EX-10.2 6 sirg_ex102.htm ST. GENEVIEVE RESOURCES EMERALD MINE TECHNICAL REVIEW sirg_ex102.htm
 
 

 
ST. GENEVIEVE RESOURCES LTD.
EMERALD ISLE MINE

 
 
 

TECHNICHAL REVIEW,
EVALUATION  OF ALTERNATIVES AND
PROPOSAL FOR ADDITIONAL WORK
 
 
(BEHRE DOLBEAR PROJECT 06-072)

 
 
 
 
 

December 15, 2006

 
 
 
Prepared By:
 
BEHRE DOLBEAR & COMPANY (USA), INC.
999 EIGHTEENTH STREET, SUITE 1500
DENVER, COLORADO 80202
(303) 620-0020

 
 
 

 

Behre Dolbear
founded 1911 MINERALS INDUSTRY CONSULTANTS

Behre Dolbear is the preeminent international minerals industry consultancy responding to the needs of its clients by providing superior and comprehensive business, management, technical, and environmental advisory and consulting services while adhering to the highest ethical and professional standards.

Behre Dolbear & Company, Inc.
Denver, Colorado
 
 
 
 
 Behre Dolbear & Company (USA), Inc.
Denver, Colorado
New York, New York
 
 Behre Dolbear & Company Ltd.
Toronto, Ontario
Vancouver, British Columbia
     
Behre Dolbear de Mexico, S.A. de C.V.
Guadalajara, Mexico
  Behre Dolbear Australia Pty. Ltd.
Sydney, Australia
     
Behre Dolbear International, Ltd.
London, United Kingdom
 
Behre Dolbear Chile y Cia. Ltda.
Santiago, Chile
     
Behre Dolbear Asia, Inc.
Denver, Colorado
Beijing Hong Kong
 
Behre Dolbear Capital, Inc.
Denver, Colorado
New York, New York
     
 
 
OUR PEOPLE HAVE RUN THE WORLD'S MINES

 
 

 
Behre Dolbear
BEHRE DOLBEAR & COMPANY (USA), INC.
 founded 1911 MINERALS INDUSTRY CONSULTANTS
 
 
December 15, 2006


Mr. Bryan Wilson
President
St. Genevieve Resources Ltd.
141 Adelaide Street West, Suite 901
Toronto, Ontario M5H 3L9
Canada
 
 
RE:
Behre Dolbear's Report "Emerald Isle Mine Analysis and Review for the Re-Start of Operations" - J06-072

Dear Mr. Wilson:

Attached please find the above referenced report from Behre Dolbear. It has been a pleasure to have worked with St. Genevieve Resources and we look forward to a continuing working relationship in the near future.

We hope you find our report helpful. If you wish to discuss the report in greater detail, please call me at (215) 702-8974.


Sincerely,

 
BEHRE DOLBEAR & COMPAI Y (USA), INC.
 
/s/ Donald K. Cooper
Donald K. Cooper
President
 
100 Park Avenue, Suite 1600 New York, New York 10017 212-684-4150  fax 212-684-4438
BEIJING DENVER GUADALAJARA HONG KONG LONDON NEW YORK SANTIAGO SYDNEY TORONTO VANCOUVER
www.dolbear.com

 
 

 
TABLE OF CONTENTS
 
1.0  EXECUTIVE SUMMARY   1
  1.1  INTRODUCTION    1
  1.2 STATUS AND ONGOING WORK 4
  1.3  GEOLOGY   6
  1.4 MINERAL INVENTORY AND RESERVES    6
  1.5 MINING  7
  1.6 PROCESSING   7
  1.7 INFRASTRUCTURE 8
  1.8 ENVIRONMENTAL  9
  1.9 MINERAL TITLE, LAND, AND WATER RIGHTS 10
  1.10 CAPITAL COSTS    10
  1.11 OPERATING COSTS  11
  1.12 MARKETING   11
  1.13 RISK ANALYSIS  12
2.0 DISCLAIMER   14
  2.1 ELECTRONIC DISCLAIMER   14
3.0 INTRODUCTION   15
  3.1 GENERAL 15
  3.2 BACKGROUND 15
  3.3 SCOPE OF WORK 16
  3.4 PROJECT PERSONNEL 17
  3.5 PROCEDURES 20
  3.6 ACKNOWLEDGEMENTS 21
  3.7 UNITS OF MEASUREMENT AND CURRENCY 21
4.0 GEOLOGY 22
  4.1 GEOLOGICAL SETTING   22
    4.1.1 Regional Geology  22
    4.1.2 Property Geology   24
  4.2 MINERALIZATION   26
    4.2.1 Types of Mineralization  26
    4.2.2 Genetic Model  27
  4.3
GEOCHEMISTRY OF THE EMERALD ISLE COPPER DEPOSIT
29
5.0  MINERAL RESOURCES 31
  5.1 INTRODUCTION 31
  5.2   DRILLING DATA   31
  5.3    ELECTRONIC DATA BASE  32
  5.4  DENSITY MEASUREMENTS  32
  5.5  GEOLOGICAL INTERPRETATION 32
  5.6    ASSAY STATISTICS   33
  5.7    COMPOSITING  33
  5.8  BLOCK MODEL    33
  5.9   CLASSIFICATION OF MINERAL RESOURCES    34
  5.10    POTENTIALLY MINABLE RESOURCES  35
  5.11
RISKS AND CONCLUSIONS
41
 
 
i

 
       
6.0  MINING 43
  6.1  INTRODUCTION  43
  6.2 PIT SLOPE DESIGN 43
   6.3  HAUL ROAD DESIGN  48
   6.4 WASTE DUMP DESIGN  48
  6.5 CONTRACT MINING 48
  6.6  DILUTION    49
  6.7 PRE-STRIPPING    50
  6.8   MINE STAFFING  50
  6.9 CAPITAL AND OPERATING COSTS 50
  6.10 
RISK ANALYSIS 
51
7.0 PROCESSING      52
  7.1 INTRODUCTION    52
  7.2 MINERAL PROCESSING AND METALLURGICAL TESTING   53
    7.2.1 TSC Enterprises (Arimetco)   53
    7.2.2 SGV-MSRDI   55
    7.2.3 SGV - Metcon Research 56
  7.3 ORE MINERALOGY 67
  7.4 PROPOSED FLOWSHEET 67
  7.5 RECOVERY 68
  7.6 PRODUCTION SCHEDULE 68
  7.7 REAGENTS AND CONSUMABLES  69
  7.8 METALLURGICAL ENGINEERING 69
  7.9 MANPOWER REQUIREMENTS AND WORK SCHEDULES   69
  7.10 CATHODE QUALITY  69
  7.11 COMMENTS AND RISK ANALYSIS   70
8.0  INFRASTRUCTURE  72
  8.1 INTRODUCTION 72
  8.2 TRANSPORTATION    72
  8.3 WATER SUPPLY 72
  8.4  ELECTRIC POWER SUPPLY 73
  8.5   COMMUNICATIONS  73
  8.6   SURFACE FACILITIES 74
  8.7 MINERAL TITLE, LAND, AND WATER RIGHTS 74
9.0 ENVIRONMENTAL    77
  9.1  INTRODUCTION  77
  9.2  BACKGROUND  77
  9.3  GENERAL DESCRIPTION 77
  9.4  REQUIRED PERMITS AND STATUS 78
  9.5  DOCUMENTS REVIEWED   80
  9.6  CONCLUSIONS 81
  9.7  ENVIRONMENTAL RISK ANALYSIS   81
10.0  CAPITAL COSTS  82
  10.1 INTRODUCTION AND SUMMARY 82
  10.2 MINE CAPITAL COSTS   82
  10.3 PROCESS CAPITAL COSTS    85
 
 
ii

 
  10.4 GENERAL AND ADMINISTRATIVE COSTS   86
11.0 OPERATING COSTS
  11.1   INTRODUCTION  87
  11.2 PROPERTY OPERATING COSTS 87
  11.3 MINE OPERATING COSTS   87
  11.4 PROCESSING   87
  11.5   GENERAL AND ADMINISTRATIVE   88
12.0 MARKETING EMERALD ISLE SX/EX CATHODES     92
  12.1   SUMMARY AND INTRODUCTION    92
  12.2   BACKGROUND  92
  12.3   CATHODE PRODUCTION 92
  12.4 CATHODE QUALITY 93
  12.5 CATHODE SALES  93
  12.6  TRANSPORTATION  94
  12.7   CUSTOMER CHOICE 96
  12.8 SALES RETURN AND REVENUE   97
13.0   PROJECT ECONOMICS   98
  13.1  INTRODUCTION     98
  13.2  METAL PRICES  99
  13.3  FINANCIAL ANALYSIS   99
  13.4  SENSITIVITY ANALYSIS     100
14.0    STATUS AND ONGOING WORK   102
 
         
 
APPENDIX 1.0  VALLS REPORT  A1-1
APPENDIX 2.0  MOUNTAIN STATES RESEARCH & DEVELOPMENT INC. METALLURGICAL TESTING     A2-1
APPENDIX 3.0  KD ENGINEERING CAPITAL COST ESTIMATE   A3-1
APPENDIX 4.0 MONTGOMERY WATSON HARZA CAPITAL COST ESTIMATE   A4-1
APPENDIX 5.0 KD ENGINEERING OPERATING COST REPORT  A5-1
APPENDIX 6.0  MINING CONTRACTOR BIDS A6-1
APPENDIX 7.0 EMERALD ISLE CASE 1, CASE 2, AND CASE 3 SPREADSHEETS A7-1
                                                                        
 
iii

 
 
LIST OF TABLES
 
Table 1.1  Emerald Isle Resource Summary     7  
Table 1.2 Emerald Isle Capital Cost Summary     11  
Table 1.3 Emerald Isle Average Project Operating Costs      11  
Table 4.1 Summary of Multi Element Analysis Ore and PLS (10,000 ppm = 1.0%)     30  
Table 5.1 Emerald Isle Indicated Global In-situ Resource      35  
Table 5.2  Emerald Isle Inferred Global In-situ Resource      35  
Table 5.3     Economic Parameters         36  
Table 5.4   Emerald Isle Production Schedule Case 1 - $1.75 Cu and 330,000 tpy Ore Production     39  
Table 5.5 Emerald Isle Production Schedule Case 2 - $2.75 Cu and 700,000 tpy Ore Production     40  
Table 6.1  Heap and Waste Dump Capacity      46  
Table 6.2 Pre-production and Post-production Mining Capital (US$000)      50  
Table 7.1 Arimetco Production Record      53  
Table 7.2    Screen Analysis Emerald Isle Ore Sample       57  
Table 7.3 Screen Analysis "As Received Head Sample" Emerald Isle Mine     58  
Table 7.4 Bottle Roll Acid Consumption Test Emerald Isle Pit Sample 2006     60  
Table 7.6   Emerald Isle Metallurgical Forecast and Production Case 1 (approximately) 1,000 stpd $2.00 per pound of Copper      68  
Table 7.7 Process Reagents and Consumables Case 2 (approximately) 2,000 stpd     69  
Table 7.8  Certificate of Analysis Arimetco Cathode Case No. 676      70  
Table 8.1 Fresh Water Wells Emerald Isle Mine      73  
Table 8.2 Unisource Power Rates           73  
Table 8.3 List of Mineral Claims SGV Emerald Isle Property      75  
Table 10.1   Emerald Isle Capital Costs       83  
Table 10.2  Emerald Isle Capital Costs       84  
Table 11.1 Emerald Isle Operating Cost Summary - Case 1      89  
Table 11.2 Emerald Isle Operating Cost Summary - Case 2       90  
Table 11.3 Emerald Isle Operating Cost Summary - Case 3     91  
Table 12.1 Cathode Truck and Rail Costs     95  
Table 13.1 Result of Sensitivity Analysis - Case 3      101  
 
 
 
iv

 
 
LIST OF FIGURES
 
Figure 4.1.   Regional Geology of the Emerald Isle Area, Mohave County, Arizona       23
Figure 4.2.   Property Geology           25
Figure 5.1.  Final Pit Designs With Haulage Road Designs        37
Figure 5.2.    Final Pit Designs With Haulage Road Designs    38
Figure 6.1.   Site Plan and Existing Topography       44
Figure 6.2.  Heap Location    45
Figure 6.3.   Waste Stockpile Location    47
Figure 7.1.    Cyprus Bagdad Bottle Roll Leach Tests      54
Figure 7.2.    Cyprus Bagdad Column Leach Tests      55
Figure 7.3.   Cumulative Weight Percent Passing Versus Particle Size - Emerald Isle - Assay Screen Analysis          59
Figure 7.4.   Indicated Cumulative Percent Copper Extraction Versus Time - Column Leach Study, St. Genevieve Resources, Ltd. - Crush Size Study - Bulk Sample El-060706-1      62
Figure 7.5. Indicated Cumulative Percent Iron Extraction Versus Time - Column Leach Study, St. Genevieve Resources, Ltd. - Crush Size Study - Bulk Sample El-60706-1    62
Figure 7.6.    Pregnant Leach Solution pH Versus U.S. Time - Column Leach Study, St. Genevieve Resources Ltd. - Crush Size Study - Bulk Sample El-060706-   63
Figure 7.7.  Cumulative Gangue Sulfuric Acid Consumption Versus Time - Column Leach Study, St. Genevieve Resources Ltd. - Crush Size Study - Bulk Sample El-060706-1      63
Figure 7.8. Indicated Cumulative Percent Copper Extraction Versus KL Lixiviant/Tonne of Solids - Column Leach Study, St. Genevieve Resources Ltd. - Crush Size Study - Bulk Sample El-060706-1     63
Figure 7.9. Indicated Cumulative Percent Zinc Extraction Versus Time - Column Leach Study, St. Genevieve Resources Ltd. - Crush Size Study - Bulk Sample El- 060706-1   64
Figure 7.10.   Cumulative Gangue Sulfuric Acid Consumption Versus Time - Column Leach Study, St. Genevieve Resources Ltd. - Crush Size Study - Bulk Sample El-060706-1    65
Figure 7.11.   Pregnant Leach Solution Oxidation-Reduction Potential (mV) Versus Time -Column Leach Study, St. Genevieve Resources Ltd. - Crush Size Study - Bulk Sample El-060706-1      65
Figure 7.12.   Cumulative Percent Moisture Under Leach Versus Time - Column Leach Study, St. Genevieve Resources Ltd. - Crush Size Study - Bulk Sample El- 060706-1    66
Figure 7.13.  Indicated Cumulative Percent Zinc Extraction Versus KL Lixiviant/Tonne of Solids - Column Leach Study, St. Genevieve Resources Ltd. - Crush Size Study - Bulk Sample El-060706 1   66
 
 
v

 
 
1.0     executive summary
 
1.1     introduction
 
The Emerald Isle Mine classified as an exotic copper deposit, is hosted in the basal 25 million year old Gila Conglomerate on the pediment of the Cerbat Mountain range in north western Arizona. The purpose of this report is to present the status of the Emerald Isle Mine Property, a summary of the work carried out to date, a summary of the various development issues needed to be considered, and the status of the classification of the mineral resources on the property. Based upon the supporting information included in historical data and newly constituted resource estimate, Behre Dolbear has developed a Phase 1 assessment of current plans for mining, processing, and environmental considerations. This Phase 1 assessment has determined the technical and economic viability of the current mineral inventory under various pricing scenarios and operational and cost assumptions. The Phase 1 assessment has not sought to optimize the operation nor has the mineral content of either the historical tailings or on-site low grade stockpiles been verified. From the aforementioned data, new capital and operating costs have been developed by K D Engineering (Mineral Industry Consulting and Design Services) and MWH Americas, Inc. (Civil Engineering Services) at a pre-feasibility level of accuracy for inclusion in this report. Finally, a current financial analysis has been prepared which explores project sensitivity and reports discounted cash flow (DCF) and an undiscounted net present value (NPV). Three cases or alternatives are presented for review.

This report develops the indicated resources, mine planning, processing, and operating cost requirements to complete the rehabilitation of the property along with the capital improvements necessary to resume operations at the Emerald Isle Mine. The key to the successful start-up of operations is the maintenance of existing environmental permits and the acquisition of any new permits required. The capital cost estimates to restart the Emerald Isle production includes contingency and working capital. These estimates, developed by KDMR and MWH, are based on actual current capital costs for equipment which has been specified, located, and priced by the suppliers and factored estimates based upon the experience base of KDMR and MWH. A detailed analysis of capital costs is presented in Section 10.0 and of operating costs presented in Section 11.0.
 
 
1

 
 
It will become apparent to the reader, that the Phase 1 conditions do not present a suitable technical or economic characterization of the property. Using the Phase 1 data base SGV is currently engaged in a Phase 2 analysis which will define the potential mineralization in the historical tailings and the on-site low-grade stockpiles.

Case 1
With the application of preliminary mine design and ore haulage logistics, there is a potentially mineable resources (indicated resources) of 985,227 tons at a grade of 0.63% copper and 12,413,860 pounds of copper. The mining rate is estimated at approximately 1,000 stpd of ore. A financial case utilizing the indicated resources results in the following economics. With US$7.0 million in capital expenditures, US$9.3 million per year in average operating costs and a copper price of US$2.00 per pound of copper, the mine is uneconomic. Life-of-mine undiscounted cash flow is a negative US$15.2 million.
 
Case 1 Assumptions
•  
No value has been assigned to the low-grade ore stockpiles remaining from previous El Paso Natural Gas and Arimetco operations, or the leach tailings remaining from historical El Paso Natural Gas operations;
 
•  
Metal recoveries are based upon projections developed from 85 day column leach tests as run at KDMR;
 
•  
Capital costs are factored downward from the KDMR estimate for a 2,000 stpd mining rate and ensuing copper production from the SX/EW;
 
•  
Conservative pit slopes have been used to reflect the lack of contemporary rock mechanics investigations; and
 
•  
A water supply adequate to support the operation at a production level of approximately 8,000 pounds of copper per day is developable from local resources.

Case 2
Case 2 is a moderate risk hypothetical example which assumes that a copper price of US$2.75 per pound of copper is achievable over the life of the property. It is Behre Dolbear's opinion that with the current price of copper at approximately US$3.20 per pound of copper, and the relatively short project life, the use of the US$2.75 per pound price is a reasonable assumption. Given the short project life, it could be argued that the entire project copper production could be sold forward for a minimum of US$2.83 per pound of copper, thereby validating the estimated US$2.75 per pound price.

 
2

 
 
Case 2 shows the potentially mineable resources (indicated resources) increasing to 2,095,709 tons at a grade of 0.52% copper and an average annual production of copper of 6.1 million pounds over the 3+ year life. This case yields average production costs of US$14.6 million per year, a capital investment of US$8.7 million and average operating costs of US$2.38 per pound of copper. Case 2 is uneconomic. The life-of-mine cash flow is a negative US$4.0 million. A copper price of US$3.00 per pound is required to break even.

Case 2 Assumptions
 
A copper sales price of US$2.75 pound of copper is used throughout the project life;
 
 
That sufficient fresh water can be located and developed to support the operation at 2,000 stpd ore operating rate;
 
 
Metal recoveries are based upon projections developed from 85-day column leach tests as run at KDMR; and
 
 
Ore head grades are based upon the grades indicated for the Case 1 the potentially mineable resources (indicated resources) and Behre Dolbear's estimates of the total tonnage and grade of mineralized material brought into the potentially mineable resources (indicated resources) classification by utilizing a US$2.75 per pound of copper selling price.

Case 3
Case 3 is a high risk hypothetical example which assumes that the low-grade ore stockpiles left over from the historical operations will carry a 0.35% copper grade, be shipped as ore thereby replacing an equivalent tonnage of stripping and leach with kinetics similar to the indicated resources treated in Case 1 and Case 2. In addition, the 1.6 million ton El Paso Leach Precipitation Flotation (LPF) tailings may contain up to 1,000,000 pounds of copper, of which 500,000 pounds may be recoverable by placing the sized >20 mesh Tyler material on the heap. To make Case 3 attainable, the low-grade stockpiles have to be accurately surveyed and sampled and a detailed sampling program carried out on the tailings. If the base assumptions are found to be true, the mine has an approximate 4-year life. Case 3 has average production costs of US$10.3 million per year, a capital investment of US$8.7 million and an average annual production of copper of 5.0 million pounds over the 6-year life. With average cash costs of US$2.06 per pound of copper, Case 3 yields an IRR of 21.5% with an undiscounted NPV of US$6.9 million. The results put forward for Case 3 support the Phase 2 efforts to more clearly define the potential of the historical tailings and low-grade stockpiles for inclusion in the mining plans and the need to achieve significant capital and operating cost reductions. SGV has contracted with certain parties to re-analyze the process and mining operating costs and to produce a supportable capital cost estimate for refurbishing the existing facilities.

 
3

 
 
Case 3 Assumptions
•  
That the low-grade ore stockpiles, left over from the historical operations, will in fact carry a 0.35% copper grade;
 
•  
The tailings contain sufficient copper which can be upgraded by simple screening and placing the screened oversize, >20mesh, on the existing heap; and
 
•  
That the assumptions listed in Case 1 and 2 are valid.

1.2     STATUS AND ONGOING WORK
 
SGV realized at the onset of the aforementioned valuation (Phase 1) for Cases 1, 2, and 3 that the low-grade stockpile material and the El Paso tailings material discussed in Case 3 could not be considered in a pre-feasibility level analysis because insufficient data was available to move this material to a mineable resource and ultimately to a reserve. It was decided to conduct a Phase 1 valuation considering those resources that were sufficiently drilled, sampled, and metallurgically tested to support a pre-feasibility level study. Based on the results of this analysis (provided in this report), a Phase 2 study would be conducted to optimize the exploitation of the Emerald Isle deposit.

Phase 1 - As part of their analysis of the Emerald Isle Project, Behre Dolbear completed a full assessment of the mineral resources and expected copper recovery. This phase of the report was essentially completed in late November of 2006 and sent to SGV for review in December. For this phase, Behre Dolbear relied on its associates, consultants, and outside independent professional companies to assess and re-design, where needed, the entire processing plant and related equipment. The proposed rehabilitation of the process plant and ongoing mining operations were based on agreement with SGV to be accomplished with the use of independent contractors. The permitting and regulatory matters were assessed and determined to be in order.

 
4

 
 
It was determined that additional mineral resources and sources of water would be required to support economic mining and processing activities. The Phase 1 report is discussed in depth in the main body of this report.

Phase 2 - Behre Dolbear's initial evaluation demonstrated that additional information was required on the waste dump and tailings material to fully evaluate the overall economic viability of the Emerald Isle deposit. A key variable in determining the rate of production is the availability of water in excess of that currently available from SGV's existing wells. SGV Resources recently initiated a study to determine alternative sources of water which may include the drilling of a new well.

Phase 2 examines the proposed operation in light of SGV reducing the capital cost of refurbishing the existing SXEW facilities and reducing the mining costs, including self-performing the mining operation. This phase will rely on the assessment of the resources and copper recovery data confirmed as part of Phase 1 and the base-line design, capital, and operating cost data developed by KD Engineering and MWH.

SGV realizes that a significant copper resource may be present in the El Paso tailings and the low-grade stockpile. The contribution of this resource to the overall project economics was not included in the Phase 1 evaluation due to a lack of reliable data. The tailings were sampled in late 2006 and are presently being analyzed by Metcon Laboratories. The low-grade stockpile will be sampled in early February 2007 and then sent to Metcon Laboratories for assessment. Behre Dolbear will assess the merits of the work being done by SGV and conduct a new valuation based on the revised input data. A report covering Phase 2 may be ready by late March 2007.
 
 
5

 
 
1.3  geology
 
The Emerald Isle property is located in northwestern Arizona near the eastern edge of the Basin and Range Province and just west of the western margin of the Colorado Plateau. The property is on the western flank of the Cerbat Mountains in the Wallapai Mining District, also known as the Chloride District. The Cerbat Mountains trend north and are composed of a Precambrian basement assemblage of Archean metamorphic and igneous rocks intruded by Laramide quartz-monzonite porphyry. Tertiary extrusive rocks crop out on the flanks of the range.

Mineralization in the Wallapai District is characterized by veins containing argentiferous galena, sphalerite, chalcopyrite, and pyrite. The mineralization is laterally zoned with a peripheral gold-silver zone, an intermediate lead-zinc-silver zone with minor gold, and a copper-molybdenum intrusive core. The Mineral Park porphyry copper-molybdenum deposit is located in this core.

The Emerald Isle copper deposit lies approximately 0.5 miles west of the peripheral lead-zinc-silver zone, just outside the main part of the Wallapai District. It is an exotic copper deposit in that the copper was transported from a source some distance away and deposited at its present location. The source of the mineralization is thought to be low-grade porphyry type copper mineralization at the head of Alum Wash 3.5 miles northeast of the deposit.

The copper mineralization is hosted by the Gila Conglomerate. The deposit is lens-shaped within a paleo channel some 2,500 feet long and 500 feet to 750 feet wide. The thickness of the deposit ranges from 20 feet to 300 feet and averages about 100 feet. It is generally thickest in the center and narrows at the margins of the channel.

1.4  mineral inventory and reserves
 
Behre Dolbear reviewed the drilling and assay backup data for SGV's Emerald Isle resource estimate. Key points are:
  •
The drill hole spacing results in classifying the resource as indicated and inferred. Much of the drilling is aged and Behre Dolbear was not able to verify the data sampling procedures or assaying procedures. On the other hand, most of the drilling was conducted by experienced and reputable mining companies.
 
 
 
6

 
 
  •
Behre Dolbear, at the request of SGV, produced two mineable resource estimates based on a typical short term copper price projection of US$1.75 per pound of copper and an optimistic price of US$2.75 per pound of copper. Both resource quantities are to be mined over a 3 year period. The mineable resource estimates are as shown in Table 1.1
 
Table 1.1
Emerald Isle Resource Summary
 
 
Variable
 
US$1.75 per pound of Copper
   
US$2.75 per pound of Copper
 
Mineable Resource Tons
    985,000       2,095,709  
Copper Grade % Copper
    0.63       0.52  
Stripping Ratio
 
2.3:1
   
3.3:1
 

1.5   MINING
 
a mining contractor will be engaged to conduct all operations required to move ore from the mine face through crushing and agglomeration and place it on the heap. The contractor will also conduct all operations required to move waste material from the mine face to the waste dump. Ore production will be 6,300 tons per week for the US$1.75 per pound copper case and 13,400 tons per week for the US$2.75 per pound copper case.
 
Mine operating costs, based on pre-feasibility level bids, are US$6.50 per ton of ore placed on the heap and US$4.08 per ton of waste for the US$1.75 per pound copper pit. Mine operating costs are US$4.63 per ton of ore placed on the heap and US$2.31 per ton of waste for the US$2.75 per pound of copper pit.

Initial capital costs for mining are US$991,000 for the US$1.75 per pound copper pit and US$990,000 for the US$2.75 per pound of copper pit. The contractor charges more per ton of waste for the lower production in the US$1.75 per pound copper case thus offsetting the cost of the higher pre-stripping tonnage in US$2.75 per pound of copper case.

1.6   PROCESSING
 
The Emerald Isle orebody has undergone several different metallurgical testing regimens over its history. No records are available for the test work accomplished by early 20th century operators or El Paso Natural Gas during its 1960s tenure on the property, but the leach/precipitation/flotation (LPF) operations are thought to have achieved something in the range of 80% recovery of copper from a crushing/rod mill grinding/leach/iron precipitation/flotation operation. Ore grade values are also not existent but are thought to have ranged from 0.60% copper to 1.20% copper. Tailings from that operational era have indicated assays from 0.17% copper to 0.22% copper.

 
7

 
 
Arimetco operated the property for a short time in the mid-1990s and although plagued with operational difficulties, managed cumulative heap recoveries of 62% over a period of 12 months. No operating conditions are known with the exception that the mine attempted operations at approximately 1,000 stpd but only reached that maximum in one month. The material as placed on the heap was "as mined" and probably included oversize up to 24 inch. The Arimetco plant consisted of 233 gpm SX/EW circuit which was capable of producing approximately 8,000 pounds of copper per day. The plant, including the heap loaded with 162,565 tons of material, was allowed to fall into disrepair. The production record for the Arimetco operation is shown in Table 7.1.

The copper recoveries achieved by Arimetco did not rise to the level planned for in this study. The major contributor to this variance is thought to be the size of the mine run rock which could easily have put large chunks of oxide copper into the heap. This oversize would require significant time under leach to reach higher recoveries and is the reason for proposing a single pass primary crusher at <6 inches for the SGV circuit. This is further reinforced by the consistently high recover of copper out of the heap, by Arimetco, after active mining had ceased. This suggests that a significant quantity of copper, placed on the heap by Arimetco, will be available for recovery by SGV early in the operation schedule.

1.   infrastructure
 
The Emerald Isle physical plant and mine has been in evidence for over thirty years. The main office, mine, and process plant are within three miles of the northwest-southeast U.S. Highway 93 which runs from Las Vegas, Nevada to Phoenix, Arizona. The main waste stockpile is within sight of but is not noticeable from the highway. Kingman, Arizona, the closest major metropolitan center with all needed industrial services, is about a one-half hour drive away by U.S. Highway 93. Hospital services are within 30 minutes of the facility site. Of highest concern is the availability of process water. The water available in the three SGV controlled wells is marginally acceptable for operations at the Case 1 (approximately 1,000 stpd) level but will not support Case 2 (approximately 2,000 stpd).
 
 
8

 
 
1.8    environmental
 
The Emerald Isle Mine is located on unpatented mining claims on BLM land about four miles south of Chloride, Arizona. The elevation of the site is about 3,700 feet. Annual precipitation is less than 10 inches. The surrounding sparsely vegetated land is primarily wildlife habitat. No threatened or endangered species are known to be in the vicinity of the mine.

An open pit mine and an SX-EW plant were operated at Emerald Isle by the previous operator, Arimetco International/TSC Enterprises, Inc. These facilities have been idle since 1993. The mine and plant appear to have been properly permitted by the previous operator, and the two major permits remain valid but must be transferred to SGV.

These two major permits are the Aquifer Protection Permit issued by the Arizona Department of Environmental Quality (ADEQ) and the approval of the Mining Plan of Operations and Reclamation Plan by the United States Bureau of Land Management (BLM).

The Aquifer Protection Permit will be transferred to SGV when financial assurance is provided by SGV. Financial assurance is needed for construction, operation, and closure including post closure monitoring. This financial assurance must involve a credible estimate of the construction, operating, and closure costs. Then there needs to be a letter from SGV's Chief Financial Officer stating that the company has the wherewithal to carry out the construction, operation, and closure. A letter from a financial institution indicating that the financing is in place would be helpful, perhaps required. The most recent United States Securities Exchange Commission (SEC) report may also be helpful, if financing is in place. For the closure costs, a surety bond, cash bond, letter of credit, or insurance or some combination thereof, will be needed. This is in addition to the BLM reclamation bond, but involves only additional measures to protect water resources.
 
 
9

 
 
BLM approval of the Mining Plan of Operations and Reclamation Plan is primarily awaiting provision of a reclamation bond. The amount of this bond has been calculated at $223,000 plus some yet to be determined amount for removal of Transited) (asbestos containing) pipe which connects the mine facility to the water wells. The bond will likely have to be a cash bond, e.g., a certificate of deposit. Additionally, a BLM resource specialist has questions regarding the proposed new waste rock dump, which may be able to be resolved once a detailed mining plan is completed. That plan could indicate that it is practical to return some waste rock to the pit during the life of the mine. If not, then some redesign of the dump may be required. This issue will have to be resolved before approval of SGV's Mining Plan of Operations and Reclamation Plan is forthcoming from the BLM.

Behre Dolbear believes that there is a low risk of any needed permit to be denied or delayed a year or more. There is a moderate risk of delays of 6 months to a year.

1.9   MINERAL TITLE, LAND, AND WATER RIGHTS
 
The Emerald Isle Mine property is located in Sections 22, 23, 26, and 27 of Township 23N, R18W, in the Wallapai District, Mohave County, Arizona and consists of 37 Unpatented Lode Mining Claims and 12 Mill-site Claims, registered with the Mohave County mining Recorder and the Bureau of Land Management in Kingman, Arizona. Behre Dolbear has not included verification of land and water rights under its scope of work. Title to water and land will have to be given to legal counsel for verification.

1.10   CAPITAL COSTS
 
Capital costs for the re-start of operations include refurbishment of the exposed portions of the heap liner which is in place, repair of the PLS pond, reconstruction of the raffinate pond, replacement of all heap piping and pumping, reconstruction of the SX/EW facility, reconstruction of the plant electrics including incoming power line, substation, switch gear and plant wiring, rehabilitation of the plant fresh water supply, and construction of administrative facilities. All capital costs for Case 2, with certain exceptions, have been developed by KDMR and MWH. Capital spending for Case 1, which has been factored from the Case 2 estimate, by Behre Dolbear. The capital spending requirements of the projects, not including SGV administrative costs, are shown in Table 1.2.
 
 
10

 
 
Table 1.2
 Emerald Isle Capital Cost Summary
 
Account
 
Case 1
   
Case 2 and 3
 
 
Pre-Production
(US$)
   
Sustaining
(US$)
   
Pre-Production
(US$)
   
Sustaining (US$)
 
Mine
  $ 100,000           $ 100,000        
Process
  $ 2,970,429     $ 1,848,000     $ 3,602,387     $ 2,800,000  
Infrastructure
  $ 315,000             $ 315,000          
Indirect Costs
  $ 833,400             $ 951,150          
Total
  $ 4,218,829             $ 7,741,537          

1.11    OPERATING COSTS
 
The operating costs for the project have been developed for Cases 1, 2 and 3. The key to understanding the foundation of the operating cost estimate are the detailed analyses which are included in the KDMR report in Appendix 4. The summarized average operating costs are shown in Table 1.3.
 
Table 1.3
Emerald Isle Average Project Operating Costs
 
Account
 
Case 1
   
Case 2
   
Case 3
 
 
US$/t Ore
   
US$/lb Copper
   
US$/t Ore
   
US$/lb Copper
   
US$/t Ore
   
US$/Ib Copper
 
Mining Processing
    9.59       0.92       7.49       0.85       7.46       0.86  
Administrative
    2.11       0.18       0.99       0.11       0.98       0.11  
Total
                                               
 
1.12   marketing
 
The Emerald Isle Mine's location in Northern Arizona, is 275 to 325 miles closer to the market, has an advantage over the larger copper mines to the south to serve the southern California copper market by truck or rail. Markets as far as Illinois (Chicago area) and Indiana can be served by rail. The current favorable copper market has a price premium over the COMEX copper price and the buyer pays the freight. The onset of new copper production will eventually require producers to pay the freight in a weaker market. Average shipping costs plus a probable new mine discount (2 to 3 cents) to get back into the market, a copper price discount of six cents a pound off the COMEX projected price is recommended for a pre-feasibility study. Further, a quick return to production can take advantage of the current copper market.

 
11

 
 
1.13   RISK ANALYSIS
 
The following definitions have been employed by Behre Dolbear in assigning risk factors to the various aspects and components of the ore reserve determination:
 
•  
High Risk: the factor poses an immediate danger of a failure, which if uncorrected, will have a material effect (>15%) on the project cash flow and performance and could potentially lead to project failure.
 
•  
Moderate Risk: the factor, if uncorrected, could have a significant effect (>10%) on the project cash flow and performance unless mitigated by some corrective action.
 
•  
Low Risk: the factor, if uncorrected, will have little or no effect on project cash flow and performance.

Table 1.4  presents the risk analysis summary for the Emerald Isle Mine.
 
 
12

 
 
Table 1.4
Risk Analysis Summary
St. Genevieve Resources Ltd., Emerald Isle Mine
 
Section in Report/Area
 
Risk
 
Category
 
Mitigation
Mineral Resources
 
Use of El Paso Data
 
Medium
 
Data are accepted upon the known reputation of El Paso for doing acceptable work.
Mineral Resources
 
Single Bulk Density for all rock types
 
Low
 
Low anticipated variability of bulk densities.
Mineral Resources
 
Lack of Independent BD Drilling
 
Low
 
Independent reviews by RPA and MDA make results acceptable.
Mineral Resources
 
Use of NARSC Topography Map
 
Low
 
Thorough review by BD yields acceptable risk.
Mineral Resources
 
Copper Revenue
 
Moderate
 
Future copper contracts may vary considerably
Leach Ore Feed Case 1
 
Existing drilling and assaying is found to be unreliable
 
Low
 
Behre Dolbear has investigated assaying and sampling and found the data base to be reliable.
Leach Ore Feed Case 2
 
The forecasted copper price does not materialize
 
Moderate
 
Behre Dolbear believes that forward sales support the use of the $2.75 copper price.
Leach Ore Feed Case 3
 
Low-grade stockpile ore exists at tonnages and grades as indicated
 
High
 
Data supporting the contents of the low grade stockpiles is anecdotal at best.
Mine Engineering and Planning Case 1
 
Mine Production Years 1-3+
 
Low
 
Proved reserves exist to provide a high degree of reliability to the forecast for this period.
Mine Engineering and Planning Case 2
 
Mine Production Years 1 -3+
 
Low
 
The ore basis is founded on sound data. Only copper price is at risk as addressed above.
Mine Engineering and Planning Case 3
 
Mine Production Years 1-4+
 
Moderate to High
 
A significant tonnage of material is taken from unknown stockpiles and a projected copper price of
$2.75 per pound of copper.
Mining Method
 
Mine Development Design
 
Low
 
Very little risk of a design flaw.
Current Flowsheet
 
SX/EW/Leach Flowsheet
 
Low
 
Proven on varied ores.
Recovery
 
Process Recovery
 
Low
 
Projected from 85 day column leach tests on various sizes of column leach feed.
Metallurgical Engineering Support
 
Metallurgical Engineering Support
 
Low
 
The planned staff is minimally adequate.
Process
 
Leach/SX/EW Operations
 
Low
 
Operations proven and well understood.
Process
 
Mill Maintenance
 
Low
 
While old. continued normal maintenance of the facilities is deemed adequate.
Environmental
 
Environmental-Air
 
Low
 
Future air emissions permitting issues could arise upon current agency inspection.
Environmental
 
Denial of Any Permit
 
Low
 
Potential for denial of any permit required.
Environmental
 
Permit Delay of 6 Months
 
Moderate
 
Changes to operating plan may add time to process.
Environmental
 
Longer Than 6 Month Delay
 
Low
 
Project should gain positive treatment from agencies.
Environmental
 
Superfund Status
 
Low
 
Only affected by poor management of operation.
Infrastructure
 
Infrastructure
 
High
 
Mine and Plant are well situated. However the fresh water supply for all Cases is in doubt.
Capital Costs
 
Mine Development Capital
 
Low
 
Mining Contractor Responsibility-Contract
Capital Costs
 
Process Capital
 
Moderate
 
Capital Budget reflects pre-feasibility level of accuracy with adequate contingency.
Operating Costs
 
Operating Costs
 
Low
 
Costs for consumables, labor and salaries match contemporary levels for Arizona operations.
Human Resources/Labor Relations
 
Human Resources
 
Low
 
Adequate Resources should continue to exist in area, even with a tight labor market industry wide.
Management/Org.
 
Management/Organization
 
Low
 
The proposed management organization is adequate.
Concentrate Marketing
 
Sales of LME Grade 1 Cathodes
 
Low
 
Past operations demonstrated the ability of the plant to make high quality cathodes.
3 year Production and Cash Forecast Case 1
 
Case 1 Production and Cash Forecast
 
Low
 
The Case 1 mineable reserve is well established.
3 year Production and Cash Forecast Case 2
 
Case 2 Production and Cash Forecast
 
Moderate
 
The forecast is based on an assumed copper price of $2.75 per pound of copper.
4+ year Production and Cash Forecast Case 3
 
Case 3 Production and Cash Forecast
 
High
 
A significant tonnage of leach feed is contributed by undefined low-grade stockpiles.
 
 
13

 
 
2.0     disclaimer
 
Behre Dolbear has conducted an independent technical review, at a pre-feasibility level, of St. Genevieve Resources Ltd.'s proposed Emerald Isle Mine open pit mine/heap leach/SX/EW re­start. Several site visits were made to the project site by Behre Dolbear professionals involved in this project. Behre Dolbear has reviewed technical data, reports, and studies produced by other consulting firms as well as information provided by St. Genevieve Resources Ltd. Our review was conducted on a reasonableness basis and Behre Dolbear has noted herein where such provided information engendered questions. Except for the instances in which we have noted questions, Behre Dolbear has relied upon the information provided as being accurate and suitable for use in this report.

Behre Dolbear assumes no liability for the accuracy of the information provided. We retain the right to change or modify our conclusions if new or undisclosed information is provided which might change our opinion.

Behre Dolbear does not accept any liability other than its statutory liability to any individual, organization, or company and takes no responsibility for any loss or damage arising from the use of this report, or information, data, or assumptions contained therein. With respect to the Behre Dolbear report and use thereof by St. Genevieve Resources Ltd., St. Genevieve Resources Ltd. agrees to indemnify and hold harmless Behre Dolbear, its shareholders, directors, officers, and associates from any and all losses, claims, damages, liabilities, or actions to which they or any of them may become subject under any securities act, statute, or common law and will reimburse them on a current basis for any legal or other expenses incurred by them in connection with investigating any claims or defending any actions.

2.1   electronic disclaimer
 
Electronic mail copies of this report are not official unless authenticated and signed by Behre Dolbear and are not to be modified in any manner without Behre Dolbear's expressed written consent.
 
 
14

 
 
3.0    introduction
 
3.1   general
 
St. Genevieve Resources Ltd. (SGV) has engaged Behre Dolbear & Company (USA), Inc. (Behre Dolbear) to carry out an analysis to determine the practicality of re-starting the Emerald Isle Mine operations. The main data sources for the analysis are the limited historical records from operations by El Paso Natural Gas, operations by Arimetco and contemporary exploration, reserve analysis, and metallurgical testing by SGV. The key SGV documents, which Behre Dolbear relied upon for its analysis, are the SGV 2006 Development Plan1, a NI 43-101 Report prepared by Roscoe Postle , and a Statistical Data Set analysis conducted by Vails (Appendix 1). The full text of the NI 43-101 can be found on the St. Genevieve website or http://www.sedar.com.

Behre Dolbear assembled a team of highly qualified and experienced personnel for the project, which was supervised by an experienced project manager who is responsible for the technical and financial performance of the project. The project manager is assisted by a project advisor who is responsible for the overall quality and technical content of the analysis.

3.2  background
 
The Emerald Isle Mine is located approximately 24 kilometers (km) northwest of the City of Kingman, Arizona and some 160 km (100 miles) southeast of Las Vegas, Nevada. The population of Kingman is about 10,000. The Emerald Isle Mine is situated 1.5 miles from U.S. Highway 93 within Wallapai Mining District, Mohave County, Arizona.

Historic mining activities in the Wallapai District of northern Arizona date back to the early 1860s, mostly for silver and gold within oxidized portions of veins. With the turn of the 20th Century, mining companies started to explore for base metals.
_______________________________
1. Wilson, B., "Emerald Isle Mine Scoping & Development Plan", April 26, 2006.
2. Agnerian, H. and Postle, J., "Technical Report on the Emerald Isle Copper Deposit, Arizona, U.S.A.," NI 43-101, Prepared for St. Genevieve Resources Ltd., June 13, 2006 (lsl Revision).
3. Vails, R., "Statistical Evaluation of the Emerald Isle Data Sets," May 25, 2005.
 
 
15

 
From 1917 to 1943 the property was worked at various times. From 1944 to 1948, a 300 tons per day copper leaching plant was in operation. About 55,000 tons of copper were reported to have been recovered. Results from this operation reportedly indicated leach recoveries in the order of 80% from "ore" with a head grade of 1% copper. Acid consumption was in excess of 10 pounds of acid per pound of copper produced.
 
During the past 50 years, considerable amount of work was performed by El Paso Natural Gas Company (El Paso) and contractors. These included the completion of some 24,700 feet of drilling in 130 rotary drill holes, 7,930 feet of drilling in 38 reverse circulation drill (RCD) holes, development of the present open pit, and reported production of some 1.4 million tons of oxide ore averaging approximately 1% copper.

During the 1970s, El Paso also carried out blasting and in-situ leaching at the bottom of the open pit. This was performed in conjunction with the United States Bureau of Mines (now the United States Geological Survey (USGS)). Results of this test, however, were not encouraging.

In 1980, TSC Enterprises, Inc. (TSC) acquired the Emerald Isle Property from El Paso, but the property remained inactive until 1987. In 1980, TSC was acquired by Arimetco, Inc. (Arimetco) and produced some 100,300 pounds of cement copper (82% copper) from the open pit. In 1992, TSC commissioned an 8,000 pounds per day SX/EW plant and reportedly produced 1,162,662 pounds of copper from 162,560 tonnes of ore at an average grade of 0.57% total copper (TCu). Due to the prevailing low copper price at that time, however, the plant was shut down in September 1993. Systematic testing of the copper bearing Gila Conglomerate at Emerald Isle was performed by Arimetco in 1987 and continued until 1994. In 2003, TSC changed its name to Western Consolidated Resources (Western).

3.3    scope of work
 
The role of Behre Dolbear as Independent Technical Consultant has been to develop and verify the plans for the development and operation of the Emerald Isle Mine. These plans are based on adequate data and formulated in accordance with good environmental practices. Behre Dolbear has determined that the mine can achieve the production levels at the costs, capital, and operating, as forecasted in the Case 1 life-of-mine plan, as described in this report. Alternatives, consisting of Case 2, a "2,000 stpd case with a US$2.75 per pound of copper price used in the cut off calculation, and Case 3 which presents a high risk scenario assuming that low-grade ore stockpile mineral inventory and tailings mineral inventory can be verified at economic levels.

 
16

 
 
Behre Dolbear has examined the exploration, production, and metallurgical testing history and has designed a current plan to operate the Emerald Isle Mine at both a 1,000 stpd and 2,000 stpd rate. Behre Dolbear has designed a base case plan (Case 1) for future operations that has been based on adequate data and formulated in accordance with sound mining and engineering practice, to assure that the mine can achieve its intended capacity within the capital and operating cost budget estimates. In addition, two additional cases with certain moderate to high risk assumptions have been formulated. Again, these plans have been formulated in accordance with sound mining and engineering practice, to assure that the mine can achieve its intended capacity within the capital and operating cost budget estimates.

The Emerald Isle Mine, although a minor contributor, has been a long-standing mining operation in the Wallapai Mining District. Behre Dolbear examined current environmental compliance and possible future concerns. Human resource issues have also been addressed.

The inputs to and construction of the approximately 3 year life-of-mine plan Case 1, and a medium risk approximately 3 year life-of-mine plan Case 2 were examined. A high risk, approximately 4 year, Case 3 was also developed which assumes economic values for copper in the low-grade stockpiles from historical operations and recoverable copper from the LPF tailings. Issues of risk were identified and rated in the standard Behre Dolbear system of low, moderate, and high. Items that carry no significant risk are also pointed out. The marketability of Emerald Isle cathodes is also addressed.

3.4    project personnel
 
Behre Dolbear selected a team of highly qualified and experienced personnel in the minerals industry. The Emerald Isle project team is headed by Mr. Mark Anderson, an experienced project manager. An experienced Behre Dolbear advisor was also assigned to the project, responsible for the overall quality and technical content of the study.
 
 
17

 
 
The individuals assigned to the Emerald Isle Project team were:
 
•  
Mr. Donald Cooper - Project Advisor. Mr. Cooper is President of Behre Dolbear & Company (USA), Inc. and as such will have final review and approval authority for the study. Mr. Cooper brings over 40 years of experience in the ferrous, non-ferrous, and coal extractive industries and has managed minerals projects internationally.
 
•  
Mr. Derek Ranee - Project Reviewer. Mr. Ranee is a senior associate and past president of Behre Dolbear Canada. Mr. Ranee has charge of assuring that all reserve, resource, and mineral inventory nomenclature is Canadian National Instrument No. 43-101 compliant.
 
•  
Mr. Mark Anderson - Project Manager, Metallurgy and Processing Facilities, Capital and Operating Costs, Infrastructure, and Administration and Personnel. Mr. Anderson has more than 40 years of diversified industry experience in both technical and managerial roles, including project feasibility, mine operations, and project due diligence. His experience includes evaluation of base and precious metal properties with emphasis on processing, metallurgy, project management, and feasibility analysis. His responsibilities have included construction management and operation of a 9,000,000 tonnes per year open pit copper/molybdenum mining operation with a 28,000 tonnes per day concentrator, and milling and smelting operations at a 21,500 tonnes per day copper ore mining and processing operation with byproduct gold. Prior to joining Behre Dolbear, Mr. Anderson was the general manager of Asamera Minerals Inc.'s U.S. Operations. He had combined management responsibility for the underground operations at the Cannon Gold Mine in Wenatchee, Washington and the Gooseberry Mine in Nevada, which produced gold and silver.
 
•  
Dr. Stanley Hamilton - Geology/Resources. Dr. Hamilton evaluated the geologic aspects of the project and the adequacy of the resource estimating methodology. Dr. Hamilton has 35 years of experience with base and precious metals property exploration, development and evaluation with assignments at senior management levels. In addition, Dr. Hamilton has had a long career in exploration management and the management of junior mining companies. He is particularly adept at working within the Canadian, AUSIMM, and SEC ore reserve guideline requirements for new or restarted projects.
 
 
18

 
•  
Dr. Robert Cameron - Mineral Resources. Dr. Cameron is an ore reserve and mine planning specialist for BDUSA. He has well over 20 years of experience in the minerals industry, specializing in deposit modeling and mine planning, estimation of resources and reserves, geostatistics, assay database auditing, resource/reserve auditing, adequacy of drill-hole spacing, exploration and development drilling planning, cash-flow analysis, project valuation, and feasibility/pre-feasibility studies. Dr. Cameron holds B.S., M.S., and Ph.D. degrees in mining engineering from the University of Utah. He meets the requirements for "Competent Person" as defined in the JORC Code and the requirements for "Qualified Person" as defined in Canadian National Instrument 43-101 for the purpose of mineral resource/ore reserve estimation and reporting.
 
•  
Mr. Robert Dimock - Mining, Mining Capital, and Mining Operating Costs. Mr. Dimock is a senior associate, director, and principal of Behre Dolbear & Company, Inc. Mr. Dimock has more than 35 years of experience in the mining industry with expertise in the areas of general management, corporate strategic planning, project development and management, mining, processing, construction management, and mining engineering in base and precious metals. Mr. Dimock has also had direct oversight of exploration, concentrating, smelting, refining, marketing and sales, human relations, public and government relations, HSEQ, and legal issues.
 
•  
Mr. Kenneth Paulsen - Environmental. Mr. Paulsen is a senior associate and has over 40 years diversified experience in mining operations management and management of environmental affairs in the mining and mineral processing industry. During his long career, Mr. Paulsen has provided environmental examinations of mining and mineral processing properties in connection with due diligence evaluations, environmental audits, and financial appraisals.
 
•  
Mr. William Jennings, P.E. - Economic Analysis. Mr. Jennings has 30 years experience with consulting firms. He has specialized in the economics and valuation of mineral properties, with emphasis on base metals, precious metals, and coal. On valuation and feasibility projects, Mr. Jennings prepares economic analysis models and determines taxes, cash flow, net present value, and rate of return. On projects where valuation is not amenable to standard cash flow net present value analysis, he performs valuations using other accepted techniques. Mr. Jennings is a registered professional engineer and a Certified Mineral Appraiser.
 
 
19

 
•  
Mr. William Mayrsohn - Marketing. Mr. Mayrsohn has over 40 years professional experience in the base metals industries and has highly developed marketing and hedging skills consistent with positive results in risk-averse precious metals and copper. His experience base includes strong copper, gold and silver concentrate sales experience along with effective smelter terms negotiation. In addition he has held positions as Corporate Treasurer and Senior Financial Analyst.
 
3.5     procedures
 
The project team, consisting of Messrs. Anderson, Hamilton, Cameron, Dimock, and Paulsen visited the mine site, collected relevant information, and obtained input from the SGV managerial staff. All facilities were inspected, including the open pit mine, the SX/EW plant, the existing heap, and existing surface infrastructure. Areas of special concern were the condition of historical heaps, ponds and lining systems and the SX/EW plant. At the site, attention was paid to and data gathering. Special attention was given to methods of ore reserve and resource calculation.

After the site visit detailed technical analysis of information provided was performed. Numerous follow-up conversations with SGV staff resulted from the technical analysis. In addition, selected sub-contractors (KD Engineering (KDMR) and Montgomery Watson Harza (MWH)) sent teams to the site in order to provided capital and operating costs for the re-start of SX/EW and heap leaching operations. The project manager edited this report for completeness and clarity. After preparation, the report was submitted to the Project Advisor who again edited it for clarity, accuracy, and completeness. Numerous conversations with team members concerning their findings were held with the Project Reviewer and Project Advisor.
 
 
20

 
3.6   acknowledgments
 
Behre Dolbear would like to acknowledge the complete, open cooperation of all SGV management and staff personnel involved. Mr. Howard Metzler, the SGV manager at the mine site, helped to coordinate the cooperative efforts of Behre Dolbear and the subcontractors and made himself available for questions and input during all phases of the pre-feasibility analysis. Mr. Bryan Wilson, SGV President, provided historical reserve and resource information perspective and detailed the methodology currently used in planning operations at the Emerald Isle site. Mr. Wilson cooperated fully with Dr. Hamilton and Dr. Cameron in preparing the geology and reserve components of this assignment. Mr. Wilson is also the author of the 2006 Emerald Isle Development plan cited earlier in the text.

Mr. Fred Brost, Environmental Consultant to SGV provided valuable insight and information concerning ongoing permitting challenges and the status of air and water issues at the site.

Lastly, Behre Dolbear would like to recognize and thank SGV's Director, Mr. Mike Harrington, for facilitating the project work and providing an open work environment. It was a pleasure for Behre Dolbear to work in such a cooperative atmosphere.

3.7  units of measurement and currency
 
All units of measurement used at the Emerald Isle Mine are in the English system (e.g., tons are short tons of 2,000 pounds) and U.S. dollars. There are no foreign currency transactions as all products will be sold in the U.S. dollars and all purchasing is in U.S. dollars. Behre Dolbear conforms to the English unit system for all matters in this report.
 
 
21

 
4.0     GEOLOGY
 
4.1    GEOLOGICAL SETTING
 
The majority of the geological section has been taken from the text of the 2006 Development Plan for the Emerald Isle Property as prepared by Mr. Bryan Wilson, President of SGV. Behre Dolbear has accepted this data for inclusion in this section of the analysis.

4.1.1   Regional Geology
 
The Emerald Isle Property is situated near the eastern edge of the Basin and Range Province and close to the western margin of the Colorado Plateau. It is located near the Mineral Park porphyry copper-molybdenum deposit, within the Wallapai Mining District. The Wallapai Mining District is on the western flank of the Cerbat Mountains, which trend north-south and are composed of a Precambrian basement intruded by Laramide quartz-monzonite porphyry. Tertiary extrusive rocks crop out on the flanks of the Cerbat Range (Eidel, et al, 1968). The north trending Black or River Range west of the Cerbat Mountains consists of Cretaceous and Tertiary volcanic rocks overlying a poorly exposed basement (Figure 4.1).

The Wallapai Mining District is approximately 6.5 km long wide and 18 km long and is defined by the known lateral extent of base and precious metal veining (Figure 4.1). Faults are abundant in the district, but the lack of good marker units makes offset and age relationships difficult to interpret (Wilkinson, et al, 1982).

Several large N70°W trending faults are present in the area from the Roper Ridge to Ithaca Peak and numerous smaller northwest trending faults exhibit intense fracturing and silicification (Figure 4.1). The geologic history of the Wallapai Mining District is summarized, as follows:
 
•  
A series of folded meta-sedimentary and meta-volcanic rocks occur along the western flank of the Cerbat Mountains.
 
•  
The folded rocks were intruded by regionally northeast foliated granitic gneiss of batholithic proportions.
 
•  
The north-northwest trending contact between the folded rocks and the granitic gneisses was a major structural element in the district.

 
22

 

 
Figure 4.1. Regional Geology of the Emerald Isle Area, Mohave County, Arizona
 
 
23

 
 
•  
Intrusion of the Ithaca Peak stocks at/near the intersection of this contact and the Turquoise Mountain fold.
 
•  
This contact was the locus for intrusion of rhyolite dikes and the formation of the major fault-veins of the district (Wilkinson, et al, 1982).

4.1.2   Property Geology
 
The Emerald Isle Property is located in the Sacramento Valley, about a mile from the west face of the Cerbat Range (Figure 4.1). Its geologic setting is an alluvium covered, gradually west sloping pediment and it is underlain by the Late Tertiary Gila Conglomerate and Cretaceous granitic rocks of the Ithaca Peak intrusive. The trace of fold axes in Figure 4.1 also suggests that the property area is at least partly underlain by northeast trending basement amphibolite rocks. To the south, the area is covered by Quaternary alluvium (Figure 4.2). The relief is low and undulating due to protruding bedrock and erosional dissection. The alluvium in the vicinity of the old mine represents older alluvium, as does the bulk of the detrial apron flanking the range (TSC, 1992).

The terrace beds and dissected portions of the pediment reveal poorly sorted, mixed deposits of angular to sub-angular sand, pebbles, cobbles, and boulders (up to 15 feet), representing all of the rock units in the Cerbat Range. Crude stratification exists in some places, but the bulk of the apron flanking the range is largely mixed and unconsolidated.

The alluvial veneer at the Emerald Isle Property has been consolidated by mineralizing solutions to form the blanket of copper and zinc mineralization. Due to its proximity to the Mineral Park copper-molybdenum deposit, the salts and clays eroded from the Alum Wash and Ithaca Peak porphyrys, alteration halos likely have contributed to the bonding of the Gila Conglomerate.

 
 
24

 
 
 
 
25

 
 
The most obvious structural feature on the property is the Emerald Isle Fault. The fault is normal and has a vertical displacement of about 105 feet and an unknown horizontal displacement, and is arcuate to the west. In the northeast corner of the pit, the strike is N60E, while on the south side of the pit near the old adit, the strike is N10E (see Figure 4.2). The dip varies from -45° west to -70° west. The fault is young since both the pediment and overlying alluvium are faulted (TSC, 1992).

4.2     MINERALIZATION
 
Copper mineralization at Emerald Isle is hosted by units of dark blue to black east-northeast trending and gently to moderately south dipping unconsolidated Late Tertiary Gila Conglomerate in contact with a small silicified intrusive and volcanics that form the basement.

The Gila is a polymict conglomerate with rounded fragments (<1 cm to 5 cm) of granitic as well as meta-quartzite and other material within a fine-grained matrix. Occasional larger boulders of granitic composition are also present. The contact with the intrusive stock and volcanics may be a fault contact which follows the outline of the central silicified intrusive.

The source of copper mineralization at Emerald Isle is the low-grade porphyry type copper mineralization at the head of Alum Wash, 3.5 miles northeast of the deposit, close to the Mineral Park Mine (Figure4.1) (Thomas, 1949 and 1951). Tenorite (CuO) is common and minor cuprite (CU2O), chrysocolla (CuSi03 • 2 H2O), and dioptase (F^CuSiO^, a rare mineral of copper have been identified.

The copper mineralization occurs in fractures and as interstitial cementing material within fine sand and clay. Oxides of iron and manganese are also frequently found in many fractures. All of the copper mineralization in the material projected to be mined at Emerald Isle is secondary.

4.2.1   Types of Mineralization

There are three types of copper mineralization at Emerald Isle, as follows:
 
 
• Type 1 is primary fissure vein mineralization containing copper sulfides (Thomas, 1949). This was the type of mineralization which was mined in 1917 and 1918, but is not the target at the present time.
 
 
26

 
•  
Type 2 is blanket type primary copper mineralization and has been the exploration target during the past twenty years. It occurs within the dark conglomerate ("Grey and Black Ore") and is reported to consist primarily of tenorite (CuO). This mineral is sometimes called copper pitch or melaconite and "much of it seems to be cryptocrystalline or amorphous" (Williams, 1992) and may be present with pyrolucite (MgO), a black isomorphs of the mineral chrysocolla, and hydrozincite (2 ZnC03 • 3 Zn(OH)2). It is the pitchy dark brown to black material which commonly occurs within the Gila Conglomerate.
 
•  
The third type of mineralization is represented by secondary copper minerals, in the form of copper staining, such as malachite (CUCO3 • Cu(OH)2) and chrysocolla (CuSi03 • 2 H2O). These minerals occur on fracture planes as well as within the matrix of the dark conglomerate. Minor cuprite (CU2O) and dioptase (H2CuSi04) a rare mineral of copper have also been identified. Chrysocolla also occurs as a thin veneer around tenorite grains (Williams, 1992).

4.2.2   Genetic Model
 
The rare style of secondary copper mineralization present in the Emerald Isle deposit is classified as an Exotic Ferrocrete deposit (Crete - from the Greek meaning Cement and 'Ferro' from the element Iron (also Manganese)). The copper mineralization and other dissolved minerals were dissolved by the break down by natural weathering of primary sulfide minerals. The resulting naturally occurring acid water (sulfuric acid) carried the dissolved metals in solution until there was a change in the pH and Eh of the hydrological environment. The change in the hydrological pH and Eh occurred in the basal Gila Conglomerate, which fill natural depressions which are structurally controlled in the basement rocks on the down slope pediment of the Cerbat Mountain Range. The dissolved metal load was precipitated as metal oxide cements in the interstitial voids of the coarse grained Gils sediments.

The mineralized copper deposit is contained within a paleo-channel some 2,500+ feet long, 500 feet to 750 feet wide and the thickness ranges from 20 feet to 300 feet, averaging about 100 feet in the form of a long 'baguette' shaped mineralized lens. In general, the conglomerate layer has a wedge-shaped profile, with a thin northern part and a much thicker southern part. In places, the mineralized Gila Conglomerate is absent and in other places it is very thick, possibly due to post mineralization faulting.

 
27

 
 
The morphology of the conglomerate unit suggests that source of the copper is the low-grade porphyry-type copper mineralization at Alum Wash, and mineralization is characterized by dark blue to black rock, as noted above. Early work by Thomas (1949) suggested that the chrysocolla may also be a primary mineral, because:
 
•  
"There are no relict grains of sulfides or any minerals which might have served as a primary source of the copper.
 
•  
The texture of chrysocolla, both in the vein and in the conglomerate blanket, is delicately banded and en-crusted, which suggests that formation was by open space filling and not replacement."

In a 1992 report by Mine Development Associates (MDA), Wendt noted that there were at least two undeveloped (not mined) deposits with estimated resources in the range from 10 million to 20 million tons at an average grade in the order of +0.3% copper in the vicinity of the Emerald Isle Property (Wendt, 1992). These were the Alum Wash and Vega's Vug deposits adjacent to the Mineral Park Mine (Figure 4.1). There are several copper deposits in Arizona and New Mexico, which are interpreted to have geological attributes similar to those as at Emerald Isle. Some of these deposits include:
 
•  
Mineral Creek Deposit: Located within Ray Mineral District, Pinal County, Arizona, this alluvial-hosted (stream gravels) deposit extends some 500 feet along strike and is 30 feet thick, and is reported to contain approximately one million tons at an average grade of 0.5% copper. It is situated at the base of a cliff just below the porphyry copper deposit on Ray Hill. The age of mineralization is estimated at 7,000 years and the mineral constituents are recognized as malachite, azurite, cuprite, and Tenorite (Clifton, 2004a).
 
•  
Copper Butte Deposit: Located 3 miles west of Ray Mineral District, Pinal County, Arizona and the deposit is hosted by stream channels within the Oligocene Whitetail Conglomerate, and is reported to contain approximately 100,000 tons at an average grade of 3.0% copper. The mineral constituents are recognized as chrysocolla and copper wad (Clifton, 2004a).
 
 
28

 
•  
Black Copper Area: Located some 1,000 feet north of Inspiration porphyry copper deposit, Gila County, Arizona, this deposit is hosted by stream channels within the Oligocene Whitetail Conglomerate. It extends some 10,000 feet along strike, is 100 feet wide, and is 75 feet thick. Due to its proximity the source of mineralization is believed to be the Inspiration orebody (Clifton, 2004a).
 
•  
Tyrone Oxide Deposits: Located in Grant County, Burro Mountain District, southwest New Mexico, this deposit is situated about one mile southwest of the Tyrone porphyry copper deposit, and interpreted to contain several bodies totaling some 100,000 tons at an average grade of 1.0% copper. It is hosted by stream channels within the Miocene Mangas Conglomerate and the mineral constituents are recognized as chrysocolla, black copper silicates and oxides, and malachite. Due to its proximity the source of mineralization is believed to be the Tyrone porphyry copper deposit (Clifton, 2004a).

4.3    GEOCHEMISTRY OF THE EMERALD ISLE COPPER DEPOSIT
 
The copper minerals present in the ore at the Emerald Isle ore are:
 
1. Chrysocolla (CuSi03 • 2 H20);
2. Dioptase (H2CuSi04);
3. Tenorite (CuO); and
4. Malachite (CuC03 • Cu(OH)2).

Zinc presenting appreciable quantities is present in the Emerald Isle ore as probably as Hydrozincite (2 ZnC03 • 3 Zn(OH)2 and possibly Willemite (Zn2SiO/i).
 
The zinc was detected in significant quantities in sampling carried out in the pit by SGV Resources in October 2004 and its presence in the un-mined portion of the orebody was confirmed by drilling in December 2004. There is an apparent zonation to the zinc mineralization with the higher grades being found generally on the north side of the deposit where the ratio of ZnOHx to CuOHx is much greater than 1. A partial multi-element analysis of the Emerald Isle ore is presented in Table 4.1 below:

 
29

 

Table 4.1
Summary of Multi Element Analysis Ore and PLS (10,000 ppm = 1.0%)

REPORTED :
   
12-Oct-2004
                   
           
j ICP-2A |
   
ICP-2A
   
ICP-2A
   
ICP-2A
   
ICP-2A
   
ICP-2A
   
ICP-2A
   
r ICP-2A
   
ICP-2A
 
           
Al
   
Co
   
Cu
   
Fe
   
Ni
   
Sc
      u       Y    
Zn
 
SAMPLE ID
         
ppm
   
ppm
   
ppm
   
ppm
   
... ppm
   
PPm .
   
ppm
   
ppm
   
ppm
 
  A1 1             29300       56       3070       37400       132       4.29       5       47       3520  
  A1 2             31900       60       3300       39900       140       4.64       5       50       3860  
  A2 1             25900       84       5370       30400       269       4.05    
<3
      66       10600  
  A22          
28500 <
      115       17000       32000       625       4.61       4       39       31300  
  A3 1             30910       27       14500       27200       204       4.23       6       129       4770  
  A32             21600       114       9480       22900       596       3.26       4       75       34000  
  A3 3             21600       90       5430       23000       620       3.08    
<3
      25       31200  
  A34             7380       115       17200       18500       510       1.93       5       37       22700  
  A35             18100       69       20000       35300       347       4.58       13       43       11400  
  A4 1             32300       145       6360       25500       237       3.40       5       65       5450  
  A42       27000       125       54100       27100       729       3.75       5       56       36000  
  A43               26500       106       14300       28800       568       4.16       5       121       24400  
  A44               23300       188       18600       26900       611       3.68       6       70       33100  
  E3 1               29300       31       33700       28100       191       4.42       8       J 02       4020  
  E3 2               18800       233       29300       19710       138       3.70       9       48       3210  
  E3 3               26000       25       9370       35300       93       5.70       8       129       2980  
  E4 1               22600       26       18200       30200       101       4.33       6       107       2710  
  E4 2               19500       97       18400       39800       125       4.81       8       59       2820  
  E51               11100       41       53200       16000       148       353       8       101       2690  
  E5 2               33200       234       11700       29800       161       4.81       6       84       2900  
  E5 3               22000       142       5760       38900       53       5.48       5       40       1290  
       
Average
      24133       101       17540       29177       314       4.12       6       71       13091  
                                                           
REPORTED :
   
5-Aug-2005
   
Al
   
Co
   
Cu
   
Fe
   
Ni
   
Sc
      U       Y    
Zn
 
Pregnant Leach Solution
      3056       15.8       3118    
10 "
      264       0.2       2.0    
NA
      9080  
REPORTED" :
   
5-Aug-2005
                                                                         
Raffinate Salt Cake
      30700       119.0       21600       1370       1730       5.5       15.9    
NA
      74519  
REPORTED :
   
19-OCI-2004
                                                                         
Raffinate Salt Cake CUS04 1
      41100       138       17800       2180       2580       10.70       36       257       80000  

 
30

 
5.0  mineral resources
 
5.1  introduction
 
Behre Dolbear has estimated the mineral resources and summarized the potentially economically mineable portion of that estimate using the drill hole database and other information provided by SGV. Two assumptions on the selling price for copper of $1.75 and $2.75 per pound were used to develop two estimates of the potentially mineable portion of the in-situ resource estimate. Behre Dolbear did not complete any independent verification of the sampling or drilling and relied on the information provided to them by SGV.

 
5.2  drilling data
 
Drilling at the Emerald Isle project has been conducted starting with El Paso Natural Gas and El Paso Mining and Milling (El Paso) back in the mid 1960s. El Paso's work was completed using rotary drilling. The drill chips were logged by company geologists and assays were completed by Rare Metals, a defunct laboratory owned by El Paso. Logging included marking lithologic contacts, relative moisture and/or clay content and relative alteration of the rocks. Behre Dolbear is uncertain about the methodology of sampling the drill chips or about the procedures for sample preparation and copper assays. This program amounted to approximately 85 drill holes and constitutes most of the drilling on the property. The assays for the El Paso drilling are total copper assays.

In 1992 MDA conducted an independent RC drilling program for Holcorp Mines during a due diligence review of the property. Their work consisted of drilling 38 RC holes designed to verify the tonnage and the potential grade of the deposit. On the first few RC holes the first set of assay certificates reported total copper. After some discussions on assaying procedures, the final assay certificates issued reported acid soluble copper. SVG has two sets of assay certificates for part of the 1992 drill holes. The first reports total copper and the second reports both total and acid soluble copper. The acid soluble copper assays were entered into the electronic database.

In 1993 Arimetco in conjunction with MDA drilled another 8 RC holes. These holes were an add-on of the program outlined for the Holcorp due diligence after it had been completed. These assays are also acid soluble assays.
 
 
31

 
SGV took over the property in 2004 and drilled another 18 RC and 8 core holes. Much of this work was conducted to check data validity of the old drilling and to assess the variability of the deposit. Once again, acid soluble assays are reported and coded into the database for this work.

5.3   electronic data base
 
Behre Dolbear received a hard copy of many of the drill logs and original assay certificates that were on-site. The assay results from 130 drill holes were provided in a comma delimited electronic file. Behre Dolbear compared the electronic file with the original drill logs and assay sheets and corrected any data that was mistyped or incorrectly entered.

After making the necessary adjustments, Behre Dolbear entered the drill hole files into the Techbase mine planning software. After the data were entered into Techbase, the acid soluble copper values for the 1992 and newer drilling was converted into total copper based on the following equation.

Total Cu 00 = 0-0727 + (1.017579 • ASCu)
 
5.4   density measurements
 
Arimetco had Kappes, Cassidy & Associates (Kappes Cassidy) of Sparks, Nevada carry out 20 density measurements (duplicates) on 10 mineralized samples of mineralized material from the Emerald Isle Mine in 1992 and 1993. Results of their test work indicated that the average density of the mineralized material was 2.38 g/cc or a density factor of 13.54 cubic feet per ton. Behre Dolbear has used this figure (13.54 cubic feet per ton) in its estimate of the mineral resources in the current block model.

 
5.5   geological interpretation
 
Roscoe Postle Associates Inc. (RPA) carried out an interpretation of drill hole assay data generated prior to the mining activities at Emerald Isle. Their report and analysis concludes that copper mineralization occurs primarily within the Late Tertiary Gila Conglomerate which is the same conclusion as has been reported by most of the geologic work on the property. Copper mineralization is also present in the underlying granitic rocks and occasionally in the overlying Quaternary alluvial material, as well as in the waste dumps. RPA also reports that the copper mineralization reported in the underlying granite may be due to contamination from the overlying Gila Conglomerate during the drilling. Given this information, Behre Dolbear chose to model only the copper within the Gila Conglomerate.
 
 
32

 

Rock type codes were coded into the assay database based on the lithologic unit of the sample. The geology codes used for rock types were: (2) for alluvium, (3) for the Gila Conglomerate, (4) for altered granite, and (5) for fresh granite. Almost all of the drill holes reached the underlying granitic rocks; therefore, both the top and bottom boundary of the Gila Conglomerate is easily identified. Behre Dolbear used these rock type codes to assign a lithologic code for each block in the block model. This was done using a nearest neighbor assignment based on an elliptical search dipping 10 degrees to the west corresponding to the known dip of the Gila Conglomerate in the area of interest.

5.6   ASSAY STATISTICS
 
Statistics were generated for the total copper assays within the Gila Conglomerate. All acid soluble values were first converted to total copper before the statistics were generated. This resulted in a mean of 0.45% copper with a standard deviation of 0.522 and a median of 0.273.

5.7    COMPOSITING
 
Behre Dolbear composited assays into 5 foot intervals down the hole. The rock type associated with each composite was determined and assigned to each composite interval. Composites less than 2 ft. long were excluded from the composite database. Assay values were not capped (cut) in calculating composite values. There are a total of 207 drill hole composites within the mineralized conglomerate. Statistics for the drill hole composite result in a mean of 0.45% copper with a standard deviation of 0.509 and a median of 0.260.

5.8    BLOCK MODEL
 
A 3D block model was constructed in Techbase based on the local coordinate system used for the Emerald Isle property. The block size is 20 feet in an east-west direction by 20 feet in the north-south direction by 10 feet vertical. Each block was assigned a lithologic code based on the location of the centroid of the block using a nearest neighbor search. Grades were interpolated only into the blocks coded as Gila Conglomerate using only total copper composites located within the Gila Conglomerate.

 
33

 
The kriging method was used to interpolate the total copper grades of the blocks. The search strategy utilized a search ellipse with the major and semi-major axes oriented along the strike and dip of the Gila Conglomerate and a range of 300 feet, i.e., dipping 10 degrees at an azimuth of 270 degrees. The minor axis of the search ellipsoid was 30 feet and perpendicular to the dip. A minimum of two and a maximum to 10 composites were required for interpolation.

Behre Dolbear used a composite variogram model based on the RPA variography work. The model used to interpolate the blocks in the model was a simple spherical variogram with a sill of 0.207 oriented at an azimuth of 270 degrees dipping 10 degrees towards the west. The range of the major and semi-major axes was 440 feet and the minor axis 110 feet. A nugget of 0.053 was used.

The existing surface topography for the block model was determined using the National Applied Resource Sciences Center (NARSC) topography map supplied to Behre Dolbear by SGV. The polylines were extracted from the AutoCAD "dfx" file and entered into Techbase. These data points were then used to set the current surface topography for the block model. This assumption results in some error in the resource calculation as it has been reported that a small tonnage of material has been removed from the pit since the NARSC topographic survey was completed. Behre Dolbear used the NARSC topography as it was the most current information available to them at the time of the resource modeling.

5.9    classification of mineral resources
 
Behre Dolbear would classify the mineral resources in the block model as an Indicated and Inferred resource based on the typical drill hole spacing and the kriging variance. Due to the age of the drilling and the inability to verify the assay quality and QA/QC procedures for either the drilling, data sampling procedures or assaying procedures for the El Paso drilling, which makes up over half of the drilling at Emerald Isle, Behre Dolbear is of the opinion that the present database is of moderate risk and may not technically qualify as a resource under the CIM Guidelines. However, Behre Dolbear would also note that, in general, El Paso Natural Gas and El Paso Mining had a reputation and a history of conducting quality exploration and sampling work. The Indicated and Inferred global in-situ geologic resource are summarized in Tables 5.1 and Table 5.2. These summaries do not take into account any consideration of potential mineability. Behre Dolbear classified any material within the Gila Conglomerate within 100 feet of a drill hole as Indicated and material between 100 and 300 feet from a drill hole as inferred.
 
 
34

 
 
Table 5.1
Emerald Isle
Indicated Global In-situ Resource
 
Cutoff
% Copper
   
Tons
   
Ave Grade
% Copper
0.2     4,201,463     0.46
0.3     2,688,027     0.59
0.4     1,941,500     0.68
0.5     1,412,403     0.76
0.6     987,294     0.85
0.7     685,670     0.95
0.8     435,154     1.06
 
Table 5.2
Emerald Isle
Inferred Global In-situ Resource
 
Cutoff
         
Ave Grade
% Copper
   
Tons
   
% Copper
0.2     3,980,194     0.34
0.3     1,716,686     0.48
0.4     956,275     0.59
0.5     571,933     0.68
0.6     365,730     0.76
0.7     191,137     0.86
0.8     95,125     0.97

5.10   POTENTIALLY MINABLE RESOURCES
 
Behre Dolbear used the block model to determine the potentially mineable portion of the indicated resources contained in the model. This procedure involved developing economics for mining and processing, applying recovery factors and revenue assumptions. Table 5.3 shows the major economic factors involved for the development of an economic block model. Once this block model was generated, pits were floated using a simple floating cone algorithm. The economic ultimate pit was then smoothed and haulage ramps were inserted to provide a final pit design. Then the removed materials were summarized to give potential mineable resources for the Emerald Isle deposit. The final pit designs with haulage road designs are shown in Figures 5.1 and 5.2
 
 
35

 
Table 5.3
Economic Parameters
 
Item
 
Assumption
Ore Mining
 
$1.70 per ton
Waste Mining
 
$1.70 per ton
Crushing
 
$0.25 per ton
Processing, General and Administrative, and Marketing
 
$3.85 per ton
Recovery
 
80%
Selling Price of Copper   Case 1 - $1.75 per pound
    Case 2 - $2.75 per pound
 
A mine life of 3 years was assumed for both Case 1 and Case 2. The pits were then sequenced and yearly mining schedules were developed for both economic cases. The yearly mining schedules shown by bench are shown in Tables 5.4 and 5.5. These figures do not include any allowances for mining loss or dilution (see discussion in Section 6.6).

 
36

 

 
37

 
 
 
 
38

 
Table 5.5
Emerald Isle Production Schedule
Case 2 - $2.75 Cu and 700,000 tpy Ore Production

     
Mid
Bench 
Elev
   
Year 1
   
Year 2
   
Year 3
 
          Ore+Waste    
Ore
   
Waste
   
Ore+Waste
   
Ore
    Waste    
Ore+Waste
    Ore    
Waste
 
Bench No
       
Tons
   
Tons
   
Cu
(%)
    Tons    
Cu
(%)
   
Tons
   
Tons
   
Cu
(%)
    Tons    
Cu
(%)
   
Tons
   
Tons
   
Cu(%)
   
Tons
   
Cu(%)
 
  31       3695       2,363       -       -       2,363       -       -       -       -       -       -       -       -       -    
_
      -  
  32       3685       26,588       591       0.39       25,997       -       34,860       -       -       34,860       -       21,861       -       -       21,861       -  
  33       3675       77,991       12,112       0.56       65,879       -       50,517       -       -       50,517       -       48,744       -               48,744       -  
  34       3665       148,596       37,223       0.48       111,373       -       87,740       -       -       87,740       -       89,512       6,795       0.22       82,718       0.20  
  35       3655       171,639       43,131       0.47       128,508       -       131,166       -       -       131,166       -       96,012       3,840       0.23       92,171       0.21  
  36       3645       201,476       40,768       0.42       160,708       -       158,345       -       -       158,345       -       87,740       2,659       0.24       85,081       0.17  
  37       3635       202,363       41,063       0.39       161,299       0.17       186,705       -       -       186,705       0.15       96,898       7,386       0.24       89,512       0.16  
  38       3625       200,295       37,223       0.38       163,072       0.18       186,705       295       0.22       186,410       0.16       123,781       16,544       0.24       107,237       0.16  
  39       3615       188,183       36,927       0.39       151,255       0.17       188,773       -       -       188,773       0.18       121,418       18,316       0.24       103,102       0.17  
  40       3605       168,685       31,610       0.47       137,075       0.15       176,366       1,773       0.23       174,593       0.18       112,850       9,158       0.24       103,692       0.17  
  41       3595       149,483       29,542       0.53       119,941       0.13       172,821       5,908       0.23       166,912       0.17       105,170       4,431       0.24       100,738       0.16  
  42       3585       136,484       37,223       0.45       99,261       0.12       163,072       7,386       0.24       155,686       0.17       93,944       3,545       0.23       90,399       0.16  
  43       3575       115,214       36,632       0.50       78,582       0.13       168,389       6,795       0.24       161,595       0.16       86,263       1,773       0.21       84,490       0.16  
  44       3565       111,373       36,041       0.52       75,332       0.14       169,571       6,499       0.23       163,072       0.15       77,105       295       0.21       76,809       0.15  
  45       3555       110,783       42,836       0.48       67,947       0.16       179,911       5,613       0.23       174,298       0.15       71,787       1,182       0.21       70,605       0.15  
  46       3545       104,283       44,313       0.51       59,970       0.16       186,705       3,250       0.24       183,456       0.16       66,470       295       0.21       66,174       0.15  
  47       3535       92,762       53,766       0.67       38,995       0.18       199,409       3,840       0.25       195,568       0.17       60,561       -       -       60,561       0.14  
  48       3525       84,195       50,517       0.67       33,678       0.19       198,522       4,431       0.26       194,091       0.17       54,062       295       0.21       53,766.       0.13  
  49       3515       53,176       41,654       0.43       11,521       -       210,044       9,749       0.25       200,295       0.17       52,880       2,068       0.23       50,812       0.12  
  50       3505       46,972       46,972       0.49       -       -       196,159       15,362       0.28       180,797       0.15       49,335       2,659       0.24       46,676       0.15  
  51       3495       -       -       -       -       -       229,837       78,286       0.40       151,550       0.10       45,199       3,545       0.23       41,654       0.07  
  52       3485       -       -       -       -       -       272,082       169,867       0.58       102,215       0.13       45,199       6.499       0.25       38,700       0.04  
  53       3475       -       -       -       -       -       222,451       189,364       0.59       33,087       0.15       63,811       8,567       0.26       55,244       0.08  
  54       3465       -       -       -       -       -       175,479       173,707       0.63       1,773       -       75,332       12,112       0.24       63,220       0.14  
  55       3455       -       -       -       -       -       18,021       18,021       0.47       -       -       202,067       149,778       0.64       52,289       0.18  
  56       3445       -       -       -       -       -       -       -       -       -       -       187,296       124,963       0.65       62,334       0.19  
  57       3435       -       -       -       -       -       -       -       -       -       -       151,846       99,261       0.66       52,585       0.20  
  58       3425       -       -       -       -       -       -       -       -       -       -       126,440       86,263       0.61       40,177       0.20  
  59       3415       -       -       -       -       -       -       -       -       -       -       88,331       63,811       0.51       24,520       -  
  60       3405       -       -       -       -       -       -       -       -       -       -       55,834       38,700       0.45       17,134       0.21  
  61       3395       -       -       -       -       -       -       -       -       -       -       18,021       16,248       0.40       1,773       -  
  62       3385       -       -       -       -       -       -       -       -       -       -       4,727       4,431       0.31       295       0.20  
Total
              2,392,902       700,145       0.49       1,692,757       0.15       3,963,650       700,145       0.54       3,263,505       0.16       2,580,494       695,419       0.55       1,885,075       0.15  
Three Year Total
      8,937,046-       2,095,709       0.52       6,841,337       0.15                                                                                  

 
39

 
5.11    RISKS AND CONCLUSIONS
 
•  
Use of El Paso Data - The use of the El Paso data is problematic for determining good resource estimates. While Behre Dolbear does not have any reason to doubt the validity or the quality of the work, there is little ability to review the procedures and to check any of the work. It has been accepted for inclusion for this report based on the reputation that El Paso usually conducted professional and quality exploration programs along with the history of mining and copper production on the property. It does represent more than half of the data used to calculate resource model and, the uncertainty with the data does add some risk to the forward looking projections on the grade and tonnage of the deposit. RISK to resource statement - LOW to MEDIUM.
 
•  
Single Bulk Density for the Various Rock Types - The density measurements used by the RPA reports and others on the project range from 11.91 to 15.2. Some of these values were taken outside of the Gila Conglomerate but most samples were taken within this unit. The non-Gila Conglomerate or waste material could have a different tonnage factor than utilized for the estimation of projected tonnages. As a result, actual tonnage especially in the waste could vary plus or minus 10 percent. RISK to resource statement - LOW
 
•  
Lack of Independent Drilling and Sampling by Behre Dolbear - Behre Dolbear has done no independent sampling and verification of assay results. The 1992 and 1993 drill programs were conducted by an independent consultant, MDA, partially for a due diligence review. The 2004 drill program was monitored by RPA. The people used by both firms are known to be credible by Behre Dolbear and therefore we have accepted their work. The independent samples taken by MDA and RPA and a review their drilling and sampling procedures suggests that the assays are probably realistic. RISK to resource statement - LOW.
 
•  
Use of the NARSC Topography Map - The "as-is" topography was set using the maps produced by the National Applied Resource Sciences Center. Discussions with mine personnel suggested that there has been a minor amount of mining since that time.  In addition, the pit has some 20 or 30 feet of water standing in the bottom of the existing pit bottom so, Behre Dolbear relied on measurements taken by the current property manager. Recently, there has been some information to suggest that the NARSC topography has some slight errors mostly outside of the potential mining area. It is Behre Dolbear's opinion from their review that the overall impact of these issues should be minimal. RISK to resource statement - LOW.
 
 
40

 
 
Copper Revenue - Case 2 utilized a $2.75 per pound selling price for copper. While the currently copper price is over $3.00 per pound, it is usual to use the last 12 quarter average for resource and financial planning. At the present, the use of $3.00 per pound represents a risk for the case 2 scenario in that it uses more aggressive copper pricing than is traditional for a study of this type. RISK to resource statement - LOW to MODERATE.
 
6.0mining
6.1   introduction
 
As noted in Section 5.0 and at the request of SGV, Behre Dolbear has developed a potentially mineable resource (indicated resources) estimates and mining production schedules for two copper price scenarios. The production schedules are presented in Table 5.4 and 5.5 and see Figures 5.1 and 5.2 for the ultimate open pit outline. As directed by SGV, each reserve is mined over a three year period resulting in an ore production rate of 6,400 tons per week at a stripping ratio of 2.3:1 for Case 1 and 13,300 tons per week at a 3.3:1 stripping ratio for Case 2.

The previous operator removed ore from the pit via a crushing and conveying system in the North central wall of the existing pit (see Figure 6.1 for the location and topography of the existing open pit). It is assumed that a mining contractor will be organized to drill, blast, or rip, then load the ore at the face and transport it to a contractor owned and operated in-pit crusher for single stage crushing to <6 inches. The crushed ore is to be agglomerated and conveyed to the pit rim where it will be reloaded and transported to the heap (see Figure 6.2 for the heap location and Table 6.1 for the tons of heap capacity per lift). The contractor will drill and blast or rip the waste then load and haul it to the designated waste dump (see Figure 6.3 for the waste dump location).

6.2  pit slope design
 
The existing pit contains 60 foot stands of 76 degree slopes. The highest wall of the pit to the north is standing at 58 degrees including roads. The material in the pit wall is essentially devoid of joints and there do not appear to be any faults that are adverse to the slope. The existing pit walls are quite stable as long as water is not allowed to erode them. Behre Dolbear considers it safe for the proposed new mine design effort to use a 40 degree slope between roads resulting in a 37 degree slope overall. A slope stability analysis should be conducted by a qualified geotechnical engineer before pushing back the west high wall for Case 2. Potential exists to increase the slope angle and reduce the stripping ratio for that option.

 
41

 
 
 
42

 
 
 
 
43

 
 
Table 6.1
Heap and Waste Dump Capacity

CONCEPTUAL LEACH STOCKPILE
 
ELEVATION (ft)
   
AREA (sf|
   
VOLUME (cy)
   
TONS PER LEVEL
   
CUMULATIVE TONS
 
  3,680.00       62,306.63       0.00       0.00       0.00  
  3,690.00       231,309.09       54,373.28       73,403.93       73,403.93  
  3,700.00       377,242.23       112,694.69       152,137.83       225,541.76  
  3,710.00       446,255.04       152,499.49       205,874.32       431,416.08  
  3,720.00       627,617.15       198,865.22       268,468.05       699,884.12  
  3,730.00       580,760.31       223,773.60       302,094.37       1,001,978.49  
  3,740.00       518,738.01       203,610.80       274,874.58       1,276,853.07  
  3,750.00       459,792.44       181,209.34       244,632.61       1,521,4B5.68  
  3,760.00       403,951.53       159,952.59       215,935.99       1,737,421.68  
  3,770.00       351,234.84       139,849.33       188,796.59       1,926,218.27  
  3,780.00       301,622.37       120,899.48       163,214.30       2,089,432.57  
  3,790.00       255,126.15       103,101.58       139,187.13       2,228,619.71  
  3,800.00       211,791.03       86,466.15       116,729.30       2,345,349.00  
  3,810.00       171,773.79       71,030.52       95,891.21       2,441,240.21  
 
NOTE: TONS BASED ON 100lb/cy

WASTE ROCK STOCKPILE
 
ELEVATION (ft)
   
AREA (sf)
   
VOLUME (cy)
   
TONS PER LEVEL
   
CUMULATIVE TONS
 
  3,610.00       327.06       0.00       0.00       0.00  
  3,620.00       92,986.63       17,280.31       24,494.85       24,494.85  
  3,630.00       273,995.30       67,959.62       96,332.76       120,827.60  
  3,640.00       537,232.15       150,227.31       212,947.21       333,774.81  
  3,650.00       751,508.25       238,655.63       338,294.35       672,069.16  
  3,660.00       885,374.73       303,126.48       429,681.78       1,101,750.95  
  3,670.00       979,248.72       345,300.64       4B9.463.66       1,591,214.61  
  3,680.00       1,027,995.40       371,711.88       526,901.58       2,118,116.19  
  3,690.00       981,646.55       372,155.92       527,531.01       2,645,647.20  
  3,700.00       900,640.84       348,571.74       494,100.44       3,139,747.64  
  3,710.00       812,050.50       317,165.06       449,581.48       3,589,329.12  
  3,720.00       669,470.85       274,355.81       388,899.35       3,978,228.48  
 
 
44

 
 
 
 
45

 
 
It will be important for the mining contractor to groom and minimize the disturbance of the final pit walls as was done in the previous mining operations.

The mine plan specifically avoids the existing pit bottom during the first year of operation to allow time for dewatering and drying. The costs to dewater are included in the process section because the water will be pumped to the heap as process water.
 
6.3   haul road design
 
The haul roads are designed at 8% slope and minimum 50 feet wide. This width leaves 20 feet for haulage trucks in each direction after placing a 10 feet wide berm as required by OSHA.

6.4   waste dump design
 
The waste dump is placed in a location proposed by SGV (see Figure 6.3). The dump design is based on a side slope angle of 3:1 and the capacity by elevation is presented in Table 6.1. The dump design shown in Figure 6.3 includes levels beyond the 3,720 feet level shown in Table 6.1. The highest elevation in Figure 6.3 is 3,780 feet and, at this elevation, the cumulative dump capacity is 6,819,914 tons of waste. It is assumed that all of the waste in each case is placed in the dump shown in Figure 6.3. After SGV picks the mining plan to be permitted, it would be prudent to consider placing as much waste as possible back in the pit as the mine approaches the final year of operation.

SGV is currently reconsidering the location of the waste dump and will provide an alternative location for the Phase 2 report.

6.5   contract mining
 
As noted in the introduction, the contractor will conduct all operations required to move ore from the mine face through crushing and agglomeration and place it on the described heap. The contractor will also conduct all operations required to move waste material from the mine face to the described waste dump.

SGV will provide sufficient power to the pit bottom to accommodate 890 installed horsepower for the jaw crusher and agglomerator and 400 horsepower for the conveyor system. Water as required for haul roads and the crushing operation will be provided by the owner at a location to be agreed upon between the contractor and SGV.

 
46

 
The mining contractor will provide the personnel, equipment, maintenance facilities and administrative facilities to safely and consistently meet the production levels stated in Tables 5.4 and 5.5.

Behre Dolbear received pre-feasibility level contractor mining bids from N.A. Degerstrom, KGL Associates, Inc, and R.E. Monks Construction Company, LLC. The pre-feasibility quote provided to Behre Dolbear by N. A. Degerstrom, Inc. a contractor who has conducted operations in an operation near the Emerald Isle site in the recent past is $6.50 per ton of ore and $4.08 per ton of waste at a mobilization and demobilization charge of $600,000 for Case 1 and $4.63 per ton of ore and $2.31 per ton of waste at a mobilization and demobilization charge of $600,000 for Case 2. The quotes and bid comparisons are attached as Appendix 6.

6.6   dilution
 
Typically in a mining operation of this type, a dilution factor of 5% to 7% is applied to the established mineable resource. The dilution factor is applied to account for the mixing of waste material with the ore as the edges of the orebody are mined.

As noted in Section 6.2, Behre Dolbear believes that the development of a proper slope design analysis to establish the slopes for the West pit high wall will result in a steepening of that slope as compared to the conservative overall slope of 37 degrees used in this analysis.
 
Behre Dolbear believes that the reduced stripping cost, as a result of steepening the West wall slope and reducing the waste mined, will more than offset the reduced value due to dilution; therefore, no dilution factor has been applied to the mineable resource estimate used in this analysis. When SGV revises the West pit slope angles based on a geotechnical slope design analysis, a dilution factor of 5% to 7% should be applied to the mineable resource.
 
 
47

 
6.7   PRE-STRIPPING
 
It is assumed that pre-stripping should provide sufficient stripping to make six weeks of ore production available. Based on Tables 5.4 and 5.5, pre-stripping is estimated at 60,000 tons for Case 1 and 100,000 tons for Case 2.

6.8    MINE STAFFING
 
Behre Dolbear suggests the following staffing for the Emerald Isle mining operation.
 
•  
a 5 to 10 years of experience mining geologist with experience in mine planning at a base annual salary of $70,000 per year plus fringe benefits;
 
•  
an experienced (surveying, map making, ore control) mining technician at a base salary of $55,000 per year plus fringe benefits;
 
•  
if the mining contractor plans to run two shifts, add a local mining technician at an annual salary of $30,000 plus fringe benefits; and
 
•  
include in the operating costs a quarterly two day visit by a consultant mining engineer at an annual cost of $12,000.

6.9    CAPITAL AND OPERATING COSTS
 
The capital costs for the mining operation include: pre-stripping (60,000 tons for Case 1 and 100,000 tons for Cases 2 and 3), the mobilization and demobilization charges and costs for equipping the geologist and mining technicians and providing a vehicle (see Table 6.2).
 
Table 6.2 Pre-production and Post-production Mining Capital (US$000)
 
Cost
 
Case 1
   
Case 2
 
Contractor Mobilization
    350       350  
Pre-stripping
    291       290  
Mine Engineering and Equipment
    100       100  
Contractor De-mobilization
    250       250  
Total
    991       990  
 
The contractor charges more per ton of waste for the lower production in Case 1 thus offsetting the cost of the higher pre-stripping tonnage in Case 2.
 
 
48

 
The operating costs include the contractor's charges for mining per ton of ore and waste and the costs for the personnel as noted in Sections 6.5 and 6.8.

6.10   RISK ANALYSIS
 
There is a low to moderate risk that when SGV is ready to proceed with mining that N. A. Degerstrom, Inc. may not be available to service the Emerald Isle operation and another more expensive contractor may be the lowest bidder or that costs due to inflation or scarcity of required supplies (i.e., tires or fuel) may have increased inordinately.
 
 
49

 
 
7.0     processing
 
7.1     introduction
 
The Emerald Isle orebody has undergone several different metallurgical testing regimens over its history. No records are available for the test work accomplished by early 20 century operators or El Paso Natural Gas during its tenure on the property, but the Leach/Precipitation operations are thought to have achieved something in the range of 80% recovery of copper from a crushing/rod mill grinding/leach/iron precipitation operation. Ore grade values are also not existent, but are thought to have ranged from 0.60% copper to 1.20% copper. Tailings from that operational era have indicated assays from 0.17% copper to 0.22% copper.

Arimetco operated the property for a short time in the mid-1990s and although plagued with operational difficulties, managed cumulative heap recoveries of 62% over a period of 12 months. No operating conditions are known with the exception that the mine attempted operations at approximately 1,000 stpd but only reached that maximum in one month. The material as placed on the heap was "as mined" and probably included oversize up to 24 inches. The Arimetco plant consisted of 233 gpm SX/EW circuit which was capable of producing approximately 8,000 pounds of copper per day. The plant, including the heap loaded with 162,565 tons of material, was allowed to fall into disrepair. The production record for the Arimetco operation is shown in Table 7.1.

The copper recoveries achieved by Arimetco did not rise to the level planned for in this study. The major contributor to this variance is thought to be the size of the mine run rock which could easily have put large chunks of oxide copper into the heap. This oversize would require significant time under leach to reach higher recoveries and is the reason for proposing a single pass primary crusher at <6 inches for the SGV circuit. This is further reinforced by the consistently high recover of copper out of the heap, by Arimetco, after active mining had ceased. This suggests that a significant quantity of copper, placed on the heap by Arimetco, will be available for recovery by SGV early in the operation schedule.
 
 
50

 
Table 7.1
Arimetco Production Record
 
Month
 
Tons
   
%Cu (Total)
   
Lbs Cu to Pad
   
Lbs Cu Shipped
   
Cumulative Cu Recovery %
 
Pre-July 1992
    33,365       0.43       287,939              
July 1992
                            95,976       33.4  
August 1992
    21,525       0.58       249,690       96,017       35.8  
September 1992
    19,775       0.58       229,904       144,066       42.9  
October 1992
    10,795       0.56       120,904       48,058       43.3  
November 1992
    9,276       0.87       161,385       96,082       45.8  
December 1992
                            96,070       55.0  
January 1993
    945       0.69       13,041               54.3  
February 1993
    9,975       0.62       123,690               48.6  
March 1993
    14,945       0.50       149,450       95,991       50.4  
April 1993
    15,015       0.51       153,153       48,007       48.4  
May 1993
    28,950       0.70       377,300       48,135       41.2  
June 1993
                            144,052       48.9  
July 1993
                            96,025       54.1  
August 1993
                            48,027       56.6  
September 1993
                            96,137       61.8  
Total
    162,565       0.57       1,864,942       1,152,663       61.8  
 
Contemporary metallurgical testing by SGV at both Mountain States Research and Development (MSRD) and KDMR has included bench scale bottle roll and column testing. The metallurgical recoveries of copper in these tests have exceeded 70% over 85 days of leaching and is projected by Behre Dolbear to reach 80% after 210 days under leach. The ore, as in the case of historical operations, consumes significant quantities of sulfuric acid at approximately 70 pounds per ton of ore placed on the heap. This is an average of approximately 7 pounds of H2SO4 per pound of copper produced.
 
7.2     MINERAL PROCESSING AND METALLURGICAL TESTING
 
7.2.1   TSC Enterprises (Arimetco) Bottle Roll Testing
In 1988, high-grade samples of the Emerald Isle Mine mineralized body were taken by TSC and sent to the metallurgical laboratory at Cyprus Copper's Bagdad operation. The testing consisted of bottle roll and column leach testing on samples of high-grade (1.20% copper total) material which had been reduced in size from "as received" to <3mm (6 mesh) for bottle roll testing. The results are shown in Figure 7.1.

 
51

 
 

Figure 7.1. Cyprus Bagdad Bottle Roll Leach Tests
 
The bottle roll tests were conducted with 5 g/1 H2SO4 and indicated an acid consumption of 6.0 g acid/g copper produced. This is essentially the same as in the KDMR consumable projections for the project.

Column Leach Testing
Three 80mm (3 inch) columns, containing <10mm (% inch) material were used to demonstrate the leaching of Emerald Isle Mine mineralization under varying acid concentrations. Three concentrations of H2SO4 were used (7.9 g/1, 8.2 g/1, and 14.9 g/1). The column leached at 8.2 g/1 H2SO4 will be used for comparison to contemporary testing. The acid concentration was obtained by using Mineral Park (Mercator) rafinate which contains 0.57 g/1 Cu, 1.5 g/1 Fe, and 8.2 g/1 free H2SO4. The columns were leached in two passes of 12 liters each with a 72 hour rest period between the passes. Acid consumption for the test ranged from 5.7 to 5.9 g/F^SCVg Cu. This is a bit lower than the acid consumption for the bottle roll tests and is probably due to the larger size of material leached. The results of the test are

 
52

 
 


shown in Figure 7.2.
Hours
y= 14.331Ln(x)-4.0696

 
Figure 7.2. Cyprus Bagdad Column Leach Tests
 
7.2.2   sgv-msrdi
 
In October 2004, one sample of mineralized material from the Emerald Isle open pit and two samples of tailings were sent to MSRDI for metallurgical test work. A screen assay test was run on each sample to determine the different chemical phases of copper and zinc. In addition, bottle roll leach tests using sulfuric acid and ammonia were run on each sample to assess the leach-ability of the copper and zinc in the samples. Physical separation of the copper and zinc was evaluated through flotation and gravity concentration for the samples of tailings. The following is a brief summary of the procedures and results obtained at these tests as reported by MSRDI. The complete report is attached as Appendix 2 to this report.

 
53

 

Pit Run Ore
The head grade of this sample weighing 129 kg was 0.65% TCu and 1.31% zinc. The entire sample was crushed though % inch and four, 5,000 g sample splits were prepared. The balance of the initial 129 kg sample was kept for future tests. One 5,000 g sample was split into five,
 
1,000 g samples. A second 5,000 g sample was used for screen/assay test and the third 5,000 g sample was used for a screen/assay test on attritioned ore. One, 1,000 g sample was used for a head assay and two, 1,000 g samples were used for bottle roll leach tests, one using sulfuric acid leach (for copper) and the other one using ammonia leach (for zinc). Screen assays for the head sample after crushing to <3A inch.

Based on mineralogical assay and leach tests as described, MSRDI concluded that:
 
•  
some 80% of the copper and 96% of the zinc is soluble under typical heap leaching conditions;
 
•  
copper recovery after four days of leaching the crushed ore passing —A inch was 58.1%;
 
•  
zinc recovery after four days of leaching the crushed ore passing -A inch was 78.6%;
 
•  
acid consumption was 9.74 pounds of acid per pound of copper dissolved, with no credit for the zinc dissolved; and
 
•  
in the ammonia bottle roll leach test negligible copper and zinc were dissolved.
 
7.2.3   SGV - Metcon Research
 
In July, 2006, SGV contracted with KDMR to provide metallurgical testing in support of the re­start of operations at the Emerald Isle Mine. To this end Metcon Research has completed both small column and large column leach tests and an assay characterization of the head sample.

The head sample was taken by SGV and Behre Dolbear personnel from exposed workings within the Emerald Isle Pit. The screen analysis by KDMR is as follows in Table 7.3.

The analysis of the metallurgical sample indicates the following analysis:
 
 Copper - 0.42%
 Zinc-0.55%
 Iron-2.07%
 
 
54

 
 
Table 7.2 Screen Analysis Emerald Isle Ore Sample
 
Table 7.2A
 
   
Cu Assay %
   
Cu Distri
   
jution %
 
Size
 
Wt%
   
WA Sol.
   
Acid Sol.
   
CN Sol.
   
Total1
   
WA Sol.
   
Acid Sol.
   
CN Sol.
   
Total1
 
>0.5 inches
    35.9       0.121       0.273       0.014       0.385       22.7       19.9       23.2       22.3  
0.25 inches
    27.4       0.198       0.366       0.280       0.470       28.4       20.4       35.5       20.8  
20 Mesh
    26.6       0.029       0.530       0.015       0.660       29.1       28.6       18.4       28.3  
65 Mesh
    6.6       0.348       1.200       0.037       1.390       12.1       16.2       11.4       14.9  
<65 Mesh
    3.4       0.436       2.150       0.073       2.490       7.7       14.8       11.5       13.6  
Calc. Head
    100.0       0.191       0.492       0.022       0.620       100.0       100.0       100.0       100.0  
Table 7.2B
 
   
Zn Assay %
   
Zn Distri
   
jution %
 
Size
 
Wt%
   
WA Sol.
   
Acid Sol.
   
CN Sol.
   
Total1
   
WA Sol.
   
Acide Sol.
   
CN Sol.
   
Total1
 
>0.5 inches
    35.9       0.183       0.570       0.012       0.610       23.5       21.7       22.8       23.2  
0.25 inches
    27.4       0.194       0.610       0.015       0.620       25.5       20.0       20.5       20.6  
20 Mesh
    26.6       0.233       0.750       0.018       0.830       27.2       26.4       24.8       25.8 .  
65 Mesh
    6.6       0.341       1.700       0.045       1.850       13.8       15.8       15.8       15.0  
<65 Mesh
    3.4       0.590       4.660       0.082       4.900       10.1       16.1       16.2       15.4  
Calc. Head
    100.0       0.265       1.206       0.026       0.026       1.288       100.0       100.0       100.0  
1 Total Cu = WA Sol. + Acid Sol. - CN Sol.
 
 
 
 
55

 
Table 7.3
Screen Analysis "As Received Head Sample" Emerald Isle Mine

Screen Analysis
         
Bulk Sample EI060706-1
"As Received"
               
  Nominal Openings    
Sample
    Weight    
Cumulative Weight
   
Copper
   
Iron
Millimeters
     
Inches
     
Tyler Mesh
   
Sample Weights (kg)
   
Distribution
(%)
   
Retained
(%)
     
Passing
(%)
   
Assay
 (%)
 
Content
 
Distribution
(%)
   
Assay (%)
 
Content
 
Distribution
(%)
  152.40       6             57.50       4.79       4.79       95.21                
  100.00       4             80.00       6.66       11.45       88.55                
  50.00       2             206.50       17.19       28.64       71.36                
  37.50       1.5             95.50       7.95       36.59       63.41                
  25.00       0.984       1       159.00       13.24       49.83       50.17                
  19.00       0.748    
Va
      102.50       8.53       58.37       41.63                
  12.50       0.492               136.00       11.32       69.69       30.31                
  9.50       0.374       3/g       64.00       5.33       75.02       24.98                
  6.30       0.248    
Va
      75.50       6.29       81.31       18.69                
  4.76       0.187       4       40.00       3.33       84.64       15.36                
  3.35       0.132       6       36.00       3.00       87.64       12.36                
  1.70       0.067       10       55.00       4.58       92.21       7.79                
MINUS
              10       93.50       7.79       100.00                        
Totals
      1,201.00       100.00                                
Calculated Assay
                                               
Composite Assay
                                               
 
 
56

 


 
Figure 7.3.  Cumulative Weight Percent Passing Versus Particle Size - Emerald Isle -Assay Screen Analysis
 
Preliminary bottle roll tests were run on a pulverized sample taken from EL070606-1 to determine the leachability of the sample as received from the SVG Emerald Isle Pit. The bottle roll was operated for 48 hours and delivered an acid consumption of 40 kg/tonne or 79 pounds per stdt and a copper recovery of approximately 60%. The results are tabulated in Table 7.4.

Following the successful bottle roll test three columns were assembled with <6 inch, <2 inch, and <% inch material from sample EI070606-1. The three columns would evaluate the leach kinetics for the three sizes and evaluate the probable final recovery from the Emerald Isle ore. After 85 days of leaching the columns had reached +70% copper recovery and were still adding recovery. Behre Dolbear has projected that over one year of leaching an ultimate recovery of 80% copper is attainable. The results are shown in Table 7.5.

Figures 7.4 through 7.13 illustrate the performance of the columns are shown as follows.
 
 
57

 

 
 
58

 

 
Table 7.5
Summary of Metallurgical Results
St. Genevieve Resources Ltd. - Emerald Isle Project
Crush Size Column Leach Study 
 
METCON Research Project No. M-681-01                                                                                                      Date: 11/19/06

Sample ID
Test Number
Crush Size
Cure
Lixiviant Application Flow Rate
(1/h/m2)
Leach Cycle (Days)
Pregnant Solution
Free Acid (g/1)
pH
ORP
(mV)
Cu
(g/1)
Zn
(g/1)
Fe (g/1)
Dosage (kg/t)
Time
(Days)
Bulk Sample EI060706-1
CL-07
-A inches
10
10
6
85
4.84
1.62
701
0.33
0.91
4.90
CL-08
-2 inches
10
10
6
85
5.62
1.59
714
0.33
0.92
4.90
CL-09
-6 inches
10
10
6
85
5.95
1.53
707
0.34
0.93
4.90
 

Table 7.5
Summary of Metallurgical Results
St. Genevieve Resources Ltd. - Emerald Isle Project
Crush Size Column Leach Study (continued)
 
METCON Research Project No. M-681-01                                                                                Date:11/19/06

Indicated Extraction
Sulfuric Acid Consumption
Cu
(%)
Zn
(%)
Fe
(%)
Total
(kg/t)
Gangue
(kg/t)
(kg/kg Cu)
74.94
75.79
4.82
47.88
42.98
13.53
76.02
77.21
5.12
45.70
40.81
12.87
73.10
66.44
2.12
44.21
39.39
12.59

 
59

 
 
 
 
60

 
 
 
 
61

 
 
 
 
62

 
 
 
 
63

 
 
 
 
64

 
 
7.3    ore mineralogy
 
The copper minerals present in the ore at the Emerald Isle ore are:
 
1. Chrysocolla (CuSi03 • 2 H20);
2. Dioptase (H2CuSi04);
3. Tenorite (CuO); and
4. Malachite (CuC03 • Cu(OH)2).

7.4    proposed flowsheet
 
As mined ore will be processed by the mining contractor in a design of the contractor's choosing. The circuit will consist of a primary jaw crusher, agglomeration stage, and conveyor system for removing the ore from the pit to a point on the pit rim. The contractor may chose to convey ore directly to the top of the heap or to trans load the material into haulage trucks for transport to the top of the heap.

The crushed ore, <6 inches, will be stacked on the existing leach pad (228,000 t) until it is full. The remaining resource will be placed upon a new single lined, 80 mil, HDPE lined pad. The leach solutions will be delivered to the pad at a pH of 1.5 and collected at a pH of approximately 3.0. Pregnant solution at 2.5 g/1 copper, are contacted with barren organic in the mixer settler section. The barren organic containing a typical mixture of 12% to 15% LIX 64 is contacted with PLS, recovering approximately 96% of the copper. The remnants of the existing Emerald Isle SX/EW plant is configured in two mixer settler series of solvent extraction cells coupled with one stage of stripping. Under Case 1 conditions, some 8,000 pounds of copper will be recovered as cathode per day. In the Case 2 configuration the extraction cells will be arranged in parallel, giving up some copper recovery and the result will be approximately 15,000 pounds of copper per day. Following extraction, the loaded organic will be contacted with strong electrolyte in a single stage of stripping. The barren organic will be returned to the 1st stage mixer extractor and the pregnant electrolyte will be sent to electrowinning. Under Case 1 conditions, approximately 40 stainless steel "mother sheets" and lead alloy anodes will contact the pregnant electrolyte with a direct current. The plant will produce LME Grade copper cathodes which will sell for a premium in the current market.
 
 
65

 
 
It should be noted that the issue of ultimate heap height and relative heap stability were addressed by Montgomery Watson. The overall conclusion was that the proposed heap height of approximately 130 feet is sustainable over a properly engineered and constructed foundation.
 
7.5     RECOVERY Copper
 
For the purpose of planning for heap output, Behre Dolbear has utilized the extraction curve, as developed by Metcon Research, to project copper leaching from inception. The full extraction of copper is planned for a 7 month (210 day) cycle for each panel of ore as it is introduced to irrigation. Ultimate heap copper recovery is projected to reach 80%+.

Zinc
The Emerald Isle ore will contain zinc in quantities equal to or slightly greater than the copper content. The metallurgical sample, as used by Metcon Research, contained 0.42% copper, 0.55% zinc, and 2.07% iron. The zinc probably exists in the ore as the highly soluble hydrozincite. Over time, the zinc will build up in the circuit requiring that the barren electrolyte be bled at a rate sufficient to keep quality standards up in the production of cathodes. The initial plant operations will not include any zinc removal bleed facilities, but by Year 3 or so, an evaporation pond may be required to keep zinc levels at an appropriate level.

7.6   PRODUCTION SCHEDULE
 
A ramp up schedule for Case 1 is shown in Table 7.6. The schedules for Case 2 and Case 3 are expected to follow at a similar trend.
 
Table 7.6
Emerald Isle Metallurgical Forecast and Production
Case 1 (approximately) 1,000 stpd $2.00 per pound of Copper
 
   
Qtr 1
   
Qtr 2
   
Qtr 3
   
Qtr 4
   
Total Yr 1
   
Total Yr2
   
Total Yr3
   
Total 6mo Yr 4
 
Tons Heap
    82,570       82,570       82,570       82,570       330,280       330,280       324,667        
Heap % Cu
    0.50       0.44       0.56       0.96       0.62       0.75       0.52        
PLS g/1
    2.52       2.30       2.83       4.50       3.03       3.00       2.82       0.50  
PLS gpm
    233       233       233       233       233       233       233       233  
Cu lbs
    515,791       579,205       720,001       1,132,743       2,947,739       4,168,256       2,859,617       238,106  
 
Heap recovery estimated to reach 80%+ Cu in 7 months. No production forecast past 7 months
 
 
 
66

 
 
7.7     REAGENTS AND CONSUMABLES
 
The proposed operations do not employ any process reagents or heavy consumables which are in difficult or short supply. A listing of representative reagents and supplies is indicated in Table 7.7.
 
Table 7.7
Process Reagents and Consumables
Case 2 (approximately) 2,000 stpd
 
Identification
 
Use
 
Consumption Rate
L1X  
Selectively recovers Cu from PLS
 
2,649 gal/year
Diluent (Kerosene)
 
Used to dilute the LIX to 10%
 
23,839 gal/year
Cobalt Sulfate
 
Pb Anode Corrosion Inhibitor
 
0.38 Ib/t Copper
Sulfuric Acid
 
Leaching agent for Cu
 
60 lb/t Ore

7.8     METALLURGICAL ENGINEERING
 
The metallurgical engineering support will be furnished by the process manager and a metallurgist with support from outside consultants, as needed. The level of metallurgical support is more than sufficient to control a small copper heap leach and SX/EW operation.

7.9    MANPOWER REQUIREMENTS AND WORK SCHEDULES
 
The process plant will be scheduled on a 7-day schedule operating on two 12-hour shifts. When on a 7-day, 21-shift schedule, the process section utilizes 31 operating and supervisory personnel.

Maintenance staffing is included in the process staffing, and is adequate for the planned level of operations. Maintenance personnel, primarily millwrights and electrician/instrument personnel are assigned to a 5-day-per-week, one-shift-per-day schedule. SX/EW plant operators will be trained and qualified to perform operations tasks and required mechanical maintenance.

7.10   CATHODE QUALITY
 
During the operation of the property by Arimetco, cathodes were produced which met LME grade 1 quality standards. A complete record of all Arimetco shipments was not available for review, but several certified analyses were found and compared with certain others. The certificate is representative of the samples reviewed by Behre Dolbear. The certificate of analysis was completed by Accredited Laboratories Inc., Carteret, New Jersey, a subsidiary of AMAX (Phelps Dodge). The analysis is summarized in Table 7.8.
 
 
67

 
 
Table 7.8
Certificate of Analysis
Arimetco Cathode Case No. 676
 
Field I.D.
   
Sample No.
 
Parameter
 
Results
 
Units
  082E01,02,03       9205776  
Sb
 
<3
 
ppm
             
As
 
<3
 
ppm
             
Bi
    0.3  
ppm
             
Fe
    6  
ppm
             
Pb
    4  
ppm
             
Ni
    4  
ppm
             
Se
 
<3
 
ppm
             
Ag
 
<3
 
ppm
             
Te
 
<2
 
ppm
             
Sn
 
<1
 
ppm
             
S
    2  
ppm
       
By Difference
 
Cu
    99.998  
%
 
Based on the historical record, Behre Dolbear is confident that the ore and treatment plant can combine to produce high quality cathodes. The zinc problem will, however, demand a solution as the project nears Year 2 or Year 3 of its life.

7.11    COMMENTS AND RISK ANALYSIS
 
Process risk is based upon the following comments:
 
•  
The water supply must be defined for both the approximately 1,000 and 2,000 stpd operating cases. Currently the project will be minimally able to support Case 1 (approximately 1,000 stpd) and will require a doubling of the fresh water supply from the ± 60 gpm level to ± 100 gpm. The water supply risk must be rated as high for Case 2 and Case 3.
 
 
 
68

 
 
•  
The presence of zinc, in quantities equal to or greater than the copper in solution, must also be addressed after operations begin. Because the project has a short production life, it is expected that a relatively inexpensive evaporation system may handle the problem.
 
The copper production from the El Paso low-grade ore stockpiles and from the El Paso tailings has not been substantiated at this time. Prior to start up under Case 3 conditions, SGV must sample, assay, and metallurgically test the suspected mineralization in both areas.
 
 
69

 
 
8.0    INFRASTRUCTURE
 
8.1  INTRODUCTION
 
The Emerald Isle physical plant and mine has been in evidence for over thirty years. The main office, mine, and process plant are within 1.5 miles of the northwest-southeast U.S. Highway 93 which runs from Las Vegas, Nevada to Phoenix, Arizona. The main waste stockpile is within sight of but is not noticeable from the highway. Kingman, Arizona, the closest major metropolitan center with all needed industrial, residential, and hospital services, is about a half-hour drive away by U.S. Highway 93. Of highest concern is the availability of process water. The water available in the three SGV controlled wells is marginally acceptable for operations at the Case 1 (approximately 1,000 stpd) level but will not support Case 2 of Case 3 (approximately 2,000 stpd).

8.2    TRANSPORTATION
 
Access to the Emerald Isle Property is by paved roads, U.S. Highway 93, from Phoenix, Arizona or Las Vegas, Nevada. The Emerald Isle Mine is located approximately 1.5 miles northwest of the City of Kingman, Arizona and some 100 miles southeast of Las Vegas, Nevada. The population of Kingman, Arizona is about 10,000. The Emerald Isle Mine is situated 1.5 miles from U.S. Highway 93 within the Wallapai Mining District, Mohave County, Arizona.

Rail service is available in Kingman, Arizona on the Burlington Northern Santa Fe railroad.

Kingman, Arizona has regularly scheduled (4 flights per day) air transport from the Kingman airport to Phoenix, Arizona on the Great Lakes Air Lines.

8.3     WATER SUPPLY
 
The project fresh water supply is suspect. Three wells are located near the site and were pump tested in October 2006. Table 8.1 details the results of the test.
 
 
70

 
 
Table 8.1
Fresh Water Wells Emerald Isle Mine
 
Well
No.
 
Location
 
Depth
(feet)
   
Test Yield (gpm)
 
Comments
  1  
-7,000 feet North of the Plant Site
    125       33  
Water quality appeared good
  2  
-8,000 feet North of the Plant Site
    125       -12  
Water quality poor due to  fine particulates
Pat-1
 
-2,000 feet South of the Plant Site
    300       22  
Well is on private land and will require a negotiated agreement to use

 
71

8.4     ELECTRIC POWER SUPPLY
 
An existing 69 KV line terminates approximately 1,500 feet from the mine site. The previous operation of the plant utilized on site generation. The SGV approach is to extend the existing 69 KV line to a new substation on site. The power company, Unisource, has published rates for large industrial consumers (see Table 8.2).
 
Table 8.2
Unisource Power Rates
 
Schedule
Name
Demand
 
Cost
 
Energy Charge
Energy Cost
Minimum
Demand
LPS
Large General
Service
All Demand
  $ 9.50/KW  
All Usage
$0.0533/KWH
500-1,000 KW

8.5     COMMUNICATIONS

The site can be equipped for land line telephone and internet access.
 
 
72

 
 
8.6     SURFACE FACILITIES
 
The plant facilities in general are and appear old. Currently the existing SX/EW facilities are in need of refurbishment and repair. A small office trailer is on site and may be retained for use as a mine engineering area. Additional office trailers will be required for use by administrative personnel. There is no basic analytical or sample preparation building on site. It is planned to convert one or more used shipping containers to this task and install laboratory equipment that SGV has acquired and stored on site.

Metallurgical and analytical laboratory facilities will provide for operational control. Quality control copper assays will be contracted out.

8.7    MINERAL TITLE, LAND, AND WATER RIGHTS
 
The Emerald Isle Mine property is located in Sections 22, 23, 26, 27 of Township 23N, R18W, in the Wallapai District, Mohave County, Arizona and consists of 37 Unpatented Lode Mining Claims and 12 Mill-site Claims, registered with the Mohave County Mining Recorder and the BLM in Kingman, Arizona, as shown in Table 8.3. Behre Dolbear has not included verification of land and water rights under its scope of work. Title to water and land will have to be given to legal counsel for verification.
 
The Emerald Isle claims are shown as Active with Assessment Fees paid through 2007 in the BLM LR 2000 Mining Claim Geographical Report. The two wells. No. 1 and No. 2, north of the mine belong to  the BLM but mining is specified as the use and the Emerald Isle Mine is specified as the point of use.
 
 
73

 
 
Table 8.3
List of Mineral Claims SGV Emerald Isle Property
 
Claim Name
 
Approximate Area Acres
   
AMC Number
 
Remarks
Copper Hill Mill Site No. 1
    3.5       105792    
Copper Hill Mill Site No. 2
    3.5       105793    
Copper Hill Mill Site No. 3
    3.5       105794    
Copper Hill Mill Site No. 4
    3.5       105795    
Copper Hill Mill Site No. 5
    3.5       105796    
Copper Hill Mill Site No. 6
    3.5       105797    
Copper Hill Mill Site No. 7
    3.5       105798    
Copper Hill Mill Site No. 8
    3.5       105799    
Copper Hill Mill Site No. 10
    3.5       105801    
Copper Hill Mill Site No. 11
    3.5       105802    
Copper Hill Mill Site No. 12
    3.5       105803    
Copper Hill Mill Site No. 13
    3.5       105804    
Copper Hill Mill Site No. 14
    3.5       105805    
Copper Hill Mill Site No. 15
    3.5       105805    
Copper Hill No. 2
    13.8       105785 6A55-56    
Hermes
    13.8       105786 6A62-64    
Hermes No. 2
    13.8       105787 6A63-64    
Jimtown Copper No. 1
    13.6       105788    
Valley Copper No. 1
    10.4       105789  
Overstaked
Valley Copper No. 2
    13.8       105790    
Valley Copper No. 3
    13.8       105791    
Emerald No. 1
    6.9       339597  
Overstaked
Emerald No. 2
    13.8       339598    
Franklin D. Roosevelt
    3.8       90056    
Subtotal Old Claims
    176.2            
 
 
 
74

 
 
Table 8.3
List of Mineral Claims SGV Emerald Isle Property (continued)
 
Claim Name
 
Approximate Area Acres
   
AMC Number
 
Remarks
Emerald No. 1A
    13.8       364261    
Emerald No. 2A
    13.8       364262    
Emerald No. 3
    13.8       364263    
Emerald No. 4
    13.8       364264    
Emerald No. 5
    13.8       364265    
Emerald No. 6
    13.8       364266    
Emerald No. 7
    13.8       364267    
Emerald No. 8
    13.6       364268    
Emerald No. 9
    13.8       364269    
Emerald No. 10
    4.9       364270  
Overstaked
Emerald No. 11
    12.1       364271  
Overstaked
Emerald No. 12
    0.2       364272  
Overstaked
Emerald No. 13
    13.6       364273  
Overstaked
Emerald No. 14
    5.4       364274  
Overstaked
Emerald No. 15
    13.8       364275    
Emerald No. 16
    10.4       364276  
Overstaked
Emerald No. 17
    13.8       364277    
Emerald No. 18
    6.9       364278  
Overstaked
Emerald No. 19
    13.8       364279  
Overstaked
Emerald No. 20
    6.7       364280  
Overstaked
Emerald No. 21
    13.6       364620  
Overstaked
Emerald No. 22
    7.4       364621  
Overstaked
Emerald No. 30
    0.2       365622  
Overstaked
Emerald No. 31
    12.4       364623  
Overstaked
Emerald No. 43
    3.5       364624  
Overstaked
Emerald No. 44
    0       364625  
Overstaked
Emerald No. 45
    0       364626  
Overstaked
Subtotal New Claims
    106.6            
Total
    177.9            
 
 
75

 
 
9.0    ENVIRONMENTAL
 
9.1    INTRODUCTION
 
The environmental and permitting aspects of the proposed reopening of the Emerald Isle mine were investigated by Behre Dolbear during March 2006 by visiting the mine site, discussing environmental matters with Bryan Wilson, President of SGV and Fred Brost, President of Mining and Environmental Consultants, Inc. who has been responsible for most of the recent permitting activity.

Two days were spent in the Phoenix, Arizona office of Mining and Environmental Consultants, Inc. reviewing documents, maps, and photographs and holding telephone discussions with regulatory personnel in the Arizona Department of Environmental Quality (ADEQ) and the BLM.

Since March 2006, Behre Dolbear has maintained telephone contact with Mr. Brost regarding his activities on behalf of SGV. Mr. Brost has also furnished Behre Dolbear copies of updated documents received from government agencies.
 
9.2      BACKGROUND
 
The operation of the Emerald Isle Mine, prior to its purchase in 2004 by SGV, appears to have been properly permitted by ADEQ and BLM. The previous operator, Arimetco International/TSC Enterprises, Inc. constructed a heap leach operation and SX/EW plant in 1992, utilizing ore mined from a nearby open pit. All production ceased before the end of 1993 and the facilities on the site have remained idle since that time. The two major permits for the operation, the Arizona Aquifer Protection Permit and the approval of the Mining Plan of Operations and Reclamation Plan by the BLM, as issued to the previous operator (TSC Enterprises) remain valid, but modifications to these two permits showing SGV Resources as the operator remain to be approved.

9.3      GENERAL DESCRIPTION
 
The Emerald Isle Mine is located on unpatented mining claims on BLM land, about four miles south of Chloride, Arizona an old silver mining district. Emerald Isle lies on a peneplain at the western flank of the Cerbat Range. The elevation at the mine is about 3,700 feet. The annual precipitation is less than 10 inches. Vegetation is sparse. Surrounding land is primarily wildlife habitat. No threatened or endangered species have been reported in the mine area.

 
76

 
9.4    REQUIRED PERMITS AND STATUS
 
•  
Aquifer Protection Permit - ADEQ: Financial assurance is needed for construction, operation, and closure including post closure monitoring (per Eric Wilson, ADEQ). This financial assurance must involve a credible estimate of the construction, operating, and closure costs. In addition, there needs to be a letter from SGV's Chief Financial Officer stating that the company has the financial foundation to carry out construction, operation, and closure of the property. A letter from the participating financial institutions indicating that the financing is in place would be helpful, perhaps required. The most recent SEC (10K, 10Q, 20F, or a Canadian equivalent) report may also be helpful, if financing is in place. For the closure costs, a surety bond, cash bond, letter of credit, or insurance or some combination thereof will have to be provided to ADEQ. This is in addition to the reclamation bond to be provided to BLM, but involves only additional measures to protect water resources.
 
•  
SGV will have to resolve violations which are: water in the pit and the lack of diversion structures to prevent or reduce the amount of water entering the pit. The transfer of the permit to SGV, however, is not contingent on resolving the violations. For example, the water in the pit will likely be used in the initial operation and if there is excess it will probably be evaporated. Work is in progress on the diversion structures.
 
•  
The leach pad and ponds are lined although the raffinate pond liner must be replaced. The pad liner has had an engineering inspection to assure that it remains serviceable. A geotechnical study of the heap has also been conducted to determine how high material may be safely placed.
 
•  
Fred Brost, Environmental Consultant, has prepared graphs of various parameters measured in monitoring wells from 1989 through 2006 to see if there are any trends that might require action on SGV's part. The graphs indicate that while alert levels have been exceeded from time to time, the quality of groundwater entering the property (measured in an up gradient monitoring well) is generally about the same as, or worse than, that measured in down gradient wells.
 
 
77

 
•  
Storm Water Discharge Permit - ADEQ: Behre Dolbear has a copy of a letter from ADEQ dated August 4, 2006 authorizing SGV to discharge storm water under the terms of the Arizona General Permit for Construction activities. Another such letter will be needed later for storm water discharge for mining and processing operations. SGV has the Pollution Prevention Plan required by this permit, although it will likely have to be updated. This Plan does not have to be submitted to ADEQ but must be kept on file at the mine to be available for inspection. This plan should be modified, in the future as needed, to conform with any changes made in the operation.
 
•  
Air Quality Control Permit - ADEQ: Behre Dolbear has a copy of a letter dated March 28, 2005 from ADEQ that a permit is not required at this time because planned emissions are below the permit threshold. However, if the mining plan changes from the one used by ADEQ to issue that letter, then a permit may be required. Use of a crusher will likely require a permit, although it is possible that a mining contractor, as planned for the site, will have a permit for a mobile crusher. Further consultation with ADEQ would be needed.
 
•  
Mining Plan of Operations and Reclamation Plan - BLM Approval: Primarily awaiting provision of a reclamation bond. The amount of this bond has been calculated at $223,000 plus some yet to be determined amount for removal of Transite® (asbestos containing) pipe which connects the mine facility to the water wells. Additionally, a BLM resource specialist has questions regarding the proposed new waste rock dump, which may be able to be resolved once a detailed mining plan is completed. That plan could indicate that it is practical to return some waste rock to the pit during the life of the mine. If not, then some redesign of the dump may be required. This issue will have to be resolved before approval of SGV's modification of the Mining Plan of Operations is forthcoming from the BLM.
 
 
78

 
•  
Right to Use Water From Wells North of Mine - BLM: Will remain as BLM wells, but the BLM will make it clear that mining is an approved use, and Emerald Isle is the point of use (per Lynn Feldman, BLM). These wells have state permits.
 
•  
Pump tests were conducted on Well No. 1, Well No. 2, and Pat-1 (a monitor well southwest of the mine). Well No. 1 produced 33 gpm and Pat-1 produced 22 gpm with steady draw-down after 24 hours. The test on Well No. 2 was terminated after 5 hours due to low volume and visibly poor water quality. Other sources of water are being investigated, including additional wells along the pipeline right-of-way, the City of Chloride, and the Mineral Park operation.
 
•  
Right-of-Way for Pipeline from Wells to Mine: Behre Dolbear has a copy of a letter dated December 23, 2005 from BLM to SGV stating that the assignment of right-of-way AZA-740 to SGV has been granted.
 
•  
Right-of-Way for New Power Line: Behre Dolbear has copies of two letters both dated January 20, 2006 from the BLM granting rights-of-way AZA-31567 and AZA-33319 to UNS Electric, Inc.

9.5     DOCUMENTS REVIEWED
 
•  
Aquifer Protection Permit P-101846 dated June 4, 1993 issued to TSC Enterprises and SGV's application for a transfer of the Permit dated July 25, 2005. Also a letter from ADEQ dated February 27, 2006 requesting information including financial assurance data.
 
•  
SGV's submission to the BLM of a Mining Plan of Operations and Reclamation Plan Modification dated June 2005.
 
•  
Pertinent parts of the 2005 Roscoe Postle Associates Report.
 
•  
Pertinent parts of SGV's 2006 Scoping Study and Development Plan.
 
•  
Various other communications from government agencies and pertinent regulations.
 
 
79

 
9.6      CONCLUSIONS
 
The major impediment to completing government approvals of SGV's proposed Emerald Isle operations is getting the financing in place to assure ADEQ of SGV'S ability to construct, operate, and close Emerald Isle. Additionally, bonding must be provided to the BLM. This may require a cash bond (e.g., certificate of deposit). Once the financing has been obtained, Behre Dolbear believes that any other issues remaining before final transfer of the permits to SGV can be readily resolved.
 
9.7      ENVIRONMENTAL RISK ANALYSIS
 
The following possible contributors to the overall project environmental risks have been identified. None of the identified potential risk-bearing items has a level greater than moderate. The risk areas are listed as follows:
 
•  
Potential for denial of a needed permit - LOW RISK.
 
•  
Potential for delay of 6 months to a year on a needed permit - MODERATE RISK.
 
•  
Potential for longer delay of a needed permit - LOW RISK.
 
•  
Potential for the site to be addressed by a Superfund action - LOW RISK. Unless SGV fails to carry out its plans and goes out of business, even then there is no risk to a lender unless that lender has taken actions that would allow the BLM or EPA to consider the lender to be an operator.
 
 
80

 
10.0   CAPITAL COSTS

10.1    INTRODUCTION AND SUMMARY
 
Capital costs for the restart of operations include refurbishment of the exposed portions of the heap liner which is in place, repair of the PLS pond, reconstruction of the raffinate pond, replacement of all heap piping and pumping, renovation of the SX/EW facility, reconstruction of the plant electrics including incoming power line, substation, switch gear and plant wiring, rehabilitation of the plant fresh water supply, and construction of administrative facilities. All capital costs for Case 2, with certain exceptions, have been developed by KD Engineering (see Appendix 3). Capital spending for Case 1, which has been factored from the Case 2 estimate, by Behre Dolbear, is summarized in Table 10.1.

Case 2 and Case 3 capital costs are shown in Table 10.2.
 
10.2    MINE CAPITAL COSTS
 
Basis of Estimate
The mine capital cost estimate includes the purchase costs for all mine engineering and geology equipment. The mining contractor will furnish all drilling, blasting, hauling, crushing, and conveying costs. There is no allowance for sustaining capital. All costs are stated in constant 2006 dollars with no escalation for inflation.

Estimate Qualifications
The estimate has been prepared by Behre Dolbear. Equipment bids were not solicited and the estimate includes only equipment purchased by SGV and dedicated to the support of the mine engineering and geology functions.

Current Estimate
The current mine capital cost estimate includes $100,000 pre-production capital expenses with no sustaining capital over the approximately 4 year life-of-mine plan. Details of the mine capital cost estimate are shown in Table 10.1 for Case 1 and Table 10.2 for Case 2 and Case 3.
 
 
81

 
Table 10.1
Emerald Isle Capital Costs
Case 1 (approximately) 1,000 stpd
 
   
Year
Item
 
Total ($)
   
-1 ($)
   
kd
   
2($)
 
3($)
4 (Si
Non-Contractor Mine Costs
Engineering Vehicles
    30,000       30,000                  
Engineering Equipment
    70,000       70,000                  
Total Mine Capital
    100,000       100,000                  
Process Capital
Solvent Extraction
    187,374       187,374                  
Electrowinning
    408,157       408,157                  
Tank Farm
    473,856       473,856                  
Ponds and Piping
    447,042       447,042                  
Water Development Costs
    330,000       330,000                  
Electrical
    860,000       860,000                  
Leach Pad Expansion
    1,848,000               924,000       924,000      
Miscellaneous
    264,000       264,000                      
Total Process Capital
    4,818,429       2,970,429       924,000       924,000      
Infrastructure
Administrative Building
    100,000       100,000                      
Vehicles
    70,000       70,000                      
Shop Tools and Equipment
    50,000       50,000                      
Backup Power Supply
    75,000       75,000                      
Office Equipment
    20,000       20,000                      
Total Infrastructure Capital
    315,000       315,000                      
Project Indirects
Detail Engineering
    140,000       140,000                      
Construction Management
    150,000       150,000                      
Initial Fills
    231,000       231,000                      
Bonding
    312,400       312,400                      
Total Indirects
    833,400       833,400                      
Totals
    6,066,829       4,218,829       924,000       924,000      
 
 
82

 
Table 10.2
Emerald Isle Capital Costs
Case 2 and Case 3 (approximately) 2,000 stpd
 
   
Year
Item
 
Total ($)
   
-1 ($)
   
KD
   
2($)
 
3($)
4($)
Non-Contractor Mine Costs
Engineering Vehicles
    30,000       30,000                  
Engineering Equipment
    70,000       70,000                  
Total Mine Capital
    100,000       100,000                  
Process Capital
Solvent Extraction
    211,700       211,700                  
Electrowinning
    427,420       427,420                  
Tank Farm
    591,464       591,464                  
Ponds and Piping
    532,803       532,803                  
Water Development Costs
    500,000       500,000                  
Electrical
    1,075,000       1,075,000                  
Leach Pad Expansion
    2,800,000               1,400,000       1,400,000      
Miscellaneous
    264,000       264,000                      
Total Process Capital
    6,402,387       3,602,387       1,400,000       1,400,000      
Infrastructure
Administrative Building
    100,000       100,000                      
Vehicles
    70,000       70,000                      
Shop Tools and Equipment
    50,000       50,000                      
Backup Power Supply
    75,000       75,000                      
Office Equipment
    20,000       20,000                      
Total Infrastructure Capital
    315,000       315,000                      
Project Indirects
Detail Engineering
    200,000       200,000                      
Construction Management
    150,000       150,000                      
Initial Fills
    288,750       288,750                      
Bonding
    312,400       312,400                      
Total Indirects
    951,150       951,150                      
Totals
    7,768,537       4,968,537       1,400,000       1,400,000      
 
 
83

 
 
10.3   PROCESS CAPITAL COSTS
 
The process capital cost estimate was prepared in detail by KD Engineering. Process capital related costs include Heap Leaching, Solvent Extraction, Electrowinning, and Site Electrical components. The costs for Case 1 are summarized in Table 10.1 with the Case 2 and Case 3 costs summarized in Table 10.2. The detailed KD Engineering capital cost estimate is attached as Appendix 3. The process capital total spending as shown in the KD Engineering estimate differs slightly from the Behre Dolbear report. This is due to consolidating certain charges under SGV administrative costs in Year -1. Capital costs for heap, liner, and pond construction have been addressed by MWH as shown in Appendix 4.

Basis of Estimate
The process capital cost estimate includes the purchase and installation costs for all process and related infrastructure functions. The estimates are prepared in constant 2006 U.S. dollars. The Case 2 and Case 3 estimate at approximately 2,000 stpd, as prepared by KD Engineering, was factored by Behre Dolbear to include a Case 1 estimate at approximately 1,000 stpd.

Estimate Qualifications
The capital cost estimates do not the following exclusions:
 
• Miscellaneous painting;
• Zinc removal bleed pond;
• Definitive water development costs (allowances only);
• Upgrade to the power line;
• Trade off studies;
• Mining and ore haulage costs;
• Laboratory;
• Property acquisition, if any;
• Environmental permits;
• Consultant costs;
• Research and Development costs;
• Metallurgical testing;
• Pit de-watering;
• Hazardous material removal;
 
 
84

 
 
• Insurance;
• Escalation; and
• Reclamation (assumed to be equal to salvage value plus bonding return).
 
Current Estimate Case 1
The current process capital cost estimate includes $2,970,000 in pre-production capital expenses with $1,848,000 in sustaining capital over the approximate 4-year life-of-mine plan. The process capital cost estimate for Case 1 is summarized in Table 10.1.

Case 2 and Case 3
Case 2 and Case 3 are both based on approximately 2,000 stpd of ore placement on the heap. Case 2 mines only the $2.75 copper pit, while the Case 3 hypothetical example includes the $2.75 copper pit, the low-grade stockpiles estimated at 0.35% copper, and recoverable copper from the tailings. Pre-production capital requirements for Case 2 and Case 3 are estimated at $3,602,000 with sustaining capital of $2,800,000 for the heap expansion. Capital costs for mining and screening the tailings will be borne by a mining contractor. The Case 2 estimate is detailed in Appendix 3.

10.4   GENERAL AND ADMINISTRATIVE COSTS
 
Infrastructure capital spending is typically related to common plant-wide systems, such as heating, fire protection, water storage, shop tools, communications, water treatment, electrical substation, warehouse restocking, and other. The KD Engineering estimate has included many typical infrastructure costs under the process capital budget. Pre-production capital spending for administrative/infrastructure functions is $315,000 to which is added $260,400 in Year -1 operating costs (see Appendix 3 for details of the KD Engineering estimate).
 
 
85

 
 
11.0     OPERATING COSTS
 
11.1     INTRODUCTION
 
In order to prepare operating cost estimates for Case 1, Case 2, and Case 3, Behre Dolbear relied heavily on the KD estimate, as shown in Appendix 5. Certain costs have been changed by Behre Dolbear to reflect current assumptions about the market place. The project has been divided into three operating components. These include the mine, process, and administrative functions. The preponderance of maintenance charges fall under process with a small amount included under administrative. All senior management and staff have been included in the administrative function. All operating costs in pre-production Year -1 will be summed into a capitalized development account and included along with mine wide and general and administrative capital spending in the financial analysis.

The production schedules, as shown in Table 11.1, 11.2 and 11.3, are representative of the three Cases discussed previously. These costs have been summarized for the mining, process and administrative accounts.

11.2      PROPERTY OPERATING COSTS

The property operating costs were estimated, as shown in Tables 11.1, 11.2, and 11.3.

11.3      MINE OPERATING COSTS
 
Mine operating costs include all contractor costs for drilling, blasting, loading, hauling, crushing and transport, and placement on the heap in addition to the cost of staffing the mine engineering and geology function which will perform ore control in the pit.

11.4    PROCESSING
 
Process operating costs include charges for heap leaching, pumping, solvent extraction, electrowinning, and maintenance of the plant facilities. The full year processing costs are estimated at an average of $3.0 million per annum with unit costs of $9.59 per ton of ore and $0.92 per pound of copper for Case 1. The full year processing costs are estimated at an average of $5.2 million per annum with unit costs of $7.49 per ton of ore and $0.85 per pound of copper for Case 2. The full year processing costs are estimated at an average of $4.3 million per annum with unit costs of $7.46 per ton of ore and $0.86 per pound of copper for Case 3.

 
86

 
 
11.5   GENERAL AND ADMINISTRATIVE
 
General and Administrative costs for Case 1 are estimated at an average of $593,987 per year with attendant operating costs of $2.11 per ton of ore and $0.20 per pound of copper.

General and Administrative costs for Case 2 are estimated at an average of $593,987 per year with attendant operating costs of $0.75 per ton of ore and $0.11 per pound of copper.

General and Administrative costs for Case 3 are estimated at an average of $523,000 per year with attendant operating costs of $0.98 per ton of ore and $0.11 per pound of copper.
 
87

 
 
Table 11.1
Emerald Isle Operating Cost Summary - Case 1
 
           
Year
       
 
 
   
Units
       -1        1        2        3        4        5        6        7      
Total
 
Account Operations                                                                            
Operating Days
 
Days
                                                                       
Tons Mined/Processed
 
dst
              330,280       330,280       324,667                                       985,227  
Tons Waste
 
dst
              295,715       397,931       1,606,199                                          
Ore Grade
                                                                             
Copper
 
%
              0.62       0.75       0.52                                       0.63  
Recovery
                                                                             
Copper
 
%
                                                                         
Cathodes
                                                                             
Copper
 
%
              99.998       99.998       99.998                                       99.998  
Metal Recovered
                                                                             
Copper
 
lbs
              2,947,739       4,168,256       2,859,617       238,106                               10,213,718  
                                                                               
Mine
                                                                        $    
Contractor
                                                                        $    
Ore Mining
                                                                        $    
Waste Mining
                                                                        $    
SGV Operations Total Mining
        $ 67,700         134,500       134,500                                                  
Process
                                                                        $    
Heap Leaching
                $ 1,286,027       1,286,027       1,269,525       100,000                               3,941,579  
SX/EW
                $ 1,517,910       1,696,594       1,505,009       230,000                               4,949,513  
Maintenance
                $ 168,755       168,755       168,755       50,000                               556,265  
Total Process
      S             2,972,692       3,151,376       2,943,289       380,000                               9,447,357  
Administrative
          $ 260,400       522,852       522,852       522,852       250,000                               2,078,956  
Total Administrative
          $ 260,400       522,852       522,852       522,852       250,000                               2,078,956  
Mine
  $ /t                                                                          
Process
  $ /t               9.00       9.54       9.07                                       9.59  
Administrative
  $ /t               1.58       1.58       1.61                                       2.11  
Total
  $ /t                                                                          
Mine
 
$/lb
                                                                         
Process
 
$/lb
              1.01       0.76       1.03       1.60                               0.92  
Administrative
 
$/lb
              0.18       0.13       0.18       1.05                               0.20  
Total
 
$/lb
                                                                         

 
 
88

 
 
Table 11.2
Emerald Isle Operating Cost Summary - Case 2
 
            Year        
   
Units
       -1       1       2       3       4        5        6        7    
Total
 
Account Operations                                                                            
Operating Days
 
Days
              365       365       365       180                                
Tons Ore Mined
 
dst
              700,145       700,145       695,419                                        
Tons Ore to Heap
 
dst
              700,145       700,145       695,419                                        
Toms Waste
 
dst
              1,692,757       3,263,505       1,885,075                                        
Ore Grade
                                                                           
Copper
 
%
              9.49       0.54       0.55                                        
Cathodes
                                                                           
Copper
 
%
              99.998       99.998       99.998       99.998                                
Metal Recovered
                                                                           
Copper
 
lbs
              5,396,268       6,196,442       6,384,532       430,256                                
                                                                             
Mine
                                                                        $    
Contractor
                                                                        $    
SGV Operations
        $ 67,000       134,500       134,500       134,500                                       403,500  
Total Mining
                                                                        $    
Process
                                                                        $    
Heap Leaching
                $ 2,399,621       2,399,621       2,399,621       600,000                               7,798,863  
SX/EW
                $ 1,736,501       2,001,630       2,073,352       500,000                               6,311,483  
Maintenance
                $ 482,160       482,160       482,160       150,000                                  
Total Process
                $ 4,618,282       4,883,411       4,955,133       1,250,000                               15,706,826  
Administrative
        $ 260,400       522,852       522,852       522,852       250,000                               2,078,956  
Total Administrative
        $ 260,400       522,852       522,852       522,852       250,000                               2,078,956  
Mine
  $ /t                                                                          
Process
  $ /t               6.60       6.97       7.13                                       7.49  
Administrative
  $ /t               0.75       0.75       0.75                                       0.75  
Total
  $ /t                                                                          
Mine
 
$/lb
                                                                         
Process
 
$/lb
              0.86       0.79       0.78       2.91                               0.85  
Administrative
 
$/lb
                                                                         
Total
 
$/lb
                                                                         
 
 
89

 
Table 11.3
Emerald Isle Operating Cost Summary - Case 3
 
          Year        
   
Units
       -1       1       2       3       4       5       6        7    
Total
 
Account Operations                                                                            
Operating Days
 
Days
              365       365       365       365       365       365       30        
Tons Ore Mined
 
dst
              700,145       700,145       700,145       700,145       425,790       248,380               3,474,750  
Tons Ore to Heap
 
dst
              700,145       700,145       700,145       425,790       151,440       88,340               2,766,005  
Toms Waste
 
dst
              951,315       2,282,472       2,282,472       1,331,432                               6,847,691  
Ore Grade
                                                                             
Copper
 
%
              0.39       0.51       0.56       0.77       1.16       1.16                  
Cathodes
                                                                             
Copper
 
%
              99.998       99.998       99.998       99.998       99.998       99.998               99.998  
Metal Recovered
                                                                             
Copper
 
lbs
              4,144.914       6,293,447       6,874,659       7,801,814       2,830,326       2,057,976               30,003,136  
                                                                               
Mine
                                                                        $    
Contractor
                                                                        $    
SGV Operations
        $ 67,000       134,500       134,500       134,500                                       538,000  
Total Mining
                                                                        $    
Process
                                                                        $    
Heap Leaching
                $ 2,399,621       2,399,621       2,399,621       2,399,621       1,199,811       1,199,811               11,998,105  
SX/EW
                $ 1.736,501       2,001,630       2,073,352       2,176,763       1,563,281       1,467,973               11,019,500  
Maintenance
                $ 482,160       482,160       482,160       482,160       482,160       482.160               2,892,960  
Total Process
      S             4,618,282       4,883,411       4,955,133       5,058,544       3,245,252       3,149,944               25,910,565  
Administrative
          $ 260,400       522,852       522,852       522,852       522,852       522,852       522,852               3,397,512  
Total Administrative
          $ 260,400       522,852       522,852       522,852       522,852       522,852       522,852               3,397,512  
Mine
  $ /t                                                                          
Process
  $ /t               6.60       6.97       7.08       7.22       7.62       12.68               7.46  
Administrative
  $ /t               0.75       0.75       0.75       0.75       1.23       2.11               0.98  
Total
  $ /t                                                                          
Mine
 
$/lb Cu
                                                                         
Process
 
$/lb Cu
              1.11       0.78       0.72       0.65       1.15       1.53               0.86  
Administrative
 
$/lb Cu
              0.13       0.08       0.08       0.07       0.18       0.25               0.11  
Total
 
$/lb Cu
                                                                         

 
90

 
12.0   MARKETING EMERALD ISLE SX/EX CATHODES
 
12.1     SUMMARY AND INTRODUCTION
 
The Emerald Isle Mine's location in Northern Arizona, is 275 to 325 miles closer to the market, has an advantage over the larger copper mines to the south to serve the southern California copper market by truck or rail. Markets as far as Illinois (Chicago area) and Indiana can be served by rail. The current favorable copper market has a price premium over the COMEX copper price and the buyer pays the freight. The onset of new copper production will eventually require producers to pay the freight in a weaker market. Average shipping costs plus a probable new mine discount (2 to 3 cents) to get back into the market, a copper price discount of six cents a pound off the COMEX projected price is recommended for a pre-feasibility study. Further, a quick return to production can take advantage of the current copper market.

12.2     BACKGROUND
 
The mine was formerly operated by Arimetco for one year and shut down in 1993 after producing 1.16 million pounds of wire grade cathodes. The former operator shut the mine down from a combination of low copper prices and erratic production. However, other SX/EW mines with substantially lower costs remained profitable.

12.3     CATHODE PRODUCTION
 
Cathode production at anything less than 12,000 pounds to 16,000 pounds per day will have a difficult time attracting a merchant to do the marketing without a discount (fee) to the merchant. There are some buyers that require prompt delivery after placing an order. It takes longer to accumulate a truckload at 8,000 pounds than 16,000 pounds output per day. This is due to a trend for copper buying "just-in-time" to feed the fabricating mill to avoid inventory. Consistent grade and copper output is an important selling point. Further, it is suggested, the reopening and refurbishment of the plant be done as soon as possible to take advantage of the current copper market, even at 8,000 pounds per day, while expanded output construction is underway. If possible, heap leaching could start as soon as practical. A flow of copper-bearing solutions should commence in advance of the plant reopening, as it takes time to build up the flow necessary to efficiently run the SX/EW circuit to produce wire grade cathodes.
 
 
91

 
 
It is also imperative that the mine goes into production as soon as possible to avoid costs of a weaker market as long as possible. Merchants forecast that in a weak market there will be eventual price discounts other than merchant commission, and the freight burden will be borne by the mines. Also reopening the mine in a weak market may require a discount to provide incentive for a mill to buy from an unknown reopened mine, as the last production shipped, was in 1993.
 
12.4     CATHODE QUALITY
 
Cathode quality of 99.995% minimum copper content is imperative for a wire mill or electrical circuit parts fabricator. The former production at 99.998% copper is very desirable. High purity also dilutes impurities from number one copper scrap as most mills utilize a certain amount of scrap as a means to reduce raw material costs. To ensure this quality, it is necessary to wash the cathodes after removing them from the electrolytic cells. Depending upon the cathode's surface impurities (dissolved/precipitated minerals), either a high-pressure wash or a dilute acid wash will be necessary to clean and brighten the cathodes.

Since SX/EW cathodes tend to be much lighter than electrolytic copper made from anodes, it is necessary to bundle them with copper bands to achieve a weight of around 250 pounds a bundle. These bundles makes for greater ease in feeding a melting furnace at the fabricating mill, an often over looked selling point.

12.5     CATHODE SALES
 
A minimum cathode output of 12,000 pounds to 16,000 pounds should be considered, as it will take about 13 or 15 days production to fill a rail car with 180,000 pounds of cathodes. The Burlington Northern Santa Fe railroad prices their cars on the basis of 165,000 pounds. It has been advised that the 180,000 pounds of thin cathodes is the maximum that the car can hold, especially if dunnage is required. Similarly, it would take about 3 to 4 days of production to load a truck at the mine with 44,000 pounds. In either case, a truck load-out and a fork lift is required at the mine, as the Burlington Northern Santa Fe available siding is in Kingman. In any case, the merchant has to pick up the cathode bundles at the mine site by truck.
 
Copper pricing is usually the week or month following the month of shipment or the prior month if payment is made within 15 days of the truck loading. Usually that is negotiable. In any case, shipping documents (bill of lading) is always the basis for payment. Due to the rather small output and the mine regarded as an unknown new operation, it is more cost efficient to use a merchant to sell the cathodes.

 
92

 
12.6   TRANSPORATION
 
Unless the mine builds a prohibitively costly rail siding, truck hauling is necessary either to a freight forwarder at the Burlington Northern Santa Fe rail siding or long distance hauling. For the rail rates, a load of 165,000 or more than 165,000 pounds was used. Box cars can carry a maximum of 180,000 pounds of thin SX/EW cathodes and this divisor was used to determine the rail costs per pound of cathodes.

Table 12.1 shows the distance by truck to various destinations in the Chicago, Illinois, vicinity about 1,800 miles, the same distance as rail. The closest copper fabricator in the Los Angeles-San Diego southern California area is about 320 miles to 380 miles away. Distances in excess of 1,000 miles are much more costly to ship by truck, necessitating rail shipment, where possible. The Burlington Northern Santa Fe railroad has no direct route from Kingman, Arizona to Salt Lake City, Utah. The distance is 1,361 miles by rail versus 526 miles by truck. Chicago is about the same distance by truck as it is by rail, about 1,800+ miles. There are copper fabricators some 250 miles to 300 miles closer than Chicago, with about the same mileage by rail as Salt Lake City and West Jordan, Utah. The large copper mines to the south are 300 miles farther from the market, which gives Emerald Isle a slight freight advantage. Most large fabricators have an on-site rail siding. Many buyers insist on truck shipments due to the smaller amount (44,000 pounds) and the truck's ability to arrive, when needed. Merchants will prefer the convenience of truck shipment directly to the customers, as it avoids the services of a forwarder to store and load the cathodes at the Kingman, Arizona rail siding. Rail shipments will have an extra cost of about one and a half cents a pound of cathodes to pick up the cathodes at the mine and bring them south to Kingman, Arizona for storage and box-car loading.

It may be more cost effective if the mine has a truck to haul the cathodes to Kingman, Arizona if there is sufficient rail shipping and pick up of some mine supplies for a cost-saving back-haul.
 
 
93

 
 
Table 12.1 lists the cities that have one or more copper fabricators in the general area to give an indication of the distances from the mine to the market and the resulting shipping costs per pound of cathode. Each of the locations in Table 12.1 have one or more prospective copper fabricators in the city and others in the general area to show the difference between transportation costs by truck and rail, where applicable. Both rail and truck costs are affected by the cost of fuel and trucking may be affected by location, as to the possibility of picking up more business from that area, highway congestion, and weather.

The rates in Table 12.1 reflect current fuel surcharges and conditions. An increase in oil prices causes an immediate increase in gasoline and diesel oil costs. The railroad's cost of diesel fuel is a smaller percentage of the total cost to operate than a truck. In a rising oil market, the gap between rail and truck shipments widens in favor of rail. The switch from truck to rail is governed by the presence of a convenient rail siding at the fabricating plant and box-car availability. Open-top gondola cars cost less than box-cars, but a locked, enclosed box-car is more secure and avoids pilferage. Six hundred pound smelter copper anodes are shipped in open flat cars or gondolas with no losses, but a 65 pound or 100 pound SX/EW cathode is very easily handled without a fork-lift.

Table 12.1
Cathode Truck and Rail Costs ($/lb Copper)
 
Copper Buyers
 
Mileage
   
Cost
   
(US$)
 
State
City
 
Truck
   
Rail
   
Truck
   
Rail
 
Illinois
Chicago
    1,830       1,750       0.120       0.044  
Texas
McKinney
    1,140       N/A       0.080       N/A  
Dallas
    1,134       1,199       0.085       0.039  
Houston
    1,380       1,392       0.090       0.041  
El Paso
    651       730       0.060       0.033  
California
Los Angele
    355       366       0.035       0.029  
Valencia
    349       361       0.035       0.028  
San Diego
    411       444       0.037       0.028  
Livermore
    577       644       0.060       0.031  
Hayward
    596       N/A       0.060       N/A  
 
 
 
94

 
 
12.7   CUSTOMER CHOICE
 
It will be more cost efficient to utilize the services of a merchant to sell the cathodes, as a merchant will have the necessary fabricator contacts and will also assume the credit risk of the buyer. Merchants will sell to the nearest customers, mostly in California and possibly in Texas, and some to the Salt Lake City COMEX warehouse. Although the bulk of the fabricators are in the Eastern United States, there are many in the mid-west, such as Illinois and Indiana. These will be chosen if they have a rail siding and can buy in sufficient quantity to justify rail shipment. Truck quotes to the Chicago area vary from eight to twelve cents a pound for 44,000 pounds depending upon the truck type and back-hauls back to Arizona. Regular shipments to a particular plant can be less costly. The merchant arranges for the trucking and such rates can be easily verified by a freight broker. In California alone, there are more than a dozen fabricators that can take the mine's entire output. Each merchant has a number of possibilities to sell the entire mine output, to one or several buyers.

In the performance of this market analysis, the following copper merchants were contacted.
 
•  
H&H Metals, White Plains, New York, Mr. James Holme, Telephone (914) 428-8822;and
 
•  
Glencore International Commodities, Stamford Connecticut, Mr. Steve Roland (copper desk), Telephone (203) 609-3195.
 
•  
Both have trucking companies they deal with very competitive rates.
 
•  
H&H proposed a three-cent fee due to the small output and Glencore proposed no fee, but will take the copper premium over spot, and when that disappears, they may impose a similar fee.

It is advised that several merchants be contacted for the best terms for the mine, and the marketing contract has to be carefully scrutinized for such items as the merchant assumes the credit risk for the transactions. As previously discussed, an in-house and experienced copper marketer is not cost effective, and in times of slack demand, a merchant always finds a way to sell the mine's output to preserve their commission. At a load of less than 165,000 pounds, the rate drops and at more than 165,000 pounds, the rate increases. This increased rate and a maximum of 180,000 pounds was used to determine the rail costs per pound of cathodes.
 
 
95

 
 
12.8   SALES RETURN AND REVENUE
 
At this point in time, it can be assumed that the current copper market will eventually weaken, but at an unpredictable time. To what extent certain post-mining costs, such as transportation and/or price discounts will occur for the mine's account, is also unpredictable. Merchants advise that a discount may be necessary to attract first-time buyers to the Emerald Isle mine's cathodes. A two cent discount and truck rates averaging four cents was advised, for a total of six cents off the COMEX price forecast. Again, in considering the restart of operations, time is of the essence in order to preserve the favorable current market terms and prices.

The strong demand for the first year means that production can be sold at COMEX flat copper price (no discounts). The mine could enjoy a premium over spot for some months, provided today's market conditions prevail for wire grade copper.
 
 
96

 
13.0   PROJECT ECONOMIES
 
13.1   INTRODUCTION
 
Three cases have been analyzed for the Emerald Isle Project. In Case 1, production occurs over 3 years and a total of 985,227 tons of ore is produced, from which 10.2 million pounds of copper are recovered and salable. Copper price is US$2.00 per pound. In Case 2, production occurs over 3 years and a total of 2,095,709 tons of ore is produced, from which 18.4 million pounds of copper are recovered and salable. Copper price is US$2.75 per pound. In Case 3, production occurs over 6 years and a total of 3,474,750 tons of ore is produced, from which 30.0 million pounds of copper are recovered and salable. Copper price is US$2.75 per pound. Case 3 includes all the ore from Case 2 plus stockpiled material on the site.

Cash flow spreadsheets were developed to determine the cash flow, net present value, and rate of return (see Appendix 7.0).

The production of ore and waste is shown first. The grade, contained copper and recovered copper, are shown. Input data for Case 1 are taken from Table 11.1; Case 2 - Table 11.2; and Case 3 - Table 11.3. Income from sale of copper is presented next. From the sale price, a selling and delivery expense of US$0.06 per pound is deducted before determination of net revenue from sales.

Operating costs are shown next. Unit costs are shown first per ton of ore, then shown in dollars incurred per year. Contract mining cost is taken from Section 6.5. Other operating costs are taken from Tables 11.1, 11.2, and 11.3. Annual cash operating costs are totaled. Net income before taxes is the income from sales less cash operating cost and depreciation.

Depletion is determined for tax purposes, either percentage depletion or 50% of net. Any losses carried forward for tax purposes are deducted and net taxable income is the result.

The various taxes are calculated. Copper is subject to a severance tax. There is an income tax in Arizona at the rate of 6.968%. The federal income tax is assumed to be the maximum rate of 35%. Taxes are deducted from the net income before taxes, depreciation is added back, and the result is the net income from operations.
 
Capital investments are shown. Capital is taken from Table 10.1 for Case 1 and Table 10.2 for Case 2 and Case 3. The mine capital is input from Table 6.2.

 
97

 
The cash flow is determined by deducting capital from the net income from operations. In other words, revenue less cash operating costs less taxes less capital equals net cash flow.

The net present value is given for a variety of discount rates from 0% (no discounting) to 30%. If the cash flow at 0% discount rate is positive, then the rate of return has meaning and is shown. In Case 1 and Case 2, the cash flow is negative (income from sales is insufficient to cover costs) and the rate of return is undefined (negative). For Case 3 the rate of return is meaningful.

A detailed table is presented below; the main cash flow table showing the calculation of the annual depreciation allowance. Depreciation of assets is according to the Internal Revenue Code guidelines as developed by the Internal Revenue Service (IRS). All items are depreciated over 7 years using the mid-year convention. Under that convention, it is assumed that, on average, assets are placed into service at mid-year. Depreciation is then spread over 8 calendar years, with reduced allowances in the first and eighth years. Depreciation percentages are: Year 1 -14.29%; Year 2 - 24.49%; Year 3 - 17.49%; Year 4 - 12.49%; Year 5 - 8.93%; Years 6 -8.92%; Year 7 - 8.93%; and Year 8 - 4.46%.

13.2    METAL PRICES
 
For the purposes of the economic analyses, only copper is produced and salable. For Case 1, the copper price is US$2.00 per pound; for Case 2 and Case 3 - US$2.75 per pound. Copper prices are currently in the US$3.20 per pound range.
 
13.3      FINANCIAL ANALYSIS
 
Case 1
Case 1 is uneconomic at US$2.00 per pound copper price. The cash flow is a negative US$15.2 million. Income from the sale of copper is US$19.8 million, but direct cash operating costs are US$27.8 million over the life of the Case 1 project. Severance tax is US$0.2 million. Capital investment is US$7.0 million. The rate of return is negative and the Excel formula is unable to determine a meaningful number (shown as "#Div/0" on the spreadsheet).
 
Case 2 is uneconomic at US$2.75 per pound copper price. The cash flow is a negative US$3.6 million. Income from sale of copper is US$49.5 million. Direct cash operating costs are US$43.8 million over the life of the Case 2 project. Severance and other taxes total US$0.6 million. Capital investment is US$8.7 million. The rate of return is negative (shown as negative 27.39% on the spreadsheet).

Case 3
Case 3 is economic at US$2.75 per pound copper price. The cash flow is a positive US$6.9 million. Income from sale of copper is US$80.7 million. Direst cash operating costs are US$61.8 million over the life of the Case 3 project. Severance and other taxes total US$3.4 million. Capital investment is US$8.7 million. The rate of return is 21.5%.

13.4   SENSITIVITY ANALYSIS
 
Copper price, operating cost, and capital investment were varied for the sensitivity analyses. Copper prices were varied from US$2.00 to US$3.25 in US$0.25 increments. Operating cost was varied ±10% and ±20%. Capital investment was varied ±10% and ±20%.

Case 1
At no price in the range of US$2.00 to US$3.25 did the Case 1 project show positive cash flow; thus net present value for 5% discount rate, for 10% discount rate, and rate of return are all negative.
 
 
98

 
For operating cost variance of +20%, +10%, -10%, and -20%, the results were always negative. The Case 1 project did not show positive cash flow within this range of variance.

For capital investment variance of +20%, +10%, -10%, and -20%, the results were always negative. The Case 1 project did not show positive cash flow within this range of variance.

Case 2
At no price in the range US$2.00 to US$2.75 did the Case 2 project show positive cash flow; thus net present value for 5% discount rate, for 10% discount rate, and rate of return are all negative.  At US$3.00 per pound copper price, the return on investment was 0.05% (almost perfect break even). At US$3.25 per pound copper price, the net present value at 5% discount rate is US$2.6 million; at 10% discount rate, US$1.7 million; and rate of return is 25.19%.

For operating cost variance of +20%, +10%, and -10%, the results were always negative. The Case 2 project did not show positive cash flow within this range of variance. When the operating cost is reduced 20% (-20% variance), the net present value at 5% discount rate is US$2.4 million; at 10% discount rate, US$1.5 million; and rate of return is 23.61%.

For capital investment variance of +20%, +10%, -10%, and -20%, the results were always negative. The Case 2 project did not show positive cash flow within this range of variance.

Case 3
For most variances, the Case 3 project showed positive cash flow and meaningful net present values and rates of return. Results are shown in Table 13.1.
 
Table 13.1
Result of Sensitivity Analysis - Case 3
 
       
Net Present Value (USS millions)
             
 
Copper Price per Pound
     
5% Discount Rate
     
10% Discount Rate
     
Rate of Return
 
$ 2.00    
<0
   
<0
   
<0
 
$ 2.25    
<0
   
<0
   
<0
 
$ 2.50    
<0
   
<0
      4.25 %
$2.75 (Base)
    $ 4.4     $ 2.6       21.50 %
$ 3.00     $ 9.1     $ 6.5       37.89 %
$ 3.25     $ 13.8     $ 10.4       53.72 %
Operating Cost
 
  +20 %  
<0
   
<0
   
<0
 
  +10 %   $ 0.5    
<0
      7.02 %
Base
    $ 4.4     $ 2.6       21.50 %
  -10 %   $ 8.3     $ 5.9       35.98 %
  -20 %   $ 12.2     $ 9.2       50.38 %
Capital Investment
 
  +20 %   $ 3.1     $ 1.3       15.15 %
  +10 %   $ 3.7     $ 2.0       18.12 %
Base
    $ 4.4     $ 2.6       21.50 %
  -10 %   $ 5.1     $ 3.2       25.38 %
  -20 %   $ 5.8     $ 3.9       30.04 %
 
 
99

 
14.0    STATUS AND ONGOING WORK
 
SGV realized at the onset of the aforementioned valuation (Phase 1) for Cases 1, 2, and 3 that the low-grade stockpile material and the El Paso tailings material discussed in case 3 could not be considered in an assessment of the project because insufficient data was available to move this material to a mineable resource and ultimately to a reserve. It was decided to conduct a Phase 1 valuation considering those resources that were sufficiently drilled, sampled and metallurgicaly tested to support the current assessment. Based on the results of this analysis (provided in this report), a Phase 2 study would be conducted to optimize the exploitation of the Emerald Isle deposit.

Phase 1 - As part of their analysis of the Emerald Isle Project, Behre Dolbear completed a full assessment of the mineral resources and expected copper recovery. This phase of the report was essentially completed in late November of 2006 and sent to SGV for review in December. For this phase, Behre Dolbear relied on its associates, consultants, and outside independent professional companies to assess and re-design, where needed, the entire processing plant and related equipment. The proposed rehabilitation of the process plant and ongoing mining operations were based on agreement with SGV to be accomplished with the use of independent contractors. The permitting and regulatory matters were assessed and determined to be in order.

It was determined that additional mineral resources and sources of water would be required to support economic mining and processing activities. The Phase 1 report is discussed in-depth in the main body of this report.
 
Phase 2 - Behre Dolbear's initial evaluation demonstrated that additional information was required on the waste dump and tailings material to fully evaluate the overall economic viability of the Emerald Isle deposit. A key variable, in determining the rate of production, is the availability of water in excess of that currently available from SGV's existing wells. SGV Resources recently initiated a study to determine alternative sources of water which may include the drilling of a new well.
 
 
100

 
 
Phase 2 examines the proposed operation in light of SGV reducing the capital cost of refurbishing the existing SXEW facilities and reducing the mining costs, including self performing the mining operation. This phase will rely on the assessment of the resources and copper recovery data confirmed as part of Phase 1 and the base-line design, capital and operating cost data developed by KD Engineering and MWH.
 
SGV realizes that a significant copper resource may be present in the El Paso tailings and the low-grade stockpile. The contribution of this resource to the overall project economics was not included in the Phase 1 evaluation due to a lack of reliable data. The tailings were sampled in late 2006 and are presently being analyzed by Metcon Laboratories. The low-grade stockpile will be sampled in early February 2007 and then sent to Metcon Laboratories for assessment. Behre Dolbear will assess the merits of the work being done by SGV and conduct a new valuation based on the revised input data. A report covering Phase 2 may be ready by late March.
 
 
101

 
 
 
 
 
 
 
 
 
 
 
 
APPENDIX 1.0
CALLS REPORT
 
 
 
 
 
 
 
 
 
 
 
 
 
A1-1

 
 
 
 
A1-2

 
 
 
A1-3

 
 
 
A1-4

 
 
 
A1-5

 
 
 
A1-6

 
 
 
A1-7

 
 
 
A1-8

 
 
 
A1-9

 
 
 
A1-10

 
 
 
A1-11

 
 
 
A1-12

 
 
 
A1-13

 
 
 
A1-14

 
 
 
A1-15

 
 
 
A1-16

 
 
 
A1-17

 
 
 
A1-18

 
 
 
A1-19

 
 
 
A1-20

 
 
 
A1-21

 
 
 
A1-22

 
 
 
A1-23

 
 
 
A1-24

 
 
 
A1-25

 
 
 
A1-26

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
A2-1

 
 
 
A2-2

 
 
 
A2-3

 
 
 
A2-4

 
 
 
A2-5

 
 
 
A2-6

 
 
 
A2-7

 
 
 
A2-8

 
 
A2-9

 
 
 
 
A2-10

 
 
 
A2-11

 
 
 
A2-12

 
 
 
A2-13

 
 
 
A2-14

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
A3-1

 
 
 
A3-2

 
 
 
A3-3

 
 
 
A3-4

 
 
 
A3-5

 
 
 
A3-6

 
 
 
A3-7

 
 
 
A3-8

 
 
 
A3-9

 
 
 
A3-10

 
 
 
A3-11

 
 
 
A3-12

 
 
 
A3-13

 
 
 
A3-14

 
 
 
A3-15

 
 
 
A3-16

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
A4-1

 
 
 
A4-2

 
 
 
A4-3

 
 
 
A4-4

 
 
 
A4-5

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
A5-1

 
 
 
A5-2

 
 
 
 
A5-3

 
 
 
A5-4

 
 
 
A5-5

 
 
 
A5-6

 
 
 
A5-7

 
 
 
A5-8

 
 
 
A5-9

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
A6-1

 
 
 
A6-2

 
 
 
A6-3

 
 
 
A6-4

 
 
 
A6-5

 
 
 
A6-6

 
 
 
A6-7

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
A7-1

 
 
 
A7-2

 
 
 
A7-3

 
 
 
A7-4

 
 
 
A7-5

 
 
 
A7-6

 
 
 
A7-7

 
 
 
A7-8

 
 
 
A7-9

 
 
 
A7-10

 
 
 
A7-11

 
 
 
A7-12

 
 
 
A7-13

 
 
 
A7-14

 
 
 
A7-15

 
 
 
A7-16

 
 
 
A7-17

 
 
 
A7-18

 
 
 
A7-19

 
 
 
A7-20

 
 
 
A7-21

 
 
 
A7-22

 
 
 
A7-23

 
 
 
 
A7-24

 
 
 
 
A7-25