —        228.4       —        —        2.2       —        230.6  
Department of Energy, Mines, Industry Regulation and Safety
   AUD     —        —        —        —        —        0.6       —        0.6  
Department of Water and Environmental Regulation
   AUD     —        —        —        —        —        0.7       —        0.7  
National Offshore Petroleum Safety and Environmental Management Authority
   AUD     —        —        —        —        —        9.5       —        9.5  
Government of Western Australia Construction Training Fund
   AUD     —        —        —        —        —        —        4.3       4.3  
Pilbara Ports Authority
   AUD     —        —        —        —        —        2.7       —        2.7  
Shire of Ashburton
   AUD     —        —        —        —        —        2.2       —        2.2  
Development WA Western Australian Land Authority
   AUD     —        —        —        —        —        3.8       —        3.8  
Department of Planning, Lands and Heritage
   AUD     —        —        —        —        —        0.4       —        0.4  
Shire of Exmouth
   AUD     —        —        —        —        0.3       —        —        0.3  
Barbados
    
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
0.4
 
 
 
— 
 
 
 
0.4
 
Ministry of Energy and Water
   USD     —        —        —        —        —        0.4       —        0.4  
Mexico
    
 
— 
 
 
 
0.2
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
0.2
 
Servicio de Administración Tributaria
   MXN     —        0.2       —        —        —        —        —        0.2  
Senegal
    
 
52.6
 
 
 
0.3
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
0.2
 
 
 
53.1
 
Receveur General Du Tresor
   XOF     —        0.3       —        —        —        —        —        0.3  
Ministère des Energies, du Pétrole et des Mines
5
  
In-Kind
    52.6       —        —        —        —        —        —        52.6  
National Institute for Petroleum and Gas
   USD     —        —        —        —        —        —        0.2       0.2  
Singapore
    
 
— 
 
 
 
13.0
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
13.0
 
Internal Revenue Authority of Singapore
   SGD     —        13.0       —        —        —        —        —        13.0  
Timor-Leste
    
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
0.3
 
 
 
— 
 
 
 
0.3
 
Autoridade Nacional do Petróleo e Minerais
   USD     —        —        —        —        —        0.3       —        0.3  
Trinidad and Tobago
    
 
81.6
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
85.8
 
 
 
— 
 
 
 
167.4
 
Ministry of Energy and Energy Industries
6
  
In-Kind
    81.6       —        —        —        —        —        —        81.6  
Ministry of Energy and Energy Industries
   USD     —        —        —        —        —        85.8       —        85.8  
United States of America
    
 
— 
 
 
 
106.3
 
 
 
267.9
 
 
 
19.9
 
 
 
— 
 
 
 
10.8
 
 
 
— 
 
 
 
404.9
 
Internal Revenue Service
   USD     —        83.3       —        —        —        —        —        83.3  
Louisiana Department of Revenue
   USD     —        16.0       —        —        —        —        —        16.0  
Office of Natural Resources Revenue
   USD     —        —        —        19.9       —        10.8       —        30.7  
Texas Comptroller of Public Accounts
   USD     —        7.0       —        —        —        —        —        7.0  
US Department of the Interior
   USD     —        —        267.9       —        —        —        —        267.9  
Total (US$ million)
    
 
134.2
 
 
 
2,591.2
 
 
 
496.3
 
 
 
19.9
 
 
 
0.3
 
 
 
119.4
 
 
 
4.5
 
 
 
3,365.8
 
  
 
 
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
 
 
1
The Dividends category required by the Regulations has been excluded from the table as no payments were made against this category for the year ended 31 December 2024.
2
Figures are rounded to the nearest $0.1 million.
3
Reported community and social contribution payments are those required by law or contract as required under this Form SD. Woodside makes social and community contribution payments above those required by law or contract.
4
The royalties collected are shared between the Western Australia State and Australian Federal Governments, and approximately 68% of the Federal royalties are paid to the State.
5
Production entitlement is for payments in kind for 0.7 million barrels of oil equivalent (MMboe) of crude oil and gas valued per the Production Sharing Agreement.
6
Production entitlement is for payments in kind for 5.7 MMboe of crude oil and gas valued per the Production Sharing
Agreement
.

Payments by project
 
Total
payments to
governments
(US$ million)
1,2
 
Business
segment
 
National &
Subnational
Jurisdictions
 
Currencies
used to make
the payment
 
Production
entitlements
   
Taxes
   
Royalties
   
Signature,
discovery and
production
bonuses
   
Payments for
infrastructure
improvements
   
Fees
   
Community
and social
contribution
3
   
Total
(US$ million)
 
Australia
       
 
— 
 
 
 
2,471.4
 
 
 
228.4
 
 
 
— 
 
 
 
0.3
 
 
 
22.1
 
 
 
4.3
 
 
 
2,726.5
 
Bass Strait
  Australia  
AU-VIC (Bass Strait)
  AUD     —        229.2       —        —        —        —        —        229.2  
Browse
  Australia  
AU-WA

(Indian Ocean)
  AUD     —        —        —        —        —        0.4       —        0.4  
Corporate/Other
4
  Australia   N/A   AUD     —        (135.0     —        —        —        9.1       —        (125.9
Greater Enfield
  Australia  
AU-WA

(Indian Ocean)
  AUD     —        94.1       —        —        —        0.4       —        94.5  
Julimar-Brunello/Wheatstone
  Australia  
AU-WA

(Indian Ocean)
  AUD     —        39.5       —        —        —        0.7       —        40.2  
North West Shelf
5
  Australia  
AU-WA

(Indian Ocean)
  AUD     —        151.5       228.4       —        —        5.2       0.2       385.3  
Pluto
6
  Australia  
AU-WA

(Indian Ocean)
  AUD     —        484.4       —        —        —        2.0       0.1       486.5  
Pyrenees FPSO and Macedon
  Australia  
AU-WA

(Indian Ocean)
  AUD     —        101.2       —        —        —        3.6       —        104.8  
Scarborough
  Australia  
AU-WA

(Indian Ocean)
  AUD     —        —        —        —        0.3       0.7       4.0       5.0  
Payments not attributable to a project:
7
                     
Woodside Energy Group Ltd
  Australia   N/A   AUD     —        1,506.5       —        —        —        —        —        1,506.5  
Barbados
       
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
   
 
0.4
 
 
 
— 
 
 
 
0.4
 
Payments not attributable to a project:
7
                     
Woodside Energy (Bimshire) Limited
  International   N/A   USD     —        —        —        —        —        0.4       —        0.4  
Mexico
       
 
— 
 
 
 
0.2
 
 
 
— 
 
 
 
— 
 
   
 
— 
 
 
 
— 
 
 
 
0.2
 
Trion
  International  
MX-TAM

(Gulf of Mexico)
  MXN     —        0.2       —        —        —        —        —        0.2  
Senegal
       
 
52.6
 
 
 
0.3
 
 
 
— 
 
 
 
— 
 
   
 
— 
 
 
 
0.2
 
 
 
53.1
 
Sangomar
8
  International  
SN-DK

(Atlantic Ocean)
 
In-Kind
    52.6       —        —        —        —        —        —        52.6  
Sangomar
  International  
SN-DK

(Atlantic Ocean)
  XOF     —        0.3       —        —        —        —        —        0.3  
Sangomar
  International  
SN-DK

(Atlantic Ocean)
  USD     —        —        —        —        —        —        0.2       0.2  
Singapore
       
 
— 
 
 
 
13.0
 
 
 
— 
 
 
 
— 
 
   
 
— 
 
 
 
— 
 
 
 
13.0
 
Payments not attributable to a project:
7
                     
Woodside Energy Trading Singapore Pte Ltd
  Marketing   N/A   SGD     —        12.6       —        —        —        —        —        12.6  
Woodside Energy Australia Asia Holdings Pte Ltd
  Marketing   N/A   SGD     —        0.4       —        —        —        —        —        0.4  
Timor-Leste
       
 
— 
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
   
 
0.3
 
 
 
— 
 
 
 
0.3
 
Sunrise
  International  
TL-DI

(Timor Sea)
  USD     —        —        —        —        —        0.3       —        0.3  
Trinidad and Tobago
       
 
81.6
 
 
 
— 
 
 
 
— 
 
 
 
— 
 
   
 
85.8
 
 
 
— 
 
 
 
167.4
 
Greater Angostura
9
  International  
TT-MRC

(North Atlantic Ocean)
 
In-Kind
    81.6       —        —        —        —        —        —        81.6  
Greater Angostura
  International  
TT-MRC

(North Atlantic Ocean)
  USD     —        —        —        —        —        85.8       —        85.8  
United States of America
       
 
— 
 
 
 
106.3
 
 
 
267.9
 
 
 
19.9
 
 
 
— 
 
 
 
10.8
 
 
 
— 
 
 
 
404.9
 
Gulf of America
  International  
US-LA

(Gulf of America)
  USD     —        0.2       267.9       19.9       —        10.8       —        298.8  
Payments not attributable to a project:
7
                     
Woodside Energy USA Operations Inc.
  International   N/A   USD     —        87.5       —        —        —        —        —        87.5  
Woodside Energy (Deepwater) Inc.
  International   N/A   USD     —        11.6       —        —        —        —        —        11.6  
Woodside Energy USA Services Inc.
  International   N/A   USD     —        7.0       —        —        —        —          7.0  
Total (US$ million)
       
 
134.2
 
 
 
2,591.2
 
 
 
496.3
 
 
 
19.9
 
 
 
0.3
 
 
 
119.4
 
 
 
4.5
 
 
 
3,365.8
 
 
 
 
 
 
 
 
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
   
 
 
 
 
 
1
The Dividends category required by the Regulations has been excluded from the table as no payments were made against this category for the year ended 31 December 2024.
2
Figures are rounded to the nearest $0.1 million.
3
Reported community and social contribution payments are those required by law or contract as required under this Form SD. Woodside makes social and community contribution payments above those required by law or contract.
4
Corporate/Other includes exploration, projects that are no longer producing (Griffin, Minerva and Stybarrow) and payments which cannot be attributed to a specific project.
5
North West Shelf includes Okha FPSO.
6
Includes 100% of the taxes paid by Burrup Facilities Company Pty Ltd and Burrup Train 1 Pty Ltd. Woodside holds a 90% interest in these entities.
7
Where Taxes paid to governments cannot be attributable to a project, the applicable entity has been referenced.
8
Production entitlement is for payments in kind for 0.7 million barrels of oil equivalent (MMboe) of crude oil and gas valued per the Production Sharing Agreement.
9
Production entitlement is for payments in kind for 5.7 MMboe of crude oil and gas valued per the Production Sharing Agreement.