EX-10.15 5 d539986dex1015.htm EX-10.15 EX-10.15

Exhibit 10.15

 

*Portions of this exhibit marked [*] are requested to be treated confidentially.   OMB Approval 0990-0115      

 

AWARD/CONTRACT

 

 

1.  THIS CONTRACT IS A RATED ORDER UNDER DPAS (15 CFR 350)

  u  

RATING

 

PAGE    OF    PAGES

     

  N/A

 

1

     119   

2. CONTRACT (Proc. Inst. Indent.) NO.

 

3. EFFECTIVE DATE

 

4. REQUISITION/PURCHASE REQUEST/PROJECT NO.

HHSO100201300009C      See Block 20C.     OS111976
   5.  ISSUED BY   CODE                      

6. ADMINISTERED BY (If other than Item 6)

    CODE         

Office of Acquisitions Management, Contracts, and Grants (AMCG)

330 Independence Ave., S.W. Room G640

Washington, D.C. 20201

 

 

          See Block 5.                    

7. NAME AND ADDRESS OF CONTRACTOR (No. street, county, state and ZIP Code) 

 

8. DELIVERY

 

CEMPRA, Inc.

Building 4 Quadrangle

 

 

 

  See Schedule.

6340 Quadrangle Drive, Suite 100

Chapel Hill, NC 27517

 

 

 

9/ DISCOUNT FOR PROMPT PAYMENT

  N/A.

CAGE: 4D2L7                                TIN: 45-4440364  

10. SUBMIT INVOICES

 

  ITEM
CODE DUNS No. 623713034   FACILITY CODE   ADDRESS SHOWN IN:   See Section G.
   11.  SHIP TO/MARK FOR   CODE     N/A       12.  PAYMENT WILL BE MADE BY   CODE   N/A

 

    See Block 5.

 

     

 

  See Block 5.

 

13. AUTHORITY FOR USING OTHER FULL AND OPEN COMPETITION:    N/A

     

14. ACCOUNTING AND APPROPRIATION DATA

  Appropriation Year: 2013; Object Class:25106; CAN# 1992002  $17,710,427.25

   ¨  10 U.S.C. 2304(c)(    )               ¨  41 U.S.C. 253(c)(    )

 

     
15A. ITEM NO.   15B. SUPPLIES/SERVICES       15C. UNIT PRICE    15D. AMOUNT    15E. UNIT PRICE    15F. AMOUNT 

 

See Section B.

 

 

 

                   
                                    15G. TOTAL AMOUNT OF CONTRACT             u   $17,710,427.25
16. TABLE OF CONTENTS
(ü   SEC.    DESCRIPTION   PAGE(S)        (ü )   SEC.    DESCRIPTION   PAGE(S)
PART I - THE SCHEDULE       PART II - CONTRACT CLAUSES
x     A   SOLICITATION/CONTRACT FORM   1       x   I   CONTRACT CLAUSES   57
x     B   SUPPLIES OR SERVICES AND PRICE/COST   3       PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACH.
x     C   DESCRIPTION / SPECS / WORK STATEMENT   11       x   J   LIST OF ATTACHMENTS   63
x     D   PACKAGING AND MARKING   13       PART IV - REPRESENTATIONS AND INSTRUCTIONS
x     E   INSPECTION AND ACCEPTANCE   14       x   K   REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS   64
x     F   DELIVERIES OR PERFORMANCE   15            
x     G   CONTRACT ADMINISTRATION DATA   33       ¨   L   INSTRS., CONDS., AND NOTICES TO OFFERORS    
x     H   SPECIAL CONTRACT REQUIREMENTS   39       ¨   M   EVALUATION FACTORS FOR AWARD    
CONTRACTING OFFICER WILL COMPLETE ITEM 17 OR 18 AS APPLICABLE

17.  x   CONTRACTOR’S NEGOTIATED AGREEMENT (Contractor is required to sign this document and return   1    copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all the services set forth or otherwise identified above and on any continuation sheets for the consideration stated herein. The rights and obligations of the parties to this contract shall be subject to and governed by the following documents: (a) this award/contract, (b) the solicitation, if any, and (c) such provisions, representations, certifications, and specifications, as are attached or incorporated by reference herein. (Attachments are listed herein.)

 

     

18.  ¨  AWARD (Contractor is not required to sign this document.) Your offer on Solicitation Number                                                              , including the additions or changes made by you which additions or changes are set forth in full above, is hereby accepted as to the items listed above and on any continuation sheets. This award consummates the contract which consists of the following documents: (a) the Government’s solicitation and your offer, and (b) this award/contract. No further contractual document is necessary.

   19A.  NAME AND TITLE OF SIGNER  (Type or print)     20A.  NAME OF CONTRACTING OFFICER
           

 

   Susan Cortes-Shrank   AMCG,  ASPR,  OS,  DHHS

 

 

 19B.  NAME OF CONTRACTOR   19C.  DATE SIGNED     20B.  UNITED STATES OF AMERICA       20C. DATE SIGNED
                 

 

BY

 

 

 

       
(Signature of person authorized to sign)                       (Signature of Contracting Officer)            
 NSN 7540-01-152-8069   26-107   STANDARD FORM 26 (REV. 4-85)  
 PREVIOUS EDITION UNUSABLE   Computer Generated   Prescribed by GSAFAR (48 CFR) 53.214(a)  


CONTRACT TABLE OF CONTENTS

 

PART I – THE SCHEDULE

     3   

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS

     3   

SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

     11   

SECTION D - PACKAGING, MARKING AND SHIPPING

     13   

SECTION E - INSPECTION AND ACCEPTANCE

     14   

SECTION F - DELIVERIES OR PERFORMANCE

     15   

SECTION G - CONTRACT ADMINISTRATION DATA

     32   

SECTION H - SPECIAL CONTRACT REQUIREMENTS

     38   

PART II – CONTRACT CLAUSES

     56   

SECTION I - CONTRACT CLAUSES

     56   

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

     62   

SECTION J - LIST OF ATTACHMENTS

     62   

PART IV – REPRESENTATIONS AND INSTRUCTIONS

     63   

SECTION K – REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS

     63   

 

2


PART I – THE SCHEDULE

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

ARTICLE B.1. BRIEF DESCRIPTION OF SUPPLIES OR SERVICES

This contract is for the development of Solithromycin (CEM-101), a novel fluoroketolide antibiotic of the macrolide class for the treatment of select bacterial infections. The Research and Development (R&D) effort will progress in specific stages that cover the base performance segment and four (4) option segments as specified in this contract. Work performed during the base segment and during each option segment constitutes an independent, non-severable discrete work segment that cannot be subdivided for separate performance and is necessary to support R&D tasks related to the antibiotic. Each non-severable, work segment constitutes an entire job [discrete requirement] which shall contain multiple R&D activities that when reviewed in total shall satisfy a defined end-product. The non-severable, work segment will be fully funded from an appropriation source that is current at the time the work will be authorized to begin.

The government has determined a Bona Fide Need for each non-severable discrete work segment which will conclude upon the completion of a defined task(s) that provides independent merit and value to the Government. The Contractor must achieve a defined end-product required in each discrete work segment, as outlined in Article F of this contract, before the Government will consider exercising any of the follow-on option segment(s). The Contractor’s success in completing the required tasks under each work segment must be demonstrated through the Deliverables and Milestones specified under Article F of this contract. Those deliverables will support the GO/NO GO Contract Milestones and Decision Gates specified therein. The GO/NO GO Contract Milestones and Decision Gates will constitute the basis for the Government’s decision, at its sole discretion, to exercise any follow-on option segment(s).

The base and option segments under Contract Line Items (CLINs) 0001 through 0005 are event driven work segments rather than time driven CLINs. The funds for each independent, non-severable discrete work segment [requirement], regardless of duration, are separated by CLIN, and shall only be used for the scope of work covered in each discrete work segment (Attachment J). The periods of performance listed under each of the CLINs under Article B.2 and Article B.3 below are estimated time periods. Those individual time periods may be extended to complete the tasks required under each work segment. It is possible that more than one independent, non-severable discrete work segment [requirement], may be awarded at one time and that individual CLINs may overlap and/or proceed concurrently.

ARTICLE B.2. ESTIMATED COST AND FIXED FEE

 

  a. The total estimated cost of the base performance segment is $[*]
  b. The total fixed fee for the base performance segment is $[*]. The fixed fee shall be paid subject to Allowable Cost and Payment and Fixed Fee Clauses.
  c. The total amount of the base performance segment, CLIN 0001, represented by the sum of the total estimated cost plus fixed fee is $17,710,427.25. The Government will not be responsible for any Contractor incurred costs that exceed this amount unless a modification to the contract is signed by the Contracting Officer which expressly increases this amount.
  d. It is estimated period of performance of the base performance segment is through May 23, 2015.

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

3


  e. The Contractor shall maintain records of all contract costs and such records shall be subject to the Audit and Records-Negotiation and Final Decisions on Audit Findings clauses of the General Clauses.

 

CLIN    Estimated
Period of
Performance
  
   Supplies/Services     Total Estimated  
Cost
    Fixed Fee     

Total Estimated

Cost Plus

Fixed Fee

0001

   24 May 2013 through 23 May 2015.   

Toxicology studies, PK/PD modeling, safety studies, animal model efficacy studies, select chemical synthesis activities

 

Reports and Other Data Deliverables.

    $[*]     $[*]   

$17,710,427.25

 

SOW Reference

1.2.2, 1.3.2, 1.4.1, 1.5.1, 1.5.2, 1.6.1, 1.6.2, 1.6.3, 1.6.5

ARTICLE B. 3. OPTION PRICES

 

  a. Unless the government exercises its option pursuant to the option clause contained in ARTICLE I.2, the contract consists only of the Base Work segment specified in the Statement of Work as defined in SECTONS C, for the price set forth in ARTICLE B.2 of the contract.
  b. Pursuant to FAR Clause 52.217-9 (Option to Extend the Term of the Contract), the Government may, by unilateral contract modification, require the Contractor to perform the Option Work Segments specified in the Statement of Work as defined in SECTIONS C and F of this contract. If the Government exercises the/these option(s), written notice must be given to the Contractor within 30 days after the Government has completed its analysis of the deliverables associated with the applicable GO/NO GO Decision gate; and the Government must give the Contractor a preliminary written notice of its intent to exercise the option at least 30 days before the contract expires. Specific information regarding the time frame for this notice is set forth in the OPTION CLAUSE Article in SECTION G of this contract. The estimated cost of the contract will be increased as set forth below:

OPTIONS

Option 1 (CLIN 0002) - CPFF

Option 2 (CLIN 0003) - CPFF

Option 3 (CLIN 0004) – Cost Share (Fee unallowable)

Option 4 (CLIN 0005) - CPFF

 

CLIN    Estimated
Period of
Performance
  
   Supplies/Services  

  Total Estimated  

Cost

    Fixed Fee     

Total Estimated

Cost Plus

Fixed Fee

0002

  

24 May 2014 through 5

June 2016.

  

[*]

 

Reports and Other Data Deliverables.

    $[*]     $[*]   

$[*]

 

SOW Reference

2.4.1, 2.4.2, 2.5.2, 2.6.3, 2.6.5

0003

   14 November 2015 through 27 March 2017.   

[*]

Reports and Other Data Deliverables.

  $[*]   $[*]   

$[*]

 

SOW Reference

3.3.3, 3.4.1, 3.5.2, 3.6.3, 3.6.5

0005

   9 November 2017 through 23 May 2018.   

[*]

 

Reports and Other Data Deliverables.

  $[*]   $[*]   

$[*]

 

SOW Reference

5.5.2;

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

4


Cost  
Share  
CLIN   
   Estimated
Period of
Performance
   Supplies/Services  

  Total Estimated  

Cost of CLIN
0004

 

  Total Estimated  

Cost CEMPRA
share

   Total Estimated
Cost  Government
Share

0004  

   28 March 2015   through 23 May 2018.   

[*]

 

Reports and Other Data Deliverables.

  $[*]     $[*]     

$[*]

 

SOW Reference

 

4.4.2,

 

CLIN 0004 is a cost share CLIN and is subject to FAR Clause 52.216-12

ARTICLE B. 4. PROVISIONS APPLICABLE TO DIRECT COSTS

 

a. Items Unallowable Unless Otherwise Provided

Notwithstanding the clauses, ALLOWABLE COST AND PAYMENT and FIXED FEE, incorporated in this contract, unless authorized in writing by the Contracting Officer, the cost of the following items or activities shall be unallowable as direct costs:

 

  1) Acquisition, by purchase or lease, of any interest in real property;

 

  2) Special rearrangement or alteration of facilities;

 

  3) Accountable Government Property (see the Contractor’s Guide for Control for Government Property incorporated by ARTICLE G.10. of this contract);

Note: this includes the lease or purchase of any item of general purpose office furniture or office equipment regardless of dollar value.

 

  4) Purchase or lease scientific instruments or equipment over $1,500

 

  5) Travel to attend general scientific meetings/conferences;

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

5


  6) Printing Costs (as defined in the Government Printing and Binding Regulations);

 

  7) Overtime (premium) compensation

 

  8) Entering into certain types subcontract of arrangements (See Article B.5(c) for specific obligations). Note that most consulting agreements require a Contracting Officers Authorization (COA).

 

  9) Foreign Travel;

 

  10) Patient care costs (see Attachment 6);

 

b. Travel Costs

 

  1. Total expenditures for travel (transportation, lodging, subsistence, and incidental expenses) incurred in direct performance of this contract during the base segment (CLIN001) or any option segment(s) shall not exceed $[*] without the prior written approval of the Contracting Officer.

If, pursuant to FAR Clause 52.217-9 (Option to Extend the Term of the Contract), the Government exercises an option, travel costs for each CLIN shall not exceed the following schedule:

Option 1 (CLIN 0002) -  $[*]

Option 2 (CLIN 0003) -  $[*]

Option 3 (CLIN 0004) -  $[*] (BARDA share which excludes Cempra’s portion of travel costs for this Cost Share CLIN)

Option 4 (CLIN 0005) -  $[*]

 

  2. Subject to the annual dollar limitation specified under B.4.b.1. above, the Contactor shall invoice and be reimbursed for all travel costs in accordance with Federal Acquisition Regulation (FAR) 31. .2 – Contracts with Commercial Organizations, Subsection 31.205-46, Travel Costs.

 

  3. If foreign travel is necessary, a COA will be required. Expenditures for foreign travel (transportation, lodging, subsistence, and incidental expenses) incurred in direct performance of this contract shall not exceed the amount specified in each approved COA, without the prior written approval of the Contracting Officer.

Requests for foreign travel must be submitted at least four weeks in advance and shall contain the following:

(a) meeting(s) and place(s) to be visited, with breakout of costs and dates;

(b) name(s) and title(s) of Contractor personnel to travel and their functions in the contract project;

(c) contract purposes to be served by the travel;

(d) how travel of Contractor personnel will benefit and contribute to accomplishing the contract project, or will otherwise justify the expenditure of ASPR contract funds;

(e) how such advantages justify the costs for travel and absence from the project of more than one person if such are suggested; and

(f) what additional functions may be performed by the travelers to accomplish other purposes of the contract and thus further benefit the project.

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

6


ARTICLE B.5. ADVANCE UNDERSTANDINGS

 

  a. FDA Guidance

At the time of contract award, dated May 20, 2013, specific guidance from the FDA associated with optional CLIN 0004 ([*]) in a pediatric population is not available. The Contractor will conduct a meeting with the FDA during the base period of performance (CLIN 0001) of the contract to determine an appropriate strategy for obtaining approval of Solithromycin (CEM-101) for the treatment of Community Acquired Bacterial Pneumonia in pediatric populations. The GO/NO GO Contract Milestone #1 under Article F of this contract outlines the specific end products that the Contractor must meet before the Government will consider exercising the follow-on option segment [CLIN0004]. Article F of this contract describes the Go Criteria for Milestone #1 as [*].

In the event that the FDA provides guidance that extrapolation of efficacy data from adult populations is sufficient to support a label indication for a pediatric population without performing a pediatric efficacy study, activities described in the statement of work under attachment J, item 1 may be modified.

The contracting officer may request a modified statement of work for CLIN 0004 to align with the FDA guidance to ensure the Contractor can obtain relevant data to support submission of a NDA for their pediatric indication.

Any contract modification to the statement of work under CLIN 0004 will not impact the percentage of cost sharing under CLIN 0004 as agreed to by the Government and the Contractor prior to contract award. The Contractor to Government cost sharing distribution of [*]%:[*]% may not be renegotiated.

The GO/NO GO Contract Milestones and Decision Gates will constitute the basis for the Government’s decision, at its sole discretion, to exercise CLIN 0004.

 

  b. Man-in-Plant

With seven (7) days advance notice to the Contractor in writing from the Contracting Officer, the Government may place a man-in-plant in the Contractor’s facility, who shall be subject to the Contractor’s policies and procedures regarding security and facility access at all times while in the Contractor’s facility. As determined by federal law, no Government representative shall publish, divulge, disclose, or make known in any manner, or to any extent not authorized by law, any information coming to him in the course of employment or official duties, while stationed in a contractor plant.

 

  c. Security Plan

No Security Plan is required at this point for this effort. It is anticipated a security waiver will be approved. In the event a security waiver cannot successfully be attained, a security plan must be delivered to the Government subsequently.

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

7


  d. Subcontracts and Consultants

Prior written consent from the Contracting Officer in the form of Contracting Officer Authorization (COA) is required for any subcontract that is a cost-reimbursement type or fixed price and exceeds $[*].

Contracting Officer shall request appropriate supporting documentation in order to review and determine authorization, pursuant with FAR Clause 52.244-2, Subcontracts. After receiving written consent of the subcontract by the Contracting Officer, a copy of the signed, executed subcontract and consulting agreement shall be provided to the Contracting Officer.

Note: Consulting services are treated as subcontracts and subject to the ‘consent to subcontract’ provisions set forth in this Article.

 

  d. Site Visits and Inspections

At the discretion of the USG and independent of activities conducted by the Contractor, with 48 hours notice to the contractor, the USG reserves the right to conduct site visits and inspections on an as needed basis, including collection of product samples and intermediates held by the contractor, or subcontractor. In case of subcontractor visits and inspections that are independent of activities conducted by the Contractor, the USG shall demonstrate cause for such visit and/or inspection. All costs reasonably incurred by the Contractor and subcontractor for such visit and/or inspection shall be allowed costs. The Contractor shall coordinate these visits and shall have the opportunity to accompany the USG on any such visits. Under time-sensitive or critical situations, the USG reserves the right to suspend the 48 hour notice to the Contractor. The areas included under the site visit could include, but are not limited to: security, regulatory and quality systems, and cGMP/GLP/GCP compliance.

If BARDA, the Contractor, or other parties identifies any issues during an audit, the Contractor shall capture the issues, identify potential solutions, and provide a report to BARDA for review and acceptance.

 

   

If issues are identified during the audit, Contractor shall submit a report to BARDA detailing the finding and corrective action(s) within 10 business days of the audit.

   

COR and CO will review the report and provide a response to the Contractor within 10 business days.

   

Once corrective action is completed, the Contractor will provide a final report to BARDA.

QA AUDIT:

BARDA reserves the right to participate in QA audits. Upon completion of the audit/site visit the Contractor shall provide a report capturing the findings, results and next steps in proceeding with the subcontractor. If action is requested of the subcontractor, detailed concerns for addressing areas of non-conformance to FDA regulations for GLP, GMP, or GCP guidelines, as identified in the audit report, must be provided to BARDA for review and acceptance. The Contractor shall provide responses from the subcontractors to address these concerns and plans for corrective action execution.

 

   

Contractor shall notify CO and COR of upcoming, ongoing, or recent audits/site visits of subcontractors as part of weekly communications

   

Contractor shall notify the COR and CO within 5 business days of report completion.

 

  e. Invoices - Cost and Personnel Reporting and Variances from the Negotiated Budget

See Attachment #2 for detailed requirements for Invoicing.

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

8


The Contractor agrees to provide a detailed breakdown on invoices of the following cost categories:

 

  a. Direct Labor - List individuals by name, title/position, hourly/annual rate, level of effort (actual hours or % of effort), breakdown by task performed by personnel, and amount claimed.
  b. Fringe Benefits - Cite rate and amount
  c. Overhead - Cite rate and amount
  d. Materials & Supplies - Include detailed breakdown when total amount is greater than $1,500.
  e. Travel - Identify travelers, dates, destination, purpose of trip, and amount. Cite COA, if appropriate. List separately domestic travel, general scientific meeting travel, and foreign travel.
  f. Consultant Fees - Identify individuals and amounts. Cite appropriate COA.
  g. Subcontracts - Attach Subcontractor invoice(s). Cite appropriate COA.
  h. Equipment - Cite authorization and amount. Cite appropriate COA.
  i. Other Direct Costs - Include detailed breakdown when total amount is greater than $1,500.
  j. G&A - Cite rate and amount.
  k. Total Cost
  l. Fixed Fee
  m. Total CPFF

Monthly invoices must include the cumulative total expenses to date, adjusted (as applicable) to show any amounts suspended by the Government. In order to verify allowability, further breakdown of costs may be requested at the Government’s discretion.

See Attachment #2 for detailed requirements for Invoicing

 

  f. Confidential Treatment of Sensitive Information

The Contractor shall guarantee strict confidentiality of any information/data of a sensitive nature that is provided to the Contractor by the Government during the performance of the contract. The Government has determined that the information/data that the Contractor will be provided during the performance of the contract is of a sensitive nature.

Disclosure of information/data that is sensitive in nature, in whole or in part, by the Contractor can only be made after the Contractor receives prior written approval from the Contracting Officer. Whenever the Contractor is uncertain with regard to the proper handling of information/data under the contract, the Contractor shall obtain a written determination from the Contracting Officer. (See also HHSAR clause 352.224-70).

Notwithstanding the foregoing, such information/data shall not be deemed of a sensitive nature with respect to the Contractor for purposes of this contract if such information/data: (a) was already known to the Contractor; (b) was generally available or known, or was otherwise part of the public domain, at the time of its disclosure to the Contractor; (c) became generally available or known, or otherwise became part of the public domain, after its disclosure to, or, with respect to the information/data by, the Contractor through no fault of the Contractor; (d) was disclosed to the Contractor, other than under an obligation of confidentiality or non-use, by a third party who had no obligation to the Government that controls such information/data not to disclose such information/data to others; or (e) was independently discovered or developed by the Contractor, as evidenced by its written records, without the use of information/data belonging to the Government.

 

9


Contractor may disclose information/data of a sensitive nature provided by the Government to the extent that such disclosure is: (a) made in response to a valid order of a court of competent jurisdiction or other supra-national, federal, national, regional, state, provincial or local governmental or regulatory body of competent jurisdiction; provided, however, that the Contractor shall first have given notice to the Government and give the Government a reasonable opportunity to quash such order and to obtain a protective order requiring that the information/data of a sensitive nature that is the subject of such order be held in confidence by such court or agency or, if disclosed, be used only for the purposes for which the order was issued; and provided further that if a disclosure order is not quashed or a protective order is not obtained, the information/data disclosed in response to such court or governmental order shall be limited to that information which is legally required to be disclosed in response to such court or governmental order; (b) otherwise required by law, in the opinion of legal counsel to the Contractor as expressed in an opinion letter in form and substance reasonably satisfactory to the Government, which shall be provided to the Government at least two (2) business days prior to the Contractor’s disclosure of the information/data; or (c) made by the Contractor to the Regulatory Authorities as required in connection with any filing, application or request for Regulatory Approval; provided, however, that reasonable measures shall be taken to assure confidential treatment of such information/data.

 

  g. Sharing of contract deliverables within United States Government (USG)

In an effort to build a robust medical countermeasure pipeline through increased collaboration, BARDA may share technical deliverables with USG entities responsible for Medical Countermeasure Development. In accordance with recommendations from the Public Health Emergency Medical Countermeasure Enterprise Review, agreements established in the Integrated Portfolio’s Portfolio Advisory Committee (PAC) Charter, Technology Transfer Agreements (TTA) between BARDA and the Defense Threat Reduction Agency and the National Institute of Allergies and Infectious Diseases (NIAID), BARDA may share technical deliverables set forth in Article F.2 with colleagues within the Integrated Portfolio. This advance understanding does not authorize BARDA to share financial information outside HHS. The Contractor is advised to review the terms of FAR Clause 52.227-14 regarding the Government’s rights to deliverables submitted during performance as well as the Government’s rights to data contained within those deliverables.

 

  h. Overtime Compensation

No overtime (premium) compensation is authorized under the subject contract. Billing of actual hours is limited to total productive hours in a month.

 

10


SECTION C - DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

ARTICLE C.1. STATEMENT OF WORK

Independently and not as an agent of the Government, the Contractor shall furnish all the necessary services, qualified personnel, material, equipment, and facilities not otherwise provided by the Government as needed to perform the Statement of Work set forth in SECTION J-List of Attachments, attached hereto and made a part of the contract.

ARTICLE C.2. REPORTING REQUIREMENTS

Refer to ARTICLE F.2. for specific instructions regarding Reporting Requirements.

ARTICLE C.3. EARNED VALUE MANAGEMENT SYSTEM (EVMS) IMPLEMENTATION REQUIREMENTS

The Contractor and BARDA agree that the EVMS implementation requirements that are contained in this contract are limited to the implementation requirements outlined by the 7 Principles of Earned Value Management Tier 2 System Implementation Intent Guide contained in the Attachments (Section J) of the contract. The total amount of this contract reflects the use of the 7 Principles of EVMS Implementation. Any EVMS implementation requirements that are beyond the intent of the 7 Principles of EVMS Implementation shall not proceed until the Contracting Officer sends a written request for a proposal to the Contractor and a bilateral modification is issued to the contract for the purposes of incorporating the additional costs for the performance of these requirements into the contract.

Refer to ARTICLE F.2. for specifics on EVMS deliverables.

ARTICLE C.4. PROJECT MEETING CONFERENCE CALLS ONCE EVERY TWO WEEKS

A teleconference call between the Contracting Officer’s Representative and the Contractor’s Program Manager shall occur bi-weekly (every two weeks), or at the discretion of the U.S. Government. During this call, the Program Manager will discuss the activities during the reporting period, any problems that have arisen, and the activities planned for the ensuing reporting period. The Contractor’s Program Manager may choose to include other key personnel on the conference call to give detailed updates on specific projects or this may be requested by the Contracting Officer’s Representative.

Contractor will be responsible for preparing an agenda for the conference call and providing to BARDA no later than 2 business days prior to the scheduled conference call.

ARTICLE C.5. PROJECT MEETINGS

The Contractor shall participate in Project Meetings to coordinate the performance of the contract, as requested by the Contracting Officer’s Technical Representative. These meetings may include face-to-face meetings with BARDA/AMCG in Washington, D.C. and at work sites of the Contractor and its subcontractors. Such meetings may include, but are not limited to, meetings of the Contractor (and subcontractors invited by the Contractor) to discuss study designs, site visits to the Contractor’s and subcontractor’s facilities, and meetings with the Contractor and HHS officials to discuss the technical, regulatory, and ethical aspects of the program. The Contractor must provide data, reports, and presentations to groups of outside experts (subject to appropriate protections for Contractor confidential or proprietary data) and USG personnel as required by the Contracting Officer’s Technical Representative in order to facilitate review of contract activities.

 

11


  a. Kickoff Meeting

The Contractor shall complete a Kickoff meeting within [*] days after contract award. Contractor shall provide an itinerary/agenda no later than 5 business days before meeting.

 

  b. Quarterly and Ad-Hoc Meetings

At the discretion of BARDA, the Contractor shall participate in Project Meetings to coordinate the performance of the contract, as requested by the Contracting Officer’s Representative. These meetings may include face-to-face meetings with BARDA/AMCG in Washington, D.C. or at work sites of the Contractor and its subcontractors. Such meetings may include, but are not limited to, meetings of the Contractor (and subcontractors invited by the Contractor) to discuss study designs, site visits to the Contractor’s and subcontractor’s facilities, and meetings with the Contractor and HHS officials to discuss the technical, regulatory, and ethical aspects of the program. The Contractor must provide data, reports, and presentations to groups of outside experts (subject to appropriate protections for Contractor confidential or proprietary data) and USG personnel as required by the Contracting Officer’s Representative in order to facilitate review of contract activities.

Contractor shall provide itinerary/agenda at least 5 business days in advance of face-to-face meeting.

ARTICLE C.6 SUBJECT INVENTION REPORTING REQUIREMENT

All reports and documentation required by FAR Clause 52.227-11, including, but not limited to: the invention disclosure report, the confirmatory license, and the Government support certification, shall be directed to the Contracting Officer. The final invention statement (see FAR 27.303(b)(2)(ii)) shall be submitted to the Contracting Officer on the expiration date of the contract. See also FAR clause 52.227-11 (Patent Rights-Ownership by the Contractor).

Reports and documentation submitted to the Contracting Officer shall be sent to the Contracting Officer to the address set forth in SECTION G – CONTRACT ADMINISTRATION DATA.

If no invention is disclosed or no activity has occurred on a previously disclosed invention during the applicable reporting period, a negative report shall be submitted to the Contracting Officer at the address listed above.

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

12


SECTION D – PACKAGING, MARKING AND SHIPPING

All deliverables required under this contract shall be packaged, marked and shipped in accordance with Government specifications. At a minimum, all deliverables shall be marked with the contract number and Contractor name. The Contractor shall guarantee that all required materials shall be delivered in immediate usable and acceptable condition.

Report Deliverables

Unless otherwise specified by the Contracting Officer, delivery of reports to be furnished to the Government under this contract (including invoices), shall be delivered to BARDA electronically along with a concurrent email notification to the Contracting Officer, Contract Specialist, and COR summarizing the electronic delivery.

Delivery of physical reports to be furnished shall be addressed to the COR, CO, and CS (as defined in SECTION G – CONTRACT ADMINISTRATION DATA).

 

13


SECTION E – INSPECTION AND ACCEPTANCE

 

  1. The Contracting Officer (CO) or the duly authorized representative will perform inspection and acceptance of materials and services to be provided under this contract.

 

  2. For the purpose of this SECTON, the designated Contracting Officer’s Representative (COR) is the authorized representative of the Contracting Officer. The COR will assist in resolving technical issues that arise during performance. The COR however is not authorized to change any contract terms or authorize any changes in the Statement of Work or modify or extend the period of performance, or authorize reimbursement of any costs incurred during performance.

 

  3. Inspection and acceptance will be performed at:

Biomedical Advanced Research and Development Authority/Office of Acquisition

Management, Contracts, and Grants (AMCG)

Office of the Assistant Secretary for Preparedness and Response

U.S. Department of Health and Human Services

330 Independence Avenue, S.W., Room G644

Washington, D.C. 20201

 

14


SECTION F – DELIVERIES OR PERFORMANCE

ARTICLE F.1. ESTIMATED PERIOD OF PERFORMANCE

Under CLIN 0001, the estimated period of performance for the base performance segment of this contract shall be consistent with the dates set forth in ARTICLE B.2. If the Government exercises its option(s) pursuant to the Option Clauses in Article G.11 and Article I.2 of the contract, the period of performance (PoP) will be increased as shown in the table in Article B.3.

ARTICLE F.2. DELIVERABLES

Successful performance of the final contract shall be deemed to occur upon performance of the work set forth in the Statement of Work, dated April 17, 2013 set forth in SECTION J-List of Attachments of this contract and upon delivery and acceptance, as required by the Statement of Work, by the Contracting Officer, or the duly authorized representative, of the following items in accordance with the stated delivery schedule:

The items specified below as described in the REPORTING REQUIREMENTS Article in SECTION C of this contract and the Statement of Work set forth in SECTION J-List of Attachments will be required to be delivered in accordance with and by the date(s) specified below and any specifications stated in SECTION D, PACKAGING, MARKING AND SHIPPING, of this contract. All reports identified below relate solely to the development activity funded under this contract:

 

1. Summary of Contract Deliverables

Unless otherwise stated, each deliverable in the table below shall be provided as one (1) electronic copy to the COR and CO.

CDRL#   Deliverable   Deliverable Description   Reporting Procedures and Due Dates
01   Kickoff Meeting   The Contractor shall complete a Kickoff meeting after contract award  

 

             Within [*] days of contract award.

            Contractor shall provide itinerary and agenda at least 5 business days in advance of site visit.

            COR approves and distributes itinerary and agenda within 3 business days.

            Contractor provides meeting minutes to COR within 3 business days after the meeting.

            COR reviews, comments, and approves minutes within 10 business days.

 

02  

Quarterly

Meetings

  The Contractor shall hold recurring Program Review Meetings approximately every third month. The meetings will be used to discuss contract progress in relation to the Program Management deliverables described below as well as study designs, technical, regulatory, and ethical aspects of the program.  

             Contractor provides Quarterly Status Report five business days prior to meeting. This report is an expanded version of the Monthly Status Report.

            Contractor shall provide itinerary, agenda and meeting slides at least 5 business days in advance of the meeting.

            COR approves and distributes itinerary and agenda within 3 business days.

            Contractor provides meeting minutes to COR within 3 business days after the meeting.

            COR reviews, comments, and approves minutes within 10 business days.

 

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

15


CDRL#   Deliverable   Deliverable Description   Reporting Procedures and Due Dates
03   Project Status meeting   The Contractor shall participate in teleconferences every two weeks with BARDA to discuss the performance of the contract.  

            Contractor provides agenda to COR no later than 2 business days in advance of meeting

            COR approves (with CO concurrence) and distributes agenda prior to meeting

            Contractor provides meeting minutes to COR within 3 business days of the meeting

            COR reviews, comments, and approves minutes within 10 business days.

 

04  

Monthly,

Quarterly & Annual Project Status Report/Annual Meeting

 

The Monthly and Annual Technical Progress report shall address each of the below items and be cross-referenced to the Work Breakdown Structure (WBS), Statement of Work (SOW), Integrated Master Schedule (IMS), Performance Measurement Baseline Review report (PMBR), Earned Value Management (EVM), and Contract Performance Report (CPR).

 1.  An Executive Summary highlighting the progress, issues and relevant manufacturing, non-clinical, clinical and regulatory activities. The Executive Summary should highlight only critical issues for that reporting period and resolution approach; limited to 2-3 pages.

 2.  Progress in meeting contract milestones – broken out by subtasks within each milestone, overall project assessment, problems encountered and recommended solutions. The reports shall detail the planned and actual progress during the period covered, explaining occurrences of any differences between the two and the corrective steps.

 3.  The reports shall also include a three-month rolling forecast of the key planned activities, referencing the WBS/IMS.

 4.  A tracking log of progress on regulatory submissions with the FDA number, description of submission, date of submission, status of submission and next steps.

 5.  IMS updates

 6.  Provide updated EVM CPR

 7.  Estimated and Actual Expenses.

      a. This report shall also contain a narrative or table detailing whether there is a significant discrepancy (>10%) at this time between the % of work completed and the cumulative costs incurred to date. Monthly and actual expenses should be broken down to the appropriate WBS level. This section of the report should also contain estimates for the Subcontractors’ expenses from the previous month if the Subcontractor did not submit a bill in the previous month. If the subcontractor(s) was not working or did not incur any costs in the previous month, then a statement to this effect should be included in this report for those respective subcontractors.

 

 

            Monthly Reports shall be submitted on the 20th calendar day of each month or the next business day, with an Annual Report submitted on the 20th calendar day of the final month of each contract year for the previous twelve calendar months. Monthly progress reports are not required for the periods when the Annual Report(s) and Final Report are due. The COR and CO will review the monthly reports with the Contractor and provide feedback.

 

            Contractor provides Annual Project Status Report deliverables 5 business days prior to meeting. A draft report including .ppt slides should be provided 5 business days prior to the meeting. The annual report should also include information from the annual meeting due 15 business days after the meeting.

            COR approves (with CO concurrence) and distributes agenda no later than 2 business days in advance of meeting

            COR approves (with CO concurrence) all meeting material no later than 2 business days in advance of meeting

            Contractor provides meeting minutes within 5 business days of meeting

            COR reviews, comments, and approves minutes within 10 business days of receipt

            Contractor provides FINAL annual report within 15 business days after the conclusion of the annual meeting.

            COR reviews, comments, and approves (with CO concurrence) FINAL Annual Report

            BARDA and Contractor shall participate in an in-process review.

 

 

16


CDRL#   Deliverable   Deliverable Description   Reporting Procedures and Due Dates
05   Earned Value Management (EVM) / Contract Performance Report (CPR)  

Contractor will provide a monthly Contract Performance Report (CPR) Format 1 at an agreed upon reporting level using the BARDA provided WBS and a Variance Analysis Report (Format 5).

 

The supplemental monthly CAP report shall contain, at the work package level, time phased budget (budgeted cost of work scheduled), earned value (budgeted cost of work performed), and actual costs of work performed as captured in Contractor’s EVM systems. The Contractor shall provide a rationale in the package of its use of % complete as EVMS methodology or identity if any other EVMS methodology is being used.

 

            Contractor shall provide EVM/CPR as part of the Monthly Progress Report on the 20th day of the month after the end of each month

            Contractor shall provide top level or key changes in baseline cost as a result of anticipated cost savings or risks

            BARDA may request, on a monthly or ad hoc basis that the Contractor provide raw data at a reporting level or lower level as BARDA deems necessary.

            Contractor must address, in writing, all concerns raised by BARDA.

 

06   Performance Measurement Baseline Review (PMBR)  

PMBR Report shall address each of the items listed below and be cross-referenced to the IMP, WBS, SOW, and Risk Management Plan.

1. Contractor provides baseline proposal

2. Responsibility Assignment Matrix

3. A description of the work scope through control account Work Authorization Documents and/or WBS Dictionary down to the control account level

4. Template for work packages

5. IMS with the inclusion of agreed major milestones and control account plans for all control accounts

6. Baseline revision documentation and program log(s) risk management plan

 

            Due within 90 days of contract award

            Contractor shall provide baseline proposal .ppt briefing 10 business days prior to meeting

            Contractor provides agenda to COR 2 business days in advance of meeting

            COR approves (with CO concurrence) and distributes agenda no later than 2 business days in advance of meeting

            COR approves (with CO concurrence) all meeting material no later than 2 business days in advance of meeting

            Contactor provides minutes within 3 business days of the meeting

            COR reviews and approves (with CO concurrence) minutes

            BARDA will review documentation and provide written comments and questions to Contractor

  Contractor shall address BARDA’s comments and resubmit PMBR report for BARDA approval within 10 business days.

 

07   Risk Management Plan   The Contractor shall provide a Risk Management Plan that outlines the impacts of each risk in relation to the cost, schedule, and performance objectives. The plan shall include risk mitigation strategies. Each risk mitigation strategy will capture how the corrective action will reduce impacts on cost, schedule and performance.  

            Due within 90 days of contract award

            Contractor provides updated Risk Management Plan in Monthly Progress Report

            BARDA shall provide Contractor with a written list of concerns in response plan submitted

            Contractor must address, in writing, all concerns raised by BARDA within 20 business days of Contractor’s receipt of BARDA’s concerns.

 

08   Deviation Notification and Mitigation Strategy   Process for changing IMS activities associated with cost and schedule as baselined at the PMBR. Contractor shall notify BARDA of significant changes the IMS defined as increases in cost above [*]% for Go/No Go milestones or schedule slippage of more than [*] days, which would require a PoP extension. Contractor shall provide a high level management strategy for risk mitigation.  

            Due as needed

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

17


CDRL#   Deliverable   Deliverable Description   Reporting Procedures and Due Dates
09   Go/No-Go Decision Gate Presentation   Contractor shall provide a presentation detailing technical progress made towards completion of Go/No-Go decision gate milestones following a prescribed template provided by BARDA prior to the IPR  

            Contractor shall provide presentation in .ppt format 10 business days prior to the In-Process Review (IPR)

            Contractor shall submit written justification of progress towards satisfying Go/No-Go criteria

            After reviewing, BARDA COR and CO will provide a written response.

 

10   Incident Report   Contractor shall communicate and document all critical programmatic concerns, risks, or potential risks with BARDA.  

            Due within 48 hours of activity or incident or within 24 hours for a security activity or incident

            Email or telephone with written follow-up to COR and CO

            Additional updates due to COR and CO within 48 hours of additional developments

            Contractor shall submit within 5 business days a Corrective Action Plan (if deemed necessary by either party) to address any potential issues.

            If corrective action is deemed necessary, Contractor must address in writing, its consideration of concerns raised by BARDA within 5 business days.

 

11   Draft and Final Technical Progress Report  

A draft Final Technical Progress Report containing a summation of the work performed and the results obtained for the entire contract PoP. The draft report shall be duly marked as ‘Draft’.

 

The Final Technical Progress Report incorporating feedback received from BARDA and containing a summation of the work performed and the results obtained for the entire contract PoP. The final report shall document the results of the entire contract. This report shall be in sufficient detail to fully describe the progress achieved under all milestones. The final report shall be duly marked as ‘Final’.

 

            Contractor shall provide a draft Technical Progress Report 75 calendar days before the end of the PoP and the Final Technical Progress Report on or before the completion date of the PoP.

            Subcontractor prepared reports received by the Prime Contractor shall be submitted to the COR and CO for review and comment no later than 5 business days after receipt by the prime contractor

            COR shall provide feedback on draft report within 10 business days of receipt, which the Contractor shall consider incorporating into the Final Report

            Contractor shall submit, with the Final Technical Progress Report, a summary (not to exceed 200 words) of salient results achieved during the performance of the contract.

 

12   Draft and Final Reports for Clinical and Non-Clinical Studies  

 

Contractor shall provide Draft and Final Clinical/Non-Clinical Study Reports to BARDA for review and comment.

 

            Draft report due within 45 calendar days after completion of analysis and at least 15 business days prior to submission to FDA.

            Subcontractor prepared reports received by the Prime Contractor shall be submitted to the Contracting Officer’s Representative (COR) and Contracting Officer (CO) for review and comment no later than 5 business days after receipt by Prime Contractor.

 

18


CDRL#   Deliverable   Deliverable Description   Reporting Procedures and Due Dates
           

            The Government shall provide written comments to the Draft Final Report for Clinical and Non-Clinical Studies within 10 business days after the submission.

             Final report due 30 calendar days after receiving comments on the Draft Final Report for Clinical and Non-Clinical Studies. If corrective action is recommended, Contractor must address, in writing, all concerns raised by BARDA.

            Contractor shall consider revising reports to address BARDA’s recommendations prior to FDA submission.

            Final FDA submissions shall be provided to BARDA concurrently or no later than 1 business day after submission to the FDA.

 

13   Standard Operating   Procedures     The Contractor shall make internal and subcontractor Standard Operating Procedures (SOPs) available for review electronically.   Upon request from the Contracting Officer Representative/Contracting Officer
14   Manufacturing   Campaign Reports    

Contractor shall provide Manufacturing Campaign Reports to BARDA for review and comment prior to submission to FDA.

 

The COR and CO reserve the right to request within the PoP a non-proprietary Manufacturing Campaign Report for distribution within the USG.

 

            Contractor will submit Manufacturing Campaign Reports at least 15 business days prior to FDA submission.

            If corrective action is recommended, Contractor must address, in writing, all concerns raised by BARDA.

            Contractor shall consider revising reports to address BARDA’s concerns and/or recommendations prior to FDA submission.

            Final FDA submission shall be submitted to BARDA concurrently or no later than 1 business day after submission to the FDA.

 

15   FDA Correspondence     The Contractor shall memorialize any correspondence related to this contract between Contractor and FDA and submit to BARDA. All documents shall be duly marked as either “Draft” or “Final”.  

            Contractor shall provide written summary of any FDA correspondence within 5 business days of correspondence.

 

16   FDA Meetings     The Contractor shall forward the dates and times of any meeting related to this contract with the FDA to BARDA and make arrangements for appropriate BARDA staff to attend the FDA meetings. BARDA staff shall include up to a maximum of four people (COR, CO and up to 2 subject matter experts).  

            Contractor shall notify BARDA of upcoming FDA meeting within 24 hours of scheduling Type A, B or C meetings OR within 24 hours of meeting occurrence for ad hoc meetings.

             The Contractor shall forward initial Contractor and FDA-issued draft minutes and final minutes of any meeting with the FDA to BARDA within 5 business days of receipt. All documents shall be duly marked as either “Draft” or “Final”.

 

 

19


CDRL#   Deliverable   Deliverable Description   Reporting Procedures and Due Dates
17   FDA Submissions   The Contractor shall provide BARDA the opportunity to review and comment upon all draft documents before submission to the FDA. Contractor shall provide BARDA with an electronic copy of the final FDA submission. All documents shall be duly marked as either “Draft” or “Final”.  

            Contractor shall submit draft FDA submissions to BARDA at least 15 business days prior to FDA submission

            BARDA will provide feedback to Contractor within 10 business days of receipt

            If corrective action is recommended, the Contractor must address, in writing, its consideration of all concerns raised by BARDA

            The Contractor shall consider revising their documents to address BARDA’s concerns and/or recommendations prior to FDA submission

            Final FDA submissions shall be submitted to BARDA concurrently or no later than 1 calendar day of it submission to CDER.

 

18   FDA Audits  

In the event of an FDA inspection which occurs as a result of this contract and for the product, or for any other FDA inspection that has the reasonable potential to impact the performance of this contract, the Contractor shall provide the USG with an exact copy (non-redacted) of the FDA Form 483 and the Establishment Inspection Report (EIR). The Contractor shall provide the COR and CO with copies of the plan for addressing areas of non-conformance to FDA regulations for GLP, GMP, or GCP guidelines as identified in the audit report, status updates during the plans execution and a copy of all final responses to the FDA. The Contractor shall also provide redacted copies of any FDA audits received from subcontractors that occur as a result of this contract or for this product. The Contractor shall make arrangements for BARDA representative(s) to be present during the final debrief by the regulatory inspector.

 

 

 

            Contractor shall notify CO and COR within 10 business days of a scheduled FDA audit or within 24 hours of an ad hoc site visit/audit if the FDA does not provide advanced notice.

            Contractor shall provide copies of any FDA audit report received from subcontractors that occur as a result of this contract or for this product within 5 business days of receiving correspondence from the FDA or third party.

            Within 10 business days of audit report, Contractor shall provide CO with a plan for addressing areas of nonconformance, if any are identified.

 

19   QA Audit Reports   BARDA reserves the right to participate in QA audits. Upon completion of the audit/site visit the Contractor shall provide a report capturing the findings, results and next steps in proceeding with the subcontractor. If action is requested of the subcontractor, detailed concerns for addressing areas of non-conformance to FDA regulations for GLP, GMP, or GCP guidelines, as identified in the audit report, must be provided to BARDA. The Contractor shall provide responses from the subcontractors to address these concerns and plans for corrective action execution.  

            Contractor shall notify CO and COR 10 days in advance of upcoming, ongoing, or recent audits/site visits of subcontractors as part of weekly communications

             Contractor shall notify the CO and COR within 5 business days of report completion.

20   BARDA Audit   Contractor shall accommodate periodic or ad hoc site visits by BARDA. If BARDA, the Contractor, or other parties identifies any issues during an audit, the Contractor shall capture the issues, identify potential solutions, and provide a report to BARDA.  

            If issues are identified during the audit, Contractor shall submit a report to BARDA detailing the finding and corrective action(s) within 10 business days of the audit.

             CO and COR will review the report and provide a response to the Contractor with 10 business days.

            Once corrective action is completed, the Contractor will provide a final report to BARDA.

 

20


CDRL#   Deliverable   Deliverable Description   Reporting Procedures and Due Dates
21   Technical Documents   Upon request, Contractor shall provide CO and COR with deliverables from the following contract funded activities: process Development Reports, Assay Qualification Plan/Report, Assay Validation Plan/Report, Assay Technology Transfer Report, Batch Records, SOPs, Master Production Records, Certificate of Analysis, Clinical Studies Data or Reports. The CO and COR reserve the right to request within the PoP a non-proprietary technical document for distribution within the USG.  

 

            Contractor shall provide technical document within 10 business days of CO or COR request. Contractor can request additional time on an as needed basis.

            If corrective action is recommended, the Contractor must address, in writing, concerns raised by BARDA

 

22  

Animal Model or Other

Technology Transfer

Package

  Contractor shall provide Animal Model or Other Technology Transfer Package relevant data  

 

            Contractor shall provide package within 10 business days of CO or COR request.

 

23  

Raw Data or

Data Analysis

  Contractor shall provide raw data or data analysis to BARDA upon request  

            Contractor shall provide data or data analysis to CO and COR within 20 business days of request.

 

24  

Product

Transition

Strategy

 

Contractor shall provide a 2-4 page summary document containing a Product Transition Strategy to support transition of the product(s) prior to end of the base and/or option(s) POP. The Product Transition Strategy should provide a strategic plan for further development and/or stockpiling of the product

The transition strategy shall provide options and/or a specific approach for the transition of MCM product for further development, procurement, approval and/or stockpile

 

 

            Contractor shall provide a Product Transition Strategy to support transition of the product(s) 90 days prior to the end of the (base/option) POP as addendum to the Quarterly Project Status Report

 

25   Publications   Any manuscript or scientific meeting abstract containing data generated under this contract must be submitted to BARDA for review prior to submission  

Contractor must submit all manuscript or scientific meeting abstract to CO and COR within 20 business days for manuscripts and 10 business days for abstracts

Contractor must address in writing all concerns raised by BARDA

            Final submissions shall be submitted to BARDA concurrently or no later than one (1) calendar day of its submission

 

26   Press Releases   Contractor agrees to accurately and factually represent the work conducted under this contract in all press releases  

Contractor shall ensure that the CO has received and approved an advanced copy of any press release to this contract not less than 5 business days prior to the issuance of the press release

If corrective action is required, the Contractor agrees to accurately and factually represent the work conducted under this contract in all press releases

Any final submissions shall be submitted to BARDA concurrently or no later than one (1) calendar day of its submission.

NOTE: Pursuant to federal law, no Government personnel shall publish, divulge, disclose, or otherwise make known to any non-government entity any Contractor data marked according to FAR regulation, unless permitted to do so by law or regulation.

 

21


2. Detailed Description of Select Contract Deliverables

 

  A. Monthly and Annual Progress Reports

In addition to those reports required by the other terms of this contract, the Contractor shall prepare and submit the following reports in the manner stated below and in accordance with this Article F of this contract, and in SECTION J-List of Attachments, attached hereto and made a part of the contract.

 

  i. Monthly Progress Report

This report shall include a description of the activities during the reporting period, and the activities planned for the ensuing reporting period. The first reporting period consists of the first full month of performance plus any fractional part of the initial month. Thereafter, the reporting period shall consist of each calendar month.

The Contractor shall submit a Monthly Progress Report according to the dates set forth in the summary table under this article. The format should include:

A cover page that includes the contract number and title; the type of report and period that it covers; the Contractor’s name, address, telephone number, fax number, and e-mail address; and the date of submission; The progress report shall conform to the requirements set forth in the DELIVERIES Article in SECTION F of this contract.

   

SECTION I – EXECUTIVE SUMMARY

   

SECTION II - PROGRESS

   

SECTION II Part A: OVERALL PROGRESS - A description of overall progress.

   

SECTION II Part B: MANAGEMENT AND ADMINISTRATIVE UPDATE - A description of all meetings, conference calls, etc. that have taken place during the reporting period. Include progress on administration and management issues (e.g., evaluating, and managing subcontractor performance, and personnel changes).

   

SECTION II Part C: TECHNICAL PROGRESS - For each activity related to Gantt chart, document the results of work completed and cost incurred during the period covered in relation to proposed progress, effort and budget. The report shall be in sufficient detail to explain comprehensively the results achieved. The description shall include pertinent data and/or graphs in sufficient detail to explain any significant results achieved and preliminary conclusions resulting from analysis and scientific evaluation of data accumulated to date under the contract. The report shall include a description of problems encountered and proposed corrective action; differences between planned and actual progress, why the differences have occurred and what corrective actions are planned; preliminary conclusions resulting from analysis and scientific evaluation of data accumulated to date under the project.

   

SECTION II Part D: PROPOSED WORK - A summary of work proposed related to Gantt chart for the next reporting period and preprints/reprints of papers and abstracts.

   

SECTION III: Estimated and Actual Expenses.

 

22


 

a. This report shall also contain a narrative or table detailing whether there is a significant discrepancy (>[*]%) at this time between the % of work completed and the cumulative costs incurred to date. Monthly and actual expenses should be broken down to the appropriate WBS level. This section of the report should also contain estimates for the Subcontractors’ expenses from the previous month if the Subcontractor did not submit a bill in the previous month. If the subcontractor(s) was not working or did not incur any costs in the previous month, then a statement to this effect should be included in this report for those respective subcontractors.

   

SECTION III: Earned Value Management Reporting: Contractor will provide a monthly Contract Performance Report (CPR) at an agreed upon reporting level (WBS level 3) using the BARDA provided WBS and a Variance Analysis Report. EVMS shall be applied to all Cost Plus Fixed Fee CLINs as part of the Integrated Master Project Plan following the Seven Principles of Earned Value Management. In accordance with FAR 52.215-2, Audit and Records-Negotiation, BARDA may request, on a quarterly or ad hoc basis that the Contractor provide raw data. BARDA may request additional data at a reporting level or at lower levels, as BARDA deems necessary.

A Monthly Progress Report will not be required in the same month that the Annual Progress Report is submitted.

 

  ii. Annual Progress Report

This report shall include a summation of the results of the entire contract work for the period covered. Monthly Progress Reports shall not be submitted in the same month when an Annual Progress Report is due. Furthermore, an Annual Progress Report will not be required for the period when the Final Report is due.

The first Annual Progress Report shall be submitted in accordance with the date set forth in the table under ARTICLE F.2. of this contract.

Each Annual Progress Report shall include:

A Cover page that includes the contract number and title; the type of report and period that it covers; the Contractor’s name, address, telephone number, fax number, and email address; and the date of submission; The progress report shall conform to the requirements set forth in the DELIVERIES Article in SECTION F of this contract.

 

   

SECTION I: EXECUTIVE SUMMARY - A brief overview of the work completed, and the major accomplishments achieved during the reporting period.

   

SECTION II: PROGRESS

   

SECTION II Part A: OVERALL PROGRESS - A description of overall progress.

   

SECTION II Part B: MANAGEMENT AND ADMINISTRATIVE UPDATE - A high level summary of critical meetings, etc. that have taken place during the reporting period. Include progress on administration and management to critical factors of the project (e.g. regulatory compliance audits and key personnel changes).

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

23


   

SECTION II Part C: TECHNICAL PROGRESS - A detailed description of the work performed structured to follow the activities and decision gates outlined at the Integrated Baseline Review and as described in the Integrated Master Plan. The Report should include a description of any problems (technical or financial) that occurred or were identified during the reporting period, and how these problems were resolved.

   

SECTION II Part D: PROPOSED WORK - A summary of work proposed for the next year period to include an updated Gantt Chart.

   

SECTION III: Estimated and Actual Expenses.

a. This report shall also contain a narrative or table detailing whether there were discrepancies between estimated and actual expenses over the past year. Actual expenses should be broken down to the appropriate WBS level. This section of the report should also contain estimates for outstanding costs for the previous year which may have been incurred, but not yet billed.

   

SECTION IV: EARNED VALUE MANAGEMENT REPORTING - Contractor will provide a quarterly Contract Performance Report (CPR) at an agreed upon (WBS level 3) reporting level using the BARDA provided WBS and a Variance Analysis Report. EVMS shall be applied to all Cost Plus Fixed Fee CLINs as part of the Integrated Master Project Plan following the Seven Principles of Earned Value Management. In accordance with FAR 52.215-2, Audit and Records-Negotiation, BARDA may request, on a quarterly or ad hoc basis that the Contractor provide raw data. BARDA may request additional data at a reporting level or at lower levels, as BARDA deems necessary.

Contractor also should include the following in the Annual Progress Report:

 

  1. Copies of manuscripts (published and unpublished), abstracts, and any protocols or methods developed specifically under the contract during the reporting period; and

 

  2. A summary of any Subject Inventions per the requirements under FAR Clause 52.227-11.

 

  iii. Draft Final Report and Final Report

These reports are to include a summation of the work performed and results obtained for the entire contract period of performance. This report shall be in sufficient detail to describe comprehensively the results achieved. The Draft Final Report and Final Report shall be submitted in accordance with the DELIVERIES Article in SECTION F of the contract. An Annual Progress Report will not be required for the period when the Final Report is due. The Draft Final Report and the Final Report shall be submitted in accordance with the dates set forth in ARTICLE F.2. of this contract. The report shall conform to the following format:

 

  1. Cover page to include the contract number, contract title, performance period covered, Contractor’s name and address, telephone number, fax number, email address and submission date.

 

  3. SECTION I: EXECUTIVE SUMMARY - Summarize the purpose and scope of the contract effort including a summary of the major accomplishments relative to the specific activities set forth in the Statement of Work.

 

  4. SECTION II: RESULTS - A detailed description of the work performed related to WBS and Gantt chart, the results obtained, and the impact of the results on the scientific and/or public health community including a listing of all manuscripts (published and in preparation) and abstracts presented during the entire period of performance and a summary of all inventions.

 

24


Draft Final Report: The Contractor is required to submit the Draft Final Report to the Contracting Officer’s Representative and Contracting Officer. The Contracting Officer’s Representative and Contracting Officer will review the Draft Final Report and provide the Contractor with comments in accordance with the dates set forth in ARTICLE F.2. of this contract.

Final Report: The Contractor will deliver the final version of the Final Report on or before the completion date of the contract. The final version shall include or address the Contracting Officer’s Representative comments and Contracting Officer comments on the draft report. Final Report shall be submitted on or before the completion date of the contract.

 

  iv. Summary of Salient Results

The Contractor shall submit, with the Final Report, a summary (not to exceed 200 words) of salient results achieved during the performance of the contract.

 

  v. Audit Reports

Within thirty (30) calendar days of an audit related to conformance to FDA regulations and guidance, including adherence to GLP, GMP, GCP guidelines, the Contractor shall provide copies of the audit report (so long as received from the FDA) and a plan for addressing areas of nonconformance to FDA regulations and guidelines for GLP, GMP, or GCP guidelines as identified in the final audit report.

 

  vi. Other Technical Reports

 

  1. Draft Report for Clinical and Non-Clinical Studies and Final Report for Clinical and Non-Clinical Studies

 

   

The non-clinical and clinical trial reports shall follow the format of International Conference on Harmonization document ICH E3 “Guidelines on Structure and Content of Clinical Study Reports” (http://www.pharmacontract.ch/support/su_ich_liste.htm)

   

Draft Final Report for Clinical and Non-Clinical Studies funded by this contract will be submitted to the Contracting Officer’s Representative and Contracting Officer (CO) for review and comment within the time frames set forth under this section of this contract (ARTICLE F.2.).

   

Subcontractor prepared reports received by the Prime Contractor shall be submitted to the Contracting Officer’s Representative and Contracting Officer (CO) for review and comment as set forth by the table in this Article.

   

The Government shall provide written comments to the Draft Final Report for Clinical and Non-Clinical Studies in accordance with the dates set forth by the table in this Article.

   

The comprehensive Final Report for Clinical and Non-Clinical Studies will be submitted to the Contracting Officer and the Contracting Officer’s Representative set forth by the table in this Article. The final version shall include or address the Contracting Officer’s Representative comments and Contracting Officer comments on the draft report.

 

25


  2. Supplemental Technical Documents

Upon request, Contractor shall provide CO and COR with the following contract funded documents as specified below but not limited to: Process Development Reports; Assay Qualification Plan/Report, Assay Validation Plan/Report, Assay Technology Transfer Report, Batch Records, Contractor/Subcontractor Standard Operating Procedures (SOP’s), Master Production Records, Certificate of Analysis, Clinical Studies Data or Reports. The CO and COR reserve the right to request within the Period of Performance a non-proprietary technical document for distribution within the USG. Contractor shall provide technical document within 10 business days of CO or COR request. Contractor can request additional time on an as needed basis. If edits are recommended, the Contractor must address, in writing, concerns raised by BARDA

 

  B. Deliverables Arising from FDA Correspondence

 

  i. FDA Meetings

The Contractor shall forward the dates and times of any meeting with the FDA to BARDA and make arrangements for appropriate BARDA staff to attend the FDA meetings. BARDA staff shall include up to a maximum of four people (COR, CO and up to 2 subject matter experts).

 

   

Contractor shall notify BARDA of upcoming FDA meeting within 24 hours of scheduling Type A, B or C meetings OR within 24 hours of meeting occurrence for ad hoc meetings.

   

The Contractor shall forward initial Contractor and FDA-issued draft minutes and final minutes of any meeting with the FDA to BARDA within 3 business days of receipt. All documents shall be duly marked as either “Draft” or “Final”.

 

  ii. FDA Submissions

The Contractor shall provide BARDA all documents submitted to the FDA. Contractor shall provide BARDA with an electronic copy of the final FDA submission. All documents shall be duly marked as either “Draft” or “Final”.

 

   

If draft documents are submitted for BARDA review, BARDA will provide feedback to Contractor within 10 business days of receipt.

   

If BARDA reviews draft documents, the Contractor shall consider revising their documents to address BARDA’s concerns and/or recommendations prior to FDA submission.

   

Final FDA submissions shall be submitted to BARDA concurrently or no later than 24 hours of their submission to FDA.

 

  iii. FDA Audits

In the event of an FDA inspection which occurs as a result of this contract and for the product, or for any other FDA inspection that has the reasonable potential to impact the performance of this contract, the Contractor shall provide the USG with an exact copy (non-redacted) of the FDA Form 483 and the Establishment Inspection Report (EIR). The

 

26


Contractor shall provide the COR and CO with copies of the plan for addressing areas of non-conformance to FDA regulations for GLP, GMP, or GCP guidelines as identified in the audit report, status updates during the plans execution and a copy of all final responses to the FDA. The Contractor shall also provide redacted copies of any FDA audits received from subcontractors that occur as a result of this contract or for this product. The Contractor shall make arrangements for BARDA representative(s) to be present during the final debrief by the regulatory inspector.

 

   

Contractor shall notify CO and COR within 10 business days of a scheduled FDA audit or within 24 hours of an ad hoc site visit/audit if the FDA does not provide advanced notice.

   

Contractor shall provide copies of any FDA audit report received from subcontractors that occur as a result of this contract or for this product within 3 business days of receiving correspondence from the FDA, Subcontractor, or third party.

   

Within 10 business days of audit report, Contractor shall provide CO with a plan for addressing areas of nonconformance, if any are identified.

  iv. Manufacturing Campaign Reports

Contractor shall provide Manufacturing Campaign Reports to BARDA for review and comment prior to submission to FDA.

The COR and CO reserve the right to request within the Period of Performance (PoP) a non-proprietary Manufacturing Campaign Report for distribution within the USG.

 

   

Contractor will submit Manufacturing Campaign Reports at least 15 business days prior to FDA submission.

   

If corrective action is recommended, Contractor must address, in writing, all concerns raised by BARDA.

   

Contractor shall consider revising reports to address BARDA’s concerns and/or recommendations prior to FDA submission.

   

Final FDA submission shall be submitted to BARDA concurrently or no later than 1 business day after submission to the FDA.

 

  v. Other FDA Correspondence

The Contractor shall memorialize any correspondence between Contractor and FDA and submit to BARDA. All documents shall be duly marked as either “Draft” or “Final.” Contractor shall provide written summary of any FDA correspondence within 3 business days of correspondence.

 

C. Earned Value Management (EVM) Deliverables

 

  i. Earned Value Management (EVM) / Contract Performance Report (CPR)

Contractor will provide a monthly CPR at an agreed upon reporting level using WBS and Variance Analysis report formats agreed upon by BARDA.

The supplemental monthly Control Account Plan (CAP) report shall contain, at the work package level, time phased budget (budgeted cost of work scheduled), earned value (budgeted cost of work performed), and actual costs of work performed as captured in Contractor’s EVM systems. The Contractor shall provide a rationale in the package of its use of % complete as EVMS methodology, or identity if any other EVMS methodology is being used.

 

27


   

Contractor shall provide EVM/CPR as part of the Monthly Progress Report (this requirement begins only as set forth in the Contract Milestones & Related Deliverables table, see Attachment #10)

   

Contractor shall provide top level or key changes in baseline cost as a result of anticipated cost savings or risks

   

BARDA may request, on a monthly or ad hoc basis that the Contractor provide raw data at a reporting level or lower level as BARDA deems necessary.

   

Contractor must address, in writing, all concerns raised by BARDA.

   

Reporting will commence after the EVM system has been implemented but no later than 12 months after start of base period.

 

  ii. Integrated Master Plan (IMP)

The Contractor shall provide an IMP including WBS, critical path milestones, and Earned Value Management Plan

 

   

Contractor shall provide the draft IMP within [*] days of contract award with final due [*] months after award and updated monthly as part of the Monthly Progress Report

   

Contractor must address, in writing, all concerns raised by BARDA

 

  iii. Performance Measurement Baseline Review (PMBR)

PMBR Report shall address each of the items listed below and be cross-referenced to the IMP, WBS, SOW, and Risk Management Plan.

 

   

Contractor provides baseline proposal

   

Responsibility Assignment Matrix

   

A description of the work scope through control account Work Authorization Documents and/or WBS Dictionary down to the agreed upon control account level.

   

Template for work packages

   

Integrated Master Schedule (IMS) with the inclusion of agreed major milestones and control account plans for all control accounts

   

Baseline revision documentation and program log(s) risk management plan

   

PMBR is due within 90 days of contract award

   

Contractor shall provide baseline proposal .ppt briefing 10 business days prior to meeting

   

Contractor provides agenda to COR 2 business days in advance of meeting

   

COR approves (with CO concurrence) and distributes agenda

   

COR approves (with CO concurrence) all meeting material

   

Contactor provides minutes with 2 business days of the meeting

   

COR reviews and approves (with CO concurrence) minutes

   

BARDA will review documentation and provide written comments and questions to Contractor

   

Contractor shall address BARDA’s comments and resubmit PMBR report for BARDA approval within 10 business days.

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

28


  iv. Risk Management Plan

The Contractor shall provide a Risk Management Plan that outlines the impacts of each risk in relation to the cost, schedule, and performance objectives. The plan shall include risk mitigation strategies. Each risk mitigation strategy will capture how the corrective action will reduce impacts on cost, schedule and performance.

 

  ¡  

Due within 90 days of contract award

  ¡  

Contractor provides updated Risk Management Plan in Monthly Progress Report

  ¡  

BARDA shall provide Contractor with a written list of concerns in response plan submitted

  ¡  

Contractor must address, in writing, all concerns raised by BARDA within 20 business days of Contractor’s receipt of BARDA’s concerns.

 

  v. Requirement for Notification of Deviation and Mitigation Strategy

Process for changing IMS activities associated with cost and schedule as baselined at the PMBR. Contractor shall notify BARDA of significant changes to the IMS defined as increases in cost above [*]% for Go/No Go Milestones or schedule slippage of more than 30 days, which would require an extension to the period of performance. Contractor shall provide a high level management strategy for risk mitigation. Notice due within one (1) business day after discovery.

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

29


3.  Contract WBS Milestones & Related Deliverables

 

No.      Milestone Definition    Go Criteria    No-Go Criteria    Deliverable   

WBS/

SOW#

   CLIN #
1.    [*]    [*]    [*]    [*]   

1.5.1.1

 

1.5.1.2

  

Base

CLIN

0001

2.    [*]    [*]    [*]    [*]    1.5.1.3   

Base

CLIN

0001

3.    [*]    [*]    [*]    [*]   

1.3.2.3

 

1.3.2.4

  

Base

CLIN

0001

4.    [*]    [*]    [*]    [*]    1.4.1.2   

Base

CLIN

0001

5.    [*]    [*]    [*]    [*]    1.4.1.3   

Base

CLIN

0001

6.    [*]    [*]    [*]    [*]    2.4.1.1   

Option 1

CLIN

0002

7.    [*]    [*]    [*]    [*]    2.5.2.2   

Option 1

CLIN

0002

8.    [*]    [*]    [*]    [*]   

3.3.3.1

 

3.3.3.2

  

Option 2

CLIN

0003

9.    [*]    [*]    [*]    [*]    3.3.3.3   

Option 2

CLIN

0003

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

30


No.      Milestone Definition    Go Criteria    No-Go Criteria    Deliverable   

WBS/

SOW#

   CLIN #
10.    [*]    [*]    [*]    [*]    3.5.2.2   

Option 2

CLIN

0003

11.    [*]    [*]    [*]    [*]   

4.4.2.1

 

5.5.2.1

 

5.5.2.2

  

Option 3

CLIN

0004

12.    [*]    [*]    [*]    [*]    5.5.2.1   

Option 4

CLIN

0005

13.    [*]    [*]    [*]    [*]    5.5.2.2   

Option 4

CLIN

0005

* If at any time during the contract performance period any of the above No-Go criteria are satisfied, the Government may conduct an In-Process-Review (IPR) to evaluate whether to continue activities covered by the contract. This IPR will may occur within [*] calendar days of the No-Go criteria being satisfied.

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

31


SECTION G - CONTRACT ADMINISTRATION DATA

ARTICLE G.1. CONTRACTING OFFICER

The following Contracting Officer (CO) will represent the Government for the purpose of this contract:

Susan Cortés-Shrank, Contracting Officer

DHHS/OS/ASPR/AMCG

330 Independence Avenue, S.W.

Room G640

Washington, D.C. 20201

E-mail:[*]

 

1) The Contracting Officer is the only individual who can legally commit the Government to the expenditure of public funds. No person other than the Contracting Officer can make any changes to the terms, conditions, general provisions, or other stipulations of this contract.
2) The Contracting Officer is the only person with the authority to act as agent of the Government under this contract. Only the Contracting Officer has authority to (1) direct or negotiate any changes in the statement of work; (2) modify or extend the period of performance; (3) change the delivery schedule; (4) authorize reimburse to the Contractor of any costs incurred during the performance of this contract; (5) otherwise change any terms and conditions of this contract.
3) No information other than that which may be contained in an authorized modification to this contract, duly issued by the Contracting Officer, which may be received from any person employed by the US Government, other otherwise, shall be considered grounds for deviation from any stipulation of this contract.
4) The Government may unilaterally change its COR designation.

The following Contract Specialist (CS) assigned to this contract is:

Susan Cortés-Shrank, Contracting Officer

DHHS/OS/ASPR/AMCG

330 Independence Avenue, S.W.

Room G640

Washington, D.C. 20201

E-mail: [*]

ARTICLE G.2. CONTRACTING OFFICER’S REPRESENTATIVE (COR)

The following Contracting Officer’s Representative (COR) will represent the Government for the purpose of this contract:

[*]

Contracting Officer’s Representative (COR)

Biomedical Advanced Research and Development Authority (BARDA)

Office of the Assistant Secretary for Preparedness and Response (ASPR)

Department of Health and Human Services

Mailing Address:

330 Independence Avenue, SW Room G640

Washington, D.C. 20201

[*] (Office)

Email: [*]

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

32


Alternate COR:

[*]

Branch Chief – Broad Spectrum Antimicrobials

Division of CBRN Countermeasures

Biomedical Advanced Research & Development Authority (BARDA)

Office of Secretary for Preparedness & Response (ASPR)

Department of Health and Human Services

Mailing Address:

330 Independence Avenue, SW Room G640

Washington, D.C. 20201

Office: [*]

Email: [*]

The COR is responsible for:

1) Monitoring the Contractor’s technical progress, including the surveillance and assessment of performance and recommending to the Contracting Officer changes in requirements;

 

2) Assisting the Contracting Officer in interpreting the statement of work and any other technical performance requirements;

 

3) Performing technical evaluation as required;

 

4) Performing technical inspections and acceptances required by this contract; and

 

5) Assisting in the resolution of technical problems encountered during performance. The Government may unilaterally change its COR designation.

ARTICLE G.3. KEY PERSONNEL

Pursuant to the Key Personnel clause incorporated in Section I of this contract, the following individuals are considered to be essential to the work being performed hereunder:

 

#       NAME    ORGANIZATION      TITLE
1       Prabha Fernandes, PhD    CEMPRA, Inc.   

President and CEO/

Principal Investigator

2       Gary Horwith, MD    CEMPRA, Inc.    EVP of Regulatory Affairs
3       David Oldach, MD, SVP    CEMPRA, Inc.    SVP of Clinical Research
4       David Pereira, SVP    CEMPRA, Inc.    SVP of Chemistry
5       Lily Nguyen, MBA    CEMPRA, Inc.    Director of Project Management
6       Shane Barton, CPA    CEMPRA, Inc.    Corporate Controller

The key personnel specified in this contract are considered to be essential to work performance. At least thirty (30) business days prior to diverting any of the specified individuals to other programs or contracts, including, where practicable, an instance when an individual must be replaced as a result of leaving the employ of the Contractor, the Contractor shall notify the Contracting Officer and shall submit comprehensive justification for the diversion or replacement request (including proposed substitutions for key personnel) to permit evaluation by the Government of the impact on performance under this contract. The Contractor shall not divert or otherwise replace any key personnel without the written consent of the Contracting Officer.

ARTICLE G.4. CONTRACT FINANCIAL REPORT

a. Financial reports on the attached Financial Report of Individual Project/Contract (see Attachments 2 and 3) shall be submitted by the Contractor in accordance with the instructions for completing this form, which accompany the form, in an electronic copy, not later than the

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

33


30th business day after the close of the reporting period. The line entries for subdivisions of work and elements of cost (expenditure categories) which shall be reported within the total contract are discussed in paragraph e., below. Subsequent changes and/or additions in the line entries shall be made in writing.

b. Unless otherwise stated in that part of the instructions for completing this form, entitled “PREPARATION INSTRUCTIONS,” (see Attachment 4) all columns A through J, shall be completed for each report submitted.

c. The first financial report shall cover the period consisting of the first full three calendar months following the date of the contract, in addition to any fractional part of the initial month. Thereafter, reports will be on a quarterly basis.

d. The Contracting Officer may require the Contractor to submit detailed support for costs contained in one or more interim financial reports. This clause does not supersede the record retention requirements in FAR Part 4.7.

e. The listing of expenditure categories to be reported is incorporated within the Attachment entitled, “Financial Report of Individual Project/Contract,” located in SECTION J and made a part of this contract.

f. The Government may unilaterally revise the “Financial Report of Individual Project/Contract” to reflect the allotment of additional funds.

ARTICLE G.5. INVOICE/FINANCING REQUEST AND CONTRACT FINANCIAL REPORTING

 

1) The billing address that should be shown on the invoice shall be the same as defined in ARTICLE G.2. of this contract as follows:

DHHS/OS/ASPR/AMCG

Attn: Susan Cortés-Shrank, Contracting Officer

330 Independence Ave., S.W.

Room G640

Washington, D.C. 20201

 

2) The Contractor shall submit an electronic copy of contract monthly invoices/financial reports to the Contracting Officer and Contract Specialist as defined above, in ARTICLE G of this contract.

 

3) Contractor invoices/financial reports shall conform to the form, format, and content requirements of the instructions for Invoice/Financing requests and Contract Financial Reporting made a part of the contract in Section J (See also ARTICLE B.5. and Attachment 2).

 

4) Monthly invoices must include the cumulative total expenses to date, adjusted (as applicable) to show any amounts suspended by the Government.

 

5) The Contractor agrees to immediately notify the Contracting Officer in writing if there is an anticipated overrun (any amount) or unexpended balance (greater than 10 percent) of the estimated costs for the base segment or any option segment(s) (See estimated costs under Articles B.2. and B.3., of the contract) and the reasons for the variance. Also refer to the requirements of the Limitation of Cost FAR 52.232-20 clause in the contract.

 

6) All invoice submissions shall be in accordance with FAR Clause 52.232-25 (c) in Section I of this contract.

 

34


ARTICLE G.6. REIMBURSEMENT OF COST

 

1) The Government shall reimburse the Contractor the cost determined by the Contracting Officer to be allowable (hereinafter referred to as allowable cost) in accordance with the clause entitled Allowable Cost and Payment in Section I, Contract Clauses, and FAR Subpart 31.7. Examples of allowable costs include, but are not limited to, the following:

 

  a)

All direct materials and supplies that are used in the performing of the work provided for under the contract, including those purchased for subcontracts and purchase orders.

 

  b)

All direct labor, including supervisory, that is properly chargeable directly to the contract, plus fringe benefits.

 

  c)

All other items of cost budgeted for and accepted in the negotiation of this basic contract or modifications thereto.

 

  d)

Travel costs including per diem or actual subsistence for personnel while in an actual travel status in direct performance of the work and services required under this contract subject to the following:

 

  (i)

Air travel shall be by the most direct route using “air coach” or “air tourist” (less than first class) unless it is clearly unreasonable or impractical (e.g., not available for reasons other than avoidable delay in making reservations, would require circuitous routing or entail additional expense offsetting the savings on fare, or would not make necessary connections).

 

  (ii)

Rail travel shall be by the most direct route, first class with lower berth or nearest equivalent.

 

  (iii)

Costs incurred for lodging, meals, and incidental expenses shall be considered reasonable and allowable to the extent that they comply with FAR 31.7.

 

  (iv)

Travel via privately owned automobile shall be reimbursed at not more than the current General Services Administration (GSA) FTR established mileage rate.

ARTICLE G.7.  INDIRECT COST RATES

The following rates will be utilized for billing purposes during both the base and option periods as provisional rates:

Fringe benefits at [*]% and an indirect rate estimated at [*]%.

ARTICLE G.8.  POST AWARD EVALUATION OF CONTRACTOR PERFORMANCE

1. Contractor Performance Evaluations

Interim and final evaluations of Contractor performance will be prepared on this contract in accordance with FAR Subpart 42.15. The final performance evaluation will be prepared at the time of completion of work. In addition to the final evaluation, an interim evaluation shall be submitted annually.

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

35


Interim and final evaluations will be provided to the Contractor as soon as practicable after completion of the evaluation. The Contractor will be permitted thirty days to review the document and to submit additional information or a rebutting statement. If agreement cannot be reached between the parties, the matter will be referred to an individual one level above the Contracting Officer whose decision will be final.

Copies of the evaluations, Contractor responses, and review comments, if any, will be retained as part of the contract file, and may be used to support future award decisions.

2. Electronic Access to Contractor Performance Evaluations

Contractors that have Internet capability may access evaluations through a secure Web site for review and comment by completing the registration form that can be obtained at the following address:

http://www.cpars.csd.disa.mil/cparsmain.htm

The registration process requires the Contractor to identify an individual that will serve as a primary contact and who will be authorized access to the evaluation for review and comment. In addition, the Contractor will be required to identify an alternate contact that will be responsible for notifying the cognizant contracting official in the event the primary contact is unavailable to process the evaluation within the required 30-day time frame.

ARTICLE G.9. CONTRACT COMMUNICATIONS/CORRESPONDENCE (JULY 1999)

The Contractor shall identify all correspondence, reports, and other data pertinent to this contract by imprinting the contract number from Page 1 of the contract.

ARTICLE G.10. GOVERNMENT PROPERTY

1. In addition to the requirements of the clause, GOVERNMENT PROPERTY, incorporated in SECTION I of this contract, the Contractor shall comply with the provisions of HHS Publication, “Contractor’s Guide for Control of Government Property,” which is incorporated into this contract by reference. This document can be accessed at:

http://www.hhs.gov/hhsmanuals/          (HHS Logistics Management Manual)

Among other issues, this publication provides a summary of the Contractor’s responsibilities regarding purchasing authorizations and inventory and reporting requirements under the contract.

2. Notwithstanding the provisions outlined in the HHS Publication, “Contractor’s Guide for Control of Government Property,” which is incorporated in this contract in paragraph 1. above, the Contractor shall use the form entitled, “Report of Government Owned, Contractor Held Property” for submitting summary reports required under this contract, as directed by the Contracting Officer or his/her designee. This form is included as an attachment in SECTION J of this contract.

3. Title will vest in the Government for equipment purchased as a direct cost.

ARTICLE G.11. EXERCISE OF OPTIONS

Unless the Government exercises its option pursuant to the Option Clause set forth in Section I, Article I.2, the contract will consist only of CLIN 0001 of the Statement of Work, Deliverables and Requirements as defined in Sections C, F and J of the contract. Pursuant

 

36


to FAR Clause 52.217-9 (Option to Extend the Term of the Contract) set forth in Section I of this contract, under Article I.2, the Government may, by unilateral contract modification, require the Contractor to perform the additional CLINs listed in Section B, Article B.3., and as also defined in Sections C, F of this contract. If the Government exercises an option, written notice must be given to the Contractor within [*] days after the Government has completed its analysis of the deliverables associated with the applicable GO/NO-GO Decision gates; and the Government must give the Contractor a preliminary written notice of its intent to exercise the option at least [*] days before the contract expires. The amount of the contract may then be increased as set forth in Section B, Article B.3 provided that funds are available.

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

37


SECTION H - SPECIAL CONTRACT REQUIREMENTS

If provisions set forth in this Section are not applicable to the work performed directly by the Contractor, those provisions might still apply to subcontractors performing work under this contract. It is the Contractor’s responsibility to monitor their subcontractors to confirm that these provisions are satisfied. Accordingly, those provisions shall be flowed-down as applicable.

ARTICLE H.1 CLINICAL AND NON-CLINICAL TERMS OF AWARD

BARDA has a responsibility to obtain documentation concerning mechanisms and procedures that are in place to protect the safety of participants and animals in BARDA funded clinical trials and non-clinical studies. Therefore, the Contractor shall develop a protocol for each clinical trial and non-clinical study funded under this contract and submit all such protocols and protocol amendments to the BARDA Contracting Officer’s Representative (COR) for evaluation and comment. Approval is required before work under a protocol may begin. BARDA COR comments will be forwarded to the Contractor within ten (10) business days. The Contractor must address, in writing, all concerns (e.g. study design, safety, regulatory, ethical, and conflict of interest) noted by the BARDA COR.

If the draft protocols are to be submitted to the FDA, BARDA review shall occur before submission, pursuant to the terms set forth by ARTICLE F.2 of this contract. The Contractor shall consider revising their protocols to address BARDA’s concerns and recommendations prior to FDA submission. The Contractor must provide BARDA with a copy of FDA submissions, within the time frame set forth by ARTICLE F.2 of this contract.

Execution of clinical and non-clinical studies requires written authorization from BARDA. The Government will provide written authorization to the Contractor upon either 1) receiving documentation in which all COR comments have been satisfactorily addressed; or 2) receiving documentation that the FDA has reviewed and commented on the protocol.

BARDA shall have rights to all protocols, data resulting from execution of these protocols, and final reports funded by BARDA under this contract, as set forth in PART II of this contract and defined in the FAR. BARDA reserves the right to request that the Awardee provide any contract deliverable in a non-proprietary form to ensure BARDA has the ability to review and distribute the deliverables as BARDA deems necessary.

Important information regarding performing human subject research is available at http://www3.niaid.nih.gov/healthscience/clinicalstudies/.

Any updates to technical reports are to be addressed in the Monthly and Annual Progress Reports. The Contractor shall advise the Contracting Officer’s Representative or designee in writing and via electronic communication in a timely manner of any issues potentially affecting contract performance.

 

  1. Non-Clinical Terms of Award

These Non-Clinical Terms of Award detail an agreement between the Biomedical Advanced Research and Development Authority (BARDA) and the Contractor; they apply to all grants and contracts that involve non-clinical research.

 

38


  a. Safety and Monitoring Issues

 

  i. PHS Policy on Humane Care and use of Laboratory Animals

Before award and then with the annual progress report, the Contractor must submit to BARDA a copy of the current Institutional Animal Care and Use Committees (IACUC) documentation of continuing review and approval and the Office of Laboratory Animal Welfare (OLAW) federal wide assurance number for the institution or site.

If other institutions are involved in the research (e.g., a multicenter trial or study), each institution’s IACUC must review and approve the protocol. They must also provide BARDA initial and annual documentation of continuing review and approval and federal wide assurance number.

The Contractor must ensure that the application, as well as all protocols, are reviewed by the performing institution’s IACUC.

To help ensure the safety of animals used in BARDA-funded studies, the Contractor must provide BARDA copies of documents related to all major changes in the status of ongoing protocols, including the following:

 

   

All amendments or changes to the protocol, identified by protocol version number, date, or both and date it is valid.

 

   

All material changes in IACUC policies and procedures, identified by version number, date, and all required signatories (if applicable).

 

   

Termination or temporary suspension of the study(ies) for regulatory issues.

 

   

Termination or temporary suspension of the protocol.

 

   

Any change that is made in the specific IACUC approval for the indicated study(ies).

 

   

Any other problems or issues that could affect the scientific integrity of the study(ies), i.e., fraud, misrepresentation, misappropriation of funds, etc.

Contractor must notify BARDA of any of the above changes within five (5) working days from the time the Contractor becomes aware of such changes by email or fax, followed by a letter signed by the institutional business official, detailing notification of the change of status to the local IACUC and a copy of any responses from the IACUC.

If a non-clinical protocol has been reviewed by an institutional biosafety committee (IBC) or the NIH Recombinant DNA Advisory Committee (RAC), the Contractor must provide information about the initial and ongoing review and approval, if any. See the NIH Guidelines for Research Involving Recombinant DNA Molecules.

 

39


  ii. Non-Clinical Data and Safety Monitoring Requirements

BARDA strongly recommends continued safety monitoring for all non-clinical studies of investigational drugs, devices, or biologics. FDA expects non-clinical studies to include safety in addition to efficacy. Awardee should consider evaluation of clinical relevant safety markers in the pivotal and non-pivotal, non-clinical studies. In preparation for clinical trials of licensed or not yet licensed products, it is imperative that BARDA-sponsored studies of any type measure the risk and safety parameters that are elicited and provide a safety profile from the studies for future human risk assessment.

A risk is minimal where the probability and magnitude of harm or discomfort anticipated in the proposed research are not greater than those ordinarily encountered in daily life or during the performance of routine physical or psychological examinations or tests. For example, the risk of drawing a small amount of blood from a healthy subject for research purposes is no greater than the risk of doing so as part of a routine physical examination (45 CFR 46.102(i)).

BARDA will work with the Contractor on decisions regarding the type and extent of safety data accrual to be employed before the start of efficacy or safety studies.

The Contractor shall inform BARDA of any upcoming site visits and/or audits of CRO facilities funded under this effort. BARDA reserves the right to accompany the Contractor on site visits and/or audits of CRO’s as BARDA deems necessary.

 

  b. BARDA Review Process before Non-Clinical study Execution Begins

BARDA is under the same policy-driven assurances as NIH in that it has a responsibility to ensure that mechanisms and procedures are in place to protect the safety and welfare of animals used in BARDA-funded non-clinical trials. Therefore, before study execution, the Contractor must provide the following (as applicable) for review and comment by BARDA:

 

   

IACUC approved (signed) non-clinical research protocol identified by version number, date, or both, including details of study design, euthanasia criteria, proposed interventions, and exclusion criteria.

 

   

For non-pivotal mouse studies, the Contractor will provide an annual animal care and use protocol.

 

   

Documentation of IACUC approval, including OLAW federal wide number, IACUC registration number, and IACUC name.

 

   

Contractor should reduce the number of animals required for a study using power of statistics.

 

   

Plans for the management of side effects, rules for interventions and euthanasia criteria.

 

   

Procedures for assessing and collecting safety data were appropriate.

 

40


   

If a study is contracted through Contract Research Organizations (CROs), work orders and service agreements the Contractor shall assure an integrated safety documentation plan is in place for the study site, pharmacy service records on the dosing material to be used and excipients, and laboratory services (including histopathology).

 

   

Documentation that the Contractor and all required staff responsible for the conduct of the research have received training in the protection and handling of animals, or that the CRO has the required documentation.

 

   

Purchasing of animals and/or other supplies for non-clinical studies funded in part or in whole by BARDA requires written approval by the Contracting Officer in accordance with the contract. The Contractor must have the ability to return/re-sell animals, at purchase price, to distributor or a third part, in the event that the final protocols do not obtain approval and a Contracting Officer Authorization is not granted.

 

   

Provide justification for whether studies require good laboratory practice (GLP) conditions.

 

   

Provide justification for whether studies will be classified as non-pivotal or pivotal studies.

Documentation of each of the above items shall be submitted to BARDA for evaluation and comment in conjunction with the protocol. Execution of non-clinical studies requires written authorization from BARDA in accordance with this section of the contract.

 

  c. References

Public Health Service Policy on Humane Care and Use of Laboratory Animals:

http://grants.nih.gov/grants/olaw/InvestigatorsNeed2Know.pdf

USDA Animal Welfare Act:

http://awic.nal.usda.gov/nal_display/index.php?info_center=3&tax_level=3&tax_

subject=182&topic_id=1118&level3_id=6735&level4_id=0&level5_id=0&placement_default=0

 

  2. Clinical Terms of Award

These Clinical Terms of Award detail an agreement between the Biomedical Advanced Research and Development Authority (BARDA) and the Contractor; they apply to all grants and contracts that involve clinical research.

Draft protocols for each clinical study will be submitted to BARDA for evaluation and comment. BARDA comments will be addressed and/or incorporated into the draft protocol prior to submission to the FDA for comment, if required.

BARDA shall have rights to all protocols, data generated from the execution of these protocols, and final reports, funded by BARDA under this contract, as defined in Rights in Data Clause in FAR 52.227-14. BARDA reserves the right to request that the Contractor provide any contract deliverable in a non-proprietary form, to ensure BARDA has the ability to review and distribute the deliverables, as BARDA deems necessary.

 

41


  i. Safety and Monitoring Issues

a. Institutional Review Board or Independent Ethics Committee Approval

Before award and then with the annual progress report, the Contractor must submit to BARDA a copy of the current IRB-or IEC-approved informed consent document, documentation of continuing review and approval and the OHRP federal wide assurance number for the institution or site.

If other institutions are involved in the research (e.g., a multicenter clinical trial or study), each institution’s IRB or IEC must review and approve the protocol. They must also provide BARDA initial and annual documentation of continuing review and approval, including the current approved informed consent document and federal wide number.

The Contractor must ensure that the application as well as all protocols are reviewed by their IRB or IEC.

To help ensure the safety of participants enrolled in BARDA-funded studies, the Contractor must provide BARDA copies of documents related to all major changes in the status of ongoing protocols, including the following:

 

   

All amendments or changes to the protocol, identified by protocol version number, date, or both and dates it is valid.

 

   

All changes in informed consent documents, identified by version number, dates, or both and dates it is valid.

 

   

Termination or temporary suspension of patient accrual.

 

   

Termination or temporary suspension of the protocol.

 

   

Any change in IRB approval.

 

   

Any other problems or issues that could affect the participants in the studies.

The Contractor must notify BARDA through the COR or CO of any of the above changes within five (5) working days by email or fax, followed by a letter signed by the institutional business official, detailing notification of the change of status to the local IRB and a copy of any responses from the IRB or IEC.

If a clinical protocol has been reviewed by an institutional biosafety committee (IBC) or the NIH Recombinant DNA Advisory Committee (RAC), the Contractor must provide information about the initial and ongoing review and approval, if any. See the NIH Guidelines for Research Involving Recombinant DNA Molecules.

b. Data and Safety Monitoring Requirements

BARDA strongly recommends independent safety monitoring for clinical trials of investigational drugs, devices, or biologics; clinical trial of licensed products; and clinical research of any type involving more than minimal risk to volunteers. Independent monitoring can take a variety of forms. Phase III clinical trials must be reviewed by an independent data and safety monitoring board

 

42


(DSMB); other trials may require DSMB oversight as well. The Contractor shall inform BARDA of any upcoming site visits and/or audits of CRO facilities funded under this effort. BARDA reserves the right to accompany the Contractor on site visits and/or audits of CROs as BARDA deems necessary. The Contractor shall inform BARDA 30 days in advance of a DSMB board meetings for studies funded under this effort. BARDA reserves the right to participate in the DSMB board meetings on an impromptu basis as a non-voting member.

A risk is minimal where the probability and magnitude of harm or discomfort anticipated in the proposed research and not greater than those ordinarily encountered in daily life or during the performance of routine physical or psychological examinations or tests. For examples, the risk of drawing a small amount of blood form a healthy individual for research purposes is no greater than the risk of doing so as part of a routine physical examination (45 CFR 46.102I).

Final decisions regarding the type of monitoring to be used must be made jointly by BARDA and the Contractor before enrollment starts. Discussions with the responsible BARDA Project Officer regarding appropriate safety monitoring and approval of the final monitoring plan by BARDA must occur before patient enrollment begins and may include discussions about the appointment of one of the following.

 

   

Independent Safety Monitor – a physician or other appropriate expert who is independent of the study and available in real time to review and recommend appropriate action regarding adverse events and other safety issues.

 

   

Independent Monitoring Committee (IMC) or Safety Monitoring Committee (SMC) – a small group of independent investigators and biostatisticians who review data from a particular study.

 

   

Data and Safety Monitoring Board – an independent committee charged with reviewing safety and trial progress and providing advice with respect to study continuation, modification, and termination. The Contractor may be required to use an established BARDA DSMB or to organize an independent DSMB. All phase III clinical trials must be reviewed by a DSMB; other trials may require DSMB oversight as well. Please refer to: NIAID Principles for Use of a Data and Safety Monitoring Board (DSMB) For Oversight of Clinical Trials Policy

When a monitor or monitoring board is organized, a description of it, its charter or operating procedures (including a proposed meeting schedule and plan for review of adverse events), and roster and curriculum vitae from all members must be submitted to and approved by BARDA before enrollment starts. The Contractor will also ensure that the monitors and board members report any conflicts of interest and the Contractor will maintain a record of this. The Contractor will share conflict of interest reports with BARDA.

Additionally, the Contractor must submit written summaries of all reviews conducted by the monitoring group to the BARDA within thirty (30) days of reviews or meetings.

 

43


  ii. BARDA Protocol Review Process Before Patient Enrollment Begins

BARDA has a responsibility to ensure that mechanisms and procedures are in place to protect the safety of participants in BARDA-supported clinical trials. Therefore, before patient accrual or participant enrollment, the Contractor must ensure the following (as applicable) are in place at each participating institution, prior to patient accrual or enrollment:

 

   

IRB- or IEC-approved clinical research protocol identified by version number, date, or both, including details of study design, proposed interventions, patient eligibility, and exclusion criteria.

   

Documentation of IRB or IEC approval, including OHRP federal wide number, IRB or IEC registration number, and IRB and IEC name.

   

IRB- or IEC- approved informed consent document, identified by version number, date, or both and dates it is valid.

   

Plans for the management of side effects.

   

Procedures for assessing and reporting adverse events.

   

Plans for data and safety monitoring (see above) and monitoring of the clinical study site, pharmacy, and laboratory.

   

Documentation that the Contractor and all study staff responsible for the design or conduct of the research have received training in the protection of human subjects.

Documentation to demonstrate that each of the above items are in place shall be submitted to the BARDA) for evaluation and comment in conjunction with the protocol. Execution of clinical studies requires written authorization from BARDA in accordance with this section of this contract.

 

  iii. Investigational New drug or Investigational Device Exemption Requirements

Consistent with federal regulations, clinical research projects involving the use of investigational therapeutics, vaccines, or other medical interventions (including licensed products and devices for a purpose other than that for which they were licensed) in humans under a research protocol must be performed under a Food and Drug Administration (FDA) investigational new drug (IND) or investigational device exemption (IDE).

Exceptions must be granted in writing by FDA. If the proposed clinical trial will be performed under an IND or IDE, the Contractor must provide BARDA with the name and institution of the IND or IDE sponsor, the date the IND or IDE was filed with FDA, the FDA IND or IDE number, any written comments from FDA, and the written responses to those comments.

Unless FDA notifies Contractor otherwise, The Contractor must wait thirty (30) calendar days from FDA receipt of an initial IND or IDE application before initiating a clinical trial.

The Contractor must notify BARDA if the FDA places the study on clinical hold and provide BARDA any written comments from FDA, written responses to the comments, and documentation in writing that the hold has been lifted.

 

44


The Contractor must not use grant or contract funds during a clinical hold to fund the clinical studies that are on hold. The Contractor must not enter into any new financial obligations related to clinical activities for the clinical trial on clinical hold.

 

  iv. Required Time-Sensitive Notification

Under an IND or IDE, the sponsor must provide FDA safety reports of serious adverse events. Under these Clinical Terms of Award, the Contractor must submit copies to the responsible BARDA representative or the Contracting Officer’s Representative (COR) as follows:

• Expedited safety report of unexpected or life-threatening experience or death:

A copy of any report of unexpected or life-threatening experience or death associated with the use of an IND drug, which must be reported to FDA by telephone or fax as soon as possible but no later than seven (7) days after the IND sponsor’s receipt of the information, must be submitted to BARDA representative or COR within 24 hours of FDA notification.

• Expedited safety reports of serious and unexpected adverse experiences:

A copy of any report of unexpected and serious adverse experience associated with use of an IND drug or any finding from tests in laboratory animals that suggests a significant risk for human subjects, which must be reported in writing to FDA as soon as possible but no later than 15 day after the IND sponsor’s receipt of the information, must be submitted to the BARDA representative or COR within 24 hours of FDA notification.

• IDE reports of unanticipated adverse device effect:

A copy of any reports of unanticipated adverse device effect submitted to FDA must be submitted to BARDA representative or COR within 24 hours of FDA notification.

• Expedited safety reports:

Sent to BARDA representative or the COR concurrently with the report to FDA.

• Other adverse events documented during the course of the trial should be included in the annual IND or IDE report and reported to BARDA annually.

In case of problems or issues, the BARDA representative or the Contracting Officer’s Representative will contact the Contractor within ten (10) working days by email or fax, followed within thirty (30) calendar days by an official letter to the Contractor’s Project Manager, with a copy to the institutions’ office of sponsored programs, listing issues and appropriate actions to be discussed.

 

   

Safety reporting for research not performed under an IND or IDE.

Final decisions regarding ongoing safety reporting requirements for research not performed under an IND or IDE must be made jointly by the BARDA Project Officer or the Contracting Officer’s Representative and the Contractor.

 

45


ARTICLE H.2. PROTECTION OF HUMAN SUBJECTS, HHSAR 352.270-4 (January 2006)

(a) The Contractor agrees that the rights and welfare of human subjects involved in research under this contract shall be protected in accordance with 45 CFR Part 46 and with the Contractor’s current Assurance of Compliance on file with the Office for Human Research Protections (OHRP), Department of Health and Human Services. The Contractor further agrees to provide certification at least annually that the Institutional Review Board has reviewed and approved the procedures, which involve human subjects in accordance with 45 CFR Part 46 and the Assurance of Compliance.

(b) The Contractor shall bear full responsibility for the performance of all work and services involving the use of human subjects under this contract and shall ensure that work is conducted in a proper manner and as safely as is feasible. The parties hereto agree that the Contractor retains the right to control and direct the performance of all work under this contract. The Contractor shall not deem anything in this contract to constitute the Contractor or any subcontractor, agent or employee of the Contractor, or any other person, organization, institution, or group of any kind whatsoever, as the agent or employee of the Government. The Contractor agrees that it has entered into this contract and will discharge its obligations, duties, and undertakings and the work pursuant thereto, whether requiring professional judgment or otherwise, as an independent contractor without imputing liability on the part of the Government for the acts of the Contractor or its employees.

(c) If at any time during the performance of this contract, the Contracting Officer determines, in consultation with OHRP that the Contractor is not in compliance with any of the requirements and/or standards stated in paragraphs (a) and (b) above, the Contracting Officer may immediately suspend, in whole or in part, work and further payments under this contract until the Contractor corrects the noncompliance. The Contracting Officer may communicate the notice of suspension by telephone with confirmation in writing. If the Contractor fails to complete corrective action within the period of time designated in the Contracting Officer’s written notice of suspension, the Contracting Officer may, after consultation with OHRP, terminate this contract in whole or in part, and the Contractor’s name may be removed from the list of those contractors with approved Human Subject Assurances.

ARTICLE H.3. HUMAN MATERIALS (ASSURANCE OF OHRP COMPLIANCE)

The acquisition and supply of all human specimen material (including fetal material) used under this contract shall be obtained by the Contractor in full compliance with applicable Federal, State and Local laws and the provisions of the Uniform Anatomical Gift Act in the United States, and no undue inducements, monetary or otherwise, will be offered to any person to influence their donation of human material.

The Contractor shall provide written documentation that all human materials obtained as a result of research involving human subjects conducted under this contract, by collaborating sites, or by subcontractors identified under this contract, were obtained with prior approval by the Office for Human Research Protections (OHRP) of an Assurance to comply with the requirements of 45 CFR 46 to protect human research subjects. This restriction applies to all collaborating sites without OHRP-approved Assurances, whether domestic or foreign, and compliance must be ensured by the Contractor.

Provision by the Contractor to the Contracting Officer of a properly completed “Protection of Human Subjects Assurance Identification/IRB Certification/Declaration of Exemption”, Form OMB No. 0990-0263(formerly Optional Form 310), certifying IRB review and approval of the protocol from which the human materials were obtained constitutes the written documentation required. The human subject certification can be met by submission of a self designated form provided that it contains the information required by the “Protection of Human Subjects Assurance Identification/IRB Certification/Declaration of Exemption”, Form OMB No. 0990-0263(formerly Optional Form 310).

 

46


ARTICLE H.4. RESEARCH INVOLVING HUMAN FETAL TISSUE

All research involving human fetal tissue shall be conducted in accordance with the Public Health Service Act, 42 U.S.C. 289g-1 and 289g-2. Implementing regulations and guidance for conducting research on human fetal tissue may be found at 45 CFR 46, Subpart B and http://grants1.nih.gov/grants/guide/notice-files/not93-235.html and any subsequent revisions to this NIH Guide to Grants and Contracts (“Guide”) Notice.

The Contractor shall make available, for audit by the Secretary, HHS, the physician statements and informed consents required by 42 USC 289g-1(b) and (c), or ensure HHS access to those records, if maintained by an entity other than the Contractor.

ARTICLE H.5. NEEDLE EXCHANGE

The Contractor shall not use contract funds to carry out any program of distributing sterile needles or syringes for the hypodermic injection of any illegal drug.

ARTICLE H.6. CARE OF LIVE VERTEBRATE ANIMALS, HHSAR 352.270-5 (October 2009)

(a) Before undertaking performance of any contract involving animal-related activities where the species is regulated by USDA, the Contractor shall register with the Secretary of Agriculture of the United States in accordance with 7 U.S.C. 2136 and 9 CFR sections 2.25 through 2.28. The Contractor shall furnish evidence of the registration to the Contracting Officer.

(b) The Contractor shall acquire vertebrate animals used in research from a dealer licensed by the Secretary of Agriculture under 7 U.S.C. 2133 and 9 CFR Sections 2.1-2.11, or from a source that is exempt from licensing under those sections.

(c) The Contractor agrees that the care, use and intended use of any live vertebrate animals in the performance of this contract shall conform with the Public Health Service (PHS) Policy on Humane Care of Use of Laboratory Animals (PHS Policy), the current Animal Welfare Assurance (Assurance), the Guide for the Care and Use of Laboratory Animals (National Academy Press, Washington, DC) and the pertinent laws and regulations of the United States Department of Agriculture (see 7 U.S.C. 2131 et seq. and 9 CFR Subchapter A, Parts 1-4). In case of conflict between standards, the more stringent standard shall govern.

(d) If at any time during performance of this contract, the Contracting Officer determines, in consultation with the Office of Laboratory Animal Welfare (OLAW), National Institutes of Health (NIH), that the Contractor is not in compliance with any of the requirements and standards stated in paragraphs (a) through (c) above, the Contracting Officer may immediately suspend, in whole or in part, work and further payments under this contract until the Contractor corrects the noncompliance. Notice of the suspension may be communicated by telephone and confirmed in writing. If the Contractor fails to complete corrective action within the period of time designated in the Contracting Officer’s written notice of suspension, the Contracting Officer may, in consultation with OLAW, NIH, terminate this contract in whole or in part, and the Contractor’s name may be removed from the list of those contractors with approved Assurances.

Note: The Contractor may request registration of its facility and a current listing of licensed dealers from the Regional Office of the Animal and Plant Health Inspection Service (APHIS), USDA, for the region in which its research facility is located. The location of the appropriate APHIS Regional Office, as well as information concerning this program may be obtained by contacting the Animal Care Staff, USDA/APHIS, 4700 River Road, Riverdale, Maryland 20737 (E-mail: ace@aphis.usda.gov; Web site: (http://www.aphis.usda.gov/animal_welfare).

 

47


ARTICLE H.7. ANIMAL WELFARE

All research involving live, vertebrate animals shall be conducted in accordance with the Public Health Service Policy on Humane Care and Use of Laboratory Animals. This policy may be accessed at:

http://grants1.nih.gov/grants/olaw/references/phspol.htm.

ARTICLE H.8. PROTECTION OF PERSONNEL WHO WORK WITH NONHUMAN PRIMATES

All Contractor personnel who work with nonhuman primates or enter rooms or areas containing nonhuman primates shall comply with the procedures set forth in NIH Policy Manual 3044-2, entitled, “Protection of NIH Personnel Who Work with Nonhuman Primates,” located at the following URL:

http://www1.od.nih.gov/oma/manualchapters/intramural/3044-2/

ARTICLE H.9. PUBLICATION AND PUBLICITY

No information related to data obtained under this contract shall be released or publicized without the prior written consent of BARDA.

In addition to the requirements set forth in HHSAR Clause 352.227-70, Publications and Publicity incorporated by reference in SECTION I of this contract, Section 507 of P.L. 104-208 mandates that Contractors funded with Federal dollars, in whole or in part, acknowledge Federal funding when issuing statements, press releases, requests for proposals, bid solicitations and other documents. Contractors are required to state: (1) the percentage and dollar amounts of the total program or project costs financed with Federal money and; (2) the percentage and dollar amount of the total costs financed by nongovernmental sources.

For purposes of this contract “publication” is defined as an issue of printed material offered for distribution or any communication or oral presentation of information, including any manuscript or scientific meeting abstract. Any publication containing data generated under this contract must be submitted for BARDA review no less than thirty (30) calendar days for manuscripts and fifteen (15) calendar days for abstracts before submission for public presentation or publication. Contract support shall be acknowledged in all such publications substantially as follows:

“This project has been funded in whole or in part with Federal funds from the Biomedical Advanced Research and Development Authority, Office of the Assistant Secretary for Preparedness and Response, Office of the Secretary, Department of Health and Human Services, under Contract No. HHSO100201300009C”.

ARTICLE H.10. REVIEW OF PRESS RELEASES

The contractor agrees to accurately and factually represent the work conducted under the contract in all press releases. Misrepresenting contract results or releasing information that is injurious to the integrity of BARDA may be construed as improper conduct. Press releases shall be considered to include the public release of information to any medium, excluding peer-reviewed scientific publications. The contractor shall ensure that the CO/COR has received an advance copy of any press release related to the contract not less than five (5) working days prior to the issuance of the press release.

 

48


The Contractor shall acknowledge the support of the Department of Health and Human Service, Office of the Assistant Secretary for Preparedness and Response, Biomedical Advanced Research and Development Authority, whenever publicizing the work under this contract in any media by including an acknowledgment substantially as follows:

“This project has been funded in whole or in part with Federal funds from the Department of Health and Human Services; Office of the Assistant Secretary for Preparedness and Response; Biomedical Advanced Research and Development Authority, under Contract No HHSO100201300009C.

ARTICLE H.11. REPORTING MATTERS INVOLVING FRAUD, WASTE AND ABUSE

Anyone who becomes aware of the existence or apparent existence of fraud, waste and abuse in BARDA funded programs is encouraged to report such matters to the HHS Inspector General’s Office in writing or on the Inspector General’s Hotline. The toll free number is 1-800-HHS-TIPS (1-800-447-8477). All telephone calls will be handled confidentially. The e-mail address is Htips@os.dhhs.gov and the mailing address is:

Office of Inspector General

Department of Health and Human Services

TIPS HOTLINE

P.O. Box 23489

Washington, D.C. 20026

ARTICLE H.12. PROHIBITION ON CONTRACTOR INVOLVEMENT WITH TERRORIST ACTIVITIES

The Contractor acknowledges that U.S. Executive Orders and Laws, including but not limited to E.O. 13224 and P.L. 107-56, prohibit transactions with, and the provision of resources and support to, individuals and organizations associated with terrorism. It is the legal responsibility of the Contractor to ensure compliance with these Executive Orders and Laws. This clause must be included in all subcontracts issued under this contract.

ARTICLE H.13. CONFLICT OF INTEREST

The Contractor represents and warrants that, to the best of the Contractor’s knowledge and belief, there are no relevant facts or circumstances which could give rise to an organizational conflict of interest, as defined in FAR Subpart 9.5, or that the Contractor has disclosed all such relevant information. Prior to commencement of any work, the Contractor agrees to notify the Contracting Officer promptly that, to the best of its knowledge and belief, no actual or potential conflict of interest exists or to identify to the Contracting Officer any actual or potential conflict of interest the firm may have. In emergency situations, however, work may begin but notification shall be made within five (5) working days. The Contractor agrees that if an actual or potential organizational conflict of interest is identified during performance, the Contractor shall promptly make a full disclosure in writing to the Contracting Officer. This disclosure shall include a description of actions, which the Contractor has taken or proposes to take, after consultation with the Contracting Officer, to avoid, mitigate, or neutralize the actual or potential conflict of interest. The Contractor shall continue performance until notified by the Contracting Officer of any contrary action to be taken. Remedies include termination of this contract for convenience, in whole or in part, if the Contracting Officer deems such termination necessary to avoid an organizational conflict of interest. If the Contractor was aware of a potential organizational conflict of interest prior to award or discovered an actual or potential conflict after award and did not disclose it or misrepresented relevant information to the Contracting Officer, the Government may terminate the contract for default, debar the Contractor from Government contracting, or pursue such other remedies as may be permitted by law or this contract.

 

49


ARTICLE H.14. PROHIBITION ON THE USE OF APPROPRIATED FUNDS FOR LOBBYING ACTIVITIES AND HHSAR 352.203-70 ANTI-LOBBYING (Jan 2006)

The Contractor is hereby notified of the restrictions on the use of Department of Health and Human Service’s funding for lobbying of Federal, State and Local legislative bodies.

Section 1352 of Title 10, United Stated Code (Public Law 101-121, effective 12/23/89), among other things, prohibits a recipient (and their subcontractors) of a Federal contract, grant, loan, or cooperative agreement from using appropriated funds (other than profits from a federal contract) to pay any person for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with any of the following covered Federal actions; the awarding of any Federal contract; the making of any Federal grant; the making of any Federal loan; the entering into of any cooperative agreement; or the modification of any Federal contract, grant, loan, or cooperative agreement. For additional information of prohibitions against lobbying activities, see FAR Subpart 3.8 and FAR Clause 52.203-12.

In addition, as set forth in HHSAR 352.203-70 “Anti-Lobbying” (January 2006), the current Department of Health and Human Services Appropriations Act provides that no part of any appropriation contained in this Act shall be used, other than for normal and recognized executive-legislative relationships, for publicity or propaganda purposes, for the preparation, distribution, or use of any kit, pamphlet, booklet, publication, radio, television, or video presentation designed to support, or defeat legislation pending before the Congress, or any State or Local legislature except in presentation to the Congress, or any State or Local legislative body itself.

The current Department of Health and Human Services Appropriations Act also provides that no part of any appropriation contained in this Act shall be used to pay the salary or expenses of any contract or grant recipient, or agent acting for such recipient, related to any activity designed to influence legislation or appropriations pending before the Congress, or any State or Local legislature.

ARTICLE H.15. PRIVACY ACT APPLICABILITY

 

1) Notification is hereby given that the Contractor and its employees are subject to criminal penalties for violation of the Privacy Act to the same extent as employees of the Government. The Contractor shall assure that each of its employees knows the prescribed rules of conduct and that each is aware that he or she can be subjected to criminal penalty for violation of the Act. A copy of 45 CFR Part 5b, Privacy Act Regulations, may be obtained at http://www.gpoaccess.gov/cfr/index.html

 

2) The Project Officer is hereby designated as the official who is responsible for monitoring contractor compliance with the Privacy Act.

 

3) The Contractor shall follow the Privacy Act guidance as contained in the Privacy Act System of Records number 09-25-0200. This document may be obtained at the following link: http://oma.od.nih.gov/ms/privacy/pa-files/0200.htm

ARTICLE H.16.    LABORATORY LICENSE REQUIREMENTS

The Contractor shall comply with all applicable requirements of Section 353 of the Public Health Service Act (Clinical Laboratory Improvement Act as amended). This requirement shall also be included in any subcontract for services under the contract.

 

50


ARTICLE H.17.    DISSEMINATION OF INFORMATION (May 1998)

No information related to data obtained under this contract shall be released or publicized without the prior written consent of the Contracting Officer.

ARTICLE H.18.    IDENTIFICATION AND DISPOSITION OF DATA

The Contractor will be required to ensure that certain data generated under this contract is provided to the Department of Health and Human Services (DHHS). DHHS reserves the right to review any other data determined by DHHS to have been generated under this contract. The Contractor shall ensure that copies of all data required by the Food and Drug Administration (FDA) relevant to this contract are kept for the time specified by the FDA.

ARTICLE H.19.    INFORMATION ON COMPLIANCE WITH ANIMAL CARE REQUIREMENTS

Registration with the U. S. Dept. of Agriculture (USDA) is required to use regulated species of animals for biomedical purposes. USDA is responsible for the enforcement of the Animal Welfare Act (7 U.S.C. 2131 et. seq.), http://www.nal.usda.gov/awic/legislat/awa.htm.

The Public Health Service (PHS) Policy is administered by the Office of Laboratory Animal Welfare (OLAW) http://grants2.nih.gov/grants/olaw/olaw.htm. An essential requirement of the PHS Policy http://grants2.nih.gov/grants/olaw/references/phspol.htm is that every institution using live vertebrate animals must obtain an approved assurance from OLAW before they can receive funding from any component of the U. S. Public Health Service.

The PHS Policy requires that Assured institutions base their programs of animal care and use on the Guide for the Care and Use of Laboratory Animals http://www.nap.edu/readingroom/books/labrats/ and that they comply with the regulations (9 CFR, Subchapter A) http://www.nal.usda.gov/awic/legislat/usdaleg1.htm issued by the U.S. Department of Agriculture (USDA) under the Animal Welfare Act. The Guide may differ from USDA regulations in some respects. Compliance with the USDA regulations is an absolute requirement of this Policy.

The Association for Assessment and Accreditation of Laboratory Animal Care International (AAALAC) http://www.aaalac.org is a professional organization that inspects and evaluates programs of animal care for institutions at their request. Those that meet the high standards are given the accredited status. As of the 2002 revision of the PHS Policy, the only accrediting body recognized by PHS is the AAALAC. While AAALAC Accreditation is not required to conduct biomedical research, it is highly desirable. AAALAC uses the Guide as their primary evaluation tool. They also use the Guide for the Care and Use of Agricultural Animals in Agricultural Research and Teaching. It is published by the Federated of Animal Science Societies http://www.fass.org.

ARTICLE H.20. REQUIREMENTS FOR ADEQUATE ASSURANCE OF PROTECTION OF VERTEBRATE ANIMAL SUBJECTS

The PHS Policy on Humane Care and Use of Laboratory Animals requires that applicant organizations proposing to use vertebrate animals file a written Animal Welfare Assurance with the Office for Laboratory Animal Welfare (OLAW), establishing appropriate policies and procedures to ensure the humane care and use of live vertebrate animals involved in research activities supported by the PHS. The PHS Policy stipulates that an applicant organization, whether domestic or foreign, bears responsibility for the humane care and use of animals in PHS-supported research activities. Also, the PHS policy defines “animal” as “any live, vertebrate animal used, or intended for use, in research, research training, experimentation, biological testing or for related purposes.” This Policy implements and supplements the U.S. Government

 

51


Principles for the Utilization and Care of Vertebrate Animals Used in Testing, Research, and Training, and requires that institutions use the Guide for the Care and Use of Laboratory Animals as a basis for developing and implementing an institutional animal care and use program. This Policy does not affect applicable State or local laws or regulations that impose more stringent standards for the care and use of laboratory animals. All institutions are required to comply, as applicable, with the Animal Welfare Act as amended (7 USC 2131 et. seq.) and other Federal statutes and regulations relating to animals. These documents are available from the Office of Laboratory Animal Welfare, National Institutes of Health, Bethesda, MD 20892, (301) 496-7163. See http://grants.nih.gov/grants/olaw/olaw.htm.

No PHS supported work for research involving vertebrate animals will be conducted by an organization, unless that organization is operating in accordance with an approved Animal Welfare Assurance and provides verification that the Institutional Animal Care and Use Committee (IACUC) has reviewed and approved the proposed activity in accordance with the PHS policy. Applications may be referred by the PHS back to the institution for further review in the case of apparent or potential violations of the PHS Policy. No award to an individual will be made unless that individual is affiliated with an assured organization that accepts responsibility for compliance with the PHS Policy. Foreign applicant organizations applying for PHS awards for activities involving vertebrate animals are required to comply with PHS Policy or provide evidence that acceptable standards for the humane care and use of animals will be met. Foreign applicant organizations are not required to submit IACUC approval, but should provide information that is satisfactory to the Government to provide assurances for the humane care of such animals.

ARTICLE H.21. APPROVAL OF REQUIRED ASSURANCE BY OLAW

Under governing regulations, federal funds which are administered by the Department of Health and Human Services, Office of Biomedical Advanced Research and Development Authority (BARDA) shall not be expended by the Contractor for research involving live vertebrate animals, nor shall live vertebrate animals be involved in research activities by the Contractor under this award unless a satisfactory assurance of compliance with 7 U.S.C. 2316 and 9 CFR Sections 2.25-2.28 is submitted within 30 days of the date of this award and approved by the Office of Laboratory Animal Welfare (OLAW). Each performance site (if any) must also assure compliance with 7 U.S.C. 2316 and 9 CFR Sections 2.25-2.28 with the following restriction: Only activities which do not directly involve live vertebrate animals (i.e. are clearly severable and independent from those activities that do involve live vertebrate animals) may be conducted by the Contractor or individual performance sites pending OLAW approval of their respective assurance of compliance with 7 U.S.C. 2316 and 9 CFR Sections 2.25-2.28. Additional information regarding OLAW may be obtained via the Internet at http://grants2.nih.gov/grants/olaw/references/phspol.htm

ARTICLE H.22. REGISTRATION WITH THE SELECT AGENT PROGRAM FOR WORK INVOLVING THE POSSESSION, USE, AND/OR TRANSFER OF SELECT BIOLOGICAL AGENTS OR TOXINS

Work involving select biological agents or toxins shall not be conducted under this contract until the Contractor and any affected subcontractor(s) are granted a certificate of registration or are authorized to work with the applicable select agents.

For prime or subcontract awards to domestic institutions who possess, use, and/or transfer Select Agents under this contract, the institution must complete registration with the Centers for Disease Control and Prevention (CDC), Department of Health and Human Services (DHHS) or the Animal and Plant Health Inspection Services (APHIS), U.S. Department of Agriculture (USDA), as applicable, before performing work involving Select Agents, in accordance with 42 CFR 73. No Government funds can be used for work involving Select Agents, as defined in 42 CFR 73, if the final registration certificate is denied.

 

52


For prime or subcontract awards to foreign institutions who possess, use, and/or transfer Select Agents under this contract, the institution must provide information satisfactory to the Government that a process equivalent to that described in 42 CFR 73 (http://www.cdc.gov/od/sap/docs/42cfr73.pdf) for U.S. institutions is in place and will be administered on behalf of all Select Agent work sponsored by these funds before using these funds for any work directly involving the Select Agents. The Contractor must provide information addressing the following key elements appropriate for the foreign institution: safety, security, training, procedures for ensuring that only approved/appropriate individuals have access to the Select Agents, and any applicable laws, regulations and policies equivalent to 42 CFR 73. The Government will assess the policies and procedures for comparability to the U.S. requirements described in 42 CFR Part 73. When requested by the contracting officer, the Contractor shall provide key information delineating any laws, regulations, policies, and procedures applicable to the foreign institution for the safe and secure possession, use, and transfer of Select Agents. This includes summaries of safety, security, and training plans, and applicable laws, regulations, and policies. For the purpose of security risk assessments, the Contractor must provide the names of all individuals at the foreign institution who will have access to the Select Agents and procedures for ensuring that only approved and appropriate individuals have access to Select Agents under the contract.

Listings of HHS select agents and toxins, biologic agents and toxins, and overlap agents or toxins as well as information about the registration process, can be obtained on the Select Agent Program Web site at http://www.cdc.gov/od/sap/.

ARTICLE H.23. EPA ENERGY STAR REQUIREMENTS

In compliance with Executive Order 12845 (requiring Agencies to purchase energy efficient computer equipment) all microcomputers, including personal computers, monitors, and printers that are purchased using Government funds in performance of a contract shall be equipped with or meet the energy efficient low-power standby feature as defined by the EPA Energy Star program unless the equipment always meets EPA Energy Star efficiency levels. The microcomputer, as configured with all components, must be Energy Star compliant.

This low-power feature must already be activated when the computer equipment is delivered to the agency and be of equivalent functionality of similar power managed models. If the equipment will be used on a local area network, the vendor must provide equipment that is fully compatible with the network environment. In addition, the equipment will run commercial off-the-shelf software both before and after recovery from its energy conservation mode.

ARTICLE H.24.  MANUFACTURING STANDARDS

The Good Manufacturing Practice Regulations (GMP)(21 CFR Parts 210-211) and regulations pertaining to small molecules will be the standard to be applied for manufacturing, processing, packaging, storage and delivery of this product.

If at any time during the life of the contract, the Contractor fails to comply with GMP in the manufacturing, processing, packaging, storage, stability and other testing of the manufactured drug substance or product and delivery of this product and such failure results in a material adverse effect on the safety, purity or potency of the product (a material failure) as identified by the FDA, the Contractor shall have thirty (30) calendar days from the time such material failure is identified to cure such material failure. If, within the thirty (30) calendar day period, the Contractor fails to take such an action to the satisfaction of the USG Project Officer, or fails to provide a remediation plan that is acceptable to the COR, then the contract may be terminated.

 

53


ARTICLE H.25. EXPORT CONTROL NOTIFICATION

Offerors are responsible for ensuring compliance with all export control laws and regulations that maybe applicable to the export of and foreign access to their proposed technologies. Offerors may consult with the Department of State with any questions regarding the International Traffic in Arms Regulation (ITAR) (22 CRF Parts 120-130) and /or the Department of Commerce regarding the Export Administration Regulations (15 CRF Parts 730-774).

ARTICLE H.26. INSTITUTIONAL RESPONSIBILITY REGARDING CONFLICTING INTERESTS OF INVESTIGATORS

The Contractor shall comply with the requirements of 45 CFR Part 94, Responsible Prospective Contractors, which promotes objectivity in research by establishing standards to ensure that investigators (defined as the principal investigator and any other person who is responsible for the design, conduct, or reporting of research funded under BARDA contracts) will not be biased by any conflicting financial interest. For the purposes of this part relating to financial interests, “Investigator” includes the Investigator’s spouse and dependent children. 45 CFR Part 94 is available at the following Web site: http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr;sid=9f130b6d2d48bb73803ca91ce943be3a;rgn=div5;view=text;node=45%3A1.0.1.1.53;idno=45;cc=ecfr

As required by 45 CFR Part 94, the Contractor shall, at a minimum:

a.   Maintain a written, enforceable policy on conflict of interest that complies with 45 CFR Part 94 and inform each investigator of the policy, the investigator’s reporting responsibilities, and the applicable regulations. The Contractor must take reasonable steps to ensure that investigators working as collaborators or subcontractors comply with the regulations.

b.   Designate an official(s) to solicit and review financial disclosure statements from each investigator participating in BARDA-funded research. Based on established guidelines consistent with the regulations, the designated official(s) must determine whether a conflict of interest exists, and if so, determine what actions should be taken to manage, reduce, or eliminate such conflict. A conflict of interest exists when the designated official(s) reasonably determines that a Significant Financial Interest could directly and significantly affect the design, conduct, or reporting of the BARDA-funded research. The Contractor may require the management of other conflicting financial interests in addition to those described in this paragraph, as it deems appropriate. Examples of conditions or restrictions that might be imposed to manage actual or potential conflicts of interests are included in 45 CFR Part 94, under Management of Conflicting Interests.

c.    Require all financial disclosures to be updated during the period of the award, either on an annual basis or as new reportable Significant Financial Interests are obtained.

d.   Maintain records, identifiable to each award, of all financial disclosures and all actions taken by the Contractor with respect to each conflicting interest 3 years after final payment or, where applicable, for the other time periods specified in 48 CFR Part 4, subpart 4.7, Contract Records Retention.

e.   Establish adequate enforcement mechanisms and provide for sanctions where appropriate.

If a conflict of interest is identified, the Contractor shall report to the Contracting Officer the existence of the conflicting interest found. This report shall be made and the conflicting interest managed, reduced, or eliminated, at least on a temporary basis, within sixty (60) days of that identification.

If the failure of an investigator to comply with the conflict of interest policy has biased the design, conduct, or reporting of the BARDA-funded research, the Contractor must promptly notify the Contracting Officer of the corrective action taken or to be taken. The Contracting Officer will take appropriate action or refer the matter to the Contractor for further action which may include directions to the Contractor on how to maintain appropriate objectivity in the funded research.

 

54


The Contracting Officer may at any time inquire into the Contractor’s procedures and actions regarding conflicts of interests in BARDA-funded research including a review of all records pertinent to compliance with 45 CFR Part 94. The Contracting Officer may require submission of the records or review them on site. On the basis of this review, the Contracting Officer may decide that a particular conflict of interest will bias the objectivity of the BARDA-funded research to such an extent that further corrective action is needed or that the Contractor has not managed, reduced, or eliminated the conflict of interest. The issuance of a Stop Work Order by the Contracting Officer may be necessary until the matter is resolved.

If the Contracting Officer determines that BARDA-funded clinical research, whose purpose is to evaluate the safety or effectiveness of a drug, medical device, or treatment, has been designed, conducted, or reported by an investigator with a conflict of interest that was not disclosed or managed, the Contractor must require disclosure of the conflict of interest in each public presentation of the results of the research.

ARTICLE H.27 NOTIFICATION OF CRITICAL PROGRAMMATIC CONCERNS, RISKS, OR POTENTIAL RISKS

If any action occurs that creates a cause for critical programmatic concern, risk, or potential risk to BARDA or the Contractor an Incident Report shall be delivered to BARDA.

 

   

Within 48 hours of activity or incident or within 24 hours for a security related activity or incident, Contractor must notify BARDA.

   

Additional updates due to COR and CO within 48 hours of additional developments.

   

Contractor shall submit within 5 business days a Corrective Action Plan (if deemed necessary by either party) to address any potential issues.

If corrective action is deemed necessary, Contractor must address in writing, its consideration of concerns raised by BARDA within 5 business days.

 

55


PART II - CONTRACT CLAUSES

SECTION I - CONTRACT CLAUSES

ARTICLE I.1.   FAR 52.252-2, CLAUSES INCORPORATED BY REFERENCE (FEBRUARY 1998)

This contract incorporates the following clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at: https://www.acquisition.gov/

General Clauses for Cost-Reimbursement Research and Development Contract

a.   FEDERAL ACQUISITION REGULATION (FAR) (48 CFR CHAPTER 1) CLAUSES:

 

FAR
CLAUSE NO.
  DATE    TITLE
52.202-1   Jan 2012    Definitions
52.203-3   Apr 1984    Gratuities
52.203-5   Apr 1984    Covenant Against Contingent Fees
52.203-6   Sep 2006    Restrictions on Subcontractor Sales to the Government
52.203-7   Oct 2010    Anti-Kickback Procedures
52.203-8   Jan 1997    Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
52.203-10   Jan 1997    Price or Fee Adjustment for Illegal or Improper Activity
52.203-12   Oct 2010    Limitation on Payments to Influence Certain Federal Transactions (Over $150,000)
52.203-13   Apr 2010    Contractor Code of Business Ethics and Conduct
52.203-14   Dec 2007    Display of Hotline Poster(s)
52.204-4   May 2011    Printed or Copied Double-Sided on Recycled Paper
52.204-7   Dec 2012    Central Contractor Registration
52.204-10   Aug 2012    Reporting Executive Compensation and First-Tier Subcontract Awards ($25,000 or more)
52.204-13   Dec 2012    Central Contractor Registration Maintenance
52.209-6   Dec 2010    Protecting the Government’s Interests When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment (Over $30,000)
52.215-2   Oct 2010    Audit and Records – Negotiation
52.215-8   Oct 1997    Order of Precedence - Uniform Contract Format
52.215-10    Aug 2011    Price Reduction for Defective Cost or Pricing Data (Over $700,000)
52.215-12    Oct 2010    Subcontractor Cost or Pricing Data (Over $700,000)
52.215-14   Oct 2010    Integrity of Unit Prices
52.215-15   Oct 2010    Pension Adjustments and Asset Reversions
52.215-17   Oct 1997    Waiver of Facilities Capital Cost of Money
52.215-18   Jul 2005    Reversion or Adjustment of Plans for Post-Retirement Benefits (PRB) other than Pensions
52.215-19   Oct 1997    Notification of Ownership Changes
52.215-21   Oct 2010    Requirements for Cost or Pricing Data or Information Other Than Cost or Pricing Data - Modifications
52.215-23   Oct 2009    Limitations on Pass-Through Charges (Over the Simplified Acquisition threshold)
52.216-7   Jun 2011    Allowable Cost and Payment

 

56


FAR
CLAUSE NO.
  DATE    TITLE
52.216-8   Jun 2011    Fixed Fee
52.216-12   Apr 1984    Cost Sharing Contract – no fee
52.217-9   Mar 2000   

Option to Extend the Term of the Contract

 

(a) The Government may extend the term of this contract by written notice to the Contractor within          [insert the period of time within which the Contracting Officer may exercise the option]; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 30 days before the contract expires. The preliminary notice does not commit the Government to an extension.

 

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

 

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 5 years.

52.219-16   Jan 1999    Liquidated Damages - Subcontracting Plan
52.222-2   Jul 1990    Payment for Overtime Premiums
52.222-3   Jun 2003    Convict Labor
52.222-21   Feb 1999    Prohibition of Segregated Facilities
52.222-26   Mar 2007    Equal Opportunity
52.222-35   Sep 2010    Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (Over $100,000)
52.222-36   Oct 2010    Affirmative Action for Workers with Disabilities
52.222-37   Sep 2010    Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (Over $100,000)
52.222-40   Dec 2010    Notification of Employee Rights Under the National Labor Relations Act
52.222-50   Feb 2009    Combating Trafficking in Persons
52.222-54   Jan 2009    Employment Eligibility Verification
52.223-6   May 2001    Drug-Free Workplace
52.223-18   Aug 2011    Encouraging Contractor Policy to Ban Text Messaging While Driving
52.224-1   April 1984    Privacy Act Notification
52.224-2   April 1984    Privacy Act
52.225-1   Feb 2009    Buy American Act - Supplies
52.225-13   Jun 2008    Restrictions on Certain Foreign Purchases
52.227-1   Dec 2007    Authorization and Consent, Alternate I (Apr 1984)
52.227-2   Dec 2007    Notice and Assistance Regarding Patent and Copyright Infringement
52.227-3   Apr 1984    Patent Indemnity
52.227-11   Dec 2007    Patent Rights - Ownership by the Contractor (Note: In accordance with FAR 27.303(b)(2), paragraph (e) is modified to include the requirements in FAR 27.303(b)(2)(i) through (iv). The frequency of reporting in (i) is annual.

 

57


FAR
CLAUSE NO.
  DATE    TITLE
52.227-14   Dec 2007   

Rights in Data – General, Alternate II.

 

Completed portion as follows:

 

Limited Rights Notice (Dec 2007)

 

(a) These data are submitted with limited rights under Government Contract No. HHSO10020XX000XXX (and subcontract         , if appropriate). These data may be reproduced and used by the Government with the express limitation that they will not, without written permission of the Contractor, be used for purposes of manufacture nor disclosed outside the Government; except that the Government may disclose these data outside the Government for the following purposes, provided that the Government makes such disclosure subject to prohibition against further use and disclosure:

 

(i) Use (except for manufacture) by support service contractors.

(ii) Evaluation by nongovernment evaluators.

 

(b) This Notice shall be marked on any reproduction of these data, in whole or in part.

52.227-16   Jun 1987    Additional Data Requirements
52.232-9   Apr 1984    Limitation on Withholding of Payments
52.232-17   Oct 2010    Interest
52.232-20   Apr 1984    Limitation of Cost
52.232-23   Jan 1986    Assignment of Claims
52.232-25   Oct 2008    Prompt Payment, Alternate I (Feb 2002)
52.232-33   Oct 2003    Payment by Electronic Funds Transfer--Central Contractor Registration
52.233-1   Jul 2002    Disputes
52.233-3   Aug 1996    Protest After Award, Alternate I (Jun 1985)
52.233-4   Oct 2004    Applicable Law for Breach of Contract Claim
52.242-1   Apr 1984    Notice of Intent to Disallow Costs
52.242-3   May 2001    Penalties for Unallowable Costs (Over $700,000)
52.242-4   Jan 1997    Certification of Final Indirect Costs
52.242-13   Jul 1995    Bankruptcy
52.242-15   Aug 1989    Stop Work Order. Alt I (Aug 1984)
52.243-2   Aug 1987    Changes - Cost Reimbursement, Alternate V (Apr 1984)
52.244-2   Oct 2010    Subcontracts, Alternate I (June 2007)
52.244-5   Dec 1996    Competition in Subcontracting
52.244-6   Dec 2010    Subcontracts for Commercial Items

52.245-1

Alt. II

  Aug 2010    Government Property, Alternate II (Jun 2007)
52.245-9   Aug 2010    Use and Charges
52.246-9   Apr 1984    Inspection of Research and Development (Short Form)
52.246-23   Feb 1997    Limitation of Liability
52.247-63   Jun 2003    Preference for U.S.-Flag Air Carriers
52.249-6   May 2004    Termination (Cost-Reimbursement)
52.249-14   Apr 1984    Excusable Delays
52.253-1   Jan 1991    Computer Generated Forms

 

58


b. DEPARTMENT OF HEALTH AND HUMAN SERVICES ACQUISITION REGULATION (HHSAR) (48 CFR CHAPTER 3) CLAUSES:

 

HHSAR
CLAUSE NO.
  DATE    TITLE
352.202-1   Jan 2006    Definitions - with Alternate paragraph (h) (Jan 2006)
352.203-70   Mar 2012    Anti-Lobbying
352.216-70   Jan 2006    Additional Cost Principles
352.222-70   Jan 2010    Contractor Cooperation in Equal Employment Opportunity Investigations
352.223-70   Jan 2006    Safety and Health
352.224-70   Jan 2006    Privacy Act
352.227-70   Jan 2006    Publications and Publicity
352.228-7   Dec 1991    Insurance - Liability to Third Persons
352.231-70*   Aug 2012    Salary Rate Limitation
352.231-71   Jan 2001    Pricing of adjustments
352.233-71   Jan 2006    Litigation and Claims
352.242-70   Jan 2006    Key Personnel
352.242-73   Jan 2006    Withholding of Contract Payments
352.242-74   Apr 1984    Final Decisions on Audit Findings
352.270-4   Jan 2006    Protection of Human Subjects
352.270-6   Jan 2006    Restriction on use of Human Subjects

* The provisions set forth by this clause will only apply if and when any funds are obligated from HHS funding appropriated in the 2012 government fiscal year.

[End of GENERAL CLAUSES FOR A NEGOTIATED COST-REIMBURSEMENT RESEARCH AND DEVELOPMENT CONTRACT-Rev. 12/2011].

ARTICLE I.2. ADDITIONAL FAR CONTRACT CLAUSES INCLUDED IN FULL TEXT

This contract incorporates the following clauses in full text.

FEDERAL ACQUISITION REGULATION (FAR) (48 CFR CHAPTER 1) CLAUSES:

a.   FAR Clause 52.217-9, Option to Extend the Term of the Contract (Mar 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within [*] days after the Government has completed its analysis of the deliverables associated with the applicable GO/NO GO Decision gate; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least [*] days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c). FAR Clause 52.219-28, Post-Award Small Business Program Representation (April 2009).

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

59


(a) Definitions. As used in this clause--

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall represent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts--

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall represent its size status in accordance with the size standard in effect at the time of this representation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/contractingopportunities/officials/size/index.html.

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation required by paragraph (b) of this clause by validating or updating all its representations in the Online Representations and Certifications Application and its data in the Central Contractor Registration, as necessary, to ensure that they reflect the

 

60


Contractor’s current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in ORCA, or does not have a representation in ORCA for the NAICS code applicable to this contract, the Contractor is required to complete the following representation and submit it to the contracting office, along with the contract number and the date on which the representation was completed:

The Contractor represents that it [x] is, [ ] is not a small business concern under NAICS Code assigned to contract number.

[Contractor to sign and date and insert authorized signer’s name and title].

 

61


PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

SECTION J - LIST OF ATTACHMENTS

The following documents are attached and incorporated in this contract:

1. Statement of Work

Statement of Work, dated 22 April 2013.

2. Invoice/Financing Request Instructions and Contract Financial Reporting Instructions for BARDA Cost-Reimbursement Type Contracts,

Invoice/Financing Request Instructions and Contract Financial Reporting Instructions for BARDA Cost-Reimbursement Type Contracts, 5 pages.

3. Financial Report of Individual Project/Contract, 1 page

4. Instructions for Completing Financial Report of Individual Project/Contract, 3 pages

5. Inclusion Enrollment Report

Inclusion Enrollment Report, 5/01 (Modified OAMP: 10/01), 1 page.

6. Research Patient Care Costs

Research Patient Care Costs, 1 page.

7. Report of Government Owned, Contractor Held Property

Report of Government Owned, Contractor Held Property, 1 page. Located at: http://rcb.cancer.gov/rcb-internet/forms/Govt-Owned-Prop.pdf

8. 7 Principles of Earned Value Management Tier 2 System Implementation Guide

 

62


PART IV - REPRESENTATIONS AND INSTRUCTIONS

SECTION K - REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS

The following documents are incorporated by reference in this contract:

 

1) Representations & Certifications - Status Active on SAM.gov.

 

2) Final Cost Proposal Budget received 26 March 2013.

 

3) Final Technical Proposal received 22 April 2013.

 

4) Human Subjects Assurance Identification Numbers:

 i.      Duke Clinical Research Institute (DCRI): 00009025

ii.      Celerion: FWA00003049

 

5) Animal Welfare Assurance Numbers (OLAW/PHS):

 i.      Lovelace: A3083-01

ii.      MPI Research: A3181-01

 

63


3. STATEMENT OF WORK

 

3.1 Preamble

Independently and not as an agent of the Government, the Contractor shall be required to furnish all the necessary services, qualified personnel, material, equipment, and facilities, not otherwise provided by the Government, as needed to perform the Statement of Work submitted in response to Broad Agency Announcement (BAA) BARDA CBRN BAA-12-100-SOL-00011.

The Government reserves the right to modify the milestones, progress, schedule, budget, or product to add or delete products, process, or schedule as need may arise. Because of the nature of this (R&D) contract and complexities inherent in this and prior programs, at designated milestones the Government will evaluate whether work should be redirected, removed, or whether schedule or budget adjustments should be made. In any event, the Government reserves the right to change product, process, schedule, or event to add or delete part or all of these elements as the need arises.

 

3.2 Overall Objectives and Scope

The overall objective of this contract is to advance the development of solithromycin (SOLI) as an intravenous (IV) and orally-delivered antibiotic for use in the pediatric population for the treatment of community-acquired bacterial pneumonia (CABP) and for protection against biothreat organisms, including Bacillus anthracis and Francisella tularensis. The scope of work is organized in 5 severable phases (Clinical Line Item Number [CLIN] 1 through 5):

 

LOGO

 

64


1. CLIN 1

The Contractor will carry out the following tasks and subtasks and in accordance with the agreed upon Integrated Master Schedule and Integrated Master Plan, which further details the conduct of the specific tasks and subtasks.

 

1.1 Program Management (WBS 1.1)

The Contractor outsources a majority of the work to established practitioners in each discipline, with the Contractor team providing experienced program management, coordination, and oversight. All selected purchased commercial service providers for the BARDA project have proven their ability to deliver quality work cost-effectively and on schedule. The Contractor shall provide for the following program management activities as outlined below:

 

  1.1.1 The Contractor will provide overall management, integration and coordination of all contract activities, including a technical and administrative infrastructure to ensure the efficient planning, initiation, implementation, and direction of all contract activities.

 

  1.1.2 The Principal Investigator is responsible for overall leadership for project management, communication, tracking, monitoring and reporting on status and progress, and modification to the project requirements and timelines, including projects undertaken by subcontractors.

 

  1.1.3 The Project Manager will oversee the monitoring and tracking day-to-day progress and timelines, coordinating communication and project activities; costs incurred; and program management.

 

  1.1.4 The Principal Investigator and the Project Manager will act as the BARDA Liaison with responsibility for effective communication with the Project Officer and Contracting Officer.

 

  1.1.5 The Contractor has adequate administrative staff and legal consultants to provide development of compliant subcontracts, consulting, and other legal agreements, and ensure timely acquisition of all proprietary rights, including IP rights, and reporting all inventions made in the performance of the project.

 

  1.1.6 The Contractor’s Project Management Team along with support from the Finance department has responsibility for financial management and reporting on all activities conducted by the Contractor and any subcontractors and service providers.

 

  1.1.7 Contract Review Meetings

 

  1.1.7.1 The Contractor’s team will participate in regular face-to-face meetings on a quarterly basis to coordinate and oversee the contract effort as directed by the Contracting and Project Officers. Such meetings may include, but are not limited to, meeting of the Contractor and subcontractors to discuss clinical manufacturing progress, product development, product assay development, scale up manufacturing development, clinical sample assays development, preclinical/clinical study designs and regulatory issues; meetings with individual Contractors and other HHS officials to discuss the technical, regulatory, and ethical aspects of the program; and meeting with technical consultants to discuss technical data provided by the Contractor.

 

  1.1.7.2 The Contractor will participate in teleconferences every 2 weeks between the Contractor and BARDA to review technical progress. The Contractor will include subcontractors and service providers as necessary. If additional teleconferences or face-to-face meetings are requested by BARDA, the Contractor will be available.

 

  1.1.8 Integrated Master Schedule (IMS)

1.1.8.1 Within 30 calendar days of the effective date of the contract, the Contractor will submit a first draft of an updated IMS in a format agreed upon by BARDA to the Project Officer and the Contracting Officer for review and comment. The Integrated Master Schedule will be incorporated into the contract, and will be used to monitor performance of the contract. The Contractor will include the key milestones and Go/No Go decision gates. The IMS for the period of performance will be reviewed and accepted by BARDA at the PMBR.

 

  1.1.9 Integrated Master Plan (IMP)

 

  1.1.9.1

Work Breakdown Structure: The Contractor will utilize a WBS template agreed upon by BARDA for reporting on the contact. The Contractor will expand and delineate the Contract Work

 

65


 

Breakdown Structure (CWBS) to a level agreed upon by BARDA as part of their Integrated Master Plan for contract reporting. The CWBS will be discernible and consistent. At BARDA’s request, the Contractor will furnish WBS data at the work package level or at a lower level if there is significant complexity and risk associated with the task.

 

  1.1.9.2 GO/ NO-GO Decision Gates/Contract Milestones: The IMP will outline key milestones with “Go/No Go” decision criteria (entrance and exit criteria for each phase of the project). The project plan should include, but not be limited to, milestones in manufacturing, non-clinical and clinical studies, and regulatory submissions.

 

  1.1.9.3 Earned Value Management System Plan: Subject to the requirements under HHSAR Clause 352.234-4, the Contractor will use principles of Earned Value Management System (EVMS) in the management of this contract. The Contractor will follow the Seven Principles:

 

  I. The Contractor will plan all work scope for the program to completion.

 

  II. The Contractor will break down the program work scope into finite pieces that can be assigned to a responsible person or organization for control of technical, schedule, and cost objectives.

 

  III. The Contractor will integrate program work scope, schedule, and cost objectives into a performance measurement baseline plan against which accomplishments may be measured.

 

  IV. The Contractor will use actual cost incurred and recorded in accomplishing the work performed.

 

  V. The Contractor will objectively assess accomplishments at the work performance level.

 

  VI. The Contractor will analyze significant variances from the plan, forecast impacts, and prepare an estimate at completion based on performance to date and work to be performed.

 

  VII. The Contractor will use earned value information in the company’s management processes.

We understand that elements of EVMS will be applied to all applicable projects as part of the IMP. In addition, the Contractor will submit a written summary of the management procedures that will be used to establish, maintain and comply with EVMS requirements.

 

  1.1.10 Decision Gate Reporting: On completion of a stage of the product development, as defined in the agreed upon IMS and IMP, the Contractor will prepare and submit to the Project Officer and the Contracting Officer a Decision Gate Report that contains (i) sufficient detail, documentation and analysis to support successful completion of the stage according to the predetermined qualitative and quantitative criteria that were established for Go/No Go decision making; and (ii) a description of the next stage of product development to be initiated and a request for approval to proceed to the next stage of product development.

 

  1.1.11 Risk Management Plan: The Contractor will develop a risk management plan within 90 days of contract award highlighting potential problems and/or issues that may arise during the life of the contract, their impact on cost, schedule and performance, and appropriate remediation plans. This plan will reference relevant WBS elements where appropriate. Updates to this plan will be included every 3 months (quarterly) in the monthly Project Status Report.

 

  1.1.12 Performance Measurement Baseline Review (PMBR): The Contractor will submit a plan for a PMBR to occur within [*] days of contract award. At the PMBR, the Contractor and BARDA will mutually agree upon the budget, schedule and technical plan baselines (Performance Measurement Baseline). These baselines will be the basis for monitoring and reporting progress throughout the life of the contract. The PMBR is conducted to achieve confidence that the baselines accurately capture the entire technical scope of work, are consistent with contract schedule requirements, are reasonably and logically planned, and have adequate resources assigned. The goals of the PMBR are as follows:

 

  I. Jointly assess areas such as the Contractor’s planning for complete coverage of the SOW, logical scheduling of the work activities, adequate resources, and identification of inherent risks

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

66


  II. Confirm the integrity of the Performance Measurement Baseline (PMB)

 

  III. Foster the use of EVM as a means of communication

 

  IV. Provide confidence in the validity of the Contractor’s reporting

 

  V. Identify risks associated with the PMB

 

  VI. Present any revised PMBs for mutual agreement

 

  VII. Present an IMS: The Contractor will deliver an initial program IMS that rolls up all time-phased WBS elements down to the activity level. This IMS will include the dependencies that exist between tasks. This IMS will be agreed to and finalized at the PMBR.

 

  VIII. Present the Risk Management Plan

 

  1.1.13 Deviation Request: During the course of contract performance, in response to a need to change IMS activities as baselined at the PMBR, the Contractor will submit a Deviation Report. This report will be used to request a change in the agreed-upon IMS and timelines, if necessary. This report will include: (i) discussion of the justification/rationale for the proposed change; (ii) options for addressing the needed changes from the agreed upon timelines, including a cost-benefit analysis of each option; and (iii) recommendations for the preferred option that includes a full analysis and discussion of the effect of the change on the entire product development program, timelines, and budget.

 

  1.1.14 Monthly and Annual Reports: The Contractor will deliver Project Status Reports on a monthly basis. The reports will address the items below cross referenced to the WBS, SOW, IMS, and EVMS:

 

  I. Executive summary highlighting the progress, issues, and relevant activities in manufacturing, non-clinical, clinical, and regulatory;

 

  II. Progress in meeting contract milestones, detailing the planned progress and actual progress during the reporting period, explaining any differences between the two and corrective steps;

 

  III. Updated IMS;

 

  IV. Updated EVMS;

 

  V. Updated Risk Management Plan (Every 3 months);

 

  VI. Three month rolling forecast of planned activities;

 

  VII. Progress of regulatory submissions;

 

  VIII. Estimated and actual expenses;

 

  1.1.15 Data Management: The Contractor will develop and implement data management and quality control systems/procedures, including transmission, storage, confidentiality, and retrieval of all contract data;

 

  1.1.15.1 Provide for the statistical design and analysis of data resulting from the research;

 

  1.1.15.2 Provide raw data or specific analyses of data generated with contract funding to the Project Officer, upon request.

 

1.2 [*] (WBS 1.2)

 

  1.2.1 [*] (WBS 1.2.1 - reserved)

 

  1.2.2 [*] (WBS 1.2.2)

 

  1.2.2.1 [*]

 

  1.2.2.2 [*]

 

1.3 [*] (WBS 1.3)

 

  1.3.1 [*] (WBS 1.3.1 - reserved)

 

  1.3.2 [*] (WBS 1.3.2)

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

67


  1.3.2.1 [*]

 

  1.3.2.2 [*]

 

  1.3.2.3 [*]

 

  1.3.2.4 [*]

 

  1.3.2.5 [*]

 

  1.3.3 [*] (WBS 1.3.3 - reserved)

 

1.4 [*] (WBS 1.4)

 

  1.4.1 [*] (WBS 1.4.1)

 

  1.4.1.1 [*]

 

  1.4.1.2 [*]

 

  1.4.1.3 [*]

 

  1.4.1.4 [*]

 

  1.4.2 [*] (WBS 1.4.2 - reserved)

 

1.5 [*] (WBS 1.5)

 

  1.5.1 [*] (WBS 1.5.1)

 

  1.5.1.1 [*]

 

  1.5.1.2 [*]

 

  1.5.1.3 [*]

 

  1.5.1.4 [*]

 

  1.5.2 [*] (WBS 1.5.2)

 

  1.5.2.1 [*]

 

  1.5.2.2 [*]

 

  1.5.2.3 [*]

 

  1.5.2.4 [*]

 

  1.5.2.5 [*]

 

1.6 [*] (WBS 1.6)

 

  1.6.1 [*] (WBS 1.6.1)

 

  1.6.1.1 [*]

 

  1.6.1.2 [*]

 

  1.6.1.3 [*]

 

  1.6.1.4 [*]

 

  1.6.2 [*] (WBS 1.6.2)

 

  1.6.2.1 [*]

 

  1.6.3 [*] (WBS 1.6.3)

 

  1.6.3.1 [*]

 

  1.6.3.2 [*]

 

  1.6.3.4 [*]

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

68


  1.6.4 [*] (WBS 1.6.4 - reserved)

 

  1.6.5 [*] (WBS 1.6.5).

 

       [*]

1.6.5.1  [*]

1.6.5.2  [*]

 

2. CLIN 2

 

2.1 Program Management (WBS 2.1)

 

  2.1.1 Program management scope is consistent with that outlined in CLIN 1.

 

2.2 [*] (WBS 2.2 – reserved)

 

2.3 [*] (WBS 2.3 – reserved)

 

2.4 [*] (WBS 2.4)

 

  2.4.1 [*] (WBS 2.4.1)

 

  2.4.1.1 [*]

 

  2.4.1.2 [*]

 

  2.4.2 [*] (WBS 2.4.2)

2.4.2.1  [*]

 

2.5 [*] (WBS 2.5)

 

  2.5.1 [*] (WBS 2.5.1 – reserved)

 

  2.5.2 [*] (WBS 2.5.2)

 

  2.5.2.1 [*]

 

  2.5.2.2 [*]

 

  2.5.2.4 [*]

 

2.6 [*] (WBS 2.6)

 

  2.6.1 [*] (WBS 2.6.1 - reserved)

 

  2.6.2 [*] (WBS 2.6.2 - reserved)

2.6.3 [*] (WBS 2.6.3)

 

  2.6.3.1 [*]

 

  2.6.3.2 [*]

 

  2.6.3.3 [*]

 

  2.6.3.4 [*]

 

  2.6.4 [*] (WBS 2.6.4 - reserved)

 

  2.6.5 [*] (WBS 2.6.5).

 

  2.6.5.1 [*] (WBS 2.6.5.1)

 

3. CLIN 3

 

3.1 Program Management (WBS 3.1)

 

  3.1.1 Program management scope is consistent with that outlined in CLIN 2.

 

3.2 [*] (WBS 3.2 - reserved)

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

69


3.3 [*] (WBS 3.3)

 

  3.3.1 [*] (WBS 3.3.1 – reserved)

 

  3.3.2 [*] (WBS 3.3.2 – reserved)

 

  3.3.3 [*] (WBS 3.3.3)

 

  3.3.3.1 [*]

 

  3.3.3.2 [*]

 

  3.3.3.3 [*]

 

3.4 [*] (WBS 3.4)

 

  3.4.1 [*] (WBS 3.4.1)

 

  3.4.1.1 [*]

 

  3.4.2 [*] (WBS 3.4.2 - reserved)

 

3.5 [*] (WBS 3.5)

 

  3.5.1 [*] (WBS 3.5.1 – reserved)

 

  3.5.2 [*] (WBS 3.5.2)

 

  3.5.2.1 [*]

 

  3.5.2.2 [*]

 

3.6 [*] (WBS 3.6)

 

  3.6.1 [*] (WBS 3.6.1 - reserved)

 

  3.6.2 [*] (WBS 3.6.2 - reserved)

 

  3.6.3 [*] (WBS 3.6.3)

 

  3.6.3.1 [*]

 

  3.6.4 [*] (WBS 3.6.4 - reserved)

 

  3.6.5 [*] (WBS 3.6.5)

 

  3.6.5.1 [*] (WBS 3.6.5.1)

 

4. CLIN 4 (GOVERNMENT/CONTRACTOR COST-SHARE)

 

4.1 Program Management (WBS 4.1)

 

  4.1.1 Program management scope is consistent with that in CLIN 3.

 

4.2 [*] (WBS 4.2 – reserved)

 

4.3 [*] (WBS 4.3 - reserved)

 

4.4 [*] (WBS 4.4)

 

  4.4.1 [*] (WBS 4.4.1 – reserved)

 

  4.4.2 [*] (WBS 4.4.2)

 

  4.4.2.1 [*]

 

4.5 [*] (WBS 4.5 - reserved)

 

4.6 [*] (WBS 4.6 - reserved)

 

5. CLIN 5

 

5.1 Program Management (WBS 5.1)

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

70


  5.1.1 Program management scope is consistent with that in CLIN 4.

 

5.2 [*] (WBS 5.2 - reserved)

 

5.3 [*] (WBS 5.3 - reserved)

 

5.4 [*] (WBS 5.4 - reserved)

 

5.5 [*] (WBS 5.5)

 

  5.5.1 [*] (WBS 5.5.1 – reserved)

 

  5.5.2 [*] (WBS 5.5.2)

 

  5.5.2.1 [*]

 

  5.5.2.2 [*]

 

5.6 [*] (WBS 5.6 - reserved)

 

6. OTHER ITEMS

 

6.1 Facilities, Equipment, and Other Resources

The Contractor confirms the subcontractor and all purchased commercial service providers provide equipment, facilities and other resources under Federal and HHS regulations.

 

[*] Confidential treatment requested; certain information omitted and filed separately with the SEC.

 

71


Attachment 2

INVOICE/FINANCING REQUEST AND CONTRACT FINANCIAL REPORTING

INSTRUCTIONS FOR BARDA COST-REIMBURSEMENT CONTRACTS

Format: Payment requests shall be submitted on the Contractor’s self-generated form in the manner and format prescribed herein and as illustrated in the Sample Invoice/Financing Request. Standard Form 1034, Public Voucher for Purchases and Services Other Than Personal, may be used in lieu of the Contractor’s self-generated form provided it contains all of the information shown on the Sample Invoice/Financing Request. DO NOT include a cover letter with the payment request.

Number of Copies: Payment requests shall be submitted in the quantity specified in the Invoice Submission Instructions in Section G of the Contract Schedule.

Frequency: Payment requests shall not be submitted more frequently than once every two weeks in accordance with the Allowable Cost and Payment Clause incorporated into this contract. Small business concerns may submit invoices/financing requests more frequently than every two weeks when authorized by the Contracting Officer.

Cost Incurrence Period: Costs incurred must be within the contract performance period or covered by precontract cost provisions.

Billing of Costs Incurred: If billed costs include (1) costs of a prior billing period, but not previously billed, or (2) costs incurred during the contract period and claimed after the contract period has expired, the Contractor shall site the amount(s) and month(s) in which it incurred such costs.

Contractor’s Fiscal Year: Payment requests shall be prepared in such a manner that the Government can identify costs claimed with the Contractor’s fiscal year.

Currency: All BARDA contracts are expressed in United States dollars. When the Government pays in a currency other than United States dollars, billings shall be expressed, and payment by the Government shall be made, in that other currency at amounts coincident with actual costs incurred. Currency fluctuations may not be a basis of gain or loss to the Contractor. Notwithstanding the above, the total of all invoices paid under this contract may not exceed the United States dollars authorized.

Costs Requiring Prior Approval: Costs requiring the Contracting Officer’s approval, including those set forth in an Advance Understanding in the contract, shall be identified and reference the Contracting Officer’s Authorization (COA) Number. In addition, the Contractor shall show any cost set forth in an Advance Understanding as a separate line item on the payment request.

Invoice/Financing Request Identification: Each payment request shall be identified as either:

 

(a) Interim Invoice/Contract Financing Request: These are interim payment requests submitted during the contract performance period.

 

(b) Completion Invoice: The completion invoice shall be submitted promptly upon completion of the work, but no later than one year from the contract completion date, or within 120 days after settlement of the final indirect cost rates covering the year in which the contract is physically complete (whichever date is later). The Contractor shall submit the completion invoice when all costs have been assigned to the contract and it completes all performance provisions.

 

(c) Final Invoice: A final invoice may be required after the amounts owed have been settled between the Government and the Contractor (e.g., resolution of all suspensions and audit exceptions).

Preparation and Itemization of the Invoice/Financing Request: The Contractor shall furnish the information set forth in the instructions below. The instructions are keyed to the entries on the Sample Invoice/Financing Request.

 

72


(a) Designated Billing Office Name and Address: Enter the designated billing office name and address, as identified in the Invoice Submission Instructions in Section G of the Contract Schedule.

 

(b) Contractor’s Name, Address, Point of Contact, VIN, and DUNS or DUNS+4 Number: Show the Contractor’s name and address exactly as they appear in the contract, along with the name, title, phone number, and e-mail address of the person to notify in the event of an improper invoice or, in the case of payment by method other than Electronic Funds Transfer, to whom payment is to be sent. Provide the Contractor’s Vendor Identification Number (VIN), and Data Universal Numbering System (DUNS) number or DUNS+4. The DUNS number must identify the Contractor’s name and address exactly as stated on the face page of the contract. When an approved assignment has been made by the Contractor, or a different payee has been designated, provide the same information for the payee as is required for the Contractor (i.e., name, address, point of contact, VIN, and DUNS).

 

(c) Invoice/Financing Request Number: Insert the appropriate serial number of the payment request.

 

(d) Date Invoice/Financing Request Prepared: Insert the date the payment request is prepared.

 

(e) Contract Number and Order Number (if applicable): Insert the contract number and order number (if applicable).

 

(f) Effective Date: Insert the effective date of the contract or if billing under an order, the effective date of the order.

 

(g) Total Estimated Cost of Contract/Order: Insert the total estimated cost of the contract, exclusive of fixed-fee. If billing under an order, insert the total estimated cost of the order, exclusive of fixed-fee. For incrementally funded contracts/orders, enter the amount currently obligated and available for payment.

 

(h) Total Fixed-Fee: Insert the total fixed-fee (where applicable) or the portion of the fixed-fee applicable to a particular invoice as defined in the contract.

 

(i) Two-Way/Three-Way Match: Identify whether payment is to be made using a two-way or three-way match. To determine required payment method, refer to the Invoice Submission Instructions in Section G of the Contract Schedule.

 

(j) Office of Acquisitions: Insert the name of the Office of Acquisitions, as identified in the Invoice Submission Instructions in Section G of the Contract Schedule.

 

(k) Central Point of Distribution: Insert the Central Point of Distribution, as identified in the Invoice Submission Instructions in Section G of the Contract Schedule.

 

(l) Billing Period: Insert the beginning and ending dates (month, day, and year) of the period in which costs were incurred and for which reimbursement is claimed.

 

(m) Amount Billed - Current Period: Insert the amount claimed for the current billing period by major cost element, including any adjustments and fixed-fee. If the Contract Schedule contains separately priced line items, identify the contract line item(s) on the payment request and include a separate breakdown (by major cost element) for each line item.

 

(n) Amount Billed - Cumulative: Insert the cumulative amounts claimed by major cost element, including any adjustments and fixed-fee. If the Contract Schedule contains separately priced line items, identify the contract line item(s) on the payment request and include a separate breakdown (by major cost element) for each line item.

 

(o) Direct Costs: Insert the major cost elements. For each element, consider the application of the paragraph entitled “Costs Requiring Prior Approval” on page 1 of these instructions.

 

73


  (1) Direct Labor: Include salaries and wages paid (or accrued) for direct performance of the contract. List individuals by name, title/position, hourly/annual rate, level of effort (actual hours or % of effort), breakdown by task performed by personnel, and amount claimed.

 

  (2) Fringe Benefits: List any fringe benefits applicable to direct labor and billed as a direct cost. Do not include in this category fringe benefits that are included in indirect costs.

 

  (3) Accountable Personal Property: Include any property having a unit acquisition cost of $5,000 or more, with a life expectancy of more than two years, and sensitive property regardless of cost (see the HHS Contractor’s Guide for Control of Government Property)(e.g. personal computers). Note this is not permitted for reimbursement without pre-authorization from the CO.

On a separate sheet of paper attached to the payment request, list each item for which reimbursement is requested. Include reference to the following (as applicable):

- item number for the specific piece of equipment listed in the Property Schedule, and

- COA number, if the equipment is not covered by the Property Schedule.

The Contracting Officer may require the Contractor to provide further itemization of property having specific limitations set forth in the contract.

 

  (4) Materials and Supplies: Include all consumable material and supplies regardless of amount. Detailed line-item breakdown (e.g. receipts, quotes, etc.) is required.

 

  (5) Premium Pay: List remuneration in excess of the basic hourly rate.

 

  (6) Consultant Fee: List fees paid to consultants. Identify consultant by name or category as set forth in the contract or COA, as well as the effort (i.e., number of hours, days, etc.) and rate billed.

 

  (7) Travel: Include domestic and foreign travel. Foreign travel is travel outside of Canada, the United States and its territories and possessions. However, for an organization located outside Canada, the United States and its territories and possessions, foreign travel means travel outside that country. Foreign travel must be billed separately from domestic travel.

 

  (8) Subcontract Costs: List subcontractor(s) by name and amount billed. Provide subcontract invoices/receipts as backup documentation. If subcontract is of the cost-reimbursement variety, detailed breakdown will be required. Regardless, include backup documentation (e.g. subcontractor invoices, quotes, etc.).

 

  (9) Other: Include all other direct costs not fitting into an aforementioned category. If over $1,000, list cost elements and dollar amounts separately. If the contract contains restrictions on any cost element, that cost element must be listed separately.

 

(p) Cost of Money (COM): Cite the COM factor and base in effect during the time the cost was incurred and for which reimbursement is claimed, if applicable.

 

(q) Indirect Costs: Identify the indirect cost base (IDC), indirect cost rate, and amount billed for each indirect cost category.

 

(r) Fixed-Fee: Cite the formula or method of computation for fixed-fee, if applicable. The fixed-fee must be claimed as provided for by the contract.

 

(s) Total Amounts Claimed: Insert the total amounts claimed for the current and cumulative periods.

 

74


(t) Adjustments: Include amounts conceded by the Contractor, outstanding suspensions, and/or disapprovals subject to appeal.

 

(u) Grand Totals

 

(v) Certification of Salary Rate Limitation: If required by the contract (see Invoice Submission Instructions in Section G of the Contract Schedule), the Contractor shall include the following certification at the bottom of the payment request:

“I hereby certify that the salaries billed in this payment request are in compliance with the Salary Rate Limitation Provisions in Section H of the contract.”

**Note the Contracting Officer may require the Contractor to submit detailed support for costs claimed on payment requests. Every cost must be determined to be allocable, reasonable, and allowable per FAR Part 31.

 

75


FINANCIAL REPORTING INSTRUCTIONS:

These instructions are keyed to the Columns on the sample invoice/financing request.

Column A - Expenditure Category: Enter the expenditure categories required by the contract.

Column B - Cumulative Percentage of Effort/Hrs. - Negotiated: Enter the percentage of effort or number of hours agreed to for each employee or labor category listed in Column A.

Column C - Cumulative Percentage of Effort/Hrs. - Actual: Enter the percentage of effort or number of hours worked by each employee or labor category listed in Column A.

Column D - Amount Billed - Current: Enter amounts billed during the current period.

Column E - Amount Billed - Cumulative: Enter the cumulative amounts to date.

Column F - Cost at Completion: Enter data only when the Contractor estimates that a particular expenditure category will vary from the amount negotiated. Realistic estimates are essential.

Column G - Contract Amount: Enter the costs agreed to for all expenditure categories listed in Column A.

Column H - Variance (Over or Under): Show the difference between the estimated costs at completion (Column F) and negotiated costs (Column G) when entries have been made in Column F. This column need not be filled in when Column F is blank. When a line item varies by plus or minus 10 percent, i.e., the percentage arrived at by dividing Column F by Column G, an explanation of the variance should be submitted. In the case of an overrun (net negative variance), this submission shall not be deemed as notice under the Limitation of Cost (Funds) Clause of the contract.

Modifications: Any modification in the amount negotiated for an item since the preceding report should be listed in the appropriate cost category.

Expenditures Not Negotiated: An expenditure for an item for which no amount was negotiated (e.g., at the discretion of the Contractor in performance of its contract) should be listed in the appropriate cost category and all columns filled in, except for G. Column H will of course show a 100 percent variance and will be explained along with those identified under H above.

 

76


SAMPLE INVOICE/PAYMENT REQUEST AND CONTRACT FINANCIAL REPORT

 

(a)

  Designated Billing Office Name and Address:    (c)   Invoice/Financing Request No.:
   

 

DHHS/OS/ASPR/BARDA

  

 

(d)

 

 

Date Invoice Prepared:

   

Attn: Contracting Officer

330 Independence Ave., S.W.

Room G644

Washington, D.C. 20201

  

 

(e)

 

(f)

 

 

 

Contract No. and Order No. (if applicable):             

 

Effective Date:

 

 

(b)

 

 

Contractor’s Name, Address, Point of Contact, VIN, and DUNS or DUNS+4 Number:

  

(g)

 

(h)

 

Total Estimated Cost of Conract/Order:

 

Total Fixed-Fee (if applicable):

   

 

ABC CORPORATION

  

 

(i)

 

 

¨ Two-Way Match:

    100 Main Street      ¨ Three-Way Match
    Anywhere, USA Zip Code   

 

(j)

 

 

Office of Acquisitions:

   

Name, Title, Phone Number, and E-mail Address of person to notify in the event of an improper invoice or, in the case of payment by method other than Electronic Funds Transfer, to whom payment is to be sent.

  

 

(k)

 

 

Central Point of Distribution

   

 

VIN:

      
   

DUNS or DUNS+4

 

        

 

(l) This invoice/financing request reimbursable costs for the period from          to         

 

     

Cumulative Percentage

of Effort/Hrs.

  Amount Billed                   

Expenditure Category*

                           A

  

Negotiated 

  

Actual  

C  

 

(m) 

Current 

  

(n) 

Cumulative 

  

Cost at 

Completion 

  

Contract 

Amount 

  

Variance

H

(o)    Direct Costs:

                                 

 (1) Direct Labor

                                 

 (2) Fringe Benefits

                                 

 (3) Accountable Property

                                 

 (4) Materials & Supplies

                                 

 (5) Premium Pay

                                 

 (6) Consultant Fees

                                 

 (7) Travel

                                 

 (8) Subcontracts

                                 

 (9) Other

                                 

Total Direct Costs

                                 

(p)    Cost of Money

                                 

(q)    Indirect Costs

                                 

(r)     Fixed Fee

                                 

(s)    Total Amount Claimed

                                 

(t)     Adjustments

                                 

(u)    Grand Totals

                                 
I certify that all payments are for appropriate purposes and in accordance with the contract.
   
   

 

     

 

          
       (Name of Official)       (Title)          
 
* Attach details as specified in the contract

 

77


Attachment 3

 

 

FINANCIAL REPORT OF INDIVIDUAL

PROJECT/CONTRACT

 

Note: Complete this Form in Accordance with Accompanying Instructions.

 

   Project Task:    Contract No.:    Date of Report:   

 

0990-0134

0990-0131

  

Reporting Period:

 

  

Contractor Name and Address:

 

Expenditure Category*       

 

Percentage of

Effort/Hours

 

   Cumulative 
Incurred  Cost 
at End of 
Prior Period 
  

Incurred  

Cost-  

-Current  

  

Cumulative  

Cost to Date  

(D + E)  

   Estimated  
Cost to  
Complete  
   Estimated Cost at  
Completion (F+G)  
   Negotiated  
Contract  
Amount  
   Variance (Over
or Under) (I-H)
  

 

Negotiated    

   Actual                      

 

A

   B    C    D    E    F    G    H    I    J
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        
                                                        

 

78


Attachment 4

INSTRUCTIONS FOR COMPLETING

“FINANCIAL REPORT OF INDIVIDUAL PROJECT/CONTRACT”

GENERAL INFORMATION

Purpose. This Quarterly Financial Report is designed to: (1) provide a management tool for use by be BARDA in monitoring the application of financial and personnel resources to the BARDA contracts; (2) provide contractors with financial and personnel management data which is usable in their management processes; (3) promptly indicate potential areas of contract underruns or overruns by making possible comparisons of actual performance and projections with prior estimates on individual elements of cost and personnel; and (4) obtain contractor’s analyses of cause and effect of significant variations between actual and prior estimates of financial and personnel performance.

REPORTING REQUIREMENTS

Scope. The specific cost and personnel elements to be reported shall be established by mutual agreement prior to award. The Government may require the contractor to provide detailed documentation to support any element(s) on one or more financial reports.

Number of Copies and Mailing Address. An original and two (2) copies of the report(s) shall be sent to the contracting officer at the address shown on the face page of the contract, no later than 30 working days after the end of the period reported. However, the contract may provide for one of the copies to be sent directly to the Contracting Officer’s Technical Representative.

REPORTING STATISTICS

A modification which extends the period of performance of an existing contract will not require reporting on a separate quarterly report, except where it is determined by the contracting officer that separate reporting is necessary. Furthermore, when incrementally funded contracts are involved, each separate allotment is not considered a separate contract entity (only a funding action). Therefore, the statistics under incrementally funded contracts should be reported cumulatively from the inception of the contract through completion.

Definitions and Instructions for Completing the Quarterly Report. For the purpose of establishing expenditure categories in Column A, the following definitions and instructions will be utilized. Each contract will specify the categories to be reported.

 

(1) Key Personnel. Include key personnel regardless of annual salary rates. All such individuals should be listed by names and job titles on a separate line including those whose salary is not directly charged to the contract but whose effort is directly associated with the contract. The listing must be kept up to date.

 

(2) Personnel--Other. List as one amount unless otherwise required by the contract.

 

(3) Fringe Benefits. Include allowances and services provided by the contractor to employees as compensation in addition to regular salaries and wages. If a fringe benefit rate(s) has been established, identify the base, rate, and amount billed for each category. If a rate has not been established, the various fringe benefit costs may be required to be shown separately. Fringe benefits which are included in the indirect cost rate should not be shown here.

 

(4) Accountable Personal Property. Include nonexpendable personal property with an acquisition cost of $1,000 or more and with an expected useful life of two or more years, and sensitive items regardless of cost. Form HHS 565, “Report of Accountable Property,” must accompany the contractor’s public voucher (SF 1034/SF 1035) or this report if not previously submitted. See “Contractor’s Guide for Control of Government Property.”

 

79


(5) Supplies. Include the cost of supplies and material and equipment charged directly to the contract, but excludes the cost of nonexpendable equipment as defined in (4) above.

 

(6) Inpatient Care. Include costs associated with a subject while occupying a bed in a patient care setting. It normally includes both routine and ancillary costs.

 

(7) Outpatient Care. Include costs associated with a subject while not occupying a bed. It normally includes ancillary costs only.

 

(8) Travel. Include all direct costs of travel, including transportation, subsistence and miscellaneous expenses. Travel for staff and consultants shall be shown separately. Identify foreign and domestic travel separately. If required by the contract, the following information shall be submitted: (i) Name of traveler and purpose of trip; (ii) Place of departure, destination and return, including time and dates; and (iii) Total cost of trip.

 

(9) Consultant Fee. Include fees paid to consultant(s). Identify each consultant with effort expended, billing rate, and amount billed.

 

(10) Premium Pay. Include the amount of salaries and wages over and above the basic rate of pay.

 

(11) Subcontracts. List each subcontract by name and amount billed.

 

(12) Other Costs. Include any expenditure categories for which the Government does not require individual line item reporting. It may include some of the above categories.

 

(13) Overhead/Indirect Costs. Identify the cost base, indirect cost rate, and amount billed for each indirect cost category.

 

(14) General and Administrative Expense. Cite the rate and the base. In the case of nonprofit organizations, this item will usually be included in the indirect cost.

 

(15) Fee. Cite the fee earned, if any.

 

(16) Total Costs to the Government.

PREPARATON INSTRUCTIONS

These instructions are keyed to the Columns on the Quarterly Report.

Column A--Expenditure Category. Enter the expenditure categories required by the contract.

Column B--Percentage of Effort/Hours Negotiated. Enter the percentage of effort or number of hours agreed to during contract negotiations for each labor category listed in Column A.

Column C--Percentage of Effort/Hours-Actual. Enter the cumulative percentage of effort or number of hours worked by each employee or group of employees listed in Column A.

Column D--Cumulative Incurred Cost at End of Prior Period. Enter the cumulative incurred costs up to the end of the prior reporting period. This column will be blank at the time of the submission of the initial report.

Column E--Incurred Cost-Current Period. Enter the costs which were incurred during the current period.

Column F--Cumulative Incurred Cost to Date. Enter the combined total of Columns D and E.

Column G--Estimated Cost to Complete. Make entries only when the contractor estimates that a particular expenditure category will vary from the amount negotiated. Realistic estimates are essential.

 

80


Column H--Estimated Costs at Completion. Complete only if an entry is made in Column G.

Column I--Negotiated Contract Amount. Enter in this column the costs agreed to during contract negotiations for all expenditure categories listed in Column A.

Column J--Variance (Over or Under). Complete only if an entry is made in Column H. When entries have been made in Column H, this column should show the difference between the estimated costs at completion (Column H) and negotiated costs (Column I). When a line item varies by plus or minus 10 percent, i.e., the percentage arrived at by dividing Column J by Column I, an explanation of the variance should be submitted. In the case of an overrun (net negative variance), this submission shall not be deemed as notice under the Limitation of Cost (Funds) Clause of the contract.

Modifications. List any modification in the amount negotiated for an item since the preceding report in the appropriate cost category.

Expenditures Not Negotiated. List any expenditure for an item for which no amount was negotiated (e.g., at the discretion of the contractor in performance of its contract) in the appropriate cost category and complete all columns except for I. Column J will of course show a 100 percent variance and will be explained along with those identified under J above.

 

81


Attachment 5

INCLUSION ENROLLMENT REPORT

This report format should NOT be used for data collection from study participants

Study Title:

 

                   

Total Enrollment:

 

      Protocol Number:

Contract Number:

 

                   

 

PART A. TOTAL ENROLLMENT REPORT:            Number of Subjects Enrolled to Date (Cumulative) by Ethnicity and Race

 

Ethnic Category   Sex/Gender          
  Females     Males       Unknown or Not Reported       Total

Hispanic or Latino

 

                   

Not Hispanic or Latino

 

                   

Unknown (Individuals not reporting ethnicity)

 

                   

Ethnic Category: Total of All Subjects*

 

                   

 

Racial Categories

 

                   

American Indian/Alaska Native

 

                   

Asian

 

                   

Native Hawaiian or Other Pacific Islander

 

                   

Black or African American

 

                   

White

 

                   

More than one race

 

                   

Unknown or not reported

 

                   

Racial Categories: Total of All Subjects*

 

                   

 

    

 

PART B. HISPANIC ENROLLMENT REPORT:        Number of Hispanics or Latinos Enrolled to Date (Cumulative)

 

 

Racial Categories

 

 

 

Females  

 

 

Males  

 

 

  Unknown or Not Reported   

 

 

Total

American Indian/Alaska Native

 

                   

Asian

 

                   

Native Hawaiian or Other Pacific Islander

 

                   

Black or African American

 

                   

White

 

                   

More than one race

 

                   

Unknown or not reported

 

                   

Racial Categories: Total of Hispanics or Latinos**

 

                   

*These totals must agree

** these totals must agree

                   

 

82


Attachment 6

Research Patient Care Costs

(a)        Research patient care costs are the costs of routine and ancillary services provided to patients participating in research programs described in this contract.

(b)        Research patient care costs shall be computed in a manner consistent with the principles and procedures used by the Medicare Program for determining the part of Medicare reimbursement based on reasonable costs. The Diagnostic Related Group (DRG) prospective reimbursement method used to determine the remaining portion of Medicare reimbursement shall not be used to determine research patient care costs. Research patient care rates or amounts shall be established by the Secretary of HHS or his/her duly authorized representative.

(c)        Prior to submitting an invoice for research patient care costs under this contract, the contractor must make every reasonable effort to obtain third party payment, where third party payors (including Government agencies) are authorized or are under a legal obligation to pay all or a portion of the charges incurred under this contract for research patient care.

(d)        The contractor must maintain adequate procedures to identify those research patients participating in this contract who are eligible for third party reimbursement.

(e)        Only those charges not recoverable from third party payors or patients and which are consistent with the terms and conditions of the contract are chargeable to this contract.

 

83


Attachment 7

 

Contracting Site – Contract number –

Inventory Sheet

 

DHHS TAG*

   S/N    TYPE    MAKE    MODEL    LOCATION
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                
                                

 

*Until or unless BARDA affixes an HHS generated ID, the contractor shall track and monitor all equipment, materials, and supplies purchased under this contract in a manner which affords a clear distinction from other contractor property.

 

84


Department of Health & Human Services

HHS

Office of the Assistant Secretary for Preparedness and Readiness

ASPR

Biomedical Advanced Research and Development Authority

BARDA

7 Principles of Earned Value

Management

Tier 2

System Implementation

Intent Guide

21 December 2011

 

LOGO

 


TABLE OF CONTENTS

 

 

OVERVIEW      1   
EVM IMPLEMENTATION TIERS      2   
SEVEN PRINCIPLES OF EVM      3   

Principle 1: Plan all Work Scope

     3   

Principle 2: Break Work into Finite Pieces and Define Person/Organization Responsible for Work

     3   

Principle 3a: Integrate Scope, Schedule and Budget into a Performance Measurement Baseline

     4   

Principle 3b: Control Changes to the Baseline

     5   

Principle 4: Use Actual Costs Incurred and Recorded in Accomplishing the Work Performed

     5   

Principle 5: Objectively Assess Accomplishments at the Work Performance Level

     6   

Principle 6a: Analyze Significant Variances From the Plan

     7   

Principle 6b: Prepare an Estimate at Completion Based on Performance to Date and Work to be Performed

     7   

Principle 7: Use EVMS Information in the Company’s Management Processes

     7   
APPENDICES      9   

APPENDIX 1: Glossary of Terms

     9   

Appendix 2 Supplemental EVM Implementation Guideline

     15   

Appendix 3 Sample EVM Documents

     17   

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

OVERVIEW

Earned Value Management (EVM) is a program management tool, technique, and discipline that facilitates systematic planning for and monitoring of, high value, complex projects. It integrates a project’s scope of work with the related budget and schedule to permit detailed assessment of overall performance during the life of the project.

Several government-wide guidance documents govern the definition and use of EVM systems. Guidelines outlining the qualities and characteristics of an EVM system are set forth in the American National Standards Institute/Electronic Industries Alliance (ANSI/EIA) Standard-748 (most current version). More detailed and specific guidance and direction is contained in OMB Circular A-11, Preparation, Submission and Execution of the Budget, specifically in Part 7 of that Circular A-11, Planning, Budgeting, Acquisition, and Management of Capital Assets, and its supplement, the Capital Programming Guide. Based on this collective OMB guidance, EVMS is intended to be used on those parts of acquisitions that will involve developmental effort. This would include not only those acquisitions designated by the agency as major systems but also those acquisitions that include significant developmental, modification, or upgrade during the operational or steady-state phase of a program.

The FAR rule on EVMS became effective on July 5, 2006. Its purpose is to implement EVMS policy in accordance with OMB Circular A-11. Because the new FAR coverage applies throughout the executive branch and to agencies with disparate definitions of and processes and procedures for major systems acquisitions, the FAR Council decided against a “one-size-fits all” approach and left several significant aspects of the detailed implementation up to the discretion of each covered agency.

The FAR and Health and Human Services Acquisition Regulations (HHSAR) language for EVMS will be utilized for all construction or Information Technology (IT) projects. Since most of the acquisitions at the Biomedical Advanced Research and Development Agency (BARDA) are unique in that most acquisitions are not Information Technology projects or construction projects, BARDA is developing EVM language that incorporates the 7 Principles of Earned Value Management. These principles allow flexibility to an EVM system structure but still meet the spirit of the ANSI/EIA Standard-748. It also incorporates discipline in implementation and operations and also provides the same reporting data outlined by OMB.

The Seven Principles of Earned Value Management are as follows:

 

  1. Plan all work scope to completion

 

  2. Break down the program work scope into finite pieces that can be assigned to a responsible person or organization for control of technical, schedule and cost objectives

 

  3. Integrate program work scope, schedule, and cost objectives into a performance measurement baseline plan against which accomplishments can be measured. Control changes to the baseline.

 

  4. Use actual costs incurred and recorded in accomplishing the work performed.

 

  5. Objectively assess accomplishments at the work performance level.

 

  6. Analyze significant variances from the plan, forecast impacts, and prepare an estimate at completion based on performance to date and work to be performed.

 

  7. Use earned value information in the company’s management processes.

 

1

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

EVM IMPLEMENTATION TIERS

BARDA will be implementing a tiered approach to EVM based on the type of acquisition, size of the acquisition and the technical readiness level. There are three tiers and they are as follows:

TIER 1

For all construction contracts and IT contracts the ANSI/EIA-748 Standard for Earned Value Management Systems will apply and all relevant FAR/HHSAR clauses pertaining to EVMS will be incorporated in the contract. The National Defense Industrial Association (NDIA) Program Management Systems Committee (PMSC) ANSI/EIA-748 Standard for Earned Value Management Systems Intent Guide should be used as guidance.

TIER 2

For countermeasure research and development contracts that have a total acquisition costs greater than or equal to $25 million and have a Technical Readiness Level (TRL) of less than 7 will apply EVM principles for tracking cost, schedule and technical performance that comply with the 7 Principles of EVM Implementation.

TIER 3

For countermeasure research and development contracts that have total acquisition costs less than $25 million but greater than $10 million will apply EVM principles for tracking cost, schedule and technical performance that are consistent with the 7 Principles of EVM Implementation.

This Guide is an explanation of the intent of what is expected for a Tier 2 system implementation of the 7 Principles of EVM.

 

2

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

SEVEN PRINCIPLES OF EVM

Principle 1: Plan all Work Scope

In a performance measurement system implementation the Statement of Work (SOW) should reflect all work that is to be performed. In a 7 Principles implementation a Work Breakdown Structure (WBS) shall be developed to include all elements of the SOW. The level of the WBS may not be as detailed as in a Tier 1 implementation. It would be developed at a higher level, such as level three or four, however, the government may expand specific technical legs to lower than level four and it may retract some non-technical legs to higher than 3. It is beneficial and required to develop a WBS dictionary that explains what work is going to be performed in each WBS in detail. This will ensure that the contractor has identified all work scope and left no major work undefined. It is recommended that the work packages descriptions are clear and detailed so that there is an understanding of the work that is to be performed in the work packages. For the 7 Principles implementation programs it would be acceptable for the WBS Dictionary be expanded to include information that would normally be kept on a Work Authorization Document, such as charge numbers associated with the work, period of performance, the manager who is responsible for the work, and budget associated with the WBS. The additional “WAD info” would only be added to the lowest level (i.e. level 3 or 4) of the WBS. The roll up level WBS would only include scope. By doing this documentation is limited to one document instead of two.

By developing a WBS and a WBS Dictionary/Work Authorization Document the work scope has been defined but the documentation is greatly reduced and the costs associated with developing and updating the documentation is reduced. The intent of the combination document is not to reduce the level of information provided to the government but to reduce the amount of documents that need to be produced. An example of a WBS dictionary and Work Authorization document and what is expected on the document(s) is provided.

Principle 2: Break Work into Finite Pieces and Define Person/Organization Responsible for Work

In a 7 Principles Tier 2 implementation it is recommended that the work be broken into finite pieces in the schedule tool. It is recommended to plan the work by the lowest level WBS. The lowest level WBS (level 3 or 4) should be the control account and the activities would act as the work packages. For Tier 2 programs that are of larger value (greater than $25M) the expectation is that the control account will be at least at level 4 and potentially level 5. Most of the normal functions accomplished when scheduling will be required on a 7 Principles Tier 2 implementation. These normal functions include, network scheduling, horizontal and vertical traceability, forecasting schedule start and completion dates, and running critical path analysis. As part of vertical traceability it is expected that all contract milestones will be listed on the schedule.

The schedule should include but is not limited to include the following fields:

WBS number

Control Account number

Work package number

Task name

Duration

Baseline Start and Finish Dates

Actual Start and Finish Dates

Forecast Start and Finish Dates

Predecessor/Successors

Activity Percent Complete

All the work scheduled at the lowest level WBS should be identified by a single responsible manager. This manager, known as a Control Account Manager should be identified in the schedule tool and/or in a cost tool. In a 7 Principles implementation, only individuals at the lowest level WBS need be identified and there is no requirement for the costs to roll up by organization, although if it is not cost intensive or tool restricted then developing the OBS is recommended. In many cases, BARDA will provide the top three levels of the WBS for the contractor to use.

 

3

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

Principle 3a: Integrate Scope, Schedule and Budget into a Performance Measurement Baseline

This principle integrates the work scope, the schedule and the budget into a performance measurement baseline. Since we discussed work scope and schedule the focus of this principle is the incorporation of the budget in a time-phased manner. The budget must be integrated with the scope of work and the schedule into a Performance Measurement Baseline (PMB). The budget is made up of both direct and indirect dollars. An accepted way of incorporating the budget and integrating with the scope and schedule is to resource load the Microsoft Project (or other scheduling tool) schedule. This is done by loading the individual people and their loaded rate into the tool. This budget data will be input at the work package level with a rate that includes the indirect costs. The budget will have to have the capability to be rolled up to the control account level and will need to be reported in a way that provides the responsible manager (Control Account Manager) with information needed to manage the program. Resource loading of the schedule is not the only way to incorporate the budget. As long as the budget in the budget/EV tool is linked to the schedule activities and it is flexible to change when schedule baseline dates change, then loading the budget in the Budget/EV tool is an acceptable way to integrate the cost and schedule baselines. The budget information will be displayed on the time-phased Control Account Plan reports. These reports should have the flexibility to report the dollars both in total dollars, as well as, direct and indirect broken out separately. Also the report is generally required as a deliverable on most contracts and must have the capability to include earned value or Budgeted Cost of Work Performed (BCWP) and actual costs or Actual Costs of Work Performed (ACWP).

Budgeting of subcontractor effort will vary depending on whether or not the subcontractor is a cost plus or fixed price subcontract. If it is cost plus then the expectation is that there will be monthly billing of costs from the subcontractor to the prime contractor and therefore budget must be planned in accordance with the work completed and billed. If it is fixed price then the budget should be planned with work execution or milestones completed and budget should only be planned in those months where work is expected to be completed.

It is recommended that management reserve and undistributed budget be utilized in the budgeting process. Undistributed budget is budget that has not yet been distributed to a control account and it requires additional time to plan the work and distribute the budget to a control account. It is a temporary holding account and budget should only stay in Undistributed Budget for one or two months. If the work scope is easily identified to all the control accounts then the use of Undistributed Budget may not be necessary.

Management Reserve is budget that is set aside, normally by the Program Manager, to be used to budget future but currently unknown tasks. It is associated with risk issues and is to be used to mitigate risk. It is not part of the Performance Measurement Baseline and it should not be used for out of scope work and to cover overruns.

 

4

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

Principle 3b: Control Changes to the Baseline

A properly controlled PMB is crucial to effective program management. The timely and accurate incorporation of contractual changes ensures that the information generated from the execution of the baseline plan provides an accurate picture of progress and facilitates correct management actions and decisions. The accurate and timely incorporation of authorized and negotiated changes into the PMB ensures that valid performance measurement information is generated for the new scope being executed. Near term new scope effort should be planned and have budget in control accounts. Far term new scope effort that cannot be reasonably planned in the near term can either be put in planning packages in the control account or left in Undistributed Budget if the control account has not been identified. The timely and accurate incorporation of authorized and negotiated changes into the PMB ensures that valid performance measurement information is generated for the new scope being executed. Budget revisions are made when work is added to the contract and are traceable from authorized contract target costs to the control account budgets or from management reserve. Management reserve may be used for future work when additional in-scope work has been identified.

Retroactive changes to the baseline may mask variance trends and prevent the use of performance data to project estimates of cost and schedule at completion. Controlling retroactive adjustments, which should only be made in the current period, if possible, is imperative because they could arbitrarily eliminate existing cost and schedule variances.

The use of program budget logs should be used to track and log all budget changes. The ability to track budget values for both the internal and external changes will help in the maintenance of the performance measurement baseline from program start to completion. Contractor is expected to utilize baseline change documentation facilitating the change. It should provide the rationale/justification, approval process, work scope additions or deletions, dollars, changes to schedules, estimate at completion, etc. It should also include contractual change documents for external changes, such as a contract modification, letter to proceed, not to exceed letter, change order, etc., that transmit and authorize the change or addition to work, budget, and schedule. Other documents that should change if a change of scope has been authorized is: Statement of Work, WBS (changes if applicable); WBS Dictionary (additions or deletions to scope); work authorization documents authorizing new scope, schedule and budget; schedules.

Principle 4: Use Actual Costs Incurred and Recorded in Accomplishing the Work Performed

Some of the new acquisitions at BARDA will be required to be compliant with the Cost Accounting Standards. For 7 Principles implementation contractors must utilize a work order/job order/task code charge number structure that uniquely identifies costs at the control account level. This will allow for accumulation and summarization of costs to higher levels of the work breakdown structure. Actual costs are accumulated in the formal accounting system in a manner consistent with the way the related work is planned and budgeted. Actual costs reported in the performance reports agrees with the costs recorded in the accounting system or can be explained as timing differences. The contractor will have to be able to incorporate and reconcile to the accounting system actual costs on their Contract Performance Reports (CPR) to the customer.

Depending on the amount of material and subcontractors on the program, it may be necessary for reporting purposes, to include accruals, or estimated actuals, for these costs. Since material and subcontractor invoices are not paid and recorded in the accounting system for up to several months after the work has been planned, performance data will be skewed. Accruing or estimating actual costs based on receipt (for material) and expended hours for subcontractors will alleviate this issue. The use of accrual/estimated actuals should be reviewed on a case by case basis depending on the size of program, the amount of material or subcontractor budget and costs. If the material and subcontract effort on the project is minimal (represents less than 5% of the project budget) then the time and effort needed to manage the accruals would outweigh the benefit of having the costs accrued since the performance data would only be minimally affected. Although actual costs are generally reported to the USG in total dollars the system must be able to differentiate and report direct costs and indirect costs if requested.

If the subcontractor has a fixed price contract the prime contractor, then the prime contractor must report actual costs in accordance with the work that is accomplished. This is acheived by recording the actual costs equal to the work

 

5

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

that was performed in the EVM system and on the CPR. If the subcontractor is a cost plus contract its imperative the costs the prime reports is in accordance with the costs incurred in that month. This is necessary to ensure that the data reported is not skewed. With this premise, fixed price subcontractors cost variances should not exist or be reported on the CPR whereas the cost reported for cost plus subcontractors should be based on what was incurred and not what has been invoiced to date, which may be months behind.

Principle 5: Objectively Assess Accomplishments at the Work Performance Level

In order to meet this Principle, the scheduling of the scope of work in work packages or activities need to incorporate measurable units or milestones in order to objectively assess accomplishments or obtain what we call “earned value”. These units or milestones are given a value based on labor resources needed to accomplish the work (which becomes the Budgeted Cost of Work Scheduled or BCWS). When they are accomplished (known as Budgeted Cost of Work Performed or BCWP) they receive the value associated with the budget which measures progress.

Schedule status to measure progress needs to be on at least on a monthly basis although it is preferred on a bi-weekly basis. As part of the status process progress dates, such as actual start/complete and forecast start/complete need to be updated.

Since Microsoft Project seems to be the schedule tool of choice by most contractors, there are four types of earned value methodologies utilized by Microsoft Project of which two assess progress by the completion of milestones and they are the 50/50 and 0/100 methodologies. In both cases, progress is reported for completion milestones and in the 50/50 methodology fifty percent of the value of the work package/activity is credited for starting the work. The other two earned value methodologies are assessed percent complete (also know as Supervisor’s Estimate) and level of effort (LOE). All four methodologies are legitimate earn value measurement techniques but the assessed percent complete based or supervisor’s estimates are highly discouraged. The reason is that it is highly subjective and is not based on any quantifiable criteria. BARDA will not accept these earned value methodologies unless approved as an exception on a case by case basis. If percent complete on work packages is used with objective measurable activities, the contractor must show distinct relationship between the budget planned at the work package level and the value earned at the activity level. If this is done properly then the measurement will be objective and the schedule variance will be clearly understood and easy to explain. If this is not done properly then schedule activities are not aligned with the budget in the performance measurement baseline and schedule variances will not be easy to understand. If the latter is the case, BARDA will not accept that as an acceptable earned value methodology.

There are built in weaknesses with the 0/100 and 50/50 methodologies also. If the responsible manager is being asked to plan their work in monthly increments in order to utilize the 0/100 methodology then they may be asked to break the work up in pieces that don’t make logical sense or represent the natural ending of the work. Also the 50/50 methodology, which is usually used for a two month work package, will provide skewed monthly data if the resources in the work package are not loaded equally for each month. It will give an artificial positive or negative schedule variance the first month and vice versa the next month.

Additional earned value methodologies, such as the weighted milestone methodology and percent complete with milestone gates may be utilized. The weighted milestone method allows value to be earned based on the resource value in each month, which eliminates artificial schedule variances.

For all discrete measurable work packages or control accounts, there must be an activity in each month to measure. Gaps, in which there is nothing to measure in a month or months is not acceptable.

For subcontractors that have a fixed price contract with the prime contractor, the expectation is that there will be no cost variance. The ACWP reported on the CPR will equal the BCWP earned, regardless of the payment schedule with subcontractor.

 

6

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

Principle 6a: Analyze Significant Variances From the Plan

The purpose of this principle is to ensure that the earned value data is analyzed by the contractor and reported to the customer. The 7 Principles programs should be able to calculate the cost variance (BCWP minus Actual Cost of Work Performed (ACWP) and the schedule variance (BCWP minus BCWS) at least on a cumulative basis. It is recommended that variances be calculated on a current month basis also. The EVM system should also provide both monthly and cumulative Cost Performance Index (BCWP divided by ACWP) and Schedule Performance Index (BCWP divided by the BCWS). This data should be provided at the control account level and at the roll up levels and it needs to be in a format for Control Account Managers and program management to be able to utilize in managing the work.

It is also recommended that the To-Complete Performance Index (TCPI) be included in the Control Account Manager performance report. The TCPI is a valuable index that calculates the cost performance the control account needs to perform at in order to complete the work within the current reported EAC. When the TCPI is compared against the cumulative CPI it gives a good indication whether or not the current EAC is reasonable. For example, if a cumulative CPI is .85 and the TCPI calculates to equal 1.15 that is the performance factor that work would need to perform at in order to meet the current EAC. If the cumulative CPI is .85 then it can be determined that the current EAC might not be reasonable. It allows management and Project Controls the opportunity to question the Control Account Manager as to the validity of the current EAC. As a rule in thumb if the deviation between the CPI and the TCPI is greater than .2 then the CAM should reassess the control account EAC.

These reports, which should be provided monthly, should also include the current Budget at Completion (BAC) and the current Estimate at Completion (EAC). In addition, it would be a plus if the CAM could see a report with their time-phased spread of hours and dollars for their budget plan (BCWS), work accomplished (BCWP) and actual costs (ACWP).

For all variances that exceed the contractual variance threshold will include a description of what caused the variance, impact to the control account and the program, and a corrective action.

Principle 6b: Prepare an Estimate at Completion Based on Performance to Date and Work to be Performed

Providing an updated EAC is a prime concern of the customer and the contractor. Therefore a robust EAC process should be in place whether the program is ANSI compliant or not.

Based on the performance to date the Estimates at Completion can be updated on a monthly basis by the Control Account Manager in the scheduling tool during the status process or in the cost/EVM tool at the end of the month’s process prior to submittal of the EVM report. The EAC is an element of the performance measurement system that needs to accurately reflect the contractor’s best estimate of what it will cost to complete the project.

Program management should be able to validate control account manager’s EACs by looking at performance indices, such as the To-Complete Performance Index, as well as independent statistical EACs.

Principle 7: Use EVMS Information in the Company’s Management Processes

One of the key areas that concerns government Program Management Offices (PMO) is the level of importance that contractor’s place on EVM as a management tool. During a site visit, such as conducting an Integrated Baseline Review, the PMO gauges what the interest, knowledge, and most importantly, the usage of the performance measurement data in managing the program. They want to know that the managers on the program, including the program manager, have received some earned value training. The level of involvement and use of the EVM data to manage their schedule, cost and technical issues is ascertained by questions. The PMO can also tell by how robust the EACs are and if the variance narratives are being written with impacts to the program and corrective actions being monitored by the contractor. It is important that the contractor’s management team, including the Program Manager, utilize the data from the performance measurement system as a management tool. They should be knowledgeable and understand the data. They should know what is causing the variances and ensure that the

 

7

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

variance narratives are written properly and answer what the issues, impacts and corrective actions are. They should be able to demonstrate that they use the information to assist them in the management decision process. They should hold their Control Account Managers accountable to use the data and write clear proper variance analysis report (VAR). If the Control Account Manager does not write a proper VAR then Project Controls needs to help instruct them how to do it. It is recommended that prior to the Earned Value report be sent to the government that the Program Manager has a meeting with the Control Account Managers and Project Control and review the data and ensure that the variance analysis is complete and that the Program Manager agrees with it. This review is also used to ensure that the EACs are acceptable to the Program Manager, who is ultimately responsible for the program EAC. This is an efficient and quick way to make any adjustments to the earned value report since all the key personnel are in one room. If the data appears to be unreliable then the PM needs to hold Project Controls accountable to ensure that they are using discipline in changing baselines, assessing process properly, and capturing actual costs to ensure that the data that is reported is accurate.

 

8

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

APPENDICES

The following appendices provide further support in understanding the meaning and intent of properly implementing the 7 Principles of EVM.

Appendix 1 is a glossary of the terms used in the Intent Guide.

Appendix 2 is supplemental guidance on EVM implementation. It provides some guidelines on what is expected in the implementation, required documents needed for the Performance Measurement Baseline Review, expected EVM implementation costs, EVM engines functionality needs, explains what is expected in the monthly EVM facilitation, discusses what EVM consultants need to know, and what the expected costs of EVM to BARDA.

Appendix 3 are examples of some of the EVM documents that are needed in an EVM system. There are three documents and they mostly apply to Tier 2 EVM implementations. These documents are samples and are not a reflection of the specific way the document must look. It’s included to provide contractors with an understanding of the type of information that is expected on these forms.

APPENDIX 1: Glossary of Terms

Actual Cost of Work Performed (ACWP)    The costs actually applied and recorded in accomplishing the work performed within a specified period.
Actual Direct Cost    Those costs identified specifically with a contract, based upon the contractor’s cost identification and accumulation system as accepted by the cognizant DCAA representatives. (See Direct Costs).
Advance Agreement (AA)    An agreement between the contractor and the Contract Administration Office concerning the application of an approved earned value management system to contracts within the affected facility.
Authorized Work    That effort which has been authorized and is on contract, or that for which authorized contract costs have not been agreed to but for which written authorization has been received.
Baseline    (See Performance Measurement Baseline).
Budget at Completion (BAC)    The sum of all budgets (BCWS) allocated to the contract. Synonymous with the term Performance Measurement Baseline.

Budgeted Cost for Work

Performed (BCWP)

   The sum of the budgets for completed Work Packages and completed portions of open Work Packages, plus the appropriate portion of the budgets for level of effort and apportioned effort (Also see Earned Value).

Budgeted Cost for Work

Scheduled (BCWP)

   The sum of the budgets for completed Work Packages, planning packages, etc., scheduled to be accomplished (including in-process Work Packages), plus the amount of level of effort and apportioned effort scheduled to be accomplished within a given time period.
Change Order (CO)    A formal authorization by the Procuring Contracting Officer for a change of scope to an existing contract
Contract Modification    A written and binding authorization to proceed created after change proposal negotiations.

 

9

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

Contract Budget Base (CBB)    The negotiated contract cost plus the estimated cost of authorized unpriced work, where:
   (1) Negotiated Contract Cost is that cost on which contractual agreement has been reached. For an incentive contract, it is the definitized contract target cost plus/minus the value of changes which have been priced and incorporated into the contract through contract change order or supplemental agreement. For fixed-fee contracts, it is the negotiated estimated cost. Changes to the estimated cost will consist only of the formal contract modifications or change orders or change in the contract statement of work, not for cost growth, and
   (2) Estimated cost of authorized, unpriced work is the estimated cost (excluding fee or profit) for that work for which written authorization has been received, but for which definitized contract prices have not been incorporated into the contract through supplemental agreement.
Control Account    A management control point at which actual costs can be accumulated and compared to budgeted cost for work performed. A control account is a natural control point for cost/schedule planning and control since it represents the work assigned to one responsible organizational element on one contract work breakdown structure (CWBS) element.
Control Account Manager (CAM)    A member of a functional organization responsible for task performance detailed in a Control Account and for managing the resources authorized to accomplish the tasks.

Control Account Plan (CAP)

Report

   A CAP report is a timephased report which reflects all the work and effort to be performed in a control account. The CAP report will reflect the hours and dollars by element of cost (labor, subcontract, ODC, etc).

Contract Performance Report

(CPR)

   The monthly report submitted to the customer showing the current, cumulative and at completion status, the performance measurement baseline, manpower loading, and a narrative explanation of significant program variances.
Contract Target Cost    The dollar value (excluding fee or profit) negotiated in the original contract plus the cumulative cost (excluding fee or profit) applicable to all definitized changes to the contract. It consists of the estimated cost negotiated for a cost plus fixed fee contract and the definitized target cost for an incentive contract. The contract target cost does not include the value of authorized/un-negotiated work, and is thus equal to the contract budget base only when all authorized work has been negotiated/definitized.
Cost Performance Index (CPI)    An efficiency rating reflecting a project’s budget performance - either over or under. Measured as a ratio of the budgeted value of work accomplished versus the actual costs expended for a given project time period. The formula for CPI is BCWP/ACWP.
Discrete Effort    Program effort that has a measurable output, product or service.
Direct Costs    Those costs (labor, material, etc.) that can be reasonably and consistently related directly to service performed on a unit of work, and are charged directly to the contract, without distribution to an overhead unit.
Earned Value    See Budgeted Cost for Work Performed (BCWP)

Earned Value Management

System (EVMS)

   A project management system utilized for measuring project progress in an objective manner. Combines measurements of scope, schedule, and cost in a single integrated system.

 

10

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

Estimate at Completion (EAC)    A value (expressed in dollars and/or hours) developed to represent a realistic appraisal of the final cost of tasks when accomplished. It’s the sum of direct & indirect costs to date plus the estimate of costs for all authorized Work remaining. The EAC = ACWP + the Estimate-to-Complete.
Estimate to Completion (ETC)    A value (expressed in dollar and/or hours) developed to represent a realistic appraisal of the cost of the work still required to be accomplished in completing a task.
Indirect Costs    Represents those costs, because they are incurred for common or joint objectives, are not readily subject to treatment as direct costs. (See overhead).
Integrated Baseline Review (IBR)   

An Integrated Baseline Review (IBR) also known as Performance Measurement Baseline Review (PMBR) is a formal review led by the Government Program Manager and Technical Support Staff. An IBR is conducted jointly with the Government and their Contractor counterparts.

 

The purpose of an IBR is to: verify the technical content of the Performance Measurement Baseline (PMB); assess the accuracy of the related resources (budgets) and schedules; identify potential risks.

Integrated Master Plan (IMP)    The overall program plan including the work definition, technical approach, performance criteria, and completion criteria.
Integrated Master Schedule (IMS)    The IMS expands the IMP to the work planning level. It defines the tasks, their durations, milestones, milestone dates which relate to the IMP completion criteria, and interdependencies required to complete the program. The IMP and IMS are used to track and execute the program.
Integrated Product Team (IPT)    A grouping of project personnel along project objective lines rather than along organizational lines. Integrated Product Teams are work teams that represent a transition from a functional organization structure to a multi-functional project objective arrangement.
Internal Replanning    Replanning actions performed by the program for remaining effort within the recognized total allocated budget.
Level of Effort (LOE)    Work that does not result in a final product, e. g., liaison, coordination, follow-up, or other support activities, and which cannot be effectively associated with a definable end product process result. It is measured only in terms of resources actually consumed within a given time period.
Management Reserve (MR)    An amount of the total Contract Budget Base (CBB) withheld for management control purposes rather than designated for the accomplishment of a specific task or set of tasks. It is not a part of the Performance Measurement Baseline.
Negotiated Contract Target Cost    The estimated cost negotiated in a Cost Plus Award Fee (CPAF), Cost Plus Fixed Fee (CPFF), Cost Plus Incentive Fee (CPIF) or Fixed Price Incentive Fee (FPIF) contract.
Original Budget    The budget established at, or near, the time the contract was signed, based on the negotiated contract cost.

 

11

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

Overhead    Indirect labor and material, supplies and services costs and other charges, which cannot be consistently identified with individual programs.
Other Direct Costs    A group of accounting elements which can be isolated to specific tasks, other than labor and material. Included in ODC are such items as travel, computer time, and services

Performance Measurement

Baseline (PMB)

   The time-phased budget plan against which contract performance is measured. It is formed by the budgets assigned to scheduled Control Accounts and the allocation of overhead costs. For future effort, not planned to the Control Account level, the performance measurement baseline also includes budgets assigned to higher level WBS elements, and undistributed budgets. It equals the total assigned budget less management reserve.
Performing Organization    A defined unit within the program organization structure, which applies the resources to performs the authorized scope of work.
Planning Package    A logical aggregation of far term work within a Control Account that can be identified and budgeted but not yet defined into Work Packages.
Reprogramming    Replanning of the effort remaining in the contract, resulting in a new budget allocation which exceeds the contract budget base. The resulting baseline is called an Over Target Baseline (OTB).
Responsible Organization    A defined unit within program’s organization structure that is assigned responsibility for accomplishing specific tasks.
Risk Register    Is a tool commonly used in project planning and organizational risk assessments. It is often referred to as a Risk Log. It is used for identifying, analyzing and managing risks.

Schedule Performance Index

(SPI)

   An efficiency rating reflecting how quickly or slowly project work is progressing. Measured as a ratio of work accomplished versus work planned for a given period of time. The formula for SPI is BCWP/BCWS.
Significant Variances    Those differences between planned and actual cost and schedule performance which require further review, analysis, or action. Appropriate thresholds are established as to the magnitude of variances which will require variance analysis.
Statistical Estimate at Completion    Is a single point estimate that can be quickly prepared and used to test the reasonableness of the current cost estimates and budget and to indicate when a comprehensive EAC should be prepared
Time-Phased S/P/A Report    Provides the timphased budget, performance (earned value) and actual costs at a specific level. It may be at the reporting level, control account, and/or work package level. In all cases the report will also provide the data at the total project level.

To-Complete Performance Index

(TCPI)

   An efficiency rating that provides a projection of the anticipated performance required to achieve the EAC. TCPI indicates the future required cost efficiency needed to achieve a target EAC (Estimate At Complete). Any significant difference between TCPI and the CPI needed to meet the EAC should be accounted for by management in their forecast of the final cost.

 

12

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

Total Allocated Budget (TAB)    The sum of all budgets allocated to the contract. Total allocated budget consists of the performance measurement baseline and all management reserve. The total allocated budget will reconcile directly to the Contract Budget Base (CBB). Any differences will be documented as to quantity and cause.
Undistributed Budget (UB)    Budget applicable to contract effort which has not yet been identified to WBS elements at or below the lowest level of reporting to the Government.
Variance Analysis Report (VAR)    The internal report completed by the Control Account Manager and submitted, through the Intermediate Manager, to the program manager for those Control Accounts which have variances in excess of established thresholds.
Variances    (See Significant Variances).

Work Authorization Document

(WAD)

   A form used to formally authorize and budget work to the Control Account Manager. This document must include, as a minimum, the Control Account number, Statement of Work, scheduled start and finish dates, budget, and the identity of the CAM. It must be approved by Intermediate Manager, and be agreed to by the Control Account Manager.

Work Breakdown Structure

(WBS)

  

A product-oriented, family-tree composed of hardware, software, services, data and facilities which results from system engineering efforts. A work breakdown structure displays and defines the product(s) to be developed and/ or produced and relates the elements of work to be accomplished to each other and to the end product.

 

Program WBS. The work breakdown structure that covers the acquisition of a specific defense material item and is related to contractual effort. A program work breakdown structure includes all applicable elements consisting of at least the first three levels of the work breakdown structure and extended by the program manager and /or contractor(s). A program work breakdown structure has uniform element terminology, definition, and placement in the family tree structure.

 

Contract WBS (CWBS) The complete WBS for a contract, developed and used by a contractor within the guidelines of MIL-Handbook 881 (latest revision) or NASA WBS Handbook (insert reference) or other customer guidelines and according to the contract work statement. It includes the approved work breakdown structure for reporting purposes and its discretionary extension to the lower levels by the contractor, in accordance with MIL-Handbook 881 and the contract work statement. It includes all the elements for the products (hardware, software, data, or services) which are the responsibility of the contractor.

Work Packages   

Detailed short-span jobs, or material items, identified by the contractor for accomplishing work required to complete the contract. A Work Package has the following characteristics.

 

It represents units of work at levels where work is performed.

 

It is clearly distinguishable from all other work packages.

 

It is assignable to a single organizational element.

 

It has scheduled start and finish dates and, as applicable, interim milestones, all of which are representative of physical accomplishment.

 

13

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

  

It has a budget or assigned value expressed in terms of dollars, man-hours or other measurable units.

 

Its duration is limited to a relatively short span of time or it is subdivided by discrete value milestones to facilitate the objective measurement of work performed.

 

It is integrated with detailed engineering, manufacturing, or other schedules.

Work Package Budgets    Resources which are formally assigned by the CAM to accomplish a Work Package, expressed in dollars and/or hours.

 

14

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

Appendix 2 Supplemental EVM Implementation Guideline

Implementation of a 7 Principles of EVM system should be less expensive than if there was an ANSI/EIA-748. There is no need for the system to have to go through an EVM compliance review, plus the level of documentation should be streamlined.

The implementation should include:

 

   

EVM Process flows that reflect how a company will build and maintain the EVM system. (EVM Procedures may also be included if the cost associated with them is reasonable)

   

EVM engine tool and a schedule tool. It is not necessary to load the schedule tool, such as Microsoft Project, with resources. This adds an extra strep, additional costs and little to no value. It is recommended that all resource information be loaded in the EVM engine and leave the schedule tool to what it does best, measure progress through time (duration).

   

The EVM Engine needs to be integrated with the company’s accounting system.

Documentation needed for the Performance Measurement Baseline Review (PMBR)

 

   

WBS Dictionary/Control Account Work Authorization Documentation

   

Integrated Master Schedule

   

Responsibility Assignment Matrix

   

Control Account Plans

   

PMB Log

   

Baseline Revision Documents

   

Risk Register

EVM IMPLEMENTATION COSTS

The cost for an implementation depends on the size of the contract and the tier level of EVM.

Tier 2 (projects greater than $25M) Implementation costs should range $75K-$150K

Tier 3 (projects less than $25M)

Implementation costs should range ($50K - $100K)

EVM ENGINES/TOOLS

Depending on the size of the contract would predicate the level of functionality that would be needed. For Tier 2 contracts a larger, more robust EVM engine would be needed. For the Tier 3 small contracts MS Project or the MSP wrap-around would probably suffice although the more robust EVM engines can be used also.

Tier 2

It is recommended that one of the larger and flexible EVM engines be utilized. The tool should have the flexibility to be able to download data from MS Project and be able to upload or input budget data to provide time-phased budget information down to the work package level. It should be able to incorporate the companies Organization Breakdown Structure. It should be able to maintain baseline, actual costs, forecast and performance periodic data. It should be able to forecast Estimate to Complete with the ability to set up different rate tables if necessary. It should have the capability to use all earned value methodologies. It should be able to print many types of EVM reports that can provide information to the Control Account Managers (CAM) and Program Managers (PM), as well as, the Contract Performance Report (CPR) and the Control Account Plans (CAP) that are contract deliverables.

 

15

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

Tier 3

For Tier 3 projects, a company can certainly utilize an EVM engine as listed above or a less robust, less expensive EVM engine that provides the CPR and timephased S/P/A report. It may also use the Microsoft Project wrap-around tools of which there are several on the market. These tools also will provide the CPR and timephased S/P/A report for contract deliverable purposes.

EVM FACILITATION

EVM facilitation pertains to the monthly process to include:

 

   

Schedule Status

   

Integration of accounting data into EVM engine

   

Run monthly reports for Control Account Managers (Tier 2 only)

   

Prepare the monthly Contract Performance Report (CPR) Formats 1 and 5

   

Run the Control Account Plans for both internal and external (contract requirement)

   

PMB Change Control

Depending on the size of contract, a contractor should have an EVM/cost analyst and schedule analyst for a Tier 2 contract and one combined cost/schedule analyst for a Tier 3 contract. The costs for a schedule analyst on a yearly basis for an employee hire should be equal to or less than $135K. For a cost analyst it should be equal to or less than $120K. If a company is bringing in a contractor to provide staff implementation the costs should be up to $135/hr for a schedule analyst and $120/hr for an EVM/cost analyst.

EVM CONSULTANTS

There may be the need to bring in consultants to help set up your EVM system and perhaps provide EVM staff augmentation to provide the monthly facilitation. Make sure that you shop around and get several quotes. Also make sure that the consultants understand the statement of work pertaining to the BARDA EVM requirements. Most EVM consultants are used to working with companies that have a requirement to implement an ANSI/748 compliant EVM system per the DoD requirements and it is important that they have an understanding of what is required in a 7 Principles EVM implementation so that they don’t propose much more complex EVM system than is needed. Please be advised that the government will only accept reasonable costs associated with implementing a 7 Principles of EVM system.

COST OF EVM

BARDA is working diligently to keep the costs of EVM implementation and facilitation at a reasonable level. Since the goal at BARDA is to provide an integrated, systematic approach to the development and purchase of the necessary vaccines, drugs, therapies, and diagnostic tools for public health medical emergencies, it is imperative that the funds for product development are used for that such purpose. BARDA expects the costs for implementation and monthly facilitation of EVM to range 1%-2% of development budget. This is ratified by the white paper by Dr. Christenson titled “The Costs and Benefits of the Earned Value Management Process”.

 

16

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

Appendix 3 Sample EVM Documents

WBS 1.4.1.x Cardiac (QTc) Safety

Description

Study Title: “A Phase 1 study to assess the cardiovascular safety of intravenous (IV) Panaceomycin in volunteers” (Thorough QT Study)

We will conduct a thorough evaluation of the cardiac effect of Panaceomycin Injection via a randomized, double-blind crossover study. A total of 100 participants (18-22 per arm) will randomize to one of five study arms to receive in a double-blind fashion a single IV infusion of either Panaceomycin Injection 10 mg/kg, Panaceomycin Injection at a supra-therapeutic dose, ciprofloxacin (positive control), or placebo. 12-Lead digital ECGs will be collected in triplicate via Holter monitor from each participant during dosing. Seven days after dosing, participants will be re-randomized to receive another treatment. ECGs will be collected and analyzed. A full statistical analysis and expert ECG report will be generated. Serum PK samples will also be collected at ECG collection time points and analyzed to confirm exposure.

Targeted Outcome: No evidence of delay in cardiac repolarization induced by Panaceomycin as shown by analysis of the QT interval.

 

17

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

Subcontractors

 

Vendor   

Area of Responsibility

Phase Research   

¡       

   Study Documentation Design and Development
    

¡       

   Clinical Monitoring: Includes site initiation, interim, and close-out monitoring visits,
    

¡       

   Pharmacovigilence
    

¡       

   Data Management: Includes build and maintenance of electronic case report forms (eCRFs); data query generation and resolution
    

¡       

   Biostatistics
    

¡       

   Medical Writing:
    

¡       

  

Project Management: The Project Manager will actively facilitate Phase Research’s interaction with the research site and provide close monitoring oversight in conjunction with the assigned CRA. Project Management will also assist in the finalization of all applicable study documents and provide coordination between study vendors.

    

¡       

   Pass-through Expenses
       

 

Travel for CRA monitoring visits to clinical sites, shipping and printing costs

 

    

¡       

 

  

Investigator Grants

 

Energetics   

Core Cardiac Lab

 

TBD   

Clinical study site(s)

 

Pulse Tech   

To provide Central Lab services

 

Analyx   

To perform PK analyses

 

Claritron   

To write the PK report

 

Obelisk   

To label and distribute study drug product

 

Consultants

 

Joe Josephs  

Internal Medical Monitor:

 

Sponsor medical oversight

Rolf Xerd  

Pharmacologist:

 

Design and analysis consultation for PK parameters and analysis

Julie Simms  

Clinical Trials Manager

 

Phil Thomas  

Medical Writer

 

Claire Cools  

SAS Programmer

 

Mary Doe  

Clinical Contracts

 

Jim Dodds  

Supply Chair Manager

 

 

18

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

Milestones, EV at Milestones

Consultants and Phase Project Management will earn value as Level of Effort activities. All other costs will earn value according to the schedule below.

 

Signed Study Protocol

 

           10%       

First participant dosed

 

           20%       

40 % Enrollment

 

           35%       

70% Enrollment

 

           50%       

Last participant procedure (Treatment phase)

 

           60%       

Last participant follow-up

 

           70%       

Database lock

 

           80%       

Clinical Study Report

 

           90%       

Transferred Trial Master File

 

           100%         

Deliverables

 

  1. Signed Study Protocol
  2. Top-line data
  3. Signed Clinical Study Report

External Dependencies

 

  1. Top-line Data from an External Clinical Study Identifying Panaceomycin Maximum Tolerated Dose as a single dose in Humans. The Maximum Tolerable Dose will be defined in a study not included in the BARDA contract. This dose will be used in selecting the Supra-therapeutic dose in this Thorough QT Study.
  2. Successful production of cGMP lot of Panaceomycin.
  3. Enrollment and retention of study participants.

 

Sample WBS Dictionary

 

19

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

 

 

Work Authorization

 

   

Project/Contract

 

  BARDA   WBS #   1.1.6.2
   

WBS description

 

  Program Management, Meetings and Control
   

Authorization version #

 

  1   Scheduled Start   Oct 2010   Scheduled Finish   Sep 2012

 

Work Description

 

         

 

             
      staff will manage the integration and performance control of the program.

 

For further detail, see description of scope for WBS 1.1.6.2

                       
                                         
Budget            
    Labor   $250,000            
    Subcontractors   $            
    Consultants   $            
    Material   $            
    Travel   $            
    Total     $250,000            

 

Approvals

 

    Control Account Manager   Name:   Benjamin Gay   Signature:       Date:    
                   
                                         
    Project Manager   Name:   Ronald Smith   Signature:       Date:    
                   
                                         
    Finance   Name:   Denise Blessi   Signature:       Date:    
                     
                                         

 

Sample Work Authorization Document

 

20

 


7 Principles of EVM Tier 2 System Implementation Intent Guide

 

   CAP:        1.1.1 Drug Production    Month End:       3/31/2011               

 

Control Account

Performance

                           
        Month 1     Month 2     Month 3     Month 4     Month 5     Month 6     Month 7     Month 8     Month 9     Month 10     Month 11     Month 12     Total      

BCWS

      200         30         30         40         60         80         60         80         15         25         30         25         675   

BCWP

      10         190         60                                                                                    

ACWP

      12         190         60                                                                                    

SV

      -190         160         30                                                                                    

CV

      -2                                                                                                  

 

Resource Summary

                           
        Month 1     Month 2     Month 3     Month 4     Month 5     Month 6     Month 7     Month 8     Month 9     Month 10     Month 11     Month 12     Total  

Labor

      10         10         10         10         10         10         10         10         10         10         10         10         120   

Sub DB

              20         20         30                                                                         70   

Sub DP

                                      50         70         50         70                                         240   

Sub Pack

                                                                                     20         15         40   

Material

      190                                                                                                 190   

ODC

                                                                             10                         15   

BCWS

      200         30         30         40         60         80         60         80         15         25         30         25         675   

 

Work Package

Summary

                           
    EVM       Month 1     Month 2     Month 3     Month 4     Month 5     Month 6     Month 7     Month 8     Month 9     Month 10     Month 11     Month 12     Total  

Sub Contract

Management

    LOE         10         10         10         10        10         10         10         10         10         10         10         10         120   

Purchase Materials

    0/100         190                                                                                                190   

Manufacture Drug

Substance

    MS                 20         20         30                                                                         70   

Manufacture Drug

Product

    MS                                         50         70         50         70                                         240   

Ship

    Units                                                                                10                         15   

Package & Store

    Units                                                                                        20         15         40   

BCWS

      200         30         30         40         60         80         60         80         15         25         30         25         675   

Sample Control Account Plan

 

21