001-33228
(Commission File Number)
|
20-0065053
(IRS Employer Identification No.)
|
|
Zion Oil and Gas, Inc.
|
|||
|
Date: June 1, 2011
|
By:
|
/s/ Richard J. Rinberg
|
|
|
Richard J. Rinberg
|
|||
|
Chief Executive Officer
|
|||
|
From waypoint
|
254000/707000
|
thence West
|
|
To waypoint
|
246002/707000
|
thence North-West
|
|
To waypoint
|
244869/711000
|
thence East
|
|
To waypoint
|
246000/711000
|
thence North
|
|
To waypoint
|
246682/732827
|
thence North-East
|
|
To waypoint
|
259502/735000
|
thence South
|
|
To waypoint
|
259507/732224
|
thence South along the
International border with
Jordan and back
|
|
To waypoint
|
254000/707000
|
|
1.
|
The area of the license is defined solely by the above stated waypoints. It is hereby specified that in the event of a discrepancy between maps submitted by the Licensee and the above description then the waypoints prevails
|
|
2.
|
The issuance of this license shall not make redundant- receiving any permit, confirmation or license from any public body as required by law .In addition this license shall not be deemed to make redundant arranging all aspects necessary by law through any public or private entity, including without deviating from the generality of the above, through the Israel Land Authority, Antitrust Authority, Ministry of Interior and the Ministry of Environmental Protection.
|
|
1.
|
Within 3 months from receiving the license Zion shall prepare a feasibility study and execute a contract with a seismic contractor to carry out a new 2D seismic survey for a total length of approximately 20 kilometers in the license area.
|
|
2.
|
Within 6 months from receiving the license Zion shall prepare a gravimetric data analysis to identify salt formations in the license area
|
|
3.
|
Within 8 months from receiving the license prepare a geochemical analysis of the source rocks from late Cretaceous age.
|
|
4.
|
Within 9 months from receiving the license prepare a new 2D seismic survey and submit the data and summary report.
|
|
5.
|
Within 12 months from receiving the license process the data of the new survey and submit the data and summary report.
|
|
6.
|
Within 16 months from receiving the license prepare an interpretation of the new seismic survey, integrate with existing data, prepare formation maps regarding time and depth and submit a summarized geophysical report for the entire license area.
|
|
7.
|
Within 18 months from receiving the license submit a drilling prospectus.
|
|
8.
|
Within 18 months from receiving the license execute a contract with a drilling contractor to drill to a depth of approximately 5000 meters.
|
|
9.
|
Within 24 months from receiving the license -drill to a depth of approximately 5000 meters.
|
|
10.
|
Within 4 months from completion of drilling the well submit a work plan for further activities.
|